HomeMy WebLinkAbout20140335.tiff RESOLUTION RE: APPROVE WORK ORDER FORM (FLOOD REPAIRS - WEL-BR13/44B) PURSUANT TO AGREEMENT FOR DESIGN SERVICES AND AUTHORIZE CHAIR TO SIGN - AYRES ASSOCIATES, INC. WHEREAS, the Board of County Commissioners of Weld County, Colorado, pursuant to Colorado statute and the Weld County Home Rule Charter, is vested with the authority of administering the affairs of Weld County, Colorado, and WHEREAS, the Board has been presented with a Work Order Form (Flood Repairs - WEL-BR13/44B) Pursuant to Agreement for Design Services between the County of Weld, State of Colorado, by and through the Board of County Commissioners of Weld County, on behalf of the Department of Public Works, and Ayres Associates, Inc., commencing January 13, 2014, with further terms and conditions being as stated in said work order form, and WHEREAS, after review, the Board deems it advisable to approve said work order form, a copy of which is attached hereto and incorporated herein by reference. NOW, THEREFORE, BE IT RESOLVED by the Board of County Commissioners of Weld County, Colorado, that the Work Order Form (Flood Repairs - WEL-BR13/44B) Pursuant to Agreement for Design Services between the County of Weld, State of Colorado, by and through the Board of County Commissioners of Weld County, on behalf of the Department of Public Works, and Ayres Associates, Inc., be, and hereby is, approved. BE IT FURTHER RESOLVED by the Board that the Chair be, and hereby is, authorized to sign said work order form. The above and foregoing Resolution was, on motion duly made and seconded, adopted by the following vote on the 3rd day of February, A.D., 2014, nunc pro tunc January 13, 2014. BOARD OF COUNTY COMMISSIONERS WELD COUNTY, COLORADO ATTEST: t( t_,p ��// , Ida IL/`•��� ��� n om' "" `�� ,�� ��1 •la. Rademac er, Chair Weld County Clerk to the Boa ! o.,1861 , Slit,',""' 1A" a.■ ,�ara Kirkmey Pro-Tem/tatBY. ty Clerk to the Board Sean P. Conway AP ED RM: T --- Mike Fre? n oa ty Attorney (//- William F. Garcia Date of signature 4 'S• ee /&, 6CM 2014-0335 02- 7_/41 EG0070 BC0045 WORK ORDER FORM(FLOOD REPAIRS) PURSUANT TO AN AGREEMENT BETWEEN WELD COUNTY AND AYRES ASSOCIATES INC. DATED: January 31.2014 Work Order Number: Ayres-3 Project Title: WEL-BR 13/448 Design Services(Immediate Needs Prior to Spring Runoff) Commencement Date: January 13.2014 Completion Date:April 30.2014 Limitations on compensation: Not to exceed$24,400.00 Professional agrees to perform the services The attached forms are hereby accepted and identified above and on the attached forms in incorporated herein: Exhibit A — Scope of accordance with the terms and conditions Work, Exhibit B — Cost/Fee Breakdown, contained herein and in the Professional Exhibit C—Proposed Schedule. Services Agreement between the parties, dated January 13, 2014. In the event of a conflict / between or ambiguity in the terms of the Weld Co tytublie W rkg Dep ent- Professional Services Agreement and this work --' order (including the attached forms) the By: Professional Services Agreement shall control. Projec anager Date: tit" ( ^ / By: Ayres Associates Inc. Director of Pub is Works Date: FEB 0 By: �. Title. /HA 04w,6i> 4 / eLe.1" Date: O/A/ By:e (a Doug as R emacher, OCC Chair ,4s Lb ATTEST: O 1/42 Weld County Clerk to the Board By: antit ,� I � ( � 14eC Deputy Clerk to the Board 2014-0335 C C9 00-® AYRES Ayres Associates Inc ASSOCIATES EXHIBIT A - SCOPE OF WORK Weld County 2013 Flood Recovery WEL013.0-044.0B County Road 13 over Little Thompson River Structure Description: This single-span bridge has a clear span length of 58.3 feet. Thirteen steel girders span between vertical steel pile abutments. We do not know the type of abutment foundation (spread footing versus piles). The abutments feature steel wing walls that are angled 45 degrees to the road at all four corners. The 2010 bridge inspection report gave a Sufficiency Rating of 62.6 and an Item 113 (scour critical) code of 8, which means the structure was expected to be stable under anticipated scour conditions. I•v',4i,1 4!'z.::-'0,.. ; _.., 4,.. -------....,, . # -NN W IN V.:._. ''', . '''.!.°11. I y ! "ors At.r- P'5•77. i4 ' . 'i-- ' ...e..4.:,...- ....,..- A Y` F rei +� ..�� . • '-• - _ - Flood Damages and Ongoing Issues: Damages encountered during the September 2013 floods include bridge and roadway overtopping with roadside embankment and shoulder damages both north and south of the bridge. At the bridge there was erosion and loss of the embankment fill behind the right (south) abutment sheetpile wall and wingwalls and partial loss of the embankment fill on the upstream side behind the left (north) abutment sheetpile wall and wingwall. Remnants of the old wooden bridge abutments remain in the embankment fill and were exposed during the flood. I. , _ . �+ s} fir.♦t k � it: r ` . i I r '"III'.. r u` •. i'.=." ? *�'-•� tit .: r1 AWES Ayres Associates Inc ASSOCIATES Ayres staff visited the crossing site with Richard White of Weld County on January 17, 2014. Both approaches have been repaired and the bridge is open to traffic. The main channel has widened considerably from the pre-flood condition. Topographic and geomorphic evidence suggests that the Little Thompson River is incised within its floodplain. This may be an ongoing long term degradation problem related to changes in the watershed hydrology associated with rapid urbanization in the upper portions of the watershed. Analysis of aerial photography revealed that the river immediately upstream was realigned when the bridge was built in 1966. This realignment likely shortened the channel which would produce a steepening of the channel profile. Prior to the flood, the sheetpile abutment walls were deteriorating significantly, especially along the base of the walls, which had been covered with sediment. However, removal of the overlying sediment during flood flows exposed the holes at the base of the abutment walls and subjected the fill behind the walls to potential scour and erosion. Work Recommended Prior to Spring Runoff (Phase 1): • Place additional rock riprap at the upstream corner of the north abutment c. • Place rock riprap under the bridge along the toe of the north abutment. • Survey the right of way limits, the bridge surface and along the north embankment side slopes and under the bridge along the north abutment. • Assuming no temporary easement or ROW acquisition for this construction' Work Anticipated for Phase 2: • Re-grade/stabilize the east roadway embankment north and south of the bridge (600ft) and protect shoulder/embankment slope with TRM/rock. • Remove and replace the fill behind both abutments. Potential Phase 3 work for Betterments and/or Resiliency: • Replace the bridge with a structure designed to current standards Detailed Scope of Work for Phase 1: 1. Kickoff Meeting. Ayres project manager/engineer and geomorphologist will meet with County project manager at County Public Works office. 2. Site Assessment. Ayres project manager/engineer and geomorphologist meet at the site with County project manager to observe current field conditions. assess geomorphology and discuss what emergency repairs were done. 3. Survey. Conduct boundary survey of the right of way limits and topographic survey of the road pavement and embankment within the right of way within 250ft north to 350ft south of the bridge with greater detail around the north bridge abutment. 4. Prepare brief environmental documentation for permitting work at this site. 5. Progress Meeting. Conduct one progress meeting with County project manager at County Public Works office. 6. Design. Develop design of Phase 1 riprap at the north abutment and through the bridge along the north abutment. AYRES Ayres Associates Inc ASSOCIATES 7. Plans and Deliverables. Prepare abbreviated Phase 1 drawing set along with special provisions as needed. Estimate quantities and prepare engineer's estimate of probable cost for Phase 1 activities. IA LO o o m u; 0 o 0 1y o 0 1n o o O O CD CON o um'� m m M N o o M o o O M O O O (A CO CO <- 7 T:9 of t» N 69 EA V) ,- V N V) N - 69 V3 U 0 m N 0 0 0 V CO 1n 6 c'') r V N n N V/ N t 609 U) (0A � 0, 0 (U) 10/1 O ' 7) CO CO r.-- 46 (C) C) v 1"-- LC) fl C) C U) E0 fil 69 V) V) V) C) 0 C) N ItS n co 69 ON (.-.. 69 69 69 V) ' ' 1n O 0) or, ,r- ,,.q O O i A (A co V 69 69 V9 V3 co m U) N 7 b f1' o 0 0 0 0 0 0 0 0 0 0 0 n 0) co a 69 0 (A IA 0 69 (A IA N ' ' 0 co N CO 00 CO @ Co 6) 9 V E. 0 V9 V) 69 a N 0 CO CO O a C N -0 O m Q o O L U O co co 0 m o o 0 0 0 0 0 0' C) m C') N v1 V) M V) V) (t] H9 (A N 0N CO a j, 0 .- (A N 69 N 0 ce N co C cu 70 LL U V •a) '' V) 0) f9 V) R' U — u'1 N' 1 0 1 O O c) CC o L C s. Cj o C y T o ₹ d ~ `.• J 0 0 0 0 0 0 0 0 0 0 1n o 0 W (A 69 69 69 1P CS) m In 69 u7 m (A 1n 0., O 0 0 a (1) 0 el 0 69 (A 69 _ 69 V V 1 .L.. 69 669 - V) CO Q) 7 Y O.03 1 - m 0 U C). o v (n o to o U) U) U) Q N U) a 0) N. N — v (o v) U) o • J 6. W >1 o Q S o o O O O O 0 0 0 0 0 0 u) 00 co 0 0 7D V) V) C0cA N 6) 0 N (A Gs Vi y) ,- 0 0 n (A _ 69 d' CO CO N r V O 19 E9 69 0 V) Vi V CO .7 N. O (C O a5 _ N _ 0 1f1 O 0 0 O O 0 0 0 0 0 0 1A 17 7- 6) 69 (A (A 69 O r N (f1 V) V1 ' If)be. N V) N O 69. V) V) N O _ Y) O S V1 N b1 to bi V) J IS U 0 7 a) _ =O W W _� j LL J � W Q 1:/)- 0!IF N G) H = O CO w I- V VI O N C W o a� C7 'a .17 ID x - Y Q J W I- R N I- - O O o I- 1 F Exhibit C: Schedule of Weld County Flood Repairs on the Big and Little Thompson Priority Task Completion Site Task Task Start Date Date Scoping Meetings January 13, 2014 January 28, 2014 Site Assessment January 16, 2014 January 31, 2014 Survey February 5, 2014 February 12, 2014 1 WEL027.5-048.OA Design & Plans February 13, 2014 February 28, 2014 Review& Revision? February 28, 2014 March 7, 2014 Bidding* March 10, 2014 March 24, 2014 Construction* March 31, 2014 April 28, 2014 Scoping Meetings January 13, 2014 January 28, 2014 Site Assessment January 16, 2014 January 31, 2014 Survey February 8, 2014 February 15, 2014 2 WEL017.0-050.0A Design &Plans February 17, 2014 March 1, 2014 Review& Revisions* March 1, 2014 March 7, 2014 Bidding* March 10, 2014 March 24, 2014 Construction* March 31, 2014 April 28, 2014 Scoping Meetings January 13, 2014 January 28, 2014 Site Assessment January 16, 2014 January 31, 2014 Survey February 11, 2014 February'18, 2014 3 WEL013.0-044.0B Design & Plans February 19, 2014 March 5, 2014 Review& Revision? March 5, 2014 March 12, 2014 Bidding* March 13, 2014 March 27, 2014 Construction* March 31, 2014 April 28, 2014 Scoping Meetings January 13, 2014 January 28, 2014 Site Assessment January 16, 2014 January 31, 2014 Survey February 11, 2014 February 18, 2014 4 WEL054.0-013.0A Design & Plans February 19, 2014 March 5, 2014 Review& Revisions* March 5, 2014 March 12, 2014 Bidding* March 13, 2014 March 27, 2014 Construction* March 31, 2014 April 28, 2014 *Schedule dependent upon other parties not Ayres Associates such as Weld County or the eventual contractor. Hello