Loading...
HomeMy WebLinkAbout20160186.tiff RESOLUTION RE: APPROVE SITE SPECIFIC DEVELOPMENT PLAN AND USE BY SPECIAL REVIEW PERMIT, USR15-0049, FOR A MAJOR FACILITY OF A PUBLIC UTILITY OR PUBLIC AGENCY(APPROXIMATELY 30.5 MILES OF TRANSMISSION LINES)AND FACILITY CONSTRUCTION LAYDOWN YARDS NEAR THE GREENHOUSE, COLFER, RATTLESNAKE RIDGE AND SOUTH KERSEY SUBSTATIONS (CONSISTING OF TWO CONSTRUCTION TRAILERS, MULTIPLE STORAGE CONTAINERS AND OTHER ASSOCIATED EQUIPMENT) IN THE A (AGRICULTURAL) ZONE DISTRICT - TRI-STATE GENERATION AND TRANSMISSION, INC. WHEREAS, the Board of County Commissioners of Weld County, Colorado, pursuant to Colorado statute and the Weld County Home Rule Charter, is vested with the authority of administering the affairs of Weld County, Colorado, and WHEREAS, the Board of County Commissioners held a public hearing on the 16th day of December, 2015, at the hour of 10:00 a.m., in the Chambers of the Board, for the purpose of hearing the application of Tri-State Generation and Transmission, Inc., 1100 West 116th Avenue, Westminster, CO 80233-0695, for a Site Specific Development Plan and Use by Special Review Permit, USR15-0049, for a Major Facility of a Public Utility or Public Agency (approximately 30.5 miles of transmission lines) and facility construction laydown yards near the Greenhouse, Colfer, Rattlesnake Ridge and South Kersey substations (consisting of two construction trailers, multiple storage containers and other associated equipment) in the A (Agricultural) Zone District, on the following described real estate, being more particularly described as follows: Commencing at the Greenhouse substation located within the Corporate City Limits of Fort Lupton in Section 34, T2N, R66W then crossing Sections 35, 26, and 25, T2N, R66W and then into Sections 30, 29, 28, 27, and 22, T2N, R65W into the Colfer Substation. Commencing at the Colfer Substation heading into Section 22, T2N, R65W and crossing Sections 15, 10, 11, and 2, T2N, R65W and entering Section 35, T3N, R65 and crossing into Sections 36 and 25, T3N, R65W into the Rattlesnake Ridge Substation. From Section 26, T3N, R65W the transmission line enters Section 30, T3N, R64W then crosses through Sections 30, 19, 18, 7 and 6, T3N, R64W and into Section 1, T3N, R65W then crossing Sections 36 and 25, T4N, R65W then entering Section 30, T4N, R64W and crossing Sections 30, 24, and 14, T4N, R65W into the Milton Substation. Commencing at the Milton Substation entering Section 18, T4N, R64W and crossing Sections 7 and 6, T4N, R65W and then entering Section 32, T5N, R65W and terminating at the South Kersey substation. WHEREAS, at said hearing, the applicant was present and represented by Selina Koler, and WHEREAS, the Board of County Commissioners heard all of the testimony and statements of those present, studied the request of the applicant and the recommendation of the Weld County Planning Commission and all of the exhibits and evidence presented in this matter and, having been fully informed, the Board deemed it advisable to continue the matter to March 2, 2016, at 10:00 a.m., to allow adequate time for Public Works staff to complete the County Road 49 horizontal/vertical alignments and for the applicant to work with staff to ensure the projects are well coordinated to resolve any outstanding issues, and 2016-0186 c�,. Co,,,-PL t'w I4L).AppL. 329 PL2383 SPECIAL REVIEW PERMIT (USR15-0049)-TRI-STATE GENERATION AND TRANSMISSION, INC. PAGE 2 WHEREAS, Section 23-2-230 of the Weld County Code provides standards for review of said Use by Special Review Permit, and WHEREAS, on March 2, 2016, the Board of County Commissioners heard further testimony and statements of those present, studied the request of the applicant and the recommendation of the Weld County Planning Commission and all of the exhibits and evidence presented in this matter and, having been fully informed, finds that this request shall be approved for the following reasons: 1. The submitted materials are in compliance with the application requirements of Section 23-2-260 of the Weld County Code. 2. It is the opinion of the Board of County Commissioners that the applicant has shown compliance with Section 23-2-230.6 of the Weld County Code as follows: A. The submitted materials are in compliance with the application requirements of Chapter 21 of the Weld County Code. B. The applicant has shown compliance with Section 21-3-340.A of the Weld County Code, as follows: 1) Section 21-3-340.A.1 states: "The health, welfare and safety of the citizens of the County will be protected and served." The Design Standards (Section 23-2-240), Operation Standards (Section 23-2-250), Conditions of Approval, and Development Standards ensure that there are adequate provisions for the protection of the health, safety, and welfare of the inhabitants of the neighborhood and County. 2) Section 21-3-340.A.2 states: "The natural and socio-economic environment of the County will be protected and enhanced."There are no significant prevalent natural hazards in the area that will affect, or be affected by, the project. Historically, the area has been dominated by agricultural uses, residential development and oil and gas activities. The communities nearest to the project area are Fort Lupton, Hudson, and Kersey. It is anticipated that the project would have a small beneficial impact to the local economies of these towns and the larger metropolitan cities. Construction contractors, regardless of origin, would likely spend some money in these communities for fuel, food, or other supplies. During the construction period, the local economy may see a small influx of dollars and a small increase in sales tax revenue. The footprints of the proposed structures would be the only land removed from current use. Land between the transmission structures would remain available for farming, grazing, or other operations that do not interfere with safe and reliable operation of the transmission 2016-0186 PL2383 SPECIAL REVIEW PERMIT (USR15-0049)-TRI-STATE GENERATION AND TRANSMISSION, INC. PAGE 3 lines. There are no adverse socio-economic constraints associated with the project. The project would generate additional tax revenue for Weld County. This project is not inconsistent with the Economic Development Goals and Policies described in the Weld County Comprehensive Plan. 3) Section 21-3-340.A.3 states: "All reasonable alternatives to the proposed action, including use of existing rights-of-way and joint use of rights-of-way wherever uses are compatible, have been adequately assessed and the proposed action is compatible with and represents the best interests of the people of the County and represents a fair and reasonable utilization of resources in the impact area." The transmission line corridor alternatives were evaluated to address the needs of the project. a. Scenario A: Taking no action would result in no power delivery to Members and their customers. The No Action Alternative does not meet the needs of the Project. b. Scenario B: This alternative would involve the construction of approximately 30.5 miles of 230-kV and 115-kV transmission line and three new substations. Alternative B would provide the necessary power to serve oil and gas facilities in the area, as requested by Member customers. The preferred system alternative is Alternative B, which meets the project's purpose and need and provides a cost-effective, secure, and reliable source of power for Tri-State's Members, United Power, and their customers. The process used to identify alternative locations for the transmission lines began with delineating the Study Area (for all phases of the project). The general location for the substation site and the transmission lines were initially identified based on the location of the oil and gas facilities, interconnection considerations, existing infrastructure, and residences. The locations of these features heavily influenced the area of consideration for the transmission lines and substations. Four potential routes from the proposed Greenhouse Substation to Colfer Substation to Rattlesnake Ridge Substation to Milton Substation to South Kersey Substation were evaluated. The preliminary routes for the proposed 230-kV Greenhouse—Colfer transmission line were identified along existing transmission lines and pipelines, as well as field lines. Greenhouse Substation to Colfer Substation (Greenhouse—Colfer): The preliminary routes for the proposed 230-kV Greenhouse-Colfer transmission line were identified along existing transmission lines, Highway 52, and field lines. An existing utility corridor, which is 2016-0186 PL2383 SPECIAL REVIEW PERMIT (USR15-0049)-TRI-STATE GENERATION AND TRANSMISSION, INC. PAGE 4 located directly northeast of the Greenhouse Substation and going east toward Hudson, presented an opportunity for routing, although the corridor crosses near two residences and is approximately 1.4 miles from the Platte Valley Airpark. An additional route was identified to the north that avoids the residential crossing, but passes near four additional residences. A route to the south along Highway 52 was also evaluated because of the potential to consolidate disturbance with the highway corridor. Greenhouse—Colfer Preferred Route Aternative: The preferred route makes use of the existing utility corridor between the Greenhouse Substation and the Hudson area. The route has the fewest residences, the fewest number of center pivots, is approximately 1.06 miles from the Platte Valley Airpark, and is adjacent to an existing transmission line away from the airport to the south. Greenhouse—Colfer Alternative 1: Alternative 1 follows the preferred route to the north but then turns east approximately 0.5 mile north along CR 20. This route is parallel to CR 20 for most of the route; however, it would create an additional corridor approximately 0.5 mile from the existing corridor. This route crosses four center pivots and would also impact twice as many residences. Greenhouse—Colfer Alternative 2: Alternative 2 runs east out of the Greenhouse Substation to the Hudson area (proposed Colfer Substation) south of the other alternatives along Highway 52. This route would impact nearly five times as many residences as the preferred route and would impact the most landowners. The Alternative is also the closest to the Platte Valley Airpark and would create a new obstruction for the airport to the south. Colfer Substation to Rattlesnake Ridge Substation (Colfer-Rattlesnake Ridge): The area between the Colfer Substation and the Rattlesnake Ridge Substation is primarily agricultural land (center pivots and pasture lands), with intermittent residential development. Preliminary routes for the Colfer-Rattlesnake transmission line were identified along field lines and County roads. An additional route that follows an existing transmission line owned by Xcel Energy (Xcel) to the east was also evaluated. Colfer—Rattlesnake Ridge Preferred Route Alternative: The Preferred route begins at the proposed Colfer Substation property and heads due west parallel to Xcel's existing Hudson—Fort Lupton 2016-0186 PL2383 SPECIAL REVIEW PERMIT (USR15-0049)-TRI-STATE GENERATION AND TRANSMISSION, INC. PAGE 5 line for approximately 0.8 mile where it turns due north and runs along property boundaries for 2.5 miles. The route then crosses the existing east-west utility corridor and continues north for another 1.5 miles where it turns north to the Rattlesnake Ridge Substation parcel. This route has the fewest number of road crossings, residences, and the fewest number of landowners impacted. Colfer—Rattlesnake Ridge Alternative 1: Alternative 1 heads west out of the Coffer Substation for approximately 1.8 miles where it heads north for 2.5 miles along CR 41. The transmission line crosses the County Road four times along this stretch to avoid homes and oil and gas facilities, and additional crossing could be required upon final engineering. The route then heads to the east for approximately one (1) mile where it heads north again along CR 43 for three (3) miles. The route would have to cross the CR 9 times along this stretch to avoid homes and oil and gas facilities. The route then goes west for 2.5 miles along County Road 20 where it crosses back-and-forth another two times. This route has multiple road crossings, a large number of impacted residences and a large amount of center pivots impacted. Colfer-Rattlesnake Ridge Alternative 2: This route goes south out of the Colfer Substation property for approximately 0.5 mile to the existing Hudson Substation. It then follows Xcel's existing Ennis—Hudson transmission line for 7.8 miles, crossing CR 49 twice. The route then heads north off of the existing corridor for three (3) miles. This route is the longest of the Colfer—Rattlesnake Ridge alternatives and has the majority of its route adjacent to existing transmission line corridors. However, it crosses within 500 feet of six (6) residences and impacts 17 landowners. Additionally, it is within 200 feet of ten (10) oil and gas facilities. Rattlesnake Ridge Substation to Milton Substation (Rattlesnake Ridge—Milton): The area between the Rattlesnake Ridge Substation and the Milton Substation is dominated by oil and gas development, agricultural land uses, and rural residents. The CR 49 corridor runs between the two substations and is proposed for substantial widening and re-alignment. Alternatives were evaluated that included use of the existing disturbed CR 49 corridor and also routes to the east and west of the corridor to avoid oil and gas facilities, residences, and agricultural operations. Rattlesnake Ridge—Milton Preferred Route Alternative: The preferred route out of the Rattlesnake Ridge Substation crosses 2016-0186 PL2383 SPECIAL REVIEW PERMIT(USR15-0049)-TRI-STATE GENERATION AND TRANSMISSION, INC. PAGE 6 CR 40 at the intersection of CR 44 and heads north, just east of the future road alignment for approximately 3.3 miles. It then diverts to the west off of the road to avoid homes and crosses through land owned by the State of Colorado. It crosses back into the CR 49 alignment near CR 42 and continues north for 1.2 miles where it terminates at the Milton Substation. This route had the fewest number of road crossings, residences and landowners impacted. Rattlesnake Ridge—Milton Alternative 1: Alternative 1 crosses CR 49 out of the Rattlesnake Ridge Substation and heads east along CR 30 for approximately 0.5 mile where it turns north and runs along property boundaries approximately five (5) miles where it rejoins the CR 49 alignment. It then parallels the road to the north for another 1.8 miles, crossing the road three times to avoid homes and oil and gas facilities. The route then heads northwest for 3.5 miles until it crosses CR 44 and returns the 1.4 miles to the east to terminate at the Milton Substation. Rattlesnake Ridge—Milton Alternative 2: Alternative 2 goes east along CR 30 out of the Rattlesnake Ridge Substation for 2 miles where it turns to the north and runs along property lines for another two (2) miles. It then crosses to the east and west for approximately 9 miles until it reaches CR 49 where it turns west for 1.5 miles to the Milton Substation. Milton Substation to South Kersey Substation (Milton—South Kersey): The area between the Milton Substation and the South Kersey Substation includes two airports, which dominated the routing efforts in this area. The Easton Valley View Airport occurs along CR 49 approximately 1.2 miles north of the Milton Substation. The Beaugh Field, which is a private airstrip, is located northeast of the Milton Substation approximately 0.3 mile east of CR 51. The area also includes center pivots and irrigated agriculture, residences, and oil and gas wells and tank batteries. Milton—South Kersey Preferred Route Alternative: The preferred route runs north out of the Milton Substation and turns to the east along the southern boundary of a parcel then continues north along the west side of the parcel for approximately 0.5 mile where it turns to the northeast and then north through two parcels. The route does not occur along parcel boundaries on these properties due to the approach and departure zone for the Easton Valley View Airport. North of CR 48 the route then re-joins the parcel boundary and continues to the north for 0.75 mile where it crosses County 2016-0186 PL2383 SPECIAL REVIEW PERMIT (USR15-0049)-TRI-STATE GENERATION AND TRANSMISSION, INC. PAGE 7 Road 50 onto a parcel owned by DCP Midstream, LP and into the South Kersey Substation. Milton—South Kersey Alternative 1: Alternative 1 also runs north out of the Milton Substation and then east across the southern boundary of the parcel then continues east for 0.5 mile where it turns north along CR 51. This route would cross CR 51 seven times to avoid residences and oil and gas facilities before crossing CR 50 into the South Kersey Substation. This route was not selected because of the congestion along CR 51 and would include property acquisition for one property owner. Milton—South Kersey Alternative 2: Alternative 2 follows the same route as the Preferred Route Alternative and Alternative 1 out of the substation and east across the parcel continuing east for 0.9 mile where it would turn north along parcel boundaries. The route would jog to the west to avoid a center pivot along CR 48 and would then jog west again to stay along parcel boundaries. It would continue north from there into the South Kersey Substation. This route would involve acquisition and discontinuing use of the Beaugh airfield. Public Outreach: Tri-State and their contractor, HDR, contacted landowners along the preferred and alternative routes per ownership information derived from Weld County property records. This contact has been in various forms including project introduction phone calls; project introduction and access permission letter mailings; and project introduction and access permission meetings with landowners. In addition, negotiations are in process with affected landowners to obtain Options for the purchase of easements along the preferred routes. Landowner contacts began in January, 2014, and are on-going. The proposed 30.5 miles of transmission line would consist of approximately 160-270 structures. The structures would be steel pole construction spaced approximately 600-1,000 feet apart. The transmission lines would have three conductors per circuit for a double-circuit configuration, an overhead optical ground wire for internal Tri-State communications, and one shield wire. Steel transmission poles would be set in concrete foundations. 4) Section 21-3-340.A.4 states: "A satisfactory program to mitigate and minimize adverse impacts has been presented." Colorado Parks and Wildlife (CPW) returned a referral indicating no conflicts with their interests, and the State Historical Society did not return a referral response. The project area is characterized by agricultural 2016-0186 PL2383 SPECIAL REVIEW PERMIT(USR15-0049)-TRI-STATE GENERATION AND TRANSMISSION, INC. PAGE 8 lands, oil and gas development, and residential use. The surrounding vegetation is primarily disturbed grassland. Construction would occur primarily in areas that have been previously disturbed, and impacts to native vegetation communities are expected to be minimal. The land cover is primarily grassland and herbaceous vegetation including weeds. Most access would be overland or along existing municipal or county maintained roads with limited non-maintained county roads, and minimal vegetation would be disturbed from roads. No drainages or wetlands would be impacted by the transmission lines or substation. Portions of the Rattlesnake Ridge—Milton transmission line is within the floodplain, therefore, a Weld County Floodplain Development Permit will be required for transmission structures that occur within the floodplain. The agriculture areas are likely to support a variety of common wildlife such as coyote, fox, skunk, rabbits, and various birds. There is no designated critical wildlife habitat in the vicinity of the project, although suitable habitat may exist for the state-listed Western burrowing owl. Prior to construction, Tri-State will conduct surveys for migratory birds and Western Burrowing Owls (in prairie dog towns in the vicinity of the transmission lines and substation). If any nests for migratory birds or any listed species are found, appropriate construction timing limitations will be enforced, as feasible, according to Colorado Parks and Wildlife recommendations. Where timing limitations or setback cannot be applied due to timing constraints, other alternative mitigation measures would be considered and vetted with CPW. If any federally-listed species are found, Tri-State will consult with the U.S. Fish and Wildlife Service (USFWS) regarding avoidance and mitigation. To preclude avian electrocutions and minimize collision risk, Tri-State would incorporate Avian Protection Plan (APP) standards developed by the Avian Power Line Interaction Committee (APLIC 2006) and the APP guidelines (APLIC and U.S. Fish and Wildlife Service [USFWS] 2005) to protect birds on power lines, as well as NESC-specified electric conductor clearances. Project impacts to wildlife are expected to be minimal and limited to temporary disturbance from construction activities. As part of the project, Tri-State will conduct a Class I archaeological database search of the project area, as well as a Class III pedestrian survey on properties where survey permission has been granted and where significant disturbance has previously not occurred. Any sites found to be eligible for listing on the National Heritage Research Partnership (NRHP) will be spanned and avoided by the project. There are no areas of geologic importance in the vicinity of the project. 5) Section 21-3-340.A.5 states: "The nature and location or expansion of the facility complies with all applicable provisions of the master 2016-0186 PL2383 SPECIAL REVIEW PERMIT(USR15-0049)-TRI-STATE GENERATION AND TRANSMISSION, INC. PAGE 9 plan of this County, and other applicable regional, metropolitan, state and national plans."The preferred transmission line alignment and substation location is within the three (3) mile referral area for the City of Fort Lupton, the Town of Hudson and the Town of Kersey, which each responded without concerns. 6) Section 21-3-340.A.6 states: "The nature and location or expansion of the facility does not unduly or unreasonably impact existing community services."The applicant states careful site planning can be developed with only a localized loss of agricultural land quality. Ground disturbance for the transmission line is generally limited to the area immediately around the base of each pole. The substations would occur on lands previously removed from agricultural use and agricultural practices could continue on adjacent lands. Approximately 55 construction workers would be employed during the course of the approximately 11-month construction period. The project would generate infrequent trips to the transmission line and substations during operation; the line would be inspected annually and occasionally for maintenance. No adverse effects on County roads are anticipated. Tri-State will work with the Weld County Department of Public Works to determine the appropriate access to the construction area. All mobile construction equipment would be certified to operate on Interstate highways. There may be short periods of time when traffic would be halted on County roads to allow construction vehicles to enter and exit the construction area. No improvements to Weld County roads would be required. Given the relatively short construction schedule, the site will not generate significant demands on community services such as the school district. 7) Section 21-3-340.A.7 states: "The nature and location or expansion of the facility will not create an expansion of the demand for government services beyond the reasonable capacity of the community or region to provide such services, as determined by the Board of County Commissioners." It is anticipated that the project would have a small beneficial impact to the nearby communities of Fort Lupton, Hudson, and Kersey, and larger nearby communities of Loveland, Greeley, Longmont and Thornton. Construction contractors, regardless of origin, would likely spend some money in Cheyenne or Greeley for fuel, food, or other supplies. During the construction period, the local economy may see a small influx of dollars and a small increase in sales tax revenue. The footprints of the proposed structures would be the only land removed from current use. Land between the transmission structures would remain available for farming, grazing, or other operations that do not interfere with safe and reliable operation of the transmission line. The project area is located within District 3 of the Weld County 2016-0186 PL2383 SPECIAL REVIEW PERMIT (USR15-0049)-TRI-STATE GENERATION AND TRANSMISSION, INC. PAGE 10 Sheriffs Office and is within the jurisdiction of the Fort Lupton, Hudson, Platteville-Gilcrest, Southeast Weld, Platte Valley and LaSalle Fire Protection Districts. Public roads are maintained by the Weld County Department of Public Works and the respective municipalities. The nearest hospital to the southern side of the project area is in the City of Longmont (Longmont United Hospital) and the nearest hospital to the northern side of the project area is in the City of Greeley (North Colorado Medical Center). None of these services is expected to be affected, unless emergency situations occur. There are no adverse socioeconomic impacts associated with the project. The project would not cause any residents or businesses to be displaced. The Project would generate additional tax revenue for Weld County. 8) Section 21-3-340.A.8 states: "The facility site or expansion area is not in an area with general meteorological and climatological conditions which would unreasonably interfere with or obstruct normal operations and maintenance." The proposed site was selected because it does not affect the meteorological and climatological conditions. 9) Section 21-3-340.A.9 states: "The nature and location of the facility or expansion will not adversely affect the water rights of any upstream, downstream or agricultural users, adjacent communities or other water users."The application states that the project will not impact hydrologic flow of either surface water or groundwater, nor will it affect groundwater recharge. Existing drainage patterns will be preserved. Permanent facilities would not be located in stream channels, appropriately sized culverts will be installed to maintain channel flow and morphology. The project would have no impacts on vested water rights. Construction water and water to suppress dust during construction activities would be trucked into the site. 10) Section 21-3-340.A.10 states: "Adequate water supplies are available for facility needs." Bottled water will be used during construction of the transmission line and substation. 11) Section 21-3-340.A.11 states: "The nature and location of the facility or expansion will not unduly interfere with existing easements, rights-of-way, other utilities, canals, mineral claims or roads."Agreements with holders of existing easements, rights-of- way, or utility, ditch, mineral or roads will be obtained as appropriate once the Weld County permitting processes are complete. 12) Section 21-3-340.A.12 states: "Adequate electric, gas, telephone, water, sewage and other utilities exist or shall be developed to service the site."This is an unmanned facility consisting of 9 miles 2016-0186 PL2383 SPECIAL REVIEW PERMIT(USR15-0049)-TRI-STATE GENERATION AND TRANSMISSION, INC. PAGE 11 of 230/115-kilovolt (kV) transmission line from Tri-State's existing Greenhouse Substation to the proposed 115/69/13.2-kV Colfer Substation; approximately 8.5 miles of 230/115-kV transmission line from the proposed Golfer Substation to the proposed 115/69/13.2-kV Rattlesnake Ridge Substation; approximately nine (9) miles of 230/115-kV transmission line between the proposed Rattlesnake Ridge Substation and the proposed 230/115-kV Milton Substation; approximately four (4) miles of 230/115-kV transmission line between the proposed Milton Substation and the existing South Kersey Substation, therefore, utility services are not required post construction. 13) Section 21-3-340.A.13 states: "The nature and location for expansion of the facility will not unduly interfere with any significant wildlife habitat or adversely affect any endangered wildlife species, unique natural resource or historic landmark within the impact area." Colorado Parks and Wildlife (CPW) returned a referral indicating no conflicts with their interests, and the State Historical Society did not return a referral response. The project area is characterized by agricultural lands, oil and gas development, and residential use. The surrounding vegetation is primarily disturbed grassland. Permanent removal of vegetation would occur at structure sites and substations. Construction would occur primarily in areas that have been previously disturbed, and impacts to native vegetation communities are expected to be minimal. Most access would be overland or along existing municipal or county roads, and minimal vegetation would be disturbed from roads. No drainages or wetlands would be impacted by the transmission lines or substation. The agriculture areas are likely to support a variety of common wildlife such as coyote, fox, skunk, rabbits, and various birds. There is no designated critical wildlife habitat in the vicinity of the project, although suitable habitat may exist for the state-listed Western Burrowing Owl. Prior to construction, Tri-State will conduct surveys for migratory birds and Western Burrowing Owls (in prairie dog towns in the vicinity of the transmission lines and substation). If any nests for migratory birds or any listed species are found, appropriate construction timing limitations will be enforced, as feasible, according to CPW recommendations. Where timing limitations or setback cannot be applied due to timing constraints, other alternative mitigation measures would be considered and vetted with CPW. If any federally-listed species are found, Tri-State will consult with the U.S. Fish and Wildlife Service (USFWS) regarding avoidance and mitigation. To preclude avian electrocutions and minimize collision risk, Tri-State would incorporate Avian Protection Plan (APP) standards developed by the Avian Power Line Interaction Committee (APLIC 2006) and the APP guidelines (APLIC and USFWS 2005) to protect birds on 2016-0186 PL2383 SPECIAL REVIEW PERMIT(USR15-0049)-TRI-STATE GENERATION AND TRANSMISSION, INC. PAGE 12 power lines, as well as NESC-specified electric conductor clearances. Project impacts to wildlife are expected to be minimal and limited to temporary disturbance from construction activities. As part of the project, Tri-State will conduct a Class I archaeological database search of the project area, as well as a Class III pedestrian survey on properties where survey permission has been granted and where significant disturbance has previously not occurred. Any sites found to be eligible for listing on the National Heritage Research Partnership (NRHP) will be spanned and avoided by the project. There are no areas of geologic importance in the vicinity of the project. 14) Section 21-3-340.A.14 states: "The nature and location or expansion of the facility, including expected growth and development related to the operation and provision of service, will not significantly deteriorate water or air quality in the impact area." Construction would last approximately eleven months. Construction activities associated with the proposed transmission line and substations would generate less than significant amounts of particulate matter from soil disturbances and diesel-powered equipment, and less than significant amounts of carbon monoxide and the precursor pollutants to ozone formation from tailpipe emissions. Any air pollutants generated would be widely dispersed across the project area, short term in duration, and minimized by the small scale of construction operations for the substations, and excavating foundations and placing single pole transmission structures. Air pollutants also would be minimized through implementation of dust suppression and proper vehicle maintenance. Therefore, project construction is not expected to contribute to the air quality status in the area. There would be no long-term air quality effects associated with routine operation and maintenance of the proposed transmission line and substations. Once construction activities have been completed, but before vegetation has been re-established, some minor amount of additional dust could occur. The generation of dust would be monitored by Tri-State, and the appropriate action would be taken to control the dust and ensure that potential wind erosion is minimized. Weld County is an attainment area for all measured pollutants, including particulate matter smaller than 10 micrometers in diameter (PM10). No air emissions would result from operation of the transmission line or substations. There would be no alteration in the pattern or intensity of surface drainage as a result of construction or operation of the transmission line and all substations will have an approved drainage plan. 15) Section 21-3-340.A.15 states: "The geological and topographic features of the site are adequate for all construction, clearing, 2016-0186 PL2383 SPECIAL REVIEW PERMIT (USR15-0049)-TRI-STATE GENERATION AND TRANSMISSION, INC. PAGE 13 grading, drainage, vegetation and other needs of the facility construction or expansion." The vicinity of the project site is characterized by agricultural purposes, oil and gas development, and rural residences. The surrounding vegetation is primarily disturbed grassland. Permanent removal of vegetation would occur at structure sites and substations. Construction would occur primarily in areas that have been previously disturbed, and impacts to native vegetation communities are expected to be minimal. 16) Section 21-3-340.A.16 states: "The existing water quality of affected state waters will not be degraded below state and federal standards or established baseline levels."There would be no direct impacts to water quality associated with regular operation or maintenance of the transmission lines and substations. Drainage from the substations would be directed towards detention pond(s) located on the substation properties. Drainage plans will be prepared for the Rattlesnake Ridge Substation, the Milton Substation, and the Colfer Substation. Prior to construction, a Stormwater Permit for Construction Activities would be acquired from the CDPHE, where required. 17) Section 21-3-340.A.17 states: "The proposed project will not have a significantly adverse net effect on the capacities or functioning of streams, lakes and reservoirs in the impact area, nor on the permeability, volume, recharge capability and depth of aquifers in the impact area." According to the application, construction and maintenance of the transmission lines and substations would not measurably impact surface water or groundwater quality. Additionally, there would be no long-term impacts to surface water or groundwater hydrology as a result of construction or operation of the project. The project would not impact hydrologic flow of either surface water or groundwater, nor would it affect groundwater recharge. Prior to construction, a Stormwater Permit for Construction Activities would be acquired from the CDPHE, where required. Minimal water would be used during Project construction. Water for construction purposes, including concrete foundations and dust control, would be brought in from off-site sources by a construction water provider. The source of the construction water would be from either a private well owned by the construction water company or from a municipality. No existing water rights would be impacted, and there would be no long-term use of water. If water is needed for revegetation around transmission structures or temporary access roads, the construction water provider would supply the water. No water would be required for the operation of the transmission lines or substations. 2016-0186 PL2383 SPECIAL REVIEW PERMIT (USR15-0049)-TRI-STATE GENERATION AND TRANSMISSION, INC. PAGE 14 18) Section 21-3-340.A.18 states: "The benefits of the proposed developments outweigh the losses of any natural resources or reduction of productivity of agricultural lands as a result of the proposed development." The majority of the site consists of agricultural purposes, oil and gas development, and rural residences. The facility will have limited impact on agricultural lands within the transmission line corridor project site and minimal impact on future land use. Permanent facilities upon completion will only cover approximately 81 acres. 19) Section 21-3-340.A.19 states: "The applicant has obtained or will obtain all property rights, permits and approvals necessary for the proposed project, including surface, mineral and water rights and easements for drainage, disposal, utilities, access, etc." If the applicant has not obtained all necessary property rights, permits and approvals, the Board may, at its discretion, grant the permit conditioned upon completion of the acquisition of such rights prior to issuance of a zoning or building permit by the County. The application indicates that individual land lease agreements have been obtained or will be acquired between Tri-State and the affected property owners. The applicant has obtained or will obtain all property rights, permits and approvals necessary for the proposed project, including surface, mineral and water rights and easements for drainage, disposal, utilities, access, et cetera, following approval by the Board of County Commissioners. 20) Section 21-3-340.A.20 states: "The proposed project (nonlinear facilities) will not present an unreasonable risk of exposure to or release of toxic or hazardous substances within the impact area." The determination of effects of the project shall include the following considerations: a. The means by which outdoor storage facilities for fuel, raw materials, equipment and related items are adequately enclosed by a fence or wall. b. The likelihood of hazardous materials or wastes being moved off the site by natural causes or forces. c. Containment of inflammable or explosive liquids, solids or gases. There would be temporary storage of construction materials at the four proposed project staging sites. Construction, operation, and maintenance activities would comply with all applicable federal, state, and local laws and regulations regarding the use of hazardous substances. The only hazardous chemicals anticipated 2016-0186 PL2383 SPECIAL REVIEW PERMIT(USR15-0049)-TRI-STATE GENERATION AND TRANSMISSION, INC. PAGE 15 to be used on site are those found in diesel fuel, gasoline, coolant (ethylene glycol), and lubricants in machinery. Hazardous materials would not be drained onto the ground or into streams or drainage areas. In its contract with the construction contractor, Tri-State will specify that it will hold a required pre-construction meeting with the contractor to ensure that all applicable laws and Tri-State's procedures will be followed. Enclosed containment would be provided for all trash. All construction waste, including trash and litter, garbage, other solid waste, petroleum products, and other potentially hazardous materials would be removed to a disposal facility authorized to accept such materials. The Environmental Health Department has added Development Standards No. 15 and 16 to address proper disposal of waste materials. 21) Section 21-3-340.A.21 states: "The scope and nature of the proposed project will not unnecessarily duplicate existing services within the County."The scope and nature of the proposed project will not unnecessarily duplicate existing services within the county. The project would involve construction of approximately 30.5 miles of new 230-kV transmission lines originating at the Greenhouse Substation and terminating at the South Kersey Substation. The new transmission lines would be constructed on steel structures within a 150 foot right-of-way. The transmission line would consist of approximately 160-270 structures, with conductors and phase wires, a shield wire, and an optical ground wire for internal Tri-State communications. The project will also include three new substations: Golfer Substation-115/69/13.2-kV substation located on lands to be owned by Tri-State. The Colfer Substation will include a 115-kV six breaker ring bus, expandable to an inverted breaker and a half, one 115/69/13.8kV 100 megavolt ampere (MVA) transformer, one 115/13.2kV 40 MVA transformer, and four 115-kV transmission line bays. Rattlesnake Ridge Substation-115/69/13.2-kV substation located on lands leased by United Power. The Rattlesnake Ridge Substation will include a ring bus (expandable to a breaker and a half) with 4x 115-kV breakers, a single 115/13.2kV 40 MVA transformer, and one 115/69/13.8kV 100 MVA transformer. Milton Substation-230/115-kV substation located on lands to be owned by Tri-State. The Milton Substation will include one 230/115- kV 300 MVA transformer, three 230-kV breakers and three 115-kV breakers, expandable to an ultimate arrangement that will include a 115-kV inverted breaker and a half and a 230-kV inverted breaker and a half. The substation will allow for future expansion and 2016-0186 PL2383 Il SPECIAL REVIEW PERMIT(USR15-0049)-TRI-STATE GENERATION AND TRANSMISSION, INC. PAGE 16 additional 230-kV, 115-kV, or distribution level connections. There will initially be a 230-kV connection from the Phase I Greenhouse Substation and a 115-kV connection to a future substation located just east of the Milton Substation (across CR 49) called the Neres Canal Substation. The Neres Canal Substation would be permitted by an oil and gas operator as part of a proposed gas plant. Site preparation at all of the substations will include grading, fencing, grounding, and construction foundations. The addition of equipment to the South Kersey Substation would include a breaker, line position, and associated equipment (all located inside the existing fence boundary). The project also includes construction staging areas used for the duration of construction to store equipment and stage construction located near the Davis Substation on CR 18, near the Rattlesnake Ridge Substation on CRs 43 and 30, and at the proposed Colfer and South Kersey Substations. Each staging area will have two construction trailers on-site for approximately 19 months, multiple storage containers, and other associated equipment. The proposed transmission line and associated new substations will address a specific demand for electricity from compressor facilities to meet their long-term air attainment requirements. Further, there is a vast development potential for oil and gas in this region, and this development is very dynamic and evolving. Several different companies have indicated sizeable potential electrical loads in the area beyond what is currently being considered. The applicant believes this line and associated substation will serve the additional electrical loads in the area and would provide for future reliability needs and operational flexibility under transmission contingencies, increasing the reliability to the loads in the area. 22) Section 21-3-340.A.22 states: "If the purpose and need for the proposed project are to meet the needs of an increasing population within the County, the area and community development plans and population trends demonstrate clearly a need for such development." The purpose of the new transmission line and substation is to provide electric service to the oil field and anticipated residential development with electric energy that is reliable and operates efficiently while helping to ensure an adequate and dependable supply of electrical power to meet the needs of for future development. NOW, THEREFORE, BE IT RESOLVED by the Board of County Commissioners of Weld County, Colorado, that the application of Tri-State Generation and Transmission, Inc., for a Site Specific Development Plan and Use by Special Review Permit, USR15-0049, for a Major Facility 2016-0186 PL2383 SPECIAL REVIEW PERMIT (USR15-0049)-TRI-STATE GENERATION AND TRANSMISSION, INC. PAGE 17 of a Public Utility or Public Agency (approximately 30.5 miles of transmission lines) and facility construction laydown yards near the Greenhouse, Colfer, Rattlesnake Ridge and South Kersey substations (consisting of two construction trailers, multiple storage containers and other associated equipment) in the A (Agricultural) Zone District, on the parcel of land described above be, and hereby is, granted subject to the following conditions: 1. Prior to recording the map: A. A Final Drainage Report and Certification of Compliance stamped and signed by a Professional Engineer registered in the State of Colorado is required for the Rattlesnake Ridge Substation. B. A copy of the signed and recorded (construction and post-construction) easement agreements (or other acceptable authorization from property owners) shall be submitted to the Department of Planning Services. C. County Road 16 has been annexed by the City of Fort Lupton. The City has jurisdiction over all accesses within their jurisdiction. Please contact the City to verify the access permit or for any additional requirement that may be needed to obtain or upgrade the permit. D. The applicant shall submit a Floodplain Development Permit (FHDP)for all development activities located within the special flood hazard area. The FEMA definition of development is any man-made change to improved or unimproved real estate, including, but not limited to, buildings or other structures, mining, dredging, filling, grading, paving, excavation, drilling operations, or storage of equipment and materials. E. The map shall be amended to delineate the following: 1) All sheets of the map shall be labeled USR15-0049. 2) The map shall be prepared in accordance with Section 23-2-260.D of the Weld County Code. 3) The attached Development Standards. 4) The final location of the permanent 100 to 150-foot transmission line easement with dimension of permanent right-of-way, property ownership, parcel number, all easements of record, and all physical encumbrances. 5) County Roads 18, 32, 36, 38, 39 and 42 are designated on the Weld County Road Classification Plan as gravel local roads, which require 60 feet of right-of-way at full buildout. All setbacks shall be measured from the edge of future right-of-way. These roads are maintained by Weld County 2016-0186 PL2383 SPECIAL REVIEW PERMIT (USR15-0049)-TRI-STATE GENERATION AND TRANSMISSION, INC. PAGE 18 6) CR 37 is designated on the Weld County Road Classification Plan as a paved local road, which require 60 feet of right-of-way at full buildout. All setbacks shall be measured from the edge of future right-of-way. This road is maintained by Weld County. 7) CRs 34, 41 and 44 are designated on the Weld County Road Classification Plan as a paved collector roads, which require 80 feet of right-of-way at full buildout. There is presently 60 feet of right-of- way. An additional 10 feet shall be delineated on the plat as future right-of-way. All setbacks shall be measured from the edge of future right-of-way. These roads are maintained by Weld County. 8) CR 22 is designated on the Weld County Road Classification Plan as a paved arterial road, which requires 140 feet of right-of-way at full buildout. There is presently 60 feet of right-of-way. An additional 70 feet shall be delineated on the plat as future right-of-way. All setbacks shall be measured from the edge of future right-of-way. This road is maintained by Weld County. 9) CR 49 is designated on the Weld County Classification plan as an arterial road which typically requires 140 feet of right-of-way at full buildout. Weld County is currently in the process of widening this corridor. The alignment of the road widening project varies along the section line for the corridor. Contact Department of Public Works for the location of the existing and future right of way and easements and delineate these. 10) CRs 20, 28, 30, 33, 35, 43, 45 and 47 Section Line are shown to have 30 feet of unmaintained section line right-of-way, per the Weld County GIS right-of-way map. The applicant shall delineate the existing right-of-way. All setbacks are measured from the edge of future right-of-way. 11) CRs 24, 26 and 40 Section Line are shown to have 60 feet of unmaintained section line right-of-way, per the Weld County GIS right-of-way map. The applicant shall delineate the existing right- of-way. All setbacks are measured from the edge of future right-of- way. 12) Delineate the Colfer, Rattlesnake Ridge and South Kersey Substation sites to be utilized for the base of operations and construction staging areas associated with this application. 13) Show the Weld County approved accesses and label with the approved Access Permit Number. 2016-0186 PL2383 SPECIAL REVIEW PERMIT (USR15-0049)-TRI-STATE GENERATION AND TRANSMISSION, INC. PAGE 19 14) Show the floodplain and floodway (if applicable) boundaries. Label the floodplain boundaries with the FEMA Flood Zone and FEMA Map Panel Number or appropriate study. 2. One month prior to construction activities: A. The approved access and tracking control shall be constructed prior to on- site construction. B. If more than one (1) acre is to be disturbed for construction of non-transmission line items such as substations, structures, parking lots, laydown yards etc., a Weld County Grading Permit will be required. 3. The applicant shall submit one (1) paper copy or one (1) electronic (.pdf) copy of the map for preliminary approval to the Weld County Department of Planning Services. 4. Upon completion of Conditions of Approval #1 through #3 above, the applicant shall submit an electronic version (.pdf), or one (1) paper copy, of the plat to the Weld County Department of Planning Services for preliminary approval. The plat shall be prepared in accordance with the requirements of Section 23-2-260.D of the Weld County Code. Upon approval of the plat, the applicant shall submit a Mylar plat, along with all other documentation required as Conditions of Approval. The Mylar plat and additional requirements shall be submitted within one hundred twenty(120)days from the date of the Board of County Commissioners Resolution. The Mylar plat shall be recorded in the office of the Weld County Clerk and Recorder by the Department of Planning Services. The applicant shall be responsible for paying the recording fee. 5. In accordance with Weld County Code Ordinance #2012-3, approved April 30, 2012, should the plat not be recorded within the required one hundred twenty(120) days from the date of the Board of County Commissioners Resolution, a $50.00 recording continuance charge shall added for each additional three (3) month period. 6. The Department of Planning Services respectfully requests the surveyor provide a digital copy of this Use by Special Review. Acceptable CAD formats are .dwg, .dxf, and .dgn (Microstation); acceptable GIS formats are ArcView shapefiles, Arclnfo Coverages and Arclnfo Export files format type is .e00. The preferred format for Images is .tif(Group 4). (Group 6 is not acceptable). This digital file may be sent to maps@co.weld.co.us. 7. The Applicant shall, prior to construction of any segment, submit to the Department of Planning Services a Special Review map that shows the entire length of the project. Upon submittal, the map shall be ready for recording in the 2016-0186 PL2383 SPECIAL REVIEW PERMIT (USR15-0049)-TRI-STATE GENERATION AND TRANSMISSION, INC. PAGE 20 office of the Weld County Clerk and Recorder. Thereafter, prior to constructing any individual segment, the Applicant shall submit to the Department of Planning Services a supplemental map showing the individual segment to be constructed. The supplemental map shall be ready for recording upon submittal. The above and foregoing Resolution was, on motion duly made and seconded, adopted by the following vote on the 2nd day of March, A.D., 2016. BOARD OF COUNTY COMMISSIONERS WELD,� \COUNTY, COLORADO ATTEST: ditAf/t) &C jejeo•c�c ��' -Y•� '2c'�`s�Mike Freeman, Chair Weld County Clerk to the Board • 5- — Se P. ConwayetAbk-eyvk_.. Pro- De•�� Clerk to the Band )1 %„�j /rt a , ''® ��`arbara Kirkmeye APPROVED AS TO FORM: IUUI ligii ' �l �i aeTA-1/ ^ %�►*' lie A. Cozad County Attorney ti \ .342i '`��•�:r�`'' Steve Moreno Date of signature: 2016-0186 PL2383 SITE SPECIFIC DEVELOPMENT PLAN USE BY SPECIAL REVIEW PERMIT DEVELOPMENT STANDARDS TRI-STATE GENERATION AND TRANSMISSION, INC. USR15-0049 1. The Site Specific Development Plan and Use by Special Review Permit, USR15-0049, is for a Major Facility of a Public Utility or Public Agency approximately 9 miles of 230/115-kilovolt (kV) transmission line from Tri-State's existing Greenhouse Substation located near County Roads 31 and 14 to the proposed 115/69/13.2-kV Colfer Substation located near County Roads 45 and 18; approximately 8.5 miles of 230/115-kV transmission line from the proposed Colfer Substation north to the proposed 115/69/13.2-kV Rattlesnake Ridge Substation located near County Roads 49 and 30; approximately 9 miles of 230/115-kV transmission line between the proposed Rattlesnake Ridge Substation and the proposed 230/115-kV Milton Substation located near County Roads 49 and 44; approximately 4 miles of 230/115-kV transmission line between the proposed Milton Substation and the existing South Kersey Substation located near the intersection of County Roads 51 and 50, including the addition of a circuit breaker, line position, and associated equipment inside the fence of Tri-State's existing South Kersey Substation, subject to the provisions of Section 23-4-420 of the Weld County Code and facility construction laydown yards near the Greenhouse, Colfer, Rattlesnake Ridge and South Kersey Substations (consisting of two construction trailers, multiple storage containers and other associated equipment) in the A (Agricultural) Zone District, subject to the Development Standards stated hereon - Tri-State Generation and Transmission Association / Southwest Weld Expansion Project Phase II 2. Approval of this plan may create a vested property right pursuant to Section 23-8-10 of the Weld County Code. 3. The owner of the facility shall not interfere with or cause construction delays during the construction of the Weld County Road (WCR) 49 Corridor Project, February 2016 through the end of the project. If the WCR 49 Corridor contractor cannot make reasonable accommodations to work with the applicant's contractor anywhere along the WCR 49 Corridor, the applicant's contractor shall postpone their work until the applicant's work can be done with no conflict or delays during construction of the WCR 49 Corridor Project. The decision to postpone construction by the applicant in certain areas along the WCR 49 Corridor shall be at the sole discretion of Weld County. 4. The owner of the facility shall not place any structures in County road right-of-way, whether or not the applicant has an easement in that location. 5. The owner of the facility shall pay any additional costs associated with the installation of their facilities along the Weld County Road (WCR)49 Corridor Project between US 34 and 1-76, due to the WCR 49 Corridor Project relocation of existing utilities along the corridor. 6. The owner of the facility shall provide their design (structure locations, line clearances, etc.) to Public Works for review and approval to ensure their minimum structures offset from public right-of-way and have no conflicts with other utilities, current or future, traffic signals, or other future traffic control devices such as an overpass. 2016-0186 PL2383 DEVELOPMENT STANDARDS (USR15-0049) - TRI-STATE GENERATION AND TRANSMISSION, INC. PAGE 2 7. All easements acquired by Tri-State shall be non-exclusive. In areas where Tri-State co-locates in easements with other utilities, Tri-State will accommodate those utilities by locating structures to the outside of the area where the easements overlap except as otherwise approved by Public Works and such other utility. 8. Prior to landowner offers, Tri-State shall provide Public Works all right-of-way acquisition documents within 150 feet of WCR 49 ROW, or within 150 feet of any intersecting side roads for 1,000 feet. These right-of-way acquisition documents will be reviewed and approved by Public Works to ensure there are no project conflicts. 9. The owner of the facility shall utilize access as approved by Access Permit Number, AP15-00502. 10. The owner of the facility shall obtain a right-of-way permit for project construction. 11. Any temporary or construction accesses shall be approved by Public Works. The owner of the facility shall coordinate with Public Works and the County's contractor to ensure the use of any access points do not delay or disrupt the construction of WCR 49 Corridor Project. 12. The owner of the facility shall be responsible for all costs associated with relocating or elevating their lines if the line conflicts with future roadway infrastructure within 1,000 feet in any direction from WCR 49 and any intersecting side roads per approved alignment of USR15-0049. 13. The historical flow patterns and runoff amounts will be maintained on-site. 14. There shall be no parking or staging of vehicles on County Roads. On-site parking shall be utilized. 15. The owner of the facility shall be responsible for controlling the noxious weeds, pursuant to Section 15-1-180 of the Weld County Code. 16. The substation sites shall be maintained to mitigate any impacts to the public road, including damages and/or off-site tracking. 17. Weld County is not responsible for the maintenance of on-site drainage related features. 18. Access along unmaintained County right-of-way and maintenance of the right-of-way will not be the responsibility of Weld County. 19. The owner of the facility will utilize a location near the Greenhouse, Colfer, Rattlesnake Ridge and South Kersey sites for its base of operations and construction staging areas. 20. A Right-of-Way Permit will be required at each County Road crossing, along with approved signing details. 2016-0186 PL2383 DEVELOPMENT STANDARDS (USR15-0049) - TRI-STATE GENERATION AND TRANSMISSION, INC. PAGE 3 21. Construction office trailers and storage trailers and electrical services to the trailers are subject to building permits per Section 29-3-10 of the Weld County Code. 22. All liquid and solid wastes (as defined in the Solid Wastes Disposal Sites and Facilities Act, Section 30-20-100.5, C.R.S.) shall be stored and removed for final disposal in a manner that protects against surface and groundwater contamination. 23. No permanent disposal of wastes shall be permitted at this site. This is not meant to include those wastes specifically excluded from the definition of a solid waste in the Solid Wastes Disposal Sites and Facilities Act, Section 30-20-100.5, C.R.S. 24. Waste materials shall be handled, stored, and disposed of in a manner that controls fugitive dust, fugitive particulate emissions, blowing debris, and other potential nuisance conditions. The applicant shall operate in accordance with Chapter 14, Article I, of the Weld County Code. 25. Fugitive dust should attempt to be confined on the property. Uses on the property should comply with the Colorado Air Quality Commissions Air Quality Regulations. 26. Adequate toilet facilities (portable toilets) and handwashing units shall be provided during construction of the project. 27. Environmental Protection Measures for Construction Projects, as identified in the application, shall be adhered to by Tri-State Generation and Transmission and successors. 28. This facility shall adhere to the maximum permissible noise levels allowed in the Non-Specified Zone as delineated in Section 14-9-30 of the Weld County Code. 29. A Flood Hazard Development Permit is required for all construction or development occurring in the floodplain or floodway as delineated on Federal Emergency Management Agency (FEMA) FIRM Community Panel Map #08123C-1975 effective date January 20, 2016 (Box Elder Creek Floodplain). Any development shall comply with all applicable Weld County requirements, Colorado Water Conservation Board requirements as described in Rules and Regulations for Regulatory Floodplains in Colorado, and FEMA regulations and requirements as described in 44 CFR parts 59, 60, and 65. The FEMA definition of development is any man-made change to improved or unimproved real estate, including but not limited to buildings or other structures, mining, dredging, filling, grading, paving, excavation, drilling operations, or storage of equipment and materials. 30. The operation shall comply with all applicable rules and regulations of the state and federal agencies and the Weld County Code. 31. Building Permits issued on the proposed lots will be required to adhere to the fee structure of the County-Wide Road Impact Fee Program. 2016-0186 PL2383 DEVELOPMENT STANDARDS (USR15-0049) - TRI-STATE GENERATION AND TRANSMISSION, INC. PAGE 4 32. Building Permits issued on the proposed lots will be required to adhere to the fee structure of the County Facility Fee and Drainage Impact Fee Programs. 33. The owner of the facility shall be responsible for complying with the Design Standards of Section 23-2-240 of the Weld County Code. 34. The owner of the facility shall be responsible for complying with the Operation Standards of Section 23-2-250 of the Weld County Code. 35. Necessary personnel from the Weld County Departments of Planning Services, Public Works, and Public Health and Environment shall be granted access onto the property at any reasonable time in order to ensure the activities carried out on the property comply with the Conditions of Approval and Development Standards stated herein and all applicable Weld County regulations. 36. The Use by Special Review area shall be limited to the plans shown hereon and governed by the foregoing standards and all applicable Weld County regulations. Substantial changes from the plans or Development Standards as shown or stated shall require the approval of an amendment of the Permit by the Weld County Board of County Commissioners before such changes from the plans or Development Standards are permitted. Any other changes shall be filed in the office of the Department of Planning Services. 37. The owner of the facility shall be responsible for complying with all of the foregoing Development Standards. Noncompliance with any of the foregoing Development Standards may be reason for revocation of the Permit by the Board of County Commissioners. 38. RIGHT TO EXTRACT MINERAL RESOURCES STATEMENT: Weld County has some of the most abundant mineral resources, including, but not limited to, sand and gravel, oil, natural gas, and coal. Under title 34 of the Colorado Revised Statutes, minerals are vital resources because (a)the state's commercial mineral deposits are essential to the state's economy; (b) the populous counties of the state face a critical shortage of such deposits; and (c) such deposits should be extracted according to a rational plan, calculated to avoid waste of such deposits and cause the least practicable disruption of the ecology and quality of life of the citizens of the populous counties of the state. 39. The Weld County Right to Farm Statement, as it appears in Section 22-2-20.J.2 of the Weld County Code, shall be placed on the map and recognized at all times. 2016-0186 PL2383 Hello