HomeMy WebLinkAbout20181555.tiffRESOLUTION
RE: APPROVE CONSTRUCTION AGREEMENT FOR GOVERNMENTAL ENTITIES AND
AUTHORIZE CHAIR TO SIGN - PUBLIC SERVICE COMPANY OF COLORADO, DBA
XCEL ENERGY
WHEREAS, the Board of County Commissioners of Weld County, Colorado, pursuant to
Colorado statute and the Weld County Home Rule Charter, is vested with the authority of
administering the affairs of Weld County, Colorado, and
WHEREAS, the Board has been presented with a Construction Agreement for
Governmental Entities between the County of Weld, State of Colorado, by and through the Board
of County Commissioners of Weld County, on behalf of the Department of Public Works, and
Public Service Company of Colorado, dba Xcel Energy, commencing May 14, 2018, and ending
upon completion of the project, or December 31, 2018, whichever is sooner, with further terms
and conditions being as stated in said agreement, and
WHEREAS, after review, the Board deems it advisable to approve said agreement, a copy
of which is attached hereto and incorporated herein by reference.
NOW, THEREFORE, BE IT RESOLVED by the Board of County Commissioners of Weld
County, Colorado, that the Construction Agreement for Governmental Entities between the
County of Weld, State of Colorado, by and through the Board of County Commissioners of Weld
County, on behalf of the Department of Public Works, and Public Service Company of Colorado,
dba Xcel Energy, be, and hereby is, approved.
BE IT FURTHER RESOLVED by the Board that the Chair be, and hereby is, authorized
to sign said agreement.
The above and foregoing Resolution was, on motion duly made and seconded, adopted
by the following vote on the 14th day of May, A.D., 2018.
BOARD OF COUNTY COMMISSIONERS
WELC)-OUNTY, COLORADO
ATTEST: deetifeti G:.xsto•ci
Weld County Clerk to the Board
BY:
Deputy Clerk to the
APPRO = D AS
ounty attorney
Date of signature: Of,-o`1-i?
Mike Freeman
Stele Moreno, Chair,
rbara Kirkmeyer,ro-Tem
Sean P. Conway
Cozad
PW (TmIER),
CA(BE3 PFff/BC)
047-08- 19
2018-1555
EG0075
Esther Gesick
From:
Sent:
To:
Cc:
Subject:
Attachments:
Frank Haug
Thursday, May 10, 2018 3:08 PM
Commissioners
Bruce Barker; Jay McDonald; Esther Gesick
Agenda item for Monday -XCEL upgrade of transformer for CNG site
Xcel Energy Customer Information Packet - 1113 H ST GREELEY CO.PDF
Commissioners, we would like to put an agenda item on for Monday, which is attached. It is an agreement with Xcel for
$15,375.04 to upgrade a transformer and the electric service to the CNG site. We are not wanting to interrupt the
project, which is why I am sending this email rather than a pass around. This is within budget. While it says that the cost
is $0. It is in fact the $15K, they just state that it is $0 up front and they will bill us later since we are an existing
customer. Please let me know if you want any more information or to handle the situation differently, thanks.
2018-1555
1 E.C7oo'7 5
Account No.
Job No. 10227579
Job Address 1113 H ST
GREELEY, CO 80631-9147
Xcel Energy'
Public Service Company of Colorado
5245 Ronald Reagan Blvd Suite 104
Johnstown, CO 80534
May 3, 2018
Dear Weld County Public Works Dept,
Thank you for choosing Xcel Energy to be your energy provider. We appreciate your business, and our goal is to
deliver you reliable service at an affordable price.
This letter contains important information about your requested service. Please read all details below as
well as any accompanying information and respond accordingly to ensure your project is completed
accurately and timely.
This letter relates to your request for
➢ Electric Rebuild
Your portion of the cost of this project is $0.00. A hard copy invoice will be sent to you via U.S. Mail Postal
Service in the coming days. Please see the attached payment options document for more instructions. Upon
receipt of payment and other required documentation as noted below, your project will be scheduled and you will
be notified of the scheduled date. If paying by check, please note the account number identified at the top of this
letter on your check to ensure accurate and timely payment processing.
Below is a list of additional documentation that you will need to review, sign, and return to Xcel Energy by email or
U.S. Postal Service to the address listed at the bottom of the letter. Please retain a copy of all documentation for
your records.
• Documents to be returned to Xcel Energy:
❑ Construction Agreement For Governmental Entities
❑ Frost Agreement
❑ Contingency List
➢ Additional enclosures:
o Concurrence Drawings
If you have any questions about the enclosures or about your specific job, please contact Yarani Vazquez at 970-
622-2909 and reference your account number and/or job number above.
We look forward to being your energy provider.
Sincerely,
Yarani Vazquez
CONTRACTOR*PROF/CONSULTANT
5245 Ronald Reagan Blvd Suite 104
Johnstown, CO 80534
UC Synergetic
Yarani.M.Vazquez@xcelenergy.com
/10,
Xcel Energy:
CONSTRUCTION AGREEMENT FOR GOVERNMENTAL ENTITIES
CONTRACT NO. 10227579
This Construction Agreement for Governmental Entities, "Construction Agreement", is between Public
Service Company of Colorado, a Colorado corporation, d.b.a. XCEL ENERGY, hereinafter referred to as
"Company" and WELD COUNTY PUBLIC WORKS DEPT, County hereinafter referred to as "Applicant". This
version of Construction Agreement is specifically designed for Applicants which are governmental entities. The
Applicant has requested the Company construct and install the necessary Electric Distribution Line Extension,
hereinafter referred to as "Extension", to provide Plan A — Permanent Service or, under limited conditions, Plan
B — Indeterminate Service, to serve 1113 H ST in the City of GREELEY in the County of WELD in the State of
Colorado. This Construction Agreement is subject to the Company's Distribution Extension Policy, as stated in
the Company's tariffs, available for inspection at the Colorado Public Utilities Commission and on the
Company's website, and such policy and tariffs are incorporated herein by this reference. Any capitalized term in
this Construction Agreement that is not expressly defined herein shall have the meaning set forth in our policy
and tariffs.
The Company has completed the engineering design and cost estimate to provide the Extension based
upon the information Applicant has provided and the service requirements that you have requested. The
estimated total Construction Cost to provide the requested Extension is $15,375.04. Based upon the information
provided, the Company's design for the Extension includes 3 meters and/or 214 kW of demand for Electric
service. Your potentially awardable Construction Allowance for such number of meters, and/or demand for
Electric service, based on the rate schedule as applicable for the Electric service for which the Extension is being
constructed, is $15,375.04. Your estimated Construction Payment is $0.00. If the Applicant elects to have the
Company advance the Construction Payment for the duration of the construction period, Applicant will be billed
by the Company in accordance with the Company's tariffs, within 30 days after the construction of the Extension
is complete. The Applicant will have 90 days thereafter to pay such bill. If the Applicant does not elect to have
the Company advance the required Construction Payment, the Applicant shall pay the Company the Construction
Payment before approval of this Extension Agreement and commencement of construction.
The Company will not approve this Construction Agreement unless and until the following two
requirements have been satisfied: 1) execution and return to Company of this Construction Agreement by
Applicant, and of any other Enclosures that are applicable and 2) receipt of one -line diagrams, load information
and any other necessary information requested by the Company in order to calculate the appropriate equipment
needed to determine the Company's estimate of the Applicant's load. The Construction Payment quoted above
shall be effective for sixty (60) days from the Contract Origination Date set forth below. Should this
Construction Agreement not be returned to, and accepted by, the Company within those 60 days the Construction
Costs may be re -estimated and this Construction Agreement may be terminated and replaced with a new
Construction Agreement.
A Construction Allowance will be calculated and awarded to Applicant as provided by this Construction
Agreement and the Company's aforementioned policy and tariffs. Construction Allowance will be awarded in a
one-time payment if the Company estimates a Permanent Service will be physically connected (ie. a permanent
meter will be set) within one year from the execution of this Construction Agreement or upon Company review
and acceptance of a final plat of the development or subdivision that has been approved by the governmental entity
having jurisdiction as applicable. If Construction Allowance is awarded in one payment under this Construction
Agreement, Applicant shall not be entitled to any future Construction Allowance or Refunds with respect to this
Extension. Unless and until a one-time Construction Allowance payment is awarded by the Company,
Construction Allowances will be calculated and awarded on a per -meter and/or volumetric basis, when new
* Confidential Information - Required Field (to be filled out by the customer)
Revision April 19, 2018
1
CONTRACT NO.10227579
permanent meters are set, in conformance with the aforementioned policies and tariffs. The one-time awardable
Construction Allowance may differ from the sum stated above if the final plat submitted contains different facts or
information from that which was originally provided by Applicant as the basis for this Construction Agreement.
Additional payments greater than this estimated Construction Payment may be required if customer
associated delays, obstructions, permit fees, or design changes in the field are encountered which are not included
in the original job or Construction Cost estimate. The Construction Cost stated above does not include special
items such as but not limited to frost or rock conditions. In the event the Company encounters any special items
during construction, the Company shall bill Applicant for such special items as a non-refundable contribution in
aid of construction.
This Construction Agreement does not include any Construction Cost of Service Lateral Extensions.
Any costs and payments with respect to Service Lateral Extensions will be calculated and contracted separately
from this Construction Agreement.
Applicant may not assign this Construction Agreement without the prior written consent of the Company.
Applicant agrees to execute the Company's standard right-of-way agreement granting, free of charge to
Company, any rights -of -way upon, over or under Applicant's property that may be required for Company to
accomplish the objective of this Construction Agreement, to obtain such other rights -of -way, free of charge and
on other terms satisfactory to Company, from other parties as may be required. Applicant recognizes the
Company's ability to perform under this Construction Agreement is contingent upon the obtaining any other
rights -of -way from other parties if required. The Company shall not be required to expend more than
commercially reasonable efforts to assist in the acquisition of any third party right-of-way.
If there is a possibility that other utilities or facilities will be installed jointly with the Extension,
Applicant must personally contact the local telephone company, the local cable TV company and/or any other
utility company to arrange for the installation and payment of any costs of their facilities.
If there is a possibility that the Extension will be constructed during frost conditions, Applicant shall
execute a Frost Agreement and return such with this Construction Agreement. Should Applicant not do so,
Applicant's project may be delayed until frost conditions have ceased and there is no further chance of
encountering frost. Please refer to the Frost Agreement for terms and conditions of that service.
Upon the acceptance of the terms and conditions of this Construction Agreement, Applicant must return
all applicable documents and the Construction Payment (unless Applicant chooses to have the Company advance
the Construction Payment in accordance with its tariffs), payable to Public Service Company of Colorado, at the
address shown below. The Company is unable to accept checks with any sort of lien waiver because our tariffs do
not allow it, and Applicant agrees that any attempt to create a lien waiver in such a manner (including by any
printed or stamped lien waiver on a check) shall be ineffective and void. After an executed original of this
Construction Agreement, all applicable documentation and the Construction Payment (unless Applicant chooses
to have the Company advance the Construction Payment in accordance with its tariffs) is received and accepted
by the Company and all other prerequisites have been satisfied, a work order will be issued and released to
construction so the Extension can be scheduled. The Company's current lead-time to begin construction after
receiving the non-refundable payment (if applicable) and signed documents is approximately 6-8 weeks. You will
be notified of which week the Applicant's construction is scheduled to begin. If you have any questions
regarding this project, please call a Company representative at 970-622-2909.
The Company looks forward to being your energy provider.
Sincerely,
Yarani Vazquez
UC Synergetic
Construction Agreement Origination Date: May 3, 2018
* Confidential Information - Required Field (to be filled out by the customer)
Revision April 19, 2018
2
CONTRACT NO. 10227579
Mailing address:
UC Synergetic
5245 Ronald Reagan Blvd Suite 104
Johnstown, Co 80534
Applicant has reviewed and accepts the terms and conditions of this Construction Agreement. Applicant will
return a signed Construction Agreement and will pay the applicable Construction Payment amount of $0.00
within 90 days after construction is complete. Applicant will send an original signed copy of this Construction
Agreement with the any applicable agreements/documents.
Applicant: WELD LINTY PUBLIC WORKS DEPT.County
*Signature: / / *Date: MAY 14 2018
Chair, Board of Weld
*Print Name: Steve Moreno *Title: County Commissioners
*Mailing address: { PO Box 758
Greeley, CO 80632
e
*Phone: _970-400-4228
Company Representative
Date: 5/9/18
Name: Pat Kreager
Title: Manager Distribution Design
Signature:
* Confidential Information - Required Field (to be filled out by the customer)
Revision April 19, 2018
3
•oig- t 555
It....!Energy
ELECTRIC CONTINGENCY LIST
*CUSTOMER: WELD COUNTY PUBLIC WORKS DEPT by Board of Weld County Commissioners
ADDRESS: 1113 H ST
CITY: GREELEY
DESIGN NO: 768775
SIGNATURE ** DATE MAY 14 201
8
' Return copy of signed document to your Xcel Energy Representative
Steve Moreno, Chair
Public Service Company of Colorado d/b/a Xcel Energy has completed the engineering design and cost estimate for
your electric distribution request. Public Service Company will insta- the facilities, as shown on the attached engineering
sketch, when all contractual obligations and customer -supplied conditions are met. The specified conditions listed below
were used to determine the most effective design to meet your request. If, for any reason, this does not meet your
request as intended, please review with Public Service Company's Engineering personnel. Engineering will discuss any
possible revision and will expedite any necessary revised costs in order to meet your schedule as planned. (Please be
aware that additional estimates may be subject to re -engineering charges.) Public Service Company looks forward to
completing the installation of these facilities for you and providing for any future energy needs you may have.
GENERAL:
• All necessary easements and rights -of -way must be provided to Public Service Company at least ten (10) days prior
to the start of construction.
• The design and estimate are contingent upon Public Service Company acquiring the following permits and/or
approvals:
❑ Town Permit
❑ County Permit
❑ State Highway crossing permit
❑ Railroad Crossing permit
❑ Bureau of Land Management (BLMVI) approval
❑ Grading and drainage permit
❑ Water Board crossing
❑ Special permit
❑ Corps of Engineer's permit
• Developers are required to have curb and gutter installed prior to installation of electric distribution facilities.
• When construction consists of five or fewer sites, all sites must be ready. On larger projects, approximately 50% of
the sites must be ready.
• Property pins, necessary curve points, easements, proposed structures and facility equipment locations, as
determined to need staking by the Company, must be staked and visible in the field.
• ❑ If checked, customer has agreed to install sleeves at crossings.
• Water line, sewer lines septic systems, leach fields or any other underground obstruction must be staked, flagged and
installed prior to Public Service Company electric construction.
• All street/easements/service lateral routes are to be within plus or minus six (6) inches of final grade except for
transformer, switch cabinet locations, pedestal and other surface mounted equipment, which must be exact final
grade.
• Landscaping and pouring/paving of driveways must be delayed until after instaation of facilities (services
excluded) .
• Where slopes exist that prohibit trenching, the customer must provide temporary grade for trenching equipment.
• The construction route must be clear of all obstructions.
• Construction material must be cleared from route.
• Temporary trailers, buildings or other obstacles must be moved.
• Xcel Energy will trim/clear trees along the construction route. If the customer elects to trim/clear the trees on
his/her own property, will be deducted.
Revision December 4, 2017
go -- 555
* Confidential Information
• Public Service Company is required to provide the following trench specifications:
❑ Wheel Compaction feet of trench
❑ 85% Standard Proctor Compaction feet of trench
❑ 95% Standard Proctor Compaction feet of trench
❑ 950/0 Modified Proctor Compaction feet of trench
❑ Bore feet of trench
• Public Service Company will not be responsible for the repair or replacement costs resulting from damages to items,
which are not marked prior to beginning this installation.
• Customer will be responsible for replacement of existing sod, shrubs, trees, etc. and repairing existing paving, at no
cost to Public Service Company.
• The customer must insure that all Public Service Company facilities remain accessible at all times for routine
maintenance purposes.
• All roof drains are to be directed away from Public Service Company equipment in a manner to prevent damage
and/or settling of facilities.
• The area on the door side of transformers and/or switch cabinets is to remain clear of obstructions for ten (10) feet
minimum distance at all times for maintenance purposes.
• If transformers/switch cabinets need bumper protection, the customer is responsible for the installation and cost of
installing the protection. Contact the design engineer for bumper protection clearance requirements.
• If there are known contaminants on the property it is the owners responsibility to remove these prior to Public
Service (PSCo) installing our facilities. If contaminates are encountered that were previously unknown, all work will
be stopped until owner remediates the site to ensure Public Service Company's Crews are working in non -
contaminated soils and that all facilities are setting on or buried in non -contaminated soils.
• The developer/owner shall be responsible for all federal, state law(s), and local ordinances of any soil and or debris
excavated from the property that is contaminated with hazardous substances, wastes, petroleum, etc. The
developer/owner shall be responsible for environmental conditions and the costs that result in PSCo causing or
exacerbating a release of hazardous substances or that will require PSCo to adopt greater or different procedures
for utility installation than its standard business practices when dealing with clean, uncontaminated soils.
• If you prefer to avoid frost charges by waiting until frost depth is six inches (6") or less, you must notify Public
Service Company at the time of your application for service installation. Otherwise, please complete and return the
Frost Agreement.
METER AND SERVICE INFORMATION
• The permanent address must be attached to the building before the permanent meter will be set.
• Multiple unit structures must have each meter housing permanently identified before the meter will be set.
• Multiple unit structures with banked metering require separate trenches for any customer -owned facilities.
• No customer -owned facilities will be allowed in any easement granted by the property owner to Public Service
Company.
• Customer is responsible to provide required clearances for all electric and gas metering equipment (see the "Xcel
Energy Standard for Electric Installation and Use", aka Blue Book).
• Public Service Company will install all residential underground electric services (see the "Xcel Energy Standard for
Electric Installation and Use").
• All commercial electric underground services, complete to transformer, pedestal or terminal pole shall be installed,
owned and maintained by the customer.
• Adequate conduit under concrete, decks or other obstructions shall be the responsibility of the customer.
• Overhead to underground conversion of meters and risers, including all wiring and building repairs, shall be the
responsibility of the customer.
Revision December 4, 2017
Xcel Energy
May 3, 2018
WELD COUNTY PUBLIC WORKS DEPT
PO BOX 758
GREELEY, CO 80632-0758
RE: Frost Installation Conditions
Due to the possibility that ground frost conditions may exist during installation of your
distribution facilities and if applicable, service laterals, it is necessary that Xcel Energy
inform you of our policy regarding installation in frozen ground.
If frost conditions deeper than six inches (6") are encountered, additional costs will be
charged at a cost of $2.20 per linear foot. Also, if "select" backfill is required, Xcel
Energy will charge an additional amount based on actual costs.
Charges for trenching in frost will be billed after the job has been completed; therefore,
you may want to have a representative present during the trenching operation to confirm
the frost depth.
If you prefer to avoid frost charges by waiting until frost depth is six inches (6") or less,
you must notify me at the time of your application, otherwise please complete and return
the attached Frost Agreement.
If you have any questions or comments, please call me at the number listed below.
Sincerely,
Yarani Vazquez
UC Synergetic
Mailing address: UC Synergetic
5245 Ronald Reagan Blvd Suite 104
Johnstown, CO 80534
* Confidential Information - Must be executed by authorized person. Revision April 19, 2018
For Installation of as an
1
ST AG E ME I T
or Electric Distribution and Service Laterals
WELD COUNTY PUBLIC WORKS DEPT1 hereinafter referred to as "Customer", having
entered into an agreement with Public Service Company of Colorado, a Colorado corporation, d/b/
a Xcel Energy to install gas and/or electric facilities into its project known as Recoil Commercial UG
Fi;lectric Distribution , located at (service address) 1113 H ST, GRVFLFJY further agrees that if
ground frost conditions deeper than six (6") are encountered at the time of installation of the Gas
and/or F{;lectric Distribution and if applicable, Service Laterals, "Customer" hereby authorizes Xcel
Knergy to install the above facilities and to pay the actual additional non-refundable frost charges.
By signing this Agreement, "Customer" requests to proceed with the installation regardless of frost
conditions and such installation wI- be done with the actual frost charges biJ ed by Xcel Fit,nergy and
paid by the "Customer". These charges are in addition to any previous extension charges and are
not refundable. Such charges are due and payable within thirty (30) days after the billing.
Should the decision be made to defer installation unti- there is six inches (6") or less frost in the
ground, rescheduling of installation will be done with consideration made for previously scheduled
installations. Notification of the approximate date of installation will be given by Xcel Knergy as
soon as practicable after frost conditions have ceased.
If this Frost Agreement includes Service Laterals for this project, please list addresses or lot and
block numbers that are covered by this Agreement.
CUSTOM _ N
*By w cc�� � �� " "� E _ )ate:
Steve Moreno, Chair
Board of Weld Cognt�y_ Commissioners
(Type or Print Name and Title of Signer)
Mailing Address: PO BOX 758
GREFILK,Y, CO, 80632-0758
XCVL KIN F',RGY R _ KPRES _ KNITATIVE
Yarani Vazquez
UC Synergetic
Mailing address: UC Synergetic
5245 Ronald Reagan Blvd Suite 104
Johnstown, CO 80534
f
Lee! Energy Representative
MA
142
a
18
Date May 3, 2018
* Confidential Infoirnation - Must be executed by authorized person. Revision April 19, 2018
9555
113 H Street, Greeley, CO 80631
Feeder GRLY1033G
Req,On.Commercial UG Elel
�urrnmary
Remove:
(1) 75 KVA Transformer [71/35]
JA Fuse
Install;'
{1}600 KVAT
{3} 65A.Fuse
ldl
Otis e
MikeeB,
Designer
Yaran[.Vazquez 970-622-2909
tu
35
75
71
35
Install:
(4) 500 KVA
30 Padmount
Transformer
480f277V
[724,812401-
N 17TH AVE is 600ft
277/480
500
748
230
000
1113
orth
65SM- 0
ZABC 67
30
UPRIGHT LOADBREAK CENTER
3A53
3155
DISCLAIMER: THERE ARE NO REPRESENTATIONS OR WARRANTIES (EXPRESS OR IMPLIED) ABOUT THE ACCURACY OF THIS PRINT. THIS PRINT IS PROVIDED WITH NO CLAIM AS TO PRINT COMPLETENESS,
TIMELINESS. ACCURACY OF CONTENT OR USEFULNESS. STATE LAW REQUIRES ANYONE DIGGING. GRADING OR EXCAVATING TO OBTAIN A PRIOR FIELD LOCATE OF ALL UTILITIES; THIS PRINT DOES NOT
DISCHARGE THIS REQUIREMENT OR ANY OTHER REQUIREMENT. THE COMPANY AND ITS AFFILIATES ASSUME NO LEGAL RESPONSIBILITY OR LIABILITY FOR THE RECIPIENT'S USE (OR ANY OTHER PARTIES' USE)
OF THE PRINT, INCLUDING THE RECIPIENTS INTENDED PURPOSE IN USING THE PRINT. NO COMPANY EMPLOYEE OR OTHER PARTY HAS BEEN AUTHORIZED TO PROVIDE THIS PRINT FOR PLANNING OR ESTIMATING
PURPOSES; RELY ON THIS PRINT AT YOUR OWN RISK BY ACCEPTING THIS PRINT, THE RECIPIENT B ANY OTHER PARTY RECEIVING A COPY OF THE PRINT ACKNOWLEDGES AND AGREES TO THIS DISCLAIMER.
For All Field Locates Cell 811
.,, nWP,MMetiftd,TT1"Up,M4"s
Service Request# : 10227579
Design Number : 000005768775
Designer/Planner ID: 231832
Designer/Planner Name: Vazquez,Yarani
Designer/Planner Ph # : 970-622-2909
Manager Approval:
a G:
T: C:
7-0NRINIABROMBRIIBr, •,.,..
Division: Greeley Region
County : Weld
City : Greeley
Address: 1113 H St
T: 6N R:65W S:31
Map# 2220406 03 Permit
F ederGRLY1033G Voltage: 12470
Phase: ABC BkupDevlO:
System: Pressure:
Size : Material :
Dead End :
Work Order #: 101392656
Date: 05/03/2018
Sketch: 1 of 2 Sketch Data
Scale: 1" equals 100'
7 XcetEnergy`
CONSTRUCTION
ee WeWILT/. DESIGNED)
D OE. INDICATED
oY STHAVE ACTUAL
YEASUREMENTSFROMTHEFIELDSI,
1113 H Street, Greeley, CO 80631
Feeder::GRLY1033G
Recon Commercial UG Elect
Summary
Remove-,
(,,,,,1),,,,,7-544Y, A Transformer [71/35]
(13v07'Fuse
c Distribution
Install:
(1) 500 KVA Transformer [748/230]
(3) 65A Fuse
Locates Required
No Permits Required No Restoration Required
No TCP Required
Customer Contact:
Mike Bedell 970-301-078
Designercontact:
Yar6nllquez 870.622; 2909
1555
1555
500
86
54
9B
GRLY1033G
1551
AL
A'
B:
C
65SM-20 :I
65.N1-20
48 250
50SM-20
3170
100X
90/46
81 250
45
DISCLAIMER: THERE ARE NO REPRESENTATIONS OR WARRANTIES (EXPRESS OR IMPLIED) ABOUT THE ACCURACY OF THIS PRINT. THIS PRINT IS PROVIDED WTH NO CLAIM AS TO PRINT COMPLETENESS.
TIMELINESS. ACCURACY OF CONTENT OR USEFULNESS. STATE LAW REQUIRES ANYONE DIGGING. GRADING OR EXCAVATING TO OBTAIN A PRIOR FIELD LOCATE OF ALL UTILITIES: THIS PRINT DOES NOT
DISCHARGE THIS REQUIREMENT OR ANY OTHER REQUIREMENT. THE COMPANY AND ITS AFFILIATES ASSUME NO LEGAL RESPONSIBILITY OR LIABILITY FOR THE RECIPIENT'S USE (OR ANY OTHER PARTIES' USE)
OF THE PRINT. INCLUDING THE RECIPIENTS INTENDED PURPOSE IN USING THE PRINT. NO COMPANY EMPLOYEE OR OTHER PARTY HAS BEEN AUTHORIZED TO PROVIDE THIS PRINT FOR PLANNING OR ESTIMATING
PURPOSES; RELY ON THIS PRINT AT YOUR OWN RISK. BY ACCEPTING THIS PRINT. THE RECIPIENT B ANY OTHER PARTY RECEIVING A COPY OF THE PRINT ACKNOWLEDGES AND AGREES TO THIS DISCLAIMER.
For All Field Locates Call 811
i441fit.C(rder]/rfarmailpr{ ...
Service Request# 10227579
Design Number : 000000768775
Designer/Plannee ID: 231832
Designer/Planner Name: Vazquez,Yarani
Designer/Planner Ph 0 : 970-622-2909
Manager Approval:
E G:
T: C:
Division: Greeley Region
County : Weld
City Greeley
Address: 1113 H St
T.. 6N R:65W 0:31
Map# 222040803 Permit
4Feeder.GRLY1033G
Voltage: 12470
Phase: ABC BkupDevlD:
System: Pressure:
Size : Material :
Dead End :
Work Order 0: 101392656
Date: 05/03/2010
Sketch: 2 of 2 Sketch Data
Scale: 1" equals 100'
XCe!Er)ergy'
oar ealazveuneeeaNEel
❑ c ea
ueuavp aenee.MUST Fnoa reel
M „REMaxrs.ROM THE am STE)
Hello