To Commissioner Roe Date May CI 1278
CREE:.i;Y. GOLD.
COLORADO From
Subject: Construction Schedule, 1978
The schedule is based on 26 weeks with no allowance for equipment
availability, delivery of material , or weather delays .
DISTRICT III
County Road 49 Begin construction - April 26 , 1978
Complete construction - June 14 , 1978
County Road 59 Begin construction - June 8 , 1978
Complete construction - June 20, 1978
DISTRICT I
County Road 120 Begin construction - June 20, 1978
Complete construction - July 20, 1978
County Road 90 Begin construction - July 18 , 1978
Complete construction - August 18 , 1978
County Road 74 Begin construction - August 21 , 1978
Complete construction - September 19, 1978
County Road 392 Begin construction - September 18 , 1978
Complete construction - September 29 , 1978
DISTRICT II
35th Avenue Begin construction - May 15, 1978
Complete construction - June 1 , 1978
County Road 66 Begin construction - October 2 , 1978
Complete construction - October 12 , 1978
County Road 54 Begin construction - October 11 , 1978
Complete construction - October 19 , 1978
County Road 7 Begin construction - October 23 , 1978
Complete construction - October 30, 1978
The low density surfacing and chip and seal will begin approximately
June 1 , 1978 and be completed August 15, 1978 .
This schedule will be continually revised to keep current with actual
time on each job. A revised schedule will be presenteito the Commissioners
on a monthly basis .