HomeMy WebLinkAbout20143250.tiff LOCAL AGENCY OFFER AMENDMENT
Local Agency Offer Amendment
C 030-064
In accordance with Section 7 of the Master Agreement 14 HA4 64551 ("Master Agreement")
between the State of Colorado, Department of Transportation ("CDOT") and Weld County
("Local Agency"), the authorized person signing below for Local Agency hereby submits this
Local Agency Offer Amendment to CDOT for modification of Task Order No. 20054ER1
("Original Task Order") under the Master Agreement for the Flood Damaged Area in WCR 54
CR 13A Bridge over Big Thompson River ("Project Location").
All terms not defined in this Local Agency Offer Amendment shall have the meanings given in
the Master Agreement and/or Original Task Order.
The Local Agency hereby requests that the Original Task Order, and all prior amendments
thereto, if any, be modified as follows: Exhibit C as revised to include the State match.
In connection with this Local Agency Offer Amendment, the Local Agency approves the
attached documents and incorporates them by reference, if applicable:
• Task Order Scope
• Task Order Budget
• Local Agency Contract Administration Checklist
• Damage Inspection Report (Form FHWA 1547)
Local Agency hereby requests modification of the Original Task Order for the Project Location.
" Person signing for the Local Agency hereby swears and affirms that he/she are authorized to act on the
Local Agency's behalf(as indicated in Exhibit B of the Master Agreement)and acknowledge that the State is
relying on hislher representation to that effect.
Pied/4j'
Signature of Authorized Person (Local Agency)
Office of Emergency Management - Director
Title
September 11, 2014
Date
2014-3250
C� et :: �m
!O-2o 2°N `866465
Co07O
Sheet of
Report Number.
U.R Department et DETAILED DAMAGE INSPECTION REPORT 200s4_wele_County_o6&Plt(alK)
Transportation -
Fede r ',alle;'' (Title 23, Federal-aid Highways) Inspection Date:
10/30/2013
-
Location(Name of Road and Milepost) FHWA Disaster Number:
CD-13-1
Weld County Site 06 Federal-aid Route Number:
County Road 54(CR13A Bridge)Over Big Thompson River 00054
Description of Damage (ONLY ONE ITEM MAY BE CHECKED) State: County:
0 Emergency Reims 0 Permanent Repair ❑ Debris Removal CO Weld
Extreme rain amounts caused floodwater that washed out the roadway and abutment backat at the east abutments; Work Order Number:
overtopped the roadway and dunned gap feet of shoulder,embankment,and pavement;and damaged scour
protection elements at the abutments In the main channel at the bridge.Permanent repairs are necessary to dewater,
remove emergency materials,pavement and restore the bridge barknll and scour protection to pre-dbartecondition
once emergency repairs are complete.
Cost Estimate
Description of Work to Date Cost
(Cquipmamt,Labor,and Materials) Unit Unit Price Quantity.Completed Remaining
Major Earthwork Items CY , $ 110.80 40 $ 4,432.00
Aggregate Base Course CY o $ -
Surfacing-HMA TN 0 _
Surfacing-Concrete SY p- 0 $ -
Structure Repairs IS $ 88,800.00 1 $ 88,800.00
v
Walls SF 0 $ -
Drainage LF 0 $ -
Misc.Items L5 $ 3,000.00 1 $ 3,000.00
General Construction Items _l5 $ 29,446.99 1 $ 29,446.99
Winter Work&Dewatering Items LS $ 12,567.90 1 $ 12,567.90
Minor Contract Revisions LS $ 20,737.03 1 _ $ 20,737.03
Credit-(Pavement)Constructed In ER Phase $ 3,474.74
Construction Estimate Subtotal $ 162,458.66
Right-of-Way $ 2,000.00
Preliminary Engineering $ 24,14759
Construction Engineering $ 15,898.39
Indirects, _$ -
Method Estimated Project Total $ 204,504.65
❑ Loud Forces ❑ State Forces ❑ Contract
Environmental Assessment Recommendation Prepared By: Date:
9 Categorical Exdidon 0 ENE15 Ryan Sisson,P.E. 02/11/14
Concurrence FHWA Engineer(Print Name): FHWA Engineer(Signature): Date:
9 Yes ❑ No W. D. Daugherty,P. E. it it„. ., — 03/03/2014
Concurr ce State Engineer(Print Name): State Engineer(Signature): Date:
pigin
es 0 No Miranda Lange,P.E. ' /��_ ,.,IN:6 t� It--
Concurrence Local,$j$ency Print Name): lot I Agen Signature): 1 :
® Yes 0 No k)wk ti./bi 4,S;I( _ ni.�.l L J—4.,2 c
FHWA USE ONLY Form FHWA-1547
FEMA Eligible: 0 Yes 0 No CDOT 11.5.2013
•
EXHIBIT C -FUNDING PROVISIONS Task order#: 20054 ER1
Estimated Cost of Work Project Name; ERLA WCR 54 CR 13A BRDGE OVER BIG T
•
• The estimated total cost the Work is as follows:
t BUDGETED FUNDS
a, Federal Funds $ 124,215.00
(100%of Participating Costs) $46.174.00
(82.79%of Participating Costs) $78.041.00
E Local Funds $8 111 50
(0%of Participating Costs)
(8.605%of Participating Costs) $8.1 11,50
c. State Funds $8,111.50
• (8.605%of Participating Costs) $8,111.50
TOTAL BUDGETED FUNDS: $ 140,438.00 $ 140438.00
2 IESTIMATED PAYMENT TO LOCAL AGENCY*:
a, Federal Funds Budgeted(la) 124,215.00
b. State Funds Budgeted(Ic) 8111 50
f TOTAL ESTIMATED PAYMENT TO LOCAL AGENCY*:[$ 132,326.50 I
3 FOR CDOT ENCUMBRANCE PURPOSES
Encumbered
WBS Element Phase Function Payable Participating Percentage Budgeted Funds Funds""
Design 3020
ROW 3111/3114
(Acs/Relod
ROW 3114
_ Incidentals
•
Const 1%) 3301
•
20054.10.50 Miscellaneous 3404 $ 140,438.00 $140,438.00
Willies 3988
Environmental 3403
TOTAL ENCUMBERED FUNDS: $ 140,438.00 $ 140,438.00
*The"Total Estimated Payment to Local Agency"amount assumes that that the entire budgeted amount in Section 1 will be
encumbered.Local Agency is not entitled to payment for any amounts that are not encumbered.
**The Agreement Funds payable by the State to Local Agency pursuant to this Agreement Is limited to the aggregate amount of
encumbered funds identified in Section 3 above multiplied by the Payable Participating Percentage for Federal Funds or State Funds
identified in Section 3.
Page 1 of 2
Single Audit Act
All state and local government and non-profit organizations receiving more than$500,000 from all
funding sources defined as federal financial assistance for Single Audit Act of 1984,as amended
(PL 98-502; PL 104-156)(collectively the"Single Audit Act"),purposes shall comply with the
audit requirements of OMB Circular A-I33 (Audits of States,Local Governments and Non-Profit
Organizations)and OMB Circular A-133 Compliance Supplement,as amended.See also,49 CFR
18.20 through 18.26.The Single Audit Act requirements applicable to the Local Agency receiving
Federal Funds are as follows:
i.Expenditure less than$500,000
If the Local Agency expends less than$500,000 in Federal Funds(all federal sources,
not just highway funds)in its fiscal year then this requirement does not apply.
ii.Expenditure exceeding than$500,000-Highway Funds Only
If the Local Agency expends more than$500,000 in Federal Funds,but only received
federal highway funds(Catalog of Federal Domestic Assistance,CFDA 20.205)then a
program specific audit shall be performed.This audit will examine the"financial"
procedures and processes for this program area.
iii. Expenditure exceeding than $500,000-Multiple Funding Sources
If the Local Agency expends more than$500,000 in Federal Funds,and the Federal
Funds are from multiple sources(FTA, HUD,NPS,etc.)then the Single Audit Act
applies,which is an audit on the entire organization/entity.
iv. Independent CPA
Single audit shall only be conducted by an independent CPA,not by an auditor on staff.
An audit is an allowable direct or indirect cost.
THE REST OF THIS PAGE INTENTIONALLY LEFT BLANK
Page 2 of 2
Weld County Request for Reimbursement
CDOT Project#C 030-064
Task Order# 15 HA4 71579
Reimbursement Request#1
Request for Reimbursement Date 7/31/2014
Labor Equipment Material Contractor
202/Contracted Construction $ 71,460.99
207/ Field Testing $ 150.22 $ 28.00
208/General Services(Engineering) $ 3,468.25 $ 25,594.54
209/Inspection $ 260.42 # $ 45.50
210/Lab Testing $ 157.69
301/Class A Patching $ 1,955.55 $ 548.00 $ 870.10
304/ Mechanical Patching
307/Shoulder Work $ 94.20 $ 240.00
314/ Hauling Asphalt
401/Site Work $ 1,928.73 $3,726.00 $ 1,218.75
410/Tree Trimming with Contractor
411/ Bridge Repair $ 1,581.73 $1,168.00 $2,017.91
600/Hauling Solids $ 849.61 $1,342.50 $1,392.36 $ 675.00
800/Signing $ 284.86 $ 128.00
805/Sign Production $ 29.74
900/General Administration $ 144.49 $ 238.12
901/Travel Time Employees $ 581.16 $ 267.00
902/Work Support Activities $ 611.10
907/Mobilization of Equipment $ 88.53 $ 189.00
$12,186.28 $7,682.00 $4,518.49 $ 98,949.28
Total $ 123,336.05 A
Not included in invoice by Weld County
All labor by Weld County was
excluded by Weld County $12,186.28
202/Contracted Construction $ 71,460.99
208/General Services(Engineering)
Ayres(amount estimated from detail sheet) $ 4,186.83
Ayres(amount estimated from detail sheet) $ 3,982.50
$12,186.28 $ - $ - # $ 79,630.32 B
Not Included Total (A-B) $ 91,816.60
Requested Total $ 31,519.45 C
Weld County Request for Reimbursement
CDOT Project#C 030-064
Task Order It 15 HA4 71579
Reimbursement Request#1
Request for Reimbursement Date 7/31/2014
Exceptions to the Invoice by CDOT
Ayres Invoice 153005
Mileage paid at$.77/mile 77.71 Miles C $ 0.21 $ 16.32
(Pay mileage at$.56/mile)
Equipment Rent $ 536.75 $ 536.75
(Equipment Rent not allowed by
Weld County Contract)
Martin Materials Invoice 12288899 $ 870.11
(Insufficient backup to show
that the asphalt was delivered
to the site.Check backup needs
to be verified.)
Pete Lien &Sons Invoice 13POS/112634 $ 171.00
(No evidence this was delivered to the project)
Pete Lien &Sons Invoice 13POS/112366 $ 171.00
(No evidence this was delivered to the project)
Pete Lien &Sons Invoice 13P05/112367 $ 171.00
(No evidence this was delivered to the project)
Pete Lien &Sons Invoice 13P05/112368 $ 171.00
(No evidence this was delivered to the project)
Pete Lien &Sons Invoice 13P05/112414 $ 138.28
(No canceled check)
Pete Lien &Sons Invoice 13POS/112417 $ 162.91
(No canceled check)
Pete Lien &Sons Invoice 13POS/112418 $ 156.52
(No evidence this was delivered to the project)
Pete Lien &Sons Invoice 13P05/112474 $ 269.50
(No evidence this was delivered to the project)
Pete Lien &Sons Invoice 13POS/112495 $ 148.31
(No evidence this was delivered to the project)
Pete Lien &Sons Invoice 13P05/112496 $ 146.83
(No evidence this was delivered to the project)
Pete Lien &Sons Invoice 13POS/112498 $ 153.67
(No evidence this was delivered to the project)
Pete Lien &Sons Invoice 13POS/112502 $ 157.89
(No evidence this was delivered to the project)
$ 3,441.09 D
Recommended Payment(C-D) $ 28,078.36
Weld County Request for Reimbursement
CDOT Project#C 030-064
Task Order#15 HA4 71579(SA 20054)
Reimbursement Request#2
Request for Reimbursement Date 7/31/2014
Labor Equipment Material Contractor
202/Contracted Construction $ 71,460.99
207/ Field Testing $ 150.22 $ 28.00
208/General Services(Engineering) $ 3,468.25 $ 25,594.54
209/Inspection $ 260.42 # $ 45.50
210/Lab Testing $ 157.69
301/Class A Patching $ 1,955.55 $ 548.00 $ 870.10
304/ Mechanical Patching
307/Shoulder Work $ 94.20 $ 240.00
314/ Hauling Asphalt
401/Site Work $ 1,928.73 $3,726.00 $ 1,218.75
410/Tree Trimming with Contractor
411/Bridge Repair $ 1,581.73 $1,168.00 $2,017.91
600/Hauling Solids $ 849.61 $1,342.50 $1,392.36 $ 675.00
800/Signing $ 284.86 $ 128.00
805/Sign Production $ 29.74
900/General Administration $ 144.49 $ 238.12
901/Travel Time Employees $ 581.16 $ 267.00
902/Work Support Activities $ 611.10
907/Mobilization of Equipment $ 88.53 $ 189.00
$12,186.28 $7,682.00 $4,518.49 $ 98,949.28
Total $ 123,336.05 A
Not included in invoice by Weld County
All labor by Weld County was
excluded by Weld County $12,186.28
Claimed on Invloice#1 $ 31,519.45
208/General Services(Engineering)
Ayres(amount estimated from detail sheet) $ 4,186.83
Ayres(amount estimated from detail sheet) $ 3,982.50
$12,186.28 $ - $ - # $ 39,688.78 B
Not Included Total (A-B) $ 51,875.06
Requested Total $ 71,460.99 C
Weld County Request for Reimbursement
CDOT Project#C 030-064
Task Order#15 HA4 71579 (SA 20054)
Reimbursement Request#2
Request for Reimbursement Date 7/31/2014
Exceptions to the Invoice by CDOT
None $
$ - D
Recommended Payment(C-D) $ 71,460.99