HomeMy WebLinkAbout20172569.tiffRESOLUTION
RE: EXTENSION OF REGULATING, WARNING AND GUIDING TRAFFIC DURING THE
TEMPORARY CLOSURE OF COUNTY ROAD 69 BETWEEN COUNTY ROADS 74 AND
80 FOR AN ADDITIONAL EIGHT (8) DAYS, FOR UNANTICIPATED DELAYS DUE TO
CONTRACTOR REQUESTING ADDITIONAL TIME
WHEREAS, the Board of County Commissioners of Weld County, Colorado, pursuant to
Colorado statute and the Weld County Home Rule Charter, is vested with the authority of
administering the affairs of Weld County, Colorado, and
WHEREAS, pursuant to Section 42-4-106(6)(a), C.R.S.:
"...local authorities, with their respective jurisdiction may, for the
purpose of road construction and maintenance, temporarily close to
through traffic or to all vehicular traffic any highway or portion
thereof for a period not to exceed a specified number of work days
for project completion and shall, in conjunction with any such road
closure establish appropriate detours or provide for an alternative
routing of the traffic affected...", and
WHEREAS, the Board, pursuant to said statute and upon the basis of traffic and personal
investigations, has determined that conditions exist which make it necessary to temporarily close
said County Roads to through traffic and to regulate, warn and guide vehicular traffic by posting
signs thereon.
NOW, THEREFORE, BE IT RESOLVED that the Board of County Commissioners of Weld
County, Colorado, deems it necessary to regulate, warn and guide vehicular traffic on County
roads and any intersections thereof, and it hereby authorizes and orders the posting of such traffic
control devices as shall be reasonably necessary to regulate, warn and/or guide traffic thereon
for the safety of the general public and that said traffic control devices shall conform to the Federal
Manual on Uniform Traffic Control Devices.
BE IT FURTHER RESOLVED that the Board of County Commissioners of Weld County,
Colorado, does declare and establish that County Road 69, between County Roads 74 and 80,
be extended, with said extended closure being effective July 21, 2017, for an additional eight (8)
days through July 28, 2017, for unanticipated delays due to the contractor requesting additional
time, and further, that standard official traffic control devices shall be erected at said closure giving
notice of the restrictions.
cc , 5o c RS), O
Co S+o.te PAtco�
g/ico/11
2017-2569
EG0024
TEMPORARY CLOSURE - COUNTY ROAD 69
PAGE 2
The above and foregoing Resolution was, on motion duly made and seconded, adopted
by the following vote on the 24th day of July, A.D., 2017, nunc pro tunc July 21, 2017.
BOARD OF COUNTY COMMISSIONERS
WELD COUNTY, COLORADO
ATTEST: dulititelti jeigo•vi
Weld County Clerk to the Board
BY
uty Clerk to the Board
APP' • ' D A
oun y Attorney
Date of signature: IS
EXCUSED
Julie A. Cozad, Chair
Steve Moreno, Pro -Tern
Sean P. Conway
ike Freeman
arbara Kirkmeyer
2017-2569
EG0024
MEMORANDUM
TO: Clerk to the Board DATE: July 18, 2017
FROM: Janet Lundquist, Public Works Department
SUBJECT: BOCC Agenda Item
CR 69 between CR 74 to CR 80 was scheduled to be closed to thru traffic from 7/12/17 to
7/21/17 to install two drainage pipes and earthwork near the CR 74 & SH 392 project. The
contractor has requested an extension till 7/28/17.
See attached diagram.
C Csersy Iundquist\DesktopWBenda Road Closures - I docx
2017-2569
-71,94
66,007V
ICRTIIEMCCIOWN, TN{4. (M'raR PC
MHT M9 CR 69 CLOSURE & DETOUR
NORTH OF CR 74
7/6/2017
Min
I, ** s� La ears satraeu'—l-I lia it roc
N r
▪ ann. Fooymo.o.
si• gqun�io'a..
Cu •.�M—'e.w..:voiA
11.0.1.01.98tw ...a ou W anweia
waxen
onsairrncea c mass et le as. le R.N • M
▪ OW *Andel KLL
{N.. caleerOMI
K10it Cnanimum s �wNLR•
Nam w_s1 »���tilale
•. OMM:Opi flit 114
o.m, ok OOlltl
1 9Y04Oyp
.9.l.O C IOIaY 1 RWq
LOCALAM/CC OM.
I. R'OOI ARMIN MWI
I. Ceittt t Heil
•.0•OJlyy%p py11
N.t'out 111
I lq *rout
•
HOR1HdN COLORADO
TRAFFIC CONTROL. He0.Ley'
Lat : - N� F.R<.R 64.•\_40
n•aa
raa•a NIT Re
�NCTC•tReF MALT
Hello