HomeMy WebLinkAbout20161564.tiff Xcel Energy- Siting and Land Rights
1800 Larimer Street,Suite 400
PUBLIC SERVICE COMPANY Denver,Colorado 80202-4256
Telephone:303.571.7225
May 2, 2016 RECEIVED
BY CERTIFIED MAIL
Tom Parko MAY 0 9 2016
Planning Director
Weld County WELD COUNTY
1555 N 17th Ave COMMISSIONERS
Greeley CO 80631
Dear Mr. Parko,
Each year Public Service Company of Colorado ("Public Service"), an Xcel Energy Company, is
required to file a schedule of proposed new construction or extensions of electric transmission
facilities and generation facilities for the following three calendar years pursuant to Rule 3206 of
the Public Utilities Commission (PUC) Rules Regulating the Service of Electric Utilities. A copy
of the Company's 2016 Rule 3206 Report, which was filed on May 2, 2016, is enclosed for your
information.
The purpose of the report is to provide the PUC with an opportunity to determine whether or not
specific projects require a Certificate of Public Convenience and Necessity. Interested parties
may file comments with the Commission regarding any of the projects listed in the report.
Public Service is planning several new electric transmission projects in Weld County to facilitate
replacement of the existing 44 kV transmission system, improve reliability, increase the local
load serving capability, and accommodate potential generation resources.
These projects include:
1. Ault-Cloverly 115 kV line, Graham Creek and Husky substations (also known as North
Greeley Area Project). The project consists of two new substations and two new
transmission lines. One substation is planned to be located near the town of Ault and the
other planned to be located near the town of Eaton. Completion of this project is
tentatively scheduled for 2019.
2. Weld-Rosedale 230 kV transmission line, consisting of approximately 13 miles of new
230 kV transmission between the existing Weld substation and the existing Rosedale
substation.
3. Milton-Rosedale 230 kV transmission project, consisting of approximately 7 miles of new
230kV transmission between the existing Rosedale substation south of Greeley, and the
proposed Milton substation. Together the Weld-Rosedale and Milton-Rosedale Projects
are also known as the Southern Greeley Area Project.
4. The Southwest Weld Expansion Project. In 2016, Public Service expects to make a joint
filing to the Colorado Public Utilities Commission with Tri-State Generation and
Transmission Inc. to participate in their Southwest Weld Expansion Project (SWEP). The
SWEP is a plan to initiate transmission development in the region to improve reliability
and increase the capability to serve load growth in the area. Portions of the project are
planned to be located near Hudson.
Page 1 of 2
affnlinGt.elleaCOw 2016-1564
Consistent with the requirements of § 29-20-108 (4)(a), C.R.S., this letter constitutes notice to
you of Public Service's intent to begin sometime during the next three calendar years the work
that will lead to the construction of these electric transmission facilities.
If they haven't already, Public Service representatives will be contacting you to discuss these
projects in more detail and to determine all applicable permits that may be required prior to
beginning construction at the facilities. Please feel free to contact me at 303-571-7225 if you
have any questions or require additional information regarding any of the projects identified in
the enclosed Rule 3206 Report.
Sincerely,
Susan Innis
Manager, Siting and Land Rights
Attachment
cc:
Michelle Martin Planning Manager
Kim Ogle Planner
Mike Freeman County Commissioner District 1
Julie Cozad County Commissioner District 2
Barbara County Commissioner District 3
Kirkmeyer
Sean Conway County Commissioner At-Large
Steve Moreno County Commissioner At-Large
Page 2 of 2
Xcel EnergysM
PUBLIC SERVICE COMPANY
RULE 3206 REPORT
PROPOSED CONSTRUCTION OR
EXTENSION OF TRANSMISSION
FACILITIES
2017 THROUGH 2019
Proceeding No. 16M-0039E
May 2, 2016
INDEX
ITEMS PAGE
A. NEW PROJECTS THAT MAY REQUIRE A CPCN 2
SOUTHWEST WELD EXPANSION PROJECT PARTICIPATION 3
AULT- CLOVERLY 230/115 KV TRANSMISSION 6
WELD - ROSEDALE 230 KV LINE 9
ROSEDALE - MILTON 230 KV LINE 12
RUSH CREEK - MISSILE SITE TRANSMISSION 15
B. NEW PROJECTS OF 230 KV AND ABOVE THAT THE COMPANY
WOULD REQUEST THE COMMISSION TO DETERMINE THAT A CPCN
IS NOT REQUIRED 19
WOLCOTT 40 MVAR 230 KV SHUNT REACTOR 18
C. NEW PROJECTS THE COMPANY CONSIDERS TO BE IN THE
ORDINARY COURSE OF BUSINESS PURSUANT TO RULE 3206(B)(I)
OR (II) AND FOR WHICH THE UTILITY IS REQUESTING THE
COMMISSION FIND TO BE IN THE ORDINARY COURSE OF
BUSINESS
NONE
D. STATUS OF PROJECTS LISTED IN PRIOR REPORTS 21
2
Public Service Company of Colorado
Transmission Construction Project
Name of the project:
Southwest Weld Expansion Project Participation
Project description:
In 2016, Public Service expects to make a joint filing with Tri-State
Generation and Transmission Inc. (Tri-State) to participate in their
Southwest Weld Expansion Project (SWEP). The Commission granted
Tri-State a CPCN in Proceeding No. 14A-0896E and Proceeding 15A-
0728E, Decision Nos. C14-1482 and C15-1135 respectively. The joint
filing would seek to amend the Tri-State CPCN to include the Public
Service participation in the project. The SWEP is a plan to initiate
transmission development in the region to improve reliability and increase
the capability to serve load growth in the area. The objectives of
participation for Public Service are to provide service for its own customer
load growth, align with plans to replace the 44 kV transmission system in
and around Greeley, and accommodate new generation resources. The
SWEP consists of 230 kV and 115 kV transmission that begins near Ft.
Lupton, Colorado, travels east towards Colfer, and then heads north and
ultimately connects to the existing transmission a few miles south of
Kersey. The project also includes a 230 kV line between Ft. Lupton and
Henry Lake substations. Public Service and Tri-State executed an
agreement to cooperate in SWEP in November 2014, which provides for
Public Service ownership rights for up to 40% of the project. Refer to
Attachment A, Exhibit—H from the Tri-State CPCN application filing, for the
one-line diagram of this project.
Estimated cost of the project:
$27 million (Transmission dollars — Public Service share only)
Manner in which the project is expected to be financed:
Public Service capital budget for Public Service's share of the project
Projected date for the start of construction of the project:
Under Construction by Tri-State
3
Estimated date of completion of the project:
December 2018
Estimated in-service date of the project:
December 2018
Proposed general location:
The project will be located in Weld County, Colorado.
Prudent avoidance measures being evaluated for transmission facilities:
The proposed project will be built to meet all prudent avoidance
requirements for noise and magnetic fields.
4
Attachment A
6
W R
iu
w R
t4
rn
o ,
vi
n
d o
Z h o v
y0
y 8 v
CA O
m a ! W
_ ^ o i v)
0
0
I� U > i w
W ^a > i
la. 0 •w ZO v .._.._..7 o p.n m " A , -II
I .
I v v• x z
1 I - o to
w
' I �v
i
Y
co m n
W
cc
z Z W
0
4
a
Southwest Weld Expansion Project
5
Public Service Company of Colorado
Transmission Construction Project
Name of the project:
Ault— Cloverly 230/115 kV Transmission
Project description:
This project consists of constructing approximately 20 miles of new
transmission in northeast Colorado, north of the City of Greeley. The
transmission will originate from the existing Western Area Power
Administration (Western) Ault Substation and terminate at a new Public
Service Cloverly Substation, on the northeast edge of Greeley. The
transmission will also interconnect with two other new substations. The
first substation is referred to as "Husky", and is planned to be built near
the existing Public Service Ault 44 kV Substation. The second substation
is referred to as "Graham Creek" and is planned to be built near the
existing Public Service Eaton 44 kV Substation. The Cloverly Substation
will replace the existing Pleasant Valley Substation. Previous documents
have referred to the Husky Substation as "New Ault", and the Graham
Creek Substation as "New Eaton". The approximately six mile
transmission between Ault and Husky will be constructed to allow future
double-circuit capability, but will initially be operated as a single-circuit 230
kV line. The approximately 14 mile transmission between the Husky and
Graham Creek substations will be built to allow for future double-circuit
230 kV operation, but will initially be operated as a single-circuit at 115 kV
line. The primary purpose of this project is to replace the existing
antiquated 44 kV system in the area with higher voltage transmission.
The project will improve reliability, and also increase load-serving
capability and allow for future resource accommodation in the area. Refer
to Attachment B for the orientation map of this project.
Estimated cost of the project:
$62 million (Transmission dollars)
Manner in which the project is expected to be financed:
Public Service capital budget
Projected date for the start of construction of the project:
2018
6
•
Estimated date of completion of the project:
June 2020
Estimated in-service date of the project:
June 2020
Proposed general location:
The project will be located in Weld County, Colorado. The project area
shown in Attachment B is the general geographical area within which
alternative transmission corridors could potentially be identified. The
ultimate study area to be analyzed for potential routes could be larger or
smaller than the area shown in this map.
Prudent avoidance measures being evaluated for transmission facilities:
The proposed project will be built to meet all prudent avoidance
requirements for noise and magnetic fields.
7
Attachment B
ULT
' Husky Substation
Q ULT
(4"kV)
_ x.e
r.
t•to
Ault-Cloverly
115kV Line,
__.. c,,.,e ){'ELD e
-. — COUNT)" -
E ,ToN
Is
3
cti
Cloverly
- '-'' -1 Graham Creek' e' - Substation
Substation L+EAS.NT
VALLEY
1----------.... NC,'
u _ o^..ssp,
[U si
Wes _
•
N s
Legend a
SI
tw,
E Substation A wwww
-^^^-44kV OH Electric Transmission Line i _
—230kV OH Electric Transmission Line -
e 33 sms
—115kV OH Electric Transmission Line "_, n,_s_ S•urces Esri,geLottne,NAV'iEQ...JSGS;Intermap,in,NRCAN,Esri
......,<,wi -- - - "'°.Japan,METI,;Esri China(Hong Kong),Esri(Thailand),TomTom,2012
Approximate location of the Ault— Cloverly 115 kV Transmission Project
8
Public Service Company of Colorado
Transmission Construction Project
Name of the project:
Weld — Rosedale 230 kV Line
Project description:
This project consists of approximately 13 miles of new 230 kV
transmission between the existing Public Service Weld Substation and the
existing Public Service Rosedale Substation. The Rosedale Substation
will be upgraded to accommodate 230 kV line termination and a 230/115
kV, 280 MVA transformer. This project, along with the Rosedale — Milton
230 kV project will allow Public Service to improve its ability to serve new
loads in the region, particularly those associated with future oil and gas
development. The project aligns with plans to replace the existing 44 kV
transmission system, and will improve reliability by alleviating potential
overloads. The project not only improves load-serving capability, but also
allows for future resource accommodation. Refer to Attachment C for the
orientation map of this project.
Estimated cost of the project:
$43 million (Transmission dollars)
Manner in which the project is expected to be financed:
Public Service capital budget
Projected date for the start of construction of the project:
March 2019
Estimated date of completion of the project:
June 2022
Estimated in-service date of the project:
June 2022
9
Proposed general location:
The project will be located in Weld County, Colorado. The project area
shown in Attachment C is the general geographical area within which
alternative transmission corridors could potentially be identified. The
ultimate study area to be analyzed for potential routes could be larger or
smaller than the area shown in this map.
Prudent avoidance measures being evaluated for transmission facilities:
The proposed project will be built to meet all prudent avoidance
requirements for noise and magnetic fields.
10
Attachment C
p t 2 s
A.S. �� o
.4f.
wu=
a i
VI.,1 at.
CR o-4 3
I WELD
Weld - m
4M 1, EaU,3.
Rosedale , =
230kV 'Line
- um at um St
.. hxiu si x]usr-
...»._._.tom •,� \, *3:ne _ .aau
�r,---' •0SEo0t7LEe~. Q,
,t WELD.. _,e.a;, - . ,...
4.fi lim I.
y..
> c
rite y s
e
t L.
n.
.. e
Ncrest
Legend
E Substation
---^44kV OH Electric Transmission Line
—230kV OH Electric Transmission Line
-115kV OH Electric Transmission Line =
I Sources:Esri,DeLorme,NAVTEQ,USGS,Intermap,iPC,NRCAN,Esri
Japan,METI,Esri China(Hong Kong),Esri(Thailand),TomTom,2012
Approximate location of the Weld — Rosedale 230 kV Line Project
11
Public Service Company of Colorado
Transmission Construction Project
Name of the project:
Milton - Rosedale 230 kV Transmission
Project description:
This project consists of building approximately 7 miles of new 230 kV
transmission between the Public Service Rosedale Substation, south of
Greeley, and the proposed Milton Substation, which is a northern terminus
for the Southeast Weld Expansion Project (SWEP). This project along
with the Weld — Rosedale 230 kV Line project (included in this report) will
facilitate replacement of the existing Greeley 44 kV transmission system,
improve reliability, increase the local load serving capability, and
accommodate potential generation resources.
Refer to Attachment D for the orientation map of this project.
Estimated cost of the project:
$19 million (Transmission dollars)
Manner in which the project is expected to be financed:
Public Service capital budget
Projected date for the start of construction of the project:
June 2019
Estimated date of completion of the project:
December 2022
Estimated in-service date of the project:
December 2022
12
Proposed general location:
The project will be located in Weld County, Colorado. The project area
shown in Attachment D is the general geographical area within which
alternative transmission corridors could potentially be identified. The
ultimate study area to be analyzed for potential routes could be larger or
smaller than the area shown in this map.
Prudent avoidance measures being evaluated for transmission facilities:
The proposed project will be built to meet all prudent avoidance
requirements for noise and magnetic fields.
13
Attachment D
d 20th Se a t I e2oe,so
d
c+Y ',..:,k,,,,d,
i I.,
E21;Ie SF - rc i'.
u � _rs.c•'
of
ROSEDALE
2 Kersey..
j
Evans Couaty.Roa454. �._... .....
421,451 Jl/
v
i- 1- '''''' Milton - Rosedale t
230kV Line and
>� 2M,y Milton Substation
f
e
Todd Ave County Road 59.
i 716,er L+ Cf?-59
-(r_.:6
a
c
ccc Coun 1 Road 40 ..... CR-At
2
f
K
2
ounty Rood 40_. a CR44
v T
V
U
J
e 44- ...._. )f vratni -_..-.- _ an ii _.....
m
c.,,,,,,,,Rcsdl2. _...CF :Mv;..,-.@nell7-Rlaa CF
V
El
_ County Road 40 ... s _ CO.. .........
V
9
Legend N
,, E Substation A cR,a
—^pa44kV OH Electric Transmission Line 1
. 115kV OH Electric Transmission Line Sources:Esri,DeLorme,NAVTEO,USGS,Intermap,iPC,NRCAN,Esri
-- ' . --"-•-'• ----^ � - Japan,METI,Esri China(Hong Kong),Esri(Thailand),TomTom,2012
Approximate location of the Milton — Rosedale 230 kV Transmission
project
14
Public Service Company of Colorado
Transmission Construction Project
Name of the project:
Rush Creek - Missile Site 345 kV Transmission
Project description:
The recommended project consists of constructing the following new
transmission facilities to enable the interconnection of proposed Rush
Creek 1 (400 MW) and Rush Creek 2 (200 MW) wind generating facilities:
1. Approximately forty miles of 345 kV transmission between the
Missile Site Substation and a new Rush Creek 1 345 kV Switching
Station.
2. Approximately fifty miles of 345 kV transmission between Rush
Creek 1 and Rush Creek 2 facilities.
3. A new Rush Creek 1 345 kV Switching Station
This project is required to interconnect the new 600 MW wind injection as
part of the Public Service Rule 3660(h) filing. Refer to Attachment E for
the orientation map of this project.
In the alternative, the Company could construct the Rush Creek — Missile
Site Gen-Tie at 230 kV.
Estimated cost of the project:
$121.4 million
Manner in which the project is expected to be financed:
Public Service capital budget
Projected date for the start of construction of the project:
2017
Estimated date of completion of the project:
December 2018
15
Estimated in-service date of the project:
December 2018
Proposed general location:
The project will be located in Arapahoe, Elbert, and Lincoln counties in
Colorado. The project area shown in Attachment E is the general
geographical area within which alternative transmission corridors could
potentially be identified.
Prudent avoidance measures being evaluated for transmission facilities:
The proposed project will be built to meet all prudent avoidance
requirements for noise and magnetic fields.
16
Attachment E
WELD f MORGAN I
COUNTY COUNTY
JO
Rush Creek GenTie - Missile Site
345kV Line
ADAMS
E aem Age COUVT-Y f zo
,rgndale Rd a ,1 WASHINGTON
2; COUNTY
62
.0 I. dY5a 142===-= 6. Anton
-.!=r6,6=6.,.. .4-1-6.6,142====111.6./�,p
St burg _ _ — �--^
x CUUL7'
�''` AR4�P4HOE
COUNTY
/ ..r Trail
rw
` 117 I
i
28
gale : - I
I
a
Rush Creek r`
Switching Station
I Fl.
,..,An lb
5 ��Iea ..-' x.' RIT CARSON+.
ELBERT �' — °° �� GO.UNTY
COUNTY
i,
105 "„.-.
a
Matheson 2..6 I :. „�
1 LINCOLN
�P 69 , COUNTY
Cal -
1. ,g7 l �,� al
Judge Orr Rd I
r
7 t I
I. ,
\
I 1 \
ElPASO I C \.. I
COUNTY '-------- - — --- --' CHEYENNE
R A'
g, COUNTY
I
Legend N 24 i
Q Substation N I' 1.
-345kVOH Electric Transmission Line P1 ;,r,va jl:
-230kV OH Electric Transmission Line 1 i.
Sources:Esri,DeLorme,NAVTEQ,USG5,Intermap,IPC,NRCAN,Esri
--- - - - ' -' -• a. Japan,METI,Esri China(Hong Kong),Esri(Thailand),TomTom,2012
Approximate Location of the Rush Creek— Missile Site 345 kV Transmission
project
17
Public Service Company of Colorado
Transmission Construction Project
Name of the project:
Wolcott 40 MVAR 230 kV Shunt Reactor
Project description:
The project consists of installing 40 MVAR (two steps of 20 MVAR) shunt
reactors on the 230 kV bus of the Wolcott Substation. This project
replaces the Foidel Creek Shunt Reactor project approved in Colorado
PUC Proceeding No. 15M-0043E, Decision No. C15-0590. Based on
additional analyses, the location of the reactor will be moved to the
existing Wolcott Substation, south of Foidel Creek. The purpose of the
project is to improve voltage performance in the region.
Refer to Attachment F for the orientation map of the proposed project.
Justification for Requesting Normal Course of Business:
This project is needed to improve voltage issues in the region. The shunt
reactors will be located inside the existing Public Service Wolcott
Substation.
Estimated cost of the project:
$6.2 million
Manner in which the project is expected to be financed:
Public Service capital budget
Projected date for the start of construction of the project:
September 2016
Estimated date of completion of the project:
May 2017
Estimated in-service date of the project:
May 2017
18
Proposed general location:
The proposed project will be located inside the existing Wolcott Substation
in Eagle County, Colorado.
Prudent avoidance measures being evaluated for transmission facilities:
No new transmission lines are required. No prudent avoidance measures
are required.
19
Attachment F
13 1
lablot
_ Ac'• 72
EAGLE
COUNTY
e Wolcott 40MVAR 230kV
Shunt Reactor End
i
E.Agt
Legend N
El Substation A
—230kV OH Electric Transmission Line
—115kV OH Electric Transmission Line Sources:Esri,DeLorme,NAVTEQ,USGS,Intermap,iPC,NRCAN,Esri
..u,...:- - ...e�a„F..... --• _ - _ - Japan,METI,Esri China(Hong Kong),Esri(Thailand),TomTom,2012
Approximate Location of the Wolcott 40 MVAR Shunt Reactor Project
20
STATUS OF PROJECTS LISTED IN PRIOR REPORTS
(The project costs reported in the following table are
Transmission dollars only)
21
Change in
Item# Project Name Status? Reason For Change
Projects in-service in 2015
1 Rosedale 115 kV Line Tap Yes Completed
(WAPA)
2 Beaver Creek— Brush 115 kV Yes Completed
Reconductor Project
3 Leetsdale 230/115 kV, 280 MVA Yes Completed
#2
4 Malta 230/115 kV, 100 MVA#2 Yes Completed
5 Mt. Harris 138/69 kV, 50 MVA #2 Yes Completed
6 Russell 230/13.8 kV, 50 MVA# 1 Yes Completed
Replacement
22
Change
in
Item# Project Name Status? Reason For Change
2016 ISD Projects
7 Arvada 230/13.8 kV, 50 MVA# Yes In-service date of Bank #1 changed
1&2 Replacement from 6/2016 to 12/2016 due to
construction schedule. Bank #2
replacement is completed. No
CPCN is required for this project
pursuant to Decision No.C13-1075,
Proceeding No.13M-0019E. Project
cost for bank#1  is $2 million.
8 Weld 230/115 kV, 150 MVA Yes In-service date changed from
Transformer Replacement and 11/2015 to 5/2016 due to outage
Substation Upgrade restrictions. No CPCN is required
for this project pursuant to Decision
No. C11-0927, Proceeding No.
11M-317E. Project cost is $10
million.
9 Federal Heights 115/13.8 kV, No Scheduled for in-service 7/2016. No
50 MVA#3 CPCN is required for this project
pursuant to Decision No. C11-0749,
Proceeding No. 11M-317E. Project
cost is $1.1 million.
10 Rifle-Parachute 230 kV Line#2 No Scheduled for in-service 12/2016. A
CPCN for this project was granted
in Decision No. C13-0256,
Proceeding No. 13A-00032E.
Project cost is $28.5 million.
11 Happy Canyon 115 kV (IREA No Scheduled for in-service 12/2016.
load service, 115/12A7 kV, 50 No CPCN is required for this project
MVA) pursuant to Decision No. C06-0761,
Case No. 6396. Project cost is $3
million.
23
Change
in
Item# Project Name Status? Reason For Change
12 Cherokee —Arvada — Russell — Yes In-service date changed from
Ridge 230 kV Line Conversion 6/2016 to 12/2016 due to
construction schedules. No CPCN
is required for this project pursuant
to Decision No. C13-0879,
Proceeding No. 13M-0019E. Project
cost is $4.7 million.
13 Sheridan 115/13.8 kV, 50 Yes In-service date changed from
MVA#2 2/2016 to 6/2016 due to the time
required for construction. No CPCN
is required for this project per
Decision No. C12-0777, Proceeding
No. 12M-165E. Project cost is $0.27
million.
14 Grand Junction 138/115 kV, 50 No Scheduled for in-service 6/2016. No
MVA Transformer CPCN is required for this project
Replacement Project pursuant to Decision No. C14-0732,
Proceeding No. 14M-0061E.
Project cost is $8 million.
15 North 115/13.8 kV, 50 MVA# 3 No Scheduled for in-service 6/2016. No
Transformer CPCN is required for this project
pursuant to Decision No. C14-0732,
Proceeding No. 14M-0061E. Project
cost is $0.8 million.
16 Palmer Lake 115 kV, 26.5 ohm, Yes Project cancelled after considering
800 Amp Series Reactor alternative mitigation measures.
2017 ISD Projects
17 Littleton 115/13.8 kV, 50 MVA No Scheduled for in-service 6/2017. No
# 3 Distribution Project CPCN is required for this project
pursuant to Decision No. C14-0732,
Proceeding No. 14M-0061E. Project
cost is $1 million.
24
Change
in
Item# Project Name Status? Reason For Change
18 Foidel Creek 25 MVAR, 230 Yes Project replaced by "Wolcott 40
kV Shunt Reactor MVAR Shunt Reactor" project filed
under "Normal Course of Business"
projects in this report
19 Sullivan 230/13.8 kV, 50 MVA No Scheduled for in-service 6/2017. No
# 3 Distribution Project CPCN is required for this project
pursuant to Decision No. C14-0732,
Proceeding No. 14M-0061E. Project
cost is $1.2 million.
20 Moon Gulch 230/13.8 kV, 50 Yes In-service date changed from
MVA Distribution Substation 6/2018 to 12/2017 due to
accelerated load growth in the area.
A CPCN was granted for this project
in Decision No. C16-0054,
Proceeding No. 15A-0929E. Project
cost is $1.9 million. Project cost
decreased because the new site
location closer to the line being
tapped.
2018 ISD Projects
21 Thornton Distribution Yes In-service date changed from 2017
Substation to 6/2018 due to permitting issues.
A CPCN for this project was granted
in Decision No. C15-0473,
Proceeding No. 14A-1002E. Project
cost is $18.6 million.
22 Bluestone Valley 230 kV Yes New in-service is 6/2018. No CPCN
Substation and De Beque- is required for this project pursuant
Bluestone Valley 69 kV Line to Decision No. C09-0681,
Proceeding No. 09M-392E. Project
cost for the 69 kV is $7.2 million.
Detailed project description is
included in Attachment G.
23 Avery 230/13.8 kV, 28 MVA No Scheduled for in-service 5/2017. A
Distribution Substation CPCN was granted for this project
in Decision No. C15-0461,
25
Change
in
Item# Project Name Status? Reason For Change
Proceeding No. 15A-0159E. Project
cost is $8.1 million.
2019 ISO Projects
24 Pawnee- Daniels Park 345 kV Yes In coordination with the Rule
Transmission Line Project and 3660(h) filing, Public Service is filing
Harvest Mile 230/345 kV a petition to move the in-service for
Substation this project to 2019 from 2022. A
CPCN was granted for this project
in Decision No. C15-0316,
Proceeding No. 14A-0287E. Project
cost is $178.3 million.
2020 ISO Projects
2021 ISD Projects
25 Avon — Gilman 115 kV Line Yes In-service date changed from
and 45 MVAR Capacitor Bank 6/2019 to 2021 delays in land
at Vail Substation acquisition. No CPCN is required
for this project pursuant to Decision
No. C15-0590, Proceeding No.
15M-0043E. Project cost is $22.9
million.
26 Barker Substation (Distribution, No Scheduled for in-service in 12/2021.
230/13.8 kV, 50 MVA) No CPCN is required for this project
pursuant to Decision No. C10-0644,
Proceeding No. 10M-206E. Project
cost is $18.1 million.
2022 ISO Projects
None
26
Change
in
Item# Project Name Status? Reason For Change
ISD To Be Determined
27 Foidel Creek 230 kV Line Tap Yes Project is delayed. A CPCN is
required for this project pursuant to
Decision No. C13-0879, Proceeding
No.13M-0019E. Detailed project
cost estimates will be performed
during the CPCN filing.
28 Wilson#1 Sub (Distribution, Yes Project delayed due to slower load
115/13.8 kV, 14 MVA) growth. No CPCN is required for
this project pursuant to Decision No.
C10-0644, Proceeding No. 10M-
206E. Project cost is $3.5 million in
2015 dollars.
29 Monfort 15MVAR, 44 kV Yes Project delayed as long term
Capacitor Banks alternatives are being studied. No
CPCN is required for this project
pursuant to Decision No.C13-0879,
Proceeding No. 13M-0019E.
Project cost is $1.29 million in 2011
dollars.
30 Vasquez 115/13.8 kV, 28 MVA Yes Project delayed due to slower load
# 2 Transformer growth. No CPCN is required for
this project pursuant to Decision No.
C15-0590, Proceeding No. 15M-
0043E. Project cost is $0.34 million
in 2015 dollars.
31 New Castle 115/69-24.9 kV Yes Project delayed due to slower load
Substation (Distribution, 16 growth. No CPCN is required for
MVA) this project pursuant to Decision No.
C08-0676, Case No. 6396. Project
cost is $1.43 million in 2015 dollars.
27
Change
in
Item# Project Name Status? Reason For Change
32 Wheeler-Wolf Ranch 230 kV No Project delayed due to slower load
Transmission Project growth. No CPCN is required for
this project per Decision No. C14-
0732 and Proceeding No.14M-
0061E. Project cost is $17 million in
2015 dollars.
33 Parachute - Cameo 230 kV No Project delayed due to slower load
Transmission Line growth. A CPCN is required for this
project pursuant to Decision No.
C10-0644 in Proceeding No. 10M-
206E. Project cost is $48.1 million in
2010 dollars.
34 Lamar- Front Range 345 kV No Planning studies have been
Transmission Line Project completed and project study reports
are available. No decisions have
been made with respect to project
implementation. A CPCN is
required for this project pursuant to
Decision No. C10-0644, Proceeding
No. 10M-206E.
35 Lamar- Vilas 230/345 kV No See Lamar— Front Range (item#34
Transmission Line Project above).
36 Weld County Transmission No No specific transmission project has
Expansion Project been identified at this time. It is
(Prior versions: TOT7 expected that a CPCN will be
Expansion Project &Ault— required based on the decision
Cherokee Project) regarding the previously reported
Ault — Cherokee Project (Decision
No. C10-0644, Proceeding No.
10M-206E). Project cost has not
been determined.
28
Change
in
Item# Project Name Status? Reason For Change
37 Rifle(Ute)-Story Gulch 230 kV No Delayed due to slower load growth.
Transmission Line Project A CPCN is required for this project
pursuant to Decision No. C10-0644,
Proceeding No. 10M-206E. Project
cost is $24 million in 2010 dollars.
38 Glenwood Springs — Rifle Yes Project delayed due to slower load
69/115 kV Conversion growth. Project cost will be
estimated when an in-service date
is determined.
29
Attachment G
Bluestone Valley Project Scope Update (item # 22 in Status of Projects
Listed in Prior Reports)
The original scope of this project consisted of a new Bluestone Valley 230/69 kV
Substation. The substation would include a 230/69 kV transformer and would
interconnect the existing Parachute - Cameo 230 kV line and the existing
DeBeque - Cameo 69 kV line. From Bluestone Valley Substation, a new line
would be constructed to a new Grand Valley Power Clear Creek Substation.
Public Service has now split this project into two phases: A 69 kV phase and a
230 kV phase of the project. Public Service intends to move forward with the 69
kV portion of the project now. The 230 kV phase may be constructed at a later
time based on local load growth.
The current plan is to construct a new Bluestone Valley 69 kV Switching Station
with associated 69 kV buswork, switches and circuit breaker. The switching
station will connect to the existing DeBeque - Cameo 69 kV line by way of a 1.4
mile, in-and-out 69 kV double circuit line. The 69 kV double circuit line will likely
use single 477 kcmil ACSR conductor. The project will result in a DeBeque -
Bluestone Valley - Cameo 69 kV line. The purpose of the project is to improve
the reliability of the local 69 kV transmission system.
This phase of the project is estimated to cost approximately $7.2 million dollars.
The proposed project will be located near the Town of DeBeque in Mesa County
in northwest Colorado. The expected in-service date is June, 2018.
The Bluestone Valley Substation project was originally reported in the 2009 Rule
3206 filing. The 2009 filing listed the project as a new 230 kV substation that
would interconnect the Rifle (Parachute) — Cameo 230 kV line. The Commission
determined that no CPCN was required in Decision No. C09-0681, Proceeding
No. 09M-392E. In 2013, Public Service modified the scope to include the 69 kV
portion of the project.
30