HomeMy WebLinkAbout20181367.tiffRESOLUTION
RE: REGULATING, WARNING AND GUIDING TRAFFIC DURING THE TEMPORARY
CLOSURE OF COUNTY ROAD 31 BETWEEN COUNTY ROADS 64 AND 66, AND
BETWEEN COUNTY ROADS 74 AND 76 FOR APPROXIMATELY FOUR (4) WEEKS,
FOR MAINTENANCE OF NATURAL GAS TRANSMISSION PIPELINE BY PUBLIC
SERVICE COMPANY OF COLORADO
WHEREAS, the Board of County Commissioners of Weld County, Colorado, pursuant to
Colorado statute and the Weld County Home Rule Charter, is vested with the authority of
administering the affairs of Weld County, Colorado, and
WHEREAS, pursuant to Section 42-4-106(6)(a), C.R.S.:
"...local authorities, with their respective jurisdiction may, for the
purpose of road construction and maintenance, temporarily close to
through traffic or to all vehicular traffic any highway or portion
thereof for a period not to exceed a specified number of work days
for project completion and shall, in conjunction with any such road
closure establish appropriate detours or provide for an alternative
routing of the traffic affected...", and
WHEREAS, the Board, pursuant to said statute and upon the basis of traffic and personal
investigations, has determined that conditions exist which make it necessary to temporarily close
said County Roads to through traffic and to regulate, warn and guide vehicular traffic by posting
signs thereon.
NOW, THEREFORE, BE IT RESOLVED that the Board of County Commissioners of Weld
County, Colorado, received a request from the Public Service Company of Colorado, and deems
it necessary to regulate, warn and guide vehicular traffic on County roads and any intersections
thereof, and it hereby authorizes and orders the posting of such traffic control devices as shall be
reasonably necessary to regulate, warn and/or guide traffic thereon for the safety of the general
public and that said traffic control devices shall conform to the Federal Manual on Uniform Traffic
Control Devices.
BE IT FURTHER RESOLVED that the Board of County Commissioners of Weld County,
Colorado, does declare and establish that County Road 31, between County Roads 64 and 66,
and between County Roads 74 and 76, be temporarily closed, with said closure being effective
May 3, 2018, for approximately four (4) weeks for maintenance of a Natural Gas Transmission
Pipeline, and further, that standard official traffic control devices shall be erected at said closure
giving notice of the restrictions.
Q,C: SO CRS) CO Sio.�t'Pa--bwa I
D is peic
062-07-tcs
2018-1367
EG0024
TEMPORARY CLOSURE - COUNTY ROAD 31
PAGE 2
The above and foregoing Resolution was, on motion duly made and seconded, adopted
by the following vote on the 30th day of April, A.D., 2018.
BOARD OF COUNTY COMMISSIONERS
WELD COUNTY, COLORADO
ATTEST: deft/44);vi EXCUSED
Steve Moreno, Chair
Weld County Clerk to the Board
BY:
Deputy Clerk to the B
APP '• -DASTO
oun
y
ney
Date of signature: 06-44-4
Sean P. Cpnway
-/,/
Julie A. Cozad
,L,te
Mike Freeman, Acting Chair Pro -Tern
2018-1367
EG0024
MEMORANDUM
TO: Clerk to the Board DATE: April 26, 2018
FROM: Amy Joseph, Public Works Department
SUBJECT: BOCC Agenda Item
Public Service Company of Colorado is requesting permission to close CR 31 between CR 64 and 66 and
CR 31 between CR 74 and CR 76 beginning Thursday, May 3rd and ending Thursday, May 31" to
complete Federally mandated maintenance on their 8" Natural Gas Transmission pipeline.
See attached closure diagram(s).
2018-1367
CC ENTERPRISES - TRAFFIC CONTROL SPECIALISTS, INC
Contractor: XCEL ENERGY WO# 4500075505
Project: 8" CHALK BLUFFS LINE - KODAK VS - CR 31 & CR 66 - WELD COUNTY
Method of Handling Traffic: ROAD CLOSURE WITH DETOUR
PREPARED BY:
Je"euiller EE.txy 03/26/2.018
ATSSA TCS DATE
PHONE: 970-242-0669
CERTIFICATION # 245588
ISSUE DATE: 01/12/2018
EXPIRATION DATE: 06/21/2021
CR 66
NOTES:
1. CONTRACTOR WILL NEED THE ROAD CLOSED AT AN
INTERSECTION UNTIL COMPLETION OF WORK.
2. AT NIGHT, HAZARDS WILL BE BARRICADED.
3. REFER TO MUTCD 2009 EDITION FIGURE 6H-20
FOR A TYPICAL APPLICATION.
4. ALL TRAFFIC CONTROL DEVICES AND SETUP
SHALL ADHERE TO THE 2009 MUTCD.
5. ACCESS TO PRIVATE DRIVEWAYS SHALL
BE MAINTAINED AT ALL TIMES.
6. SEE NOTES ABOUT CONCRETE BARRIER AND IMPACT ATTENUATORS
ON MHT 1. IF BARRIER IS NEEDED WITHIN THE WORK ZONE.
SIGNS & DEVICES:
4 - ROAD WORK AHEAD
6 - DETOUR AHEAD
2 - ROAD CLOSED
4 - DETOUR MARKER (2L/2R)
2 - ROAD CLOSED AHEAD
1 - ROAD CLOSED TO THRU TRAFFIC
2 - DETOUR ARROW (11./1R)
12 - FLASHING BEACON (TEMP) (OPTIONAL)
2 - VARIABLE MESSAGE BOARDS (OPTIONAL)
CONCRETE BARRIER (ANY WORK IN SAME LOCATION OVER 3 DAYS -
IF NEEDED WITHIN WORK ZONE)
IMPACT ATTENUATORS (POSITIVE PROTECTION FOR ALL
BLUNT ENDS ON TEMPORARY BARRIER)
VERTICAL PANELS OR DRUMS / LIGHTS (18 +/- PORTABLE FLASHING BEACON
N 47TH AVE
W aE
S
MHT 2
W O ST
'OPTIONAL USE DETERMINED BY PERMITTING PARTY
VMS
MSG 1
CR31&
CR 66
CLOSED
WILL BE SET AT 2 LOCATIONS 1 WEEK
PRIOR TO WORK START TO NOTIFY
RESIDENTS OF UPCOMING CLOSURE.
PERMITTING PARTY WILL APPROVE
VMS MESSAGE:
1. CR 31 AND CR 66
2. CR 31 AND CR 64
MSG 2 MSG 3
5/21/18 USE
TO CR 33
5/25/18 DETOUR
Total work days: 4/23/18 thru 6/1/18.
Road closures: (day and night): 5/21 thru 5/25,
Shoulder work: 4/23/18 thru 5/21/18
and 5/25/18 thru 6/1/18
X18-XCED006-2
CC ENTERPRISES - TRAFFIC CONTROL SPECIALISTS, INC
Contractor: XCEL ENERGY WO# 4500075505
Project: 8" CHALK BLUFFS LINE - KODAK VS - CR 31 & CR94 - WELD COUNTY
Method of Handling Traffic: ROAD CLOSURE WITH DETOUR
PREPARED BY:
J tr .E» 0342412024
ATSSA TCS DATE
PHONE: 970-242-0669
CERTIFICATION # 245588
ISSUE DATE: 01/12/2018
EXPIRATION DATE: 06/21/2021
CR 76
NOTES:
1. CONTRACTOR WILL NEED THE ROAD CLOSED AT AN
INTERSECTION UNTIL COMPLETION OF WORK.
2. AT NIGHT, HAZARDS WILL BE BARRICADED..
3. REFER TO MUTCD 2009 EDITION FIGURE 6H-20
FOR A TYPICAL APPLICATION.
4. ALL TRAFFIC CONTROL DEVICES AND SETUP
SHALL ADHERE TO THE 2009 MUTCD.
5. ACCESS TO PRIVATE DRIVEWAYS SHALL
BE MAINTAINED AT ALL TIMES.
6. SEE NOTES ABOUT CONCRETE BARRIER AND IMPACT ATTENUATORS
ON MHT 3. IF BARRIER IS NEEDED WITHIN THE WORK ZONE.
SIGNS & DEVICES:
4 - ROAD WORK AHEAD 2 - ROAD CLOSED AHEAD
6 - DETOUR AHEAD 2 - ROAD CLOSED TO THRU TRAFFIC
2 - ROAD CLOSED 2 - DETOUR ARROW (1L/1R)
4 - DETOUR MARKER (2L/2R) 12 - FLASHING BEACON (TEMP) (OPTIONAL)
2 - VARIABLE MESSAGE BOARDS (OPTIONAL)
CONCRETE BARRIER (ANY WORK IN SAME LOCATION OVER 3 DAYS -
IF NEEDED WITHIN WORK ZONE)
IMPACT ATTENUATORS (POSITIVE PROTECTION FOR ALL
BLUNT ENDS ON TEMPORARY BARRIER)
VERTICAL PANELS OR DRUMS / LIGHTS (18 +/- PORTABLE FLASHING BEACON
MHT 4
'OPTIONAL USE DETERMINED BY PERMITTING PARTY
ram
WILL BE SET AT 2 LOCATIONS 1 WEEK
PRIOR TO WORK START TO NOTIFY
RESIDENTS OF UPCOMING CLOSURE.
PERMITTING PARTY WILL APPROVE
VMS MESSAGE:
1. CR 31 AND CR 74
2. CR 31 AND CR 76
USE
CR 29
DETOUR
Total work days: 4/23/18 thru 6/1/18.
Road closures: (day and night): 5/21 thru 5/25.
Shoulder work: 4/23/18 thru 5/21/18
and 5/25/18 thru 6/1/18
X1 8-XCED006-4