HomeMy WebLinkAbout770015.tiff WELD COUNTY
Guidelines and Policies
for
Extension and New Development
of
Power Plants,
Electric Transmission Lines,
Pipelines
and
Other Major Public Utility Facilities
•
PUBLIC UTILITIES PLAN
July 1977
Board of County Commissioners
Edward Dunbar, Chairman
Norman Carlson Leonard Roe
Victor Jacobucci June K. Steinmark
Weld County Planning Commission
Chuck Carlson, Chairman
Harry S. Ashley J. Ben Nix
Percy Hiatt Jerry Sucla
Jerry Kiefer Irma White
Bette Kountz Marge Yost
Planning Department Staff
Gary Z. Fortner - Director, Department of Planning Services
Roy Jost - Project Planner and Coordinator
Planning Zoning_
Bill Hughes Bob Adams
Allen Jost Cathy Carter
Ken McWilliams Chuck Cunliffe
Thom Rounds Thomas Bonn
Bill Rodriguez Virgil McKee
Ann Thayer
Jim Veentsa (Intern) Project Asst.
Sheri Wilson
Drafting Secretarial
Edward Caller Shirley Phillips
Paulette Werver Kathy Hrouda
ii
DOCUMENTATION
• The method of documentation used in this project is an efficient,
simple system of citing sources recommended by Herman H. Weisman,
Basic Technical Writing (2nd ed. ; Columbus, Ohio: Charles E. Merrill
Publishing Company, 1968), p. 390. This system, instead of using a
footnote at the bottom of the page, integrates the documentation refer-
ence within the text line following immediately the matter or source to
be documented. The documentation reference begins with a parenthesis,
then lists the sequential number of the bibliographic reference source
being used, followed by a colon, the page numbers of that bibliographic
reference, and then closed by a parenthesis; for example (2:27). This
tells the reader that this material was borrowed or quoted from the
bibliography (sources cited) and that the matter quoted appears on page
27 of that source. This system is simple, efficient, and provides the
reader with all the needed information. Sources cited for this project
are listed sequentially in the order that they first appear in the report.
iii
TABLE OF CONTENTS
INTRODUCTION 1
I. PUBLIC UTILITY SYSTEMS 6
A. Electric Systems 9
B. Oil and Gas Systems 13
1. Pipelines 14
2. Storage Facilities 16
C. New Development 19
1. Reliability and Cost Factors 21
a. Interconnection and Dispersion of
Power Facilities 21
b. Right-of-way Length 21
c, Transmission Line Support Structures . . . 22
d. Underground Electric Transmission and
Distribution 23
e. Pipeline Transmission 25
2. Physical Factors 26
a. Site Size and Right-of-way Width 28
b. Cooling Water 30
c. Fuel and Energy 31
d. Access and Transportation 33
e. Existing Land Use Obstacles 34
D. Summary 36
II. PUBLIC UTILITY DEVELOPMENT AND LAND USES . . 38
A. Agricultural Areas 40
1. Power Plants 41
a. Agricultural Land Loss 42
b. Agricultural Water Loss 43
c. Pollutants 44
2. Electric Transmission Systems 46
a. Irrigated Areas 47
b. Non-Irrigated Areas 49
iv
c. Access 51
d. Cropdusting 52
3. Pipeline Systems 54
a. Irrigation Ditches 55
b. Construction Operations 56
B. Community Growth Areas 59
1. Power Plants 60
a. Socio-economic Impacts 60
b. Pollutants 62
2. Electric Transmission Systems 65
a. Appearance 65
b. Radio and T. V. Interference 68
3. Pipeline Systems 69
a. Development Patterns 70
b. Safety 71
C. Other Resource Areas 73
1. Mineral Resource Areas 74
a. Sand and Gravel Resources 75
b. Oil, Gas, Coal and Uranium Resources • • 76
2. Wildlife Areas 77
a. Raptors 78
b. Water Fowl 80
c. Fish 81
3. Cultural Resources 82
a. Archaeological Resources 83
b. Historic Sites 83
c. Scenic and Recreational Resources 84
D. Summary 86
III. POLICY GUIDELINES 88
A. Conflicts and Recommended Actions 91
1. Power Plants 92
a. Impacts on Agricultural Uses 93
b. Impacts on Communities 94
c. Impacts on Mineral, Wildlife and
Cultural Resources 98
v
2. Electrical Transmission Systems 102
a. Impacts on Agricultural Uses 103
b. Impacts on Communities 107
c. Impacts on Mineral, Wildlife and
Cultural Resources 110
3. Gas and Oil Pipeline Systems 113
a. Impacts on Agricultural Uses 114
b. Impacts on Communities 118
c. Impacts on Mineral, Wildlife and
Cultural Resources 119
B. Summary and Conclusions 123
SOURCES CITED 127
APPENDIX/REGULATIONS 130
vi
LIST OF TABLES
TABLE 1 CLASSIFICATION OF ELECTRIC LINES 11
TABLE 2 1975 COSTS FOR SINGLE-POLE TUBULAR STEEL
STRUCTURES 23
LIST OF MAPS
MAP 1 ELECTRIC COMPANY SERVICE AREAS IN WELD
COUNTY 12
MAP 2 MAJOR ELECTRIC UTILITY FACILITIES IN WELD
COUNTY 12a
MAP 3 MAJOR OIL AND GAS PIPELINES IN WELD COUNTY 17
MAP 4 MAJOR OIL AND GAS PIPELINES IN SOUTHWEST
WELD COUNTY 18
vii
Introduction
INTRODUCTION
The Weld County Public Utilities Plan was developed in conform-
ance with, and in response to, the Weld County Home Rule Charter which
became effective on January 1, 1976; specifically, those portions of
Article IV, Section 4 of the charter identified below.
4(4)(e). No utility transmission system shall be constructed until
the entity developing such system shall have made application to
the Weld County Planning Commission pursuant to the rules and
regulations of the Planning Commission and until such utility system
has been approved by the Board. Prior acquisition of utility trans-
mission easements and rights-of-way shall not be considered by
the Planning Commission or Board.
4(4)(f). The Planning Commission shall establish rules and regu-
lations covering applications for utility transmission easement
systems and hearings thereon. The application shall include all
information required by the Board including environmental and
economic impact statements.
4(4)(g). The Planning Commission shall make its recommendation
to the Board as to whether an application for a transmission utility
system should be granted or denied and the Board shall make a
final determination.
In addition, Title 24, Article 65. 1, Section 101, Colorado Revised
Statutes 1973, as amended, encourages local governments to identify,
designate, promulgate guidelines and regulations, and administer areas
and activities of state interest. Major facilities of public utilities are
included in the statute as activities of state interest and are defined as
follows:
1. Central office buildings of telephone utilities;
2. Transmission lines, power plants, and substations of
electrical utilities; and
3. Pipelines and storage areas of utilities providing natural
gas or other petroleum derivatives.
2
Regarding such public utilities, the statute states that:
"Where feasible, major facilities of public utilities shall be
located so as to avoid direct conflict'with adopted local govern-
ment, regional, and state master plans. " ( 1 :345)
Finally, the Weld County Comprehensive Plan, the basic policy guide-
line for land use decisions within Weld County, was adopted by the
County Commissioners in September 1973. This plan is based on two
fundamental premises:
1. Retain prime agricultural land for agricultural use. Since
the character and economy of the County depend on this
agricultural base, the County' s prime agricultural land and
basic agricultural way of life are to be protected.
2. Retain and build upon the twenty-eight existing incorporated
communities located in this county in order to minimize
urban and agricultural land use conflicts and to minimize the
cost of new facilities and services to the taxpayer.
In recent years, it has been recognized that electrical, oil and gas
utility facilities have the potential for creating negative impacts on both
the agricultural and urban sectors of Weld County. The disruption of
irrigation systems, breakage of farm equipment on guy lines, and the
dangers posed for crop dusting operations are examples of negative
impacts in agricultural areas. The splitting of agricultural land parcels
through the condemnation of prime lands for needed right-of-ways, and
the aesthetic degradation of both rural and urban areas as such utilities
are installed, have stressed the need for guidelines and regulatory con-
trols which will reduce negative impacts on land values and insure com-
pliance of such installations with the Weld County Comprehensive Plan.
As indicated above, Weld County is unwilling to sacrifice prime
3
agricultural lands when such sacrifice is unnecessary. However, it is
recognized that electrical, oil and gas energy are resources which also
serve the total community. They are a necessity for many urban and
agricultural uses, and make many of the conveniences of modern living
possible. As a result, this amendment to the Comprehensive Plan
addresses the trade-offs which must be considered between urban and
agricultural uses as we strive to utilize our resource base to its full
potential.
The basic purpose and intent of this plan is to (1) set forth policy
guidelines as amendments to the County Comprehensive Plan, which
minimize conflict between existing and proposed land uses and proposed
public utility structures; and (2) to promulgate regulations, as amend-
ments to the Weld County Zoning Resolution, for the administration of
activities involving the location of major electrical transmission lines,
pipelines, power plants, substations, storage areas for oil and natural
gas and central office buildings of telephone utilities. This plan is
based on interviews with personnel of numerous utilities operating with-
in Weld County, on input from various local organizations and agencies,
and on existing Weld County land use policies.
In the following sections, this Plan first examines the major
energy facilities and their relationship to existing and proposed land
uses in Weld County. The Plan then sets forth various policy guide-
lines directed at minimizing conflicts which may occur as public
utility facilities are constructed in our agricultural and urban areas.
4
Finally, the Plan establishes a permit system for reviewing applications
to construct major oil, gas and electrical facilities within the unincorpor-
ated areas of Weld County.
5
I. Public Utility
Systems
I. Public Utility Systems
There are numerous locations in Weld County where oil and gas
resources have been discovered. Many miles of pipeline have been laid
to carry these resources from production wells to nearby storage tanks
and distant processing facilities. There are also many additional miles
of line which traverse Weld County carrying oil and gas produced in other
counties and states to various processing sites and market centers located
in the Denver Metro region. This existing pipeline system is comprised
of three general categories of lines:
1) well gathering lines (3-4 inches in diameter)
2) lateral gathering lines (6-10 inches in diameter), and
3) trunk lines, mainlines or transmission lines, (10 -24
inches in diameter)
In any case, these existing lines continue to function as oil and gas are
pumped into the system from local and outside sources.
Many miles of electrical transmission line, which are much more
obvious in their presence than underground pipeline, also exist in Weld
County. At the present time, these lines carry electrical energy from
sources located in other areas to electrical utility companies throughout
this region for distribution purposes. Electrical utility systems also have
7
components with different functions, generation facilities, transmission
lines, substations and distribution lines.
The components of the existing utility systems and their functions
are presented in this section. The concerns of the utility companies for
reliable and efficient operation are also presented.
8
A. Electric Systems
There are nine agencies currently involved in the generation,
transmission and/or distribution of electricity in Weld County. These
include:
1. Home Light and Power Company,
2. Morgan County REA (Rural Electric Association),
3. Pine Bluffs REA,
4. Platte River Power Authority, Inc. ,
5. Poudre Valley REA,
6. Public Service Company of Colorado,
7. Tri-State Generation and Transmission Association,
8. Union REA, and
9. U. S. Bureau of Reclamation.
The facilities which may be associated with such companies include power
plants, transmission lines, substations and distribution lines. Home
Light and Power Company and the four REA' s operate a few miles of elec-
tric line which can be classified as transmission line, however, their
systems principally consist of primary and secondary distribution lines.
These lines generally parallel county roads and city streets or alleys.
Structures which carry distribution lines are referred to by most people
as "telephone poles. " Transmission lines, on the other hand, generally
9
utilize steel or double-pole wood structures for support and are recog-
nized by most people as electrical facilities.
Local electric distributors generally receive their energy from
agencies which generate electricity at hydroelectric or thermal (fossil-
fuel, nuclear, geothermal) generating plants, or from intermediate
distribution companies who buy power from generating agencies and sell
it to the local electric companies. At the present time, energy supplied
to Weld County is generated by distant U. S Bureau of Reclamation
projects and delivered by a system of high voltage transmission lines
to intermediate distribution companies such as Tri-State Generation
and Transmission Association or Platte River Power Authority (PRPA).
"Tri-State" delivers power to the local electric companies which
operate in Weld County. "Platte River" provides electric power to
four cities outside of Weld County ( Fort Collins, Loveland, Estes
Park, and Longmont), however, the PRPA transmission system affects
lands in this county.
The Weld County service areas of the local electric companies
are delineated on Map 1, Page 12. Map 2, page 12a
depicts all substations, power plants, electric lines (33KV and above),
and the company responsible for such lines and facilities. Table 1
classifies the various sizes of electric lines which exist in Weld
County.
10
Table 1
Classification of Electric Lines
Normal Voltage Carried in
Classification Voltage Range Weld County
secondary distribution 0-750 volts 110-220 volts
primary distribution 7. 5 -33 KV I 7. 2-12. 45 KV
34. 5KV
subtransmission 33 -69 KV 44 KV
69 KV
115 KV
transmission 69 -345 KV 230 KV
**
EHV transmission 345 KV and higher 345 KV
MKV - Kilovolt ( 1, 000 volts)
4:
EHV - Extra High Voltage (used primarily for intrastate transmis-
sion)
11
B. Oil and Gas Systems
There are a number of companies presently involved in the
production, transportation, processing and/or distribution of gas and
oil in Weld County. These companies include:
1) Adolph Coors Company
2) Amoco Production Company
3) Chevron Oil Company
4) Cheyenne Pipeline Company
5) Cities Service Oil Company
6) Colorado Interstate Gas Company
7) Continental Pipeline Company
8) Halliburton Gas Company
9) Industrial Gas Supply Company
10) Kansas-Nebraska Natural Gas Company
11) Martin Gas and Oil Company
12) Panhandle Eastern Pipeline Company
13) Pasco
14) Philips Petroleum Company
15) Public Service Company of Colorado
16) Rocky Mountains Natural Gas Company
17) Standard Oil Company
13
18) Vessels Gas Processing
19) Western Slope Gas Company
20) WyCo Pipeline Company
Many of these companies have established facilities in or near
production fields located in Weld County, while some of these com-
panies simply traverse the county with transmission facilities tied into
out-of-county production or distribution points. The "Wattenburg
Field" located in the Southwestern portion of Weld County is the largest
production area in this county. The following paragraphs describe the
facilities and various methods utilized by companies involved in the
production and transportation of gas and oil in such fields.
1. Pipelines
Generally, companies involved in petroleum production within
Weld County contract with pipeline companies to transport the product
from the well head or tank battery to processing plants, refineries,
stations, terminals, and other delivery and receiving points. Various
steps and facilities are involved in this delivery process.
In the case of crude oil, the product is moved from the well head
to a storage tank in the immediate vicinity through gathering lines.
Gathering lines are, in most cases, relatively small diameter steel
pipes (cast iron, plastic, and copper are also utilized to lesser extent)
which function at pressures up to 200 pounds per square inch (psi).
Gathering lines are also used to move crude oil and other liquid
14
hydrocarbons produced from individual wells to a main line pump
station. Main lines (transmission lines), which function at pressures
up to 1000 psi, are then used to carry the crude oil to destination. As
the oil moves through this system of pipelines, flows are maintained by
utilizing pump stations which are located at intervals along the lines.
The destination points of the oil may be a tank farm where the oil is
stored in storage tanks of various capacities; it may be a junction point
on another pipeline system which accepts the oil for further transport;
or it may be an oil refinery where the crude oil is processed into refined
products of the petroleum industry.
Once the crude oil reaches a refinery, additional pipelines may be
utilized for transportation of refined products. Normally, a products
line, as it is called, extends from a petroleum refinery to terminals
along the line where the products are delivered into tanks. Products are
distributed from these tanks to adjacent markets by tank truck or trans-
port. Refined products which may be pumped through a products
system may include gasoline, kerosene, and light fuel oils.
Natural gas pipeline systems are comprised of gathering lines,
compressor stations (pump stations), and transmission lines extending
from natural gas producing areas to the distributing systems of cities
and towns. The flow of liquid or natural gas through pipelines is directed
and controlled by a dispatcher in much the same way that the movement
of trains is controlled on a railroad. Flows are physically regulated by
15
control devices and valves, many of which are automatically operated
from control stations hundreds of miles away.
Common diameters for both oil and gas lines are between 2 inches
and 24 inches. Larger sizes are rare, but do range up to 48 inches or
more. For purposes of this plan, oil and gas transmission lines shall
be considered to be any line of 10 inches diameter or larger which creates
a hoop stress of 20% or more at their specified yield strength.
2. Storage Facilities
Storage areas for oil are usually located at the beginning or end
of a major transmission line. Storage areas at the end of a line (area of
destination) have an average capacity of 60, 000 barrels. Storage area
capacities at major points of origin average approximately 200,000
barrels. Such storage areas occur at very few locations throughout the
country. The 60, 000 barrel capacity storage area could be used as actual
supply for several days if the major transmission line were shut down.
However, the main oil supply for most areas is usually not the oil
storage facility, but the oil which is in the actual pipeline.
Storage areas for natural gas consist of small surge tanks, under-
ground caverns, and, as in the case of oil, the pipeline itself. Under-
ground caverns consist of gas tight natural caves which have been
cleaned and purged of any existing gas. Underground caverns are used
for storage purposes in this region just south of Ft. Morgan in adjacent
Morgan County.
16
C. New Development
The use of electricity, oil and natural gas is basic to our life-
style and our economy. Almost nothing is so taken for granted as that
there will be light when the switch is turned on and heat when the thermo-
stat is turned up. Utility companies which supply the energy to heat and
light our homes and businesses, and to run our machines, must antici-
pate future energy requirements prior to the time such supplies are
actually needed. In other words, new production, generation and trans -
mission facilities must be ready to go "on line" before energy shortages
occur, not after they occur. Growth rate in the demand for power is fairly
predictable and can be translated into system needs for new facilities.
Development or extension of public utility facilities, once need is deter-
mined and accepted, revolves around the question of where the needed
facilities are to be built.
Technical, economic, legal, environmental, and public opinion
factors are included in the site selection procedure used by most utilities.
Public Service Company of Colorado, for example, considers the follow-
ing elements when selecting routes for major power lines: (2:1 -4)
1) Present and proposed land use patterns and zoning regulations;
2) Social values, such as aesthetics, historical and archaeological
interests;
19
3) Existing utility corridor analysis to determine feasibility of
joint use;
4) Economic and reliability analysis to provide reasonable and
continuous service to consumers;
5) Physical evaluation of floodplains, geologic hazards, topo-
graphy, marshes, and hydrology to determine the environ-
ments' capability of accepting a power line; and
6) Vegetation and wildlife analysis in efforts to keep adverse
impacts to these resources to a minimum.
Even though each utility company may evaluate similar elements in the
site selection procedure, the importance they attach to these various
elements may differ. For instance, one company may consider agri-
cultural land use important, and go to great efforts to avoid inter-
ference with agricultural operations. At the same time, another com-
pany may consider wildlife or recreational areas more important and
attempt to avoid these land uses, to the potential detriment of agricul-
tural operations. In general, most companies follow guidelines and
criteria established by the Federal government regarding safety, land
use and environmental factors. In any case, the principal function of
the utilities industry is to supply energy at a reasonable cost, where
and when it is required. Therefore, such factors as construction costs
and system reliability become primary concerns when present or
projected needs require new construction or extension of existing facilities.
20
1. Reliability and Cost Factors
a. Interconnection and Dispersion of Power Facilities
The size and location of new facilities must be considered
in relation to the distribution of system load and the layout of the inter-
connecting transmission network. By this means, surplus energy can
be shifted at a moments notice to any area facing a temporary shortage
or to meet extra demands. Interconnection saves the building of addi-
tional facilities that would operate mainly in such periods, and con-
sequently reduces costs. Similarly, power generation points strategi-
cally located enable the power companies to better meet their customers'
needs for reliable electric energy. Electric utility companies prefer
to disperse the generation facilities in order to decrease the potential
for prolonged power failures.
The ability to supply electric energy from a variety of power
sources and via a variety of transmission routes has greatly improved
the efficiency and reliability of the utility companies.
b. Right-of-Way Length
The length of transmission line or pipeline right-of-way
is a primary factor to be considered when present or projected needs
require new construction or extension of existing facilities. In general,
a direct route between an energy source and a delivery point is con-
sidered most economical when only installation costs are given consid-
eration. In other cases, such as in mountainous areas, it is often
21
more feasible, and actually shorter, to route a line around a mountain
than over it; however, in Weld County, any non-direct route requires
increased line length and more support structures or facilities. In
the case of electrical transmission lines, power losses (energy capa-
bility and efficiency) are proportional to the length of line; therefore,
increased length results in higher operating costs. Since capital and
operating costs become part of the rate base, these additional costs
are finally passed on to the consumer.
c. Transmission Line Support Structures
The type amt design of transmission line support struc-
tures is a factor which affects capital costs. There are four basic
types of structures utilized in Weld County: (1) single pole wood;
(2) H-frame wood; (3) lattice steel; and (4) tubular steel. Numerous
variations or designs for each type structure are utilized. Single pole
wood structures are normally used for all lines of 69 KV or less. Struc-
tures used to support larger lines are often a matter of company
preference based on considerations such as cost, reliability, and public
acceptance. For example, one company may prefer to carry a 115 KV
line on H-frame wood structures, which minimize cost and still provide
a high degree of reliability. However, tubular steel poles may be used
to minimize negative impacts on land values and aesthetics. 1975 cost
approximations for single-pole tubular steel structures are listed below
in Table 2. These figures will give the reader an idea of the expense
22
involved in utilizing such structures. It should be noted that inflation
is causing costs to rise at approximately 8% per year currently.
Table 2
1975 Costs for
Single-pole Tubular Steel Structures
Up to 25° Angle 55-90o Angle
Single Circuit Double Circuit Division Pole Division Pole
$6, 000. 00 $12, 000. 00 $17, 000. 00 $20, 000. 00
According to our interview with U. S. Bureau of Reclamation
personnel, the cost of using single pole tubular steel rather than H-frame
structures is approximately 50% greater, and that the cost of lattice
steel structures is approximately 20% greater than H-frame structures
(3: Interview).
d. Underground Electric Transmission and Distribution
Underground electric power distribution is an alternative
which eliminates the need for support structures and reduces maintenance
c osts. However, underground systems are generally more expensive, and
for higher voltage lines, technologically unfeasible for long distances.
23
In general, the higher the voltage the greater the problems associated
with underground lines. Normally, when the voltage is lower, there is
a smaller difference in cost between underground and overhead lines.
For instance, when considering a particular subdivision, the cost of
underground distribution lines may vary from . 25 to 7 times the cost of
overhead lines. In other words, it may actually cost less to bury dis-
tribution lines within a mobile home park, but cost much more to place
distribution lines underground in mountain subdivisions. In most con-
ventional subdivisions, the cost for underground lines is approximately
1. 5 to 2 times greater. Underground 34. 5 KV lines cost approximately
3 to 4 times more to construct than overhead lines of the same size.
The cost factor for placing even higher voltage lines underground may
run from 10 to 30 times more. Downtown metropolitan areas are a
major exception to this "rule-of-thumb " In such areas, overhead
costs skyrocket because of intense land uses. However, in these cases,
underground lines, though still expensive, are more feasible when the
need for elimination of conflicts between utility structures and existing
uses is considered.
Information tends to indicate that the placement of high voltage
transmission lines underground could lead to substantial costs to con-
sumers of electrical energy. In general, underground facilities may be
feasible, but the decision to place lines underground in particular areas
must be given careful consideration and evaluated with reference to
24
trade-offs associated with such factors as consumer costs, feasibility,
reliability, land values, aesthetics and impacts on land uses.
In Weld County, a few electric companies are placing their dis-
tribution lines underground in order to reduce maintenance costs, even
though such lines are slightly more expensive to install. In the southern
part of the County, problems have emerged as a variety of utility com-
panies and agencies have begun laying underground systems. In many
cases, electrical cables have been damaged as trenching operations
have proceeded for additional underground utility installations. Such
problems could be eliminated through more adequate communication
between the companies and agencies involved. In the northern part of
the County, a not too unusual problem results as rodents chew up the
buried cable. In general, however, these problems are not as great or
as costly as those caused by the effects of ice and wind on overhead
lines.
e. Pipeline Transmission
Pipeline transportation of petroleum in large volumes
can be accomplished at lower costs than those incurred by utilizing
methods of overland transportation. However, there are certain prob-
lems associated with the use of pipelines. In the case of new, large-
volume production leases, a pipeline company is generally allowed a
certain time period for the connection of wells (from 60 to 120 days)
after the producer gives notice that a well is completed and ready for
25
connection. Under normal circumstances, the receipt of this notice
triggers right-of-way acquisition and commencement of pipeline
installation. Pipeline companies failing to connect in the specified
time are required to make "take-or-pay-for" payments to the producer
in order to keep the well involved subject to the contract. Such pay-
ments, or front-end money, serve to increase cost of purchased oil
and gas; a cost which is passed on to the consumer.
In terms of maintaining such pipeline systems, one of the principal
costs is the prevention or retardation of corrosion of the metal in the
pipeline. Chemical and physical. tests of soils and studies of drainage,
electrolytic, galvanic, and other conditions are required in order to
ascertain the kind and location of protective coating which will be most
useful in preventing such problems and to determine the necessity for,
and most suitable method of, cathodic protection.
2. Physical Factors
Energy sources exist naturally in the case of oil and gas and,
therefore, must be produced where they are found. Electricity, on the
other hand, is created artificially and may be produced in a variety of
locations depending on the type oti g* nerating plant proposed. Likewise,
pipeline systems may be located in a variety of right-of-way configura-
tions once the lines depart from the wellhead area.
A number of physical factors may become important in the site
selection process when electrical power generating facilities are proposed.
26
For instance, power plant site considerations call for flat land with
stable soil conditions capable of supporting foundations and heavy equip-
ment. The site should also offer reasonable protection against flooding.
Pipelines and electrical transmission lines which deliver energy from
the sources to consumer areas have few physical requisites essential
to their location. However, certain physical conditions are preferred,
and others avoided,for economic and engineering reasons. Steep
rocky areas, geologic hazards, marshes, corrosive soils, and areas
with an avalanche potential are avoided whenever possible. For
example, when a new pipeline is proposed between two points, a tenta-
tive route is selected. This route is then more precisely checked for
the physical conditions noted above by the use of information derived
from aerial and ground surveys. Rights-of-way are then purchased
along the entire route, after which an accurate engineering survey of
the exact routing of the line is within the right-of-way completed prior
to construction. Pipelines are then generally buried to a, depth below
frostline which: ( 1) avoids interference with farming or other uses of
the land surface, (2) provides protection against accidental breakage,
and (3) provides protection against increased expansion and contraction
difficulties which the line would be subjected to if laid on or just below
the surface. In general, whenever the process of site selection occurs,
several physical factors are given consideration. These may vary as
different types of facilities are considered.
27
a. Site Size and Right-of-Way Width
Land requirements for acreage and easements vary
with the size and type of facilities proposed. For example, a modern
coal-fired plant designed for 4, 000 megawatt capacity may range from
1, 000 to 2, 000 acres, depending on allowances made for fly-ash
storage and the type of cooling system utilized. In the event a man-
made reservoir is used for cooling, upwards of 4, 000 additional acres
may be required.
On the other hand, a 4, 000 megawatt capacity gas-fired or oil-
fired plant requires a land area approximating 100 to 200 acres. In
other words, one-tenth (1/10) the land acreage required of a comparable
sized coal-fired facility. Nuclear power plants of 4, 000 megawatts
require about 115 acres for the actual power generation facility. How-
ever, when cooling water systems are used in such plants, water
requirements are approximately 50 per cent greater than in comparable
fossil-fired plants. Hence, acreage needs will again depend on whether
an auxiliary cooling system is necessary (4:24).
When considering transmission facilities, right-of-way sizing
becomes an important consideration. Electric, oil and gas utility
easements must be wide enough to allow for installation, operation, and
maintenance of the lines involved. In the case of pipelines, twenty feet
is the general width for right:-of-way (R. O. W. ) easements in Weld
County. However, depending on line size, pipeline easement contracts
generally have stipulations for temporary R. O. W. widths ranging up to
28
sixty-six feet in order to accommodate construction operations. In
such cases, all R. O. W. except ten feet on each side of the easement
center line may revert back in full title to the landowner after the con-
struction period . The twenty feet of easement area must then be kept
free of any permanent structures which would interfere with operating
or maintenance procedures.
The width of electric transmission line R. O. W. is established not
only to allow for installation and maintenance of the lines, but also to
ensure that other structures are not allowed to intrude so close so as to
be susceptable to the dangers associated with the high voltage wires or
the possibility of a support structure toppling over. When considering
single-circuit transmission lines, a 115 KV line will generally have an
easement width of 75-100 feet; a 230 KV line an easement width of 150
feet; and a 345 KV line an easement width of approximately 190 feet.
Distribution line R. O.W. , however, is not considered a critical safety
necessity and may be described in such general terms as "one foot
outside of road right-of-way. "
When the location of electrical substations is being considered, a
number of other factors must be taken into account. Substation acreage
requirements range from small local site requirements of about 2z
acres or less, to large regional site requirements of 80 acres or more,
depending largely upon the load area to be served and anticipated growth
rates. The U. S. Bureau of Reclamation Ault Substation in Weld County
is an example of a large regional substation being developed to
29
accommodate a large number of major transmission lines needed to
serve a rapidly increasing population and expanding industrial base along
the Northern Colorado Front Range.
Substations are located along transmission lines in order to step-
up (increase) or to step-down (reduce) power. Power is carried by an
electric line in proportion to the square of its voltage. Thus, if
voltage is tripled, nine times as much power is carried. Electricity
is generally stepped-up outside a generation plant to much higher
voltages for economical delivery to distant load centers, where the
voltage is then stepped down to distribution levels.
Substations are usually constructed as near the center of a load
area as possible. Substations serving major transmission lines geo-
graphically cover large load areas; therefore, their placement is more
flexible than a substation handling local power distribution. In lightly
loaded rangeland areas, such as exist in the northern and eastern
sections of Weld County, these lines may extend 50-60 miles or more
from a substation. In any case, the greater the load in a particular
area - the greater the number of substations required to provide reliable
service.
b. Cooling Water
An essential requirement in power plant siting is a
supply of cooling water in sufficient quantity and of assured availability
to provide water necessary for steam condensation purposes. The
30
most efficient and, in many cases, most practical method of steam con-
densation is once-through cooling in which river or reservoir water is
passed directly through the turbine' s condenser and then returned to the
water source at a 15-25o F increase in temperature. The quantity of
cooling water required for once-through cooling of a 4, 000 megawatt
fossil-fired plant is approximately 2 million gallons per minute and for
a nuclear plant of comparable size, 3. 2 million gallons per minute.
It is highly desirable, if not essential, to locate such plants adjacent
to the body of water from which the cooling water is to be taken (4:24).
In plants of this size, where water is not available in such quan-
tities, either because of low flow conditions or environmentally estab-
lished temperature restrictions, cooling towers are necessary. The
use of such towers reduces water requirements to about 52, 000 gallons
per minute, although they create a consumptive use through evaporation
of about 37, 000 gallons per minute. Nuclear plants increase the con-
sumptive use figure by about 50 percent (4:24). In general, however,
cooling reservoirs also need a water source, both for their creation
and for replacement of water lost through natural as well as power
plant-induced evaporation. The location of a water supply source thus
remains a critical factor to be considered in siting decisions.
c. Fuel and Energy
Nuclear plants are free of any siting requirement with
regard to fuel supply. Hydroelectric and fossil-fired plants, however,
are dependent upon reliable and economical access to water or fossil fuel
supplies. Thus, the type and location of such power plants are often
determined by the location of fuel sources or the availability of water
for generation purposes.
Historically, fossil-fired plants have been largely confined to the
areas of the country producing gas, oil, or coal. However, the
staggering increase (400%) in the price of oil following the Arab oil
embargo of 1973 and the growing unavailability of gas has nearly
eliminated these two fuels as major resources in the generating of
electrical energy. In addition, experts estimate that hydroelectric
plants will generate smaller percentages of our electricity in the future
for a variety of reasons: (1) most of our great rivers have already
been dammed to capacity, (2) objections to the construction of new dams
because of the destruction of natural "wild river" systems and fish life,
and (3) the useful life of dams appears to be less than one hundred years
due to silt buildup. Therefore, unless alternative sources such as
solar energy become more economical in the future, it appears that
nuclear energy and coal are the fuels which we must rely upon to supply
our electrical needs. Thus, it may be assumed that fossil fuel plants
that are built in the future will likely be located near our nation's coal
resources.
Historically, coal has been the primary fuel used for the produc-
tion of electricity, accounting for approximately 44 per cent of the total
electricity generated, while nuclear energy has accounted for less than
1 per cent of the total. In that coal is the only fossil-fuel resource in
32
which the United States is completely self sufficient (5:Folio), it appears
that coal's capacity to supply our electrical energy needs is only limited
by the logistic and economic problems of mining and transporting the
enormous quantities necessary for generation and by associated environ-
mental problems. The Weld County Mineral Resource Study, completed
in 1975, delineates those areas of Weld County where coal resources
are to be found.
d. Access and Transportation
The existence of railroad and/or other transport
facilities are essential during construction and operation of power
plants, transmission lines and pipelines. When considering power plant
sites, it must be determined that access roads and bridges are capable
of supporting heavy loads. As power plants are constructed and oper-
ated, large amounts of fuel and components of equipment must be shipped
in and sometimes replaced. In the case of nuclear plants, access for
removal of spent fuel elements must be considered. Such elements
must be placed in massive shielded shipping casks, weighing 25 to 100
tons, for transportation to a reprocessing plant where uranium and
plutonium are separated from the fission products.
In considering site locations for pipelines or electrical transmis-
sion lines, convenient access to the facilities over all weather thorough-
fares is very important. If such access is available when leaks,
outages or other mishaps do occur, service can be restored as quickly
33
as possible. This consideration is a major reason for locating most
distribution lines adjacent to county roads and city streets. As the
size of pipelines and electric transmission lines increase and as the
distance they traverse becomes greater, access becomes less of a
concern due to the trade-offs which must occur when cost is considered.
Conformance to the rectilinear pattern formed by the road system can
increase the cost of building larger lines by a factor of 2. Therefore,
in open country, utility companies are more likely to follow terrain
features, rather than roads, as larger lines are constructed. In such
cases, if access becomes a substantial problem, lines may be checked
from an airplane to spot maintenance problems.
e. Existing Land Use Obstacles
As noted previously, whenever possible,utility com-
panies avoid locating their facilities on steep rocky areas, geologic
hazard areas, marshes, corrosive soil areas, and areas with an
avalanche potential. Federal regulations require that such site charac-
teristics be given consideration in various instances. Fossil-fuel
generating plants are required by Federal regulations to be constructed
to withstand earthquake forces So% greater than building and highway
structures covered by building codes. Nuclear plants must be designed
to withstand the maximum earthquake motion that could be expected at
the particular sites on which they are located.
34
Other physical obstacles may also enter into site evaluation. In
routing transmission and pipelines, the avoidance of residential struc-
tures is generally given precedence over most other considerations.
In these cases, right-of-way width requirements become an important
factor in determining whether a line can be placed between a residence
and a road right-of-way. In general, priorities given to various land
use considerations by particular utilities will determine to a large
extent whether specific land uses will be treated as obstacles or not.
For example, many utilities will go to great efforts to avoid routing
lines or siting facilities on park and recreation areas, on lands irri-
gated by pivot sprinklers or on lands with a potential to be irrigated by
the use of sprinklers. In such cases, these specific land uses are
treated as obstacles and avoided to the extent practical.
35
D. Summary
This section has examined the existing electric, oil and gas
facilities situation in Weld County, and has reviewed a number of factors
which are important considerations to public utility companies with
reference to new development or extension of major utility facilities.
The demands for energy supplies are increasing daily. These demands
are stimulated by the rapid population growth occurring in the front range
areas, as well as the expanding use of sprinkler irrigation systems in
dryland areas of the eastern Colorado plains. Weld County is experi-
encing a large portion of this growth and expansion, and can therefore
expect continued development and expansion of major utility facilities
needed to serve the increasing demand for energy.
Utility companies must keep a step ahead of demand pressures
with their energy supplies or energy shortages will occur. Thus,
facilities must be planned and built prior to the time they are actually
needed. In choosing locations for new facilities, a number of factors
are taken into account, including technical, economic, and physical con-
siderations. This section has noted that the priorities attached to each of
these factors may vary between companies. It is at this juncture where
the next section of this plan begins, because it is primarily differences
of priorities which have led to conflicts between utility companies and the
36
citizens of Weld County when new facilities of public utilities have
been proposed.
37
II. Public Utility Development
and Land Uses
II. Public Utility Development
and Land Uses
Two major land use categories are examined in this section with
reference to conflicts between power facilities and land uses.
a) agricultural area; and
b) community growth areas.
Although the County is principally characterized by extensive and inten-
sive agricultural production activities, a rapid population growth is
increasing pressures for residential, commercial, and industrial
development. As discussed earlier, the general policy of Weld County
concerning urban development is to encourage growth around the exist-
ing 28 incorporated towns. One reason for this policy is to minimize
urban and agricultural land use conflicts. Thus, population growth
areas are segregated from outlying agricultural lands and, therefore,
treated separately in this plan. An additional category entitled "Other
Resource Areas" examines potential conflicts between development
of power facilities and existing r 'r,•ral, wildlife, and cultural resources.
39
A. Agricultural Areas
Agriculture is a vital segment of the County economy. The County,
as a whole, is ranked number two in agricultural production among all
counties in the United States (6:4).
Irrigated agricultural lands are, in general, the most productive
lands in the County. Closely tied to water distribution systems, these
lands are found primarily within the major drainage systems of the
area. Irrigated lands, in many cases, occupy those areas most suscep-
tible to urban growth; and, therefore, to increased needs for electrical
transmission facilities. Dryland crop areas and rangeland constitute
a significant portion of Weld County' s land area. These vast acreages
are found in some of the less populated portions of the County. These
lands support large populations of wildlife and livestock, as well as
important dryland agricultural crops.
The Weld County Comprehensive Plan has recognized that "agricul-
ture" is considered a valuable re:.ource in Weld County which must be
protected from adverse impacts resulting from uncontrolled and undir-
ected business, industrial, and residential growth. " To insure this pro-
tection, the plan further states that ". . . any uses of prime irrigated
farmland for uses other than agricultural will be critically reviewed to
insure the proposed development will not adversely impact the
40
agricultural interests of the County and that development will positively
contribute to the overall economy, environment and tax base of the
county. " (7:48)
In order to provide protection of agricultural lands, the A- Agri-
cultural Zone District was established under the Weld County Zoning
Resolution with the following intent as stated in the Resolution:
The intent in establishing the A- Agricultural Zone District is
to allow all agricultural and related uses in those areas in
which agriculture is and should continue to be the predominant
land use. This district is intended to discourage encroachment
of incompatible uses upon the agricultural land in the district,
to encourage agricultural uses as the highest and best use of
the land in the district as compared with other uses in conflict
therewith, and to provide For the orderly expansion of urban
growth in conformance with the Weld County Comprehensive
Plan (8:6).
Under the resolution, only those uses compatible with agricultural
operations are allowed.
1. Power Plants
Given present technology, the nation as a whole is highly
dependent upon fossil fuels for energy production. The most abundant
fossil fuel, and historically, the primary fuel for the generation of
electricity, is coal. Weld C2itaw is underlain by vast deposits of
low-sulfur coal. Considering the high price of oil and the increasing
scarcity of natural gas, it seems that the potential exists for the
development of Weld County coal resources in conjunction with
electrical generating facilities, even though oil and natural gas
resources are present. However, whatever the fuel used, development
41
of electric generating plants can create unfavorable impacts on agri-
cultural lands. The following sections discuss the impacts which may
be anticipated from such development.
a. Agricultural Land Loss
The amount of land required for a generating plant site
can be substantial, depending on the type of plant proposed. In the
case of a coal-fired electric generating plant, more land is required if
the coal resource is to be mined at the site than if it is to be shipped
in by rail. In addition, more '. .*a is required if a new water holding
reservoir is necessary, than if -•.n. existing reservoir can be utilized.
As noted previously, typical land area requirements for a modern
4, 000 megawatt capacity coal-fired plant may range from 1, 000 to
2, 000 acres. In the event a man-made reservoir is required for a
cooling medium, upwards of 4, 000 additional acres could be neces-
sary (4:24).
Nuclear plants, as noted previously, require less land area than
fossil-fuel plants for the actual power generation facility, but, in
some cases, greater area t r cecling water requirements. The 330
megawatt Fort Saint Vrain Nuc',c3.i. Electric Generating Station near
Platteville, for example, requires 1, 190 gallons of water per minute
for cooling purposes (9 :24). Public Service Company of Colorado
purchased about three sections of land (roughly 2, 000 acres) for their
plant site, which is located at the confluence of the South Platte and
42
St. Vrain Rivers. In this case, most of the land area is still being
farmed. However, the possibility exists that substantial amounts of
ground may be diverted from agricultural production as new facilities
are added to the plant. Land requirements are thus a major concern
of Weld County with reference to future proposals for power plant
development; particularly in those instances where prime agricultural
lands would be taken out of crop production.
b. Agricultural Water Loss
Another of the principal concerns related to the
development of generating facilities is the large amount of water
necessary to operate a generating plant and the sources from which
such water is to be procured. For example, twenty acre feet of water
per year is generally required per megawatt of power generated.
In other words, a 330 megawatt generating plant would require approxi-
mately 6, 600 acre feet of water each year. If this water is to be
taken from existing agricultural water supplies, then several thousand
acres of irrigated land would be lost, even though the plant site itself
may be located in an unirrigated area. Furthermore, if coal develop-
ment takes place in conjunction with a coal-fired generating plant, it
could disturb groundwater availability and quality in and adjacent to
the areas being mined by: ( 1 ) removing or displacing the aquifer
formation, (2) blocking or diverting natural underground flows, or
(3) polluting underground water sources with leachate from acid
43
forming materials. Finally, development of an electric generating
facility could bring a large influx of construction workers, plant
workers, miners, and family members which would require diversion
of even more agricultural water for domestic purposes. In general,
water is essential to the maintenance of high agricultural productivity
in Weld County. The development of an electric generating plant
poses a potential threat to the existing county economy by diverting
substantial water supplies for cooling, production, and domestic
purposes, thereby causing a shortage of water needed for agricultural
uses.
c. Pollutants
Damage to crops and natural vegetation created by pol-
lutants is another concern in Weld County. High concentrations of
sulfur oxides, nitrogen oxides and particulate matter resulting from
coal-fired generation can destroy plant life. However, limited data
exists to help determine what affect these power plant pollutants
have on crops and natural vegetation at those concentration levels
permitted by Federal and State air pollution standards. The informa-
tion which is available indicates that: (10: Interview)
1) Damage may occur to highly sensitive crops, such as alfalfa,
from power plant sulfur dioxide (SO2) emissions, when such
emissions meet present air pollution standards. Those standards
allow release of 1300 micrograms of SO2 every three hours.
44
Damage to such crops is most likely to occur during brief periods
when high concentrations of SO2 gases are emitted.
2) Native grasses could possibly benefit from power plant
emissions of SO2 at the concentrations permitted by current
standards. Studies conducted in Montana on power plant pollutants
suggest that such concentrations of SO2 act as a fertilizer which
assists native plant growth.
3) Current standards for emission of particulate matter do not
cause negative impacts on crop production or natural vegetation.
4) Nitrogen oxides react with sunlight to form ozone which is
destructive to plant life. Ozone formation generally occurs
40-50 miles downwind from power plant sites and at concentrations
which, in themselves, are not likely to create a significant
impact. However, high oxident levels are already present in this
region, created by other man-made sources such as automobiles.
The additional oxidents emitted by the power plant could be suffic-
ient to create a harmful pollution situation.
Fly ash disposal is an additional concern. Approximately 160
pounds of this non-combustible, very fine waste matter remains from
the burning of each ton of coal. Most fly ash can be trapped and col-
lected by utilizing appropriate air quality control equipment in coal-
fired generation plants, thus preventing any serious air pollution
problems regarding this material. However, when mixed with water,
45
this waste material hardens into an impermeable mass on which
nothing will grow, and if placed in a landfill could adversely affect
groundwater supplies in and around the area. Coal and utility com-
panies are applying considerable research to this problem. They have
found that fly ash mixed with a moisture agent literally gets stronger
as it ages; suggesting that the substance may possibly be put to good
use in bricks, concrete and base material for roads (11 :5). Never-
theless, at present, fly ash is extensively deposited in landfill areas
and as such is a concern in our agricultural areas.
2. Electric Transmission Systems
Electric lines, because they are normally placed aboveground
and suspended from support structures, can create significant long-
term conflicts with agricultural operations. These problems are
especially evident in irrigated areas where agricultural lands are
more intensely developed, field sizes are smaller, farm structures
are more abundant, and lands are more densely populated. Although
aesthetics, or lack of the same, is a frequent concern voiced by
farmers and ranchers when a power line is proposed across their
property, their major concerns center around problems created by
the lines, structures, and right,of-ways which affect their farm
operations daily.
46
a. Irrigated Areas
Electrical transmission lines conflict to some extent
with all row crop operations when traversing fields. These conflicts
become most apparent when such lines are located in areas irrigated
by furrows or pivot sprinkler systems. During seeding and harvesting
operations, problems with transmission line structures and guy wires
are compounded when the farmer attempts to cultivate fields or
irrigate crops. Farmland is eliminated from cultivation around a
structure or guy wire for a distance of at least one-half the width of
a cultivator bar. For example, when a twelve row cultivator with
thirty inch row spacing is utilized in a given farm operation, an area
of approximately fifteen foot radius is left uncultivated around the
support structure. This creates two problems: ( 1) uncultivated ground
becomes a source of weeds, and (2) irrigation water must be diverted
around the area and redistributed on the other side. The latter is a
difficult problem, particulary in furrow irrigated areas. All water
from furrows interrupted by the waste area must be collected back
into one ditch, to be redistributed on the other side into an equal
number of furrows. Furthermore, this redistribution system usually
requires reworking each time the field is cultivated (generally three
times and up to five times per season depending upon the crop). This
operation can be a muddy, time consuming nuisance. In addition, in
their efforts to minimize the size of the waste area where weed control
47
will be necessary, farmers often break their equipment on the struc-
tures or guy wires. This creates additional time consuming and some -
times costly maintenance requirements.
Additional problems arise when irrigation facilities are located
underground and are therefore not readily observable. In such cases,
irrigation laterals and tailwater ditches can be damaged by construction
activities which precede the placement of a transmission line support
structure. In general, precautions should be taken to ensure that such
damage does not occur. Perhaps most effective, would be a process
wherein utility companies confer with landowners to determine if such
irrigation facilities are present. If they are, it would be possible to
determine what steps are necessary to ensure that their function is not
impaired.
Finally, support structures also interfere with the flow and even
distribution of water in flood irrigated alfalfa and pasture land, often
leaving dry areas on the downslope side of the structures. On irri-
gated lands utilizing pivot sprinklers, transmission line structures
obviously cannot be placed inside the rotation area without totally
restricting their movement. In areas using solid set or big jet
sprinklers, structures do not conflict to any great extent with irriga-
tion of crops. Nevertheless, the exact placement of structures is still
a concern of many landowners. Structures can, at times, be placed
on sites generally thought to be unacceptable, but specifically favored
by landowners over locations selected by utility companies. In many
48
instances, shifting particular support structure sites by just a few feet
can lessen impacts to farm operations.
b. Non-Irrigated Areas
In non-irrigated areas, power line right-of-ways,
including substation sites, do not generally create as significant an
impact to agricultural operations as in irrigated areas. Nevertheless,
even in these areas, placement of power line structures can create
problems if proper siting and maintenance procedures are not
observed.
In dryland areas, farmers have the same problem with weed
control created by power line support structures, that farmers have
in irrigated areas. Dryland farmers are just as likely to break
equipment in their efforts to reduce the size of weed patches created
among guy wires and support structures as are farmers in irrigated
areas. Furthermore, dryland farmers indicate that support struc-
tures located in their fields require uneven cropping techniques and
are a nuisance to work around. One of the more prominent examples
of this problem is the two parallel Bureau of Reclamation power lines
located on H-frame structures on the east side of County Road 27 west
of Nunn.
In rangeland areas, where vegetation is notably sparse, any
removal of ground cover during utility construction operations will
create erosion problems during periods of high winds or intense rains.
49
This problem is especially evident in sandy areas where sites have
been cleared and leveled for substations and aboveground pipeline
facilities. Ranchers have indicated that it may take years for natural
vegetation to be reestablished in such areas. In the meantime, blown
sand drifts along fencerows and, in some instances, covers roadways
to the extent that it must be periodically removed by road crews.
In addition to the above concerns, farmers and ranchers have
stated that utility company personnel often enter upon private lands
without first notifying the landowners involved. Such occurrences
are a concern to the landowners because they must stop whatever work
they are doing to investigate. In ranching areas, this is a particular
nuisance because of the acreages and long distances involved and the
ever-present threat of cattle rustling. Ranchers have been known to
confront "trespassers" at gunpoint to elicit their intentions. Thus, it
is particularly important that utility company personnel notify land-
owners before entering private property in order to coordinate their
activities with the landowners involved.
Another concern of farmers and ranchers which may arise
from utility company activities includes the placement and size of
easement signs. Many landowners feel that these signs are often
unnecessary and have found that such signs invite trespass from
hunters and other re creationists. It is their opinion that by reducing
the size and number of such signs, this problem will be avoided,
especially if the placement of the signs is coordinated with them.
50
c. Access
Possibilities of downed transmission lines require that
access routes be established along such lines. If the lines are located
in fields, disruption of irrigation systems and crop destruction are
likely to occur during the growing season as maintenance vehicles
enter fields to work on lines. In addition, when inclement weather
conditions exist, it is likely to be difficult if not impossible for
maintenance vehicles to enter fields. It is during such weather that
lines are usually downed; thus, service may become unavailable to
customers when it is most needed. Therefore, it seems advantageous
to all parties concerned to locate lines as closely as possible to the
existing road system. Often, utility companies do closely parallel
existing roads with their transmission lines. Support structures
which are placed within road right-of-ways are not only easily acces-
sible, they also eliminate most inteference problems with agricultural
operations encountered when they are located in fields. However,
most companies prefer to locate their lines on private property
adjacent to these road right-of-ways so that they are less likely to be
financially affected by future road expansion. When poles are
located in this manner, if the road is ever expanded, the utility com-
pany would not have to cover the cost of moving their line. If the
poles are located within the right-of-way, companies would have to
cover such costs, unless an agreement to the contrary could be
arranged between the utility company and the County Commissioners.
51
In general, such an agreement is only practical when single-pole
support structures are to be used and the county road right-of-way
is not designated for future expansion in the County Thoroughfare Plan.
In those cases where existing county road right-of-ways cannot
be utilized, efforts should be made to place structures in such a
manner that cropland fields are not split, particularly at a diagonal.
Past alternatives to routing a transmission line adjacent to or within
county road right-of-ways have included:
1) half-section lines;
2) quarter-section lines;
3) property lines;
4) field/fence lines;
5) drainage ways;
6) wasteland areas; and
7) railroad right-of-ways.
Each of these alternatives should be considered whenever the use of
road right-of ways is not feasible.
d. Cropdusting
Other concerns roust also be addressed in the placement
of electrical utility structures in agricultural areas. Cropdusting
operations, which are necessary for the production of many crops
can definitely be impacted by improper placement of lines and pole
structures. Cropdusting operations in this county are normally flown
52
during the growing season in order to alleviate insect and weed prob-
lems which threaten crops. The problem is compounded by the number
of applications required. For example, applications of insecticides to
potato and cabbage fields are required four to five times each season,
while corn and beet fields are sprayed only two to three times in the
same time interval. Application to other crops may vary greatly.
Cucumber and onion fields may be sprayed every ten to fourteen days
during the growing season, while wheat fields are normally sprayed
only once a year with herbicides or a herbicide-insecticide combina-
tion.
Electrical utility structures create the most difficulty for crop-
dusting operations in irrigated cropland areas because field sizes are
smaller (20 to 30 acres) and line concentrations are greater. The
latter results because irrigated areas are usually more densely
populated than dryland areas. In general, a plane loaded with chemi-
cals can climb over distribution lines with very little difficulty; how-
ever, as line height increases this climb becomes increasingly
difficult. Transmission lines carried on H-frame structures of stand-
ard height (60 feet) are cons tiered the maximum limit in terms of a
pilot' s ability to clear the lines, after a dusting flight over a given
field. If the lines are above this height, it is considered safer to fly
under the lines. When higher lattice and tubular steel transmission
lines are placed adjacent to normally lower distribution lines, such
"fly-under" becomes impossible. In such cases, the distribution lines
53
block the flight path of a pilot attempting to fly under the higher
transmission lines. When this occurs, the only alternative left to the
pilot is to fly over the transmission lines and still attempt to accom-
plish the task. This creates a very dangerous situation for the pilot.
Loaded planes have a tendency to "stall" in the steep climbs required
to fly over the lines. In addition, it is nearly impossible for a pilot
flying at speeds upward of 100 m. p.h. to accurately judge distances,
which is, in many cases, imperative if safe clearance of such lines is
to be the result. Finally, to accomplish his mission, a cropdusting
pilot must maintain a constant speed and altitude in order to get the
proper concentration of spray on the crop. Thus, high lines create
the same problem for helicopters as they do for fixed-wing aircraft
since a helicopter must also maintain constant speed and altitude when
making a pass over a field. Thi, becomes increasingly difficult as
more structures limit the pilot's flight path. Cropdusters currently
have a standard per acre charge for their services; however, it has
been indicated that farmers who have electric transmission lines in
their fields will eventually be charged additional fees.
3. Pipeline Systems
Pipelines, because they are normally placed underground
below plow depth, generally create less serious long-term conflicts
with agricultural operations than do overhead power lines. Most
conflicts which do arise are associated with construction operations
54
and can generally be rectified or avoided. However, aboveground
facilities associated with pipeline operations, such as compressor
stations and pig launchers, have the potential of creating long-term
land use conflicts with agricultural operations much the same as
electrical transmission support structures and substations. As a
result, essentially the same concerns apply and will therefore not be
reiterated. The following paragraphs are concerned with additional
problems encountered by agriculture as underground pipeline facilities
are installed.
a. Irrigation Ditches
A primary concern is the disruption of irrigation
systems by pipeline construction operations during the growing season.
A pipeline which transects an irrigation ditch may stop the flow of
water to cropland at critical periods, or may create weak spots in the
embankment. Such weak spots are highly susceptible to breaks
which, in effect, would prevent water from reaching those users
beyond the break point. In addition, subsidence may occur along a
pipeline which could effectively intercept and displace needed irriga-
tion waters. Thus, it is esper. s°y important to farming operations
that irrigation ditches not be cut or otherwise disturbed during the
growing season. It is preferable for pipeline companies to bore under
such ditches before or after the growing season and, where necessary,
to place temporary lines over the ditches during the growing season.
55
In any case, when traversing irrigated areas, pipelines create less
conflict with agricultural operations if the lines are placed at the tail
water end of irrigated fields rather than at other locations.
b. Construction Operations
The displacement of topsoil during construction of oil
and gas pipelines is a potential long-term problem in agricultural
areas. Under normal ditching and backhoeing procedures, the topsoil
from the ditch will be replaced on the bottom when the ditch is refilled.
This results in the less fertile '3 and C soil horizons replacing the
productive topsoil. As a result, crops grown in these areas will be
less productive. In addition, the ditching process can cause rock to
be brought to the surface. If this rock is not removed or buried below
plow depth, it will be detrimental to plowing and other field operations.
By utilizing double ditching techniques, topsoil can be replaced on
top, thus eliminating any long-term productivity problems.
An additional problem caused by pipeline construction operations
is related to fence damage and livestock movement. Pipeline con-
struction often necessitates the removal of fence sections. Even though
fence section removal is only temporary, it can, along with the very
presence of the pipeline or ditch, cause livestock movement and safety
problems. For example, cattle or sheep movement through unattended
fence cuts can result in crop damage to adjacent fields, safety hazards
to traffic and possible loss of the livestock. If notified in advance of
56
impending cuts, ranchers may move their animals or keep a better eye
on them. However, installation of temporary gates would greatly
alleviate any conflicts until the fence is properly mended.
Timing of construction operations is another important concern
in agricultural areas. Digging trenches and laying pipe through
cropland during the growing season can result in crop loss and lower
crop productivity. For instance, if a pipeline transects agricultural
land after crops have been planted, but prior to harvest time, the
crops in the easement area would either be completely lost or would
have to be prematurely harvested. Even though farmers would gen-
erally be compensated financially for such a loss by the utility com-
panies, reduced productivity is not in their best interests.
Trenching procedures during pipeline construction operations
also raise concern among farmers and ranchers in terms of changes
which may occur to existing underground utilities. This same con-
cern is also expressed by other utility companies who have had their
underground lines dug up by pipeline trenching operations in the past.
The problem may arise iron, `he limited amount of time allowed a
pipeline company to complete a'. took-up because of the normal
"take-or-pay-for" portions in their contracts with producers. In
other words, it may be less expensive for a pipeline company to com-
plete a hook-up on schedule and pay for the repair of private utility
connections and distribution lines which they dig up in the process,
rather than take the time to avoid such lines and fall behind schedule.
57
Nevertheless, landowners feel that pipeline companies should make
more effort to avoid cutting private utility connections. A cut tele-
phone line in a rural area could make an emergency sitution worse.
Loss of power at a modern dairy farm could have significant negative
impacts on milking operations and overall production activities.
Discarded crating and other trash left behind after construction
crews have completed operations is an additional cause of concern
among landowners which they would like to see alleviated in future
projects. In past cases, farmers and ranchers have had to spend
their own time and effort in picking up items of trash which interfered
with their operations and have developed bad feelings toward the utility
industry as a result. Trash removal is generally an unpleasant and
thankless task, but a necessary one. In general, those that haul
trash into an area should assume the responsibility for hauling it out.
58
B. Community Growth Areas
Rapid population growth is being experienced in Weld County.
The county as a whole has increased from a population of 89, 000 in
1970 to an estimated 115, 000 in 1976; roughly a 30% increase in six
years. Incorporated communities and lands lying in close proximity
to these communities are experiencing the greatest development
pressures from this population increase. The county encourages
such development to adjoin existing communities so long as it conforms
with the desires of the towns as expressed in their comprehensive plan.
Weld County policy discourages urban development outside of
incorporated community comprehensive planning areas, not only
because it conflicts with agricultural operations, but also because county
government was never intended to provide the urban services which such
communities do provide. This policy places a degree of responsibility
on the county to insure that any new development proposed around a
community is in conformance with the community's comprehensive plan.
In general, utility companies which make the effort to coordinate their
proposed plans with the appropriate representatives of affected commu-
nities can ensure that any conflicts with planned land uses are minimized,
and that direct conflict with adopted master plans of such communities
59
and with the policies set forth in the Weld County Comprehensive Plan
are avoided.
I. Power Plants
Development of power plants can mean that an unprecedented
population growth, as well as increased pollution will occur in this
county. If coal development is concurrent with development of a coal-
fired generation plant, then the impact will be compounded. In many
of our smaller communities, an influx of workers and their families
could easily double or triple the population of an entire town. Thus,
power plant development may have some large and far-reaching
social and economic implications for these communities which should
be addressed in order to minimize potential conflicts.
a. Socio-economic Impacts
Housing problems are generally the first negative im-
pacts to surface in communities confronted by large energy develop-
ments. With the start of construction, an influx of workers move into
local motels, apartments, and vacant houses. Later, families start
arriving. In communities with a small and limited supply of housing,
a heavy and rapid increase in housing demand results in an increase
in prices for housing, lots and rents. Many residents on fixed in-
comes, especially the elderly, are hit hard by the inflation in rents
and prices. Once all available standard housing has been taken up,
workers and their families turn to mobile homes--the most visible
60
sign of an energy impacted area. Inadequate planning, lack of control
over siting, and lack of amenities can result in "aluminum ghettos"
being scattered across the landscape (12:2). Thus, housing problems
created by rapid growth from power plant development cause consid-
erable conflict with a community's desire for quality growth.
Community service capabilities such as medical, education,
recreation, police and fire protection, water and sewer facilities, are
often overburdened by the rapid growth rate accompanying energy
projects. Even though a power plant may be a significant property
taxpayer, tax revenues from the project arrive only after the facility
has been constructed, assessed, and placed on the tax rolls; while
the impacts from such development arise immediately. Thus, local
governments may be hard-pressed to find the revenues necessary to
build new classrooms, extend water and sewer lines, and enlarge
police and fire capabilities. Medical services generally suffer the
most. In only a few years, the same number of doctors may be trying
to handle doubled loads. In this case, many people have to go outside
of the community to even getroutine care. In addition, extra loads
are placed on hospitals.
Although the severity of community impacts created by power
plants and other energy projects depends on several factors (such as
original population size, level of unemployment, condition of local
services and facilities, rate of growth, and quality of planning), the
rate of growth is the best indicator of severity of impacts which the
61
communities will face. In its studies of energy impacts, the Denver
Research Institute concluded:
"An annual growth rate of ten percent strains local service
capabilities. Above fifteen percent seems to cause break-
downs in local and regional institutions. " (12:2)
A moderate rate of growth, followed by a stable permanent population,
however, may actually enhance the quality of life within a community.
Thus, the potential rate of growth created by a proposed power plant
must be examined closely, in order to arrive at solutions which
minimize conflict with the capabilities and desires of impacted
communities as expressed in their master plans.
b. Pollutants
Urban dwellers, as well as farmers, are becoming
increasingly concerned about the potential affects that fossil-fueled
power plant emissions may have on their crops and their own health.
Nitrogen oxides, sulfur oxides, and particulate matter are the
pollutants of primary concern. However, in coal-fired plants, carbon
oxides and trace elements of mercury and fluorides are also a poten-
tial matter of concern.
Fuel quality, stack height, combustion efficiency, and emission
control equipment, such as separators, precipitators and scrubbers
control power plant emissions with varying degrees of success. For
example, a high degree of control can be achieved in removing
particulate matter (fly ash) using existing emission control equipment.
62
The addition of gas conditioning systems, in some cases, improves
the efficiency of precipitators in removing sulfur oxides. However,
the technology for sulfur oxide removal from flue gas is still not
highly refined. Processes for the removal of nitrogen oxides are not
yet available (13:15). Thus, it is important to insure that plant
construction environment studies are accomplished in order to deter-
mine the extent of adverse affects that airborne contaminents may have
upon the area surrounding proposed sites. Such studies can include
identification of indicator species of crops and animals which may be
particularly susceptible to damage by air contaminents and provide
alternatives to protecting such species from adverse impacts.
In the case of nuclear generating stations, there is no air pol-
lution problem because combustion does not take place; rather, heat
is created by the fission process. However, radiation emissions in
the form of liquid and gaseous wastes, are a matter of concern.
Even though the releases of radioactive material from nuclear gener-
ating plants, through reactor coolants, are low and dilute, "biological
concentration" can occur in the food chain if such releases are not
controlled properly. For example, dilute radioactive minerals from
power plant discharges can be taken up by algae, the algae consumed
by zooplankton, the zooplankton consumed by small fish, the small
fish eaten by larger fish, and the larger fish eaten by humans. In
the preceding process, radioactive minerals would become more
concentrated at each succeeding step, and thus more dangerous.
63
Concern in these instances is not only for human safety, but also for
the safety of wildlife. Biological concentration of radioactive minerals
is particularly harmful to raptor species, especially those with a high
fish diet, such as bald eagles. The shells of eagle eggs are often
weakened by the above process to such an extent that they are easily
broken, and thus, the eaglets are not hatched. This has created a
serious problem for a number of raptor species in many parts of the
country. Thus, radiation emissions are a concern which must be
given consideration in any proposed development of a nuclear electric
generating plant.
Thermal pollution, caused by cooling water discharges from
power plants, can have adverse effects on aquatic life. Usually, the
temperature of cooling water emerging from a power plant is 15 -250
F warmer than it is at the intake. Thus, in the immediate vicinity
of an outlet, cold water species of fish could be killed. This prob-
lem is not a major concern in Weld County which primarily supports
warm water fish species. Nevertheless, warmer water does acceler-
ate the growth of algae which: (1) can result in the de-oxygenation of
the water leading to fish kills of warm water species, and (2) may
increase the likelihood of problems presented in the previous para-
graph regarding nuclear plants. Therefore, thermal pollution is a
matter of some concern. Thus, studies are necessary to determine
the allowable increases in water temperature at any proposed power
plant site. 64
Noise pollution, which can result from power plant operations, is
an additional concern of Weld County, especially around community
growth areas. Draft fans, large pumps, compressors, metering
stations, and other large equipment can generate significnt sound levels.
However, sound proofing techniques are available, and can be used
when necessary to assure acceptable sound levels. Such techniques
can include: (1) enclosing noise producers in sound insulated struc-
tures, (2) use of trees and shrubs to absorb sound waves, and (3) the
establishment of buffer zones around a plant to increase the distance
between noise generators and surrounding landowners.
2. Electric Transmission Systems
In and around urban areas, the presence of power lines and
substations is often notably conspicuous, because of the aesthetic de-
gradation and other negative impacts which they may create. Acknow-
ledging the need for such facilities does not lessen their physical
infringement on the landscape. Increasingly, public attitudes and
social values require that more emphasis be placed on maintaining
and improving environmental quality. Thus, the development and
expansion of electric transmission systems must take into consideration
public views and values regarding healthful and pleasing surroundings.
a. Appearance
The biggest problem associated with electrical lines
and facilities in areas of concentrated population revolves around
65
aesthetics. Many individuals feel that overhead electrical lines and
other aboveground facilities are less than visually pleasing, and as
such, have a direct negative impact on land values, especially in
residential areas and to some degree in commercial areas. Right-of
ways are felt to be a waste of land and a source of weeds and other
noxious plants which spread to lawns and place a burden on home-
owners in terms of both time and money, when they must be removed.
Transmission lines, support structures, and cluttered looking sub-
stations are often mentioned as "eye sores" at public hearings,
especially when these facilities interfere with the view of the moun-
tains. Obviously, the only way high voltage transmission lines can
be completely hidden from view is to place them underground. In
many cases, this cannot be reasonably justified because of economic
and/or technological limitations. In recent years, however, electric
utilities have adopted a variety of techniques to achieve a more favor-
able visual impression as power poles and other facilities are located
in given areas. Utilization of these techniques, commonly referred
to as the "low profile approach, " generally costs between 1. 3 and 1 . 5
times that of constructing traditional facilities. The techniques
involved include the use of: ( 1) creative landscaping that is compatible
with the area; (2) construction materials which are native to the area
or which harmonize with their surroundings; (3) structural designs
which relate to the environment by blending, harmonizing or in some
cases contrasting with other visual features; (4) colors and paints
66
which minimize contrast with the environment; (5) use of natural
topography and vegetation to blend structures with the surrounding
area, or to shield structures from view; (6) buffer areas; and (7)
underground distribution lines.
In addition, the impact of major electrical facilities on the
surrounding environment can be reduced by utility companies, if
they permit the easement area to be used for other purposes. This
approach,generally called the "multi-use approach, " integrates utility
sites and easements with productive or recreational uses. It has been
used for years in agricultural areas, but it is relatively new to urban
areas. Nevertheless, in urban areas, it is possible to allow otherwise
"wasted" easements to be used by adjacent landowners for lawn and
garden purposes or by public entities for trail and other recreational
purposes. This approach necessarily involves contract use agree-
ments between the utilities and the adjacent property owners or
public entities for maintenance, liability and safety purposes. A
utility company, for example, does not want to be held liable for a
bicyclist who runs into a power pole and breaks his arm.
Two reasons why utility companies have shied away from the
multi-use approach in urban areas is because of: (1) the small lot
sizes of adjacent lands and therefore, the large number of contracts
involved; and (2) legal inconsistencies which have appeared in court
actions dealing with liability suits. For example, utilities have
complained that structures have been erected on existing easements,
67
in contravention of easement contracts; that injuries and fatalities
have resulted as a consequence; and that the utility company involved
has been held liable by the courts. Thus, the question is raised, "why
go to the trouble and expense of getting a lot of contracts signed if
they don't resolve anticipated problems and concerns? " When this
approach is used, it is generally because of action initiated by public
entities for recreational purposes.
In any case, utility companies must acknowledge that, once
established, their facilities become a part of a neighborhood environ-
ment, and that the appearance of those facilities will affect the quality
of that environment. If the utility is to be considered a good neighbor,
it must put forth the effort to make its facilities compatible with the
surrounding landscape. Utility companies which do not share the con-
cern of surrounding landowners for a pleasing environment, will find
it increasingly difficult to find neighborhoods willing to accommodate
their facilities. Today, few communities are willing to allow a utility
to construct a substation which looks like a giant erector set, which
is held together by innumerable wires and surrounded by a chain link
fence.
b. Radio and T. V. Interference
A concern, often voiced at public hearings, regarding
proposals to construct major transmission lines involves potential
radio and television interference. Both of these media are popular
68
forms of family entertainment and a means for them to keep abreast
of what is happening in the region and the outside world. Therefore,
prospects of having to put up with potential interference on their radio
and television sets as a result of high voltage power line installation,
raises deep concern among landowners living in close proximity to pro-
posed transmission facilities. Although most interference complaints
received by utility companies are caused by customer owned devices,
a sufficient number of complaints have been traced to power line
hardware or contamination problems.. Thus,concerns regarding this
subject should be taken serious and methods to minimize potential
conflicts employed.
3. Pipeline Systems
Except for an occasional strip of weeds which contains a
marker identifying some utility company, pipeline easements go
largely unnoticed by most people in urban areas. In fact, not until
they see somebody pulling up their rose bushes or digging up a local
street to repair an underground line, do any conflicts arise between
pipeline systems and the average citizen. The problems created by
pipelines in urban areas, however, can be substantial in terms of
their effect on development patterns and public safety concerns. Such
problems should be confronted and alleviated, to the extent possible,
by developers, local officials, and utility company respresentatives
prior to construction of residential units and the arrival of residents
into community growth areas. 69
a. Development Patterns
Easements for underground gas and oil lines located
in community growth areas eliminate many urban type uses and struc-
tures because utility companies do not allow construction over such
easements. These easements, in effect, become de facto non-
functional open space. Such easements are especially limiting to
development of smaller land parcels situated in high density zoning
districts, because of zoning requirements regarding setbacks and
off-street parking, and federal safety requirements regarding proxi-
mity of building structures to high pressure pipelines. Problems are
compounded in areas which have a large number of easements. Such
a situation exists around the communities of Frederick, Firestone,
and Dacono where a substantial number of gathering lines carry oil
or gas from producing wells to nearby storage tanks. In addition,
aboveground gas and oil facilities, such as compressor stations and
storage tanks, can create aesthetic problems, especially if located
in planned residential neighborhoods. These facilities are relatively
unattractive, do not fit in well with residential land uses, are sources
of weeds, and collectors of trash. Thus, Weld County is concerned
that, if located improperly, pipeline easements and facilities would
tend to lower land values and influence undesired development patterns.
70
b. Safety
Safety is another subject of concern when Weld County
considers the location of high pressure pipelines. For instance,
shallow pipelines or poorly marked pipelines may be subject to acci-
dental cuts by heavy construction equipment and farm machinery.
Gas or oil escaping from such a cut would create a potential fire or
explosion hazard to surrounding properties and to any person in the
immediate vicinity. Techniques available to reduce the possibilities
of an accidental cut include: (1) assuring that pipes are buried below
plow depths; (2) the placement of signs and markers identifying ease-
ment areas and line locations; 3) the provision of maps showing
existing line locations to highway departments and planning commis-
sions; and (4) the upgrading of pipe. in areas of increased population
density and building activity.
At the present time, pipe companies are required by Federal
regulations to upgrade in areas of existing population concentration,
but not in areas of proposed population concentration. However, Weld
County is concerned about the safety of residents that we anticipate
will someday live in community growth areas, and therefore would
desire to see the same standards of safety applied in these areas.
The filing of pipeline maps with local planning commissions is
a technique, noted above, which would insure that a community had the
necessary information available to minimize conflict between pipeline
locations and planned community projects, as well as to prevent
71
accidental pipeline cuts. In one instance, Panhandle Eastern Pipeline
Company presented a map of their plans to the town of Milliken
Planning Commission prior to constructing a pipeline through the
town's growth area. It was then found that the town had plans to con-
struct a sewer line diagonally across the same area. It was noted
that the two lines would have intersected at the same depth. There-
fore, "Panhandle Eastern" adjusted the depth of its proposed pipeline
in order to alleviate the conflict. In presenting the town a map of their
plans, Panhandle Eastern Pipeline Company prevented a potential
hazardous situation, saved the town the expense of adjusting the
location or depth of their sewer line, and created a better working
relationship with the community. Efforts such as this, contribute
greatly to minimizing conflicts created by pipeline systems within
community growth areas. Additional techniques available to reduce
potential conflicts created by pipeline easements and facilities within
community growth areas include the "low profile" and "multi-use"
approaches noted in the previous subsections.
72
C. Other Resource Areas
The conservation of our mineral, wildlife and cultural resources
is an essential part of our efforts to maintain the economic well being,
as well as the environmental quality of Weld County. Although Weld
County contains an abundance of important resources, these resources
are not inexhaustable. It has been determined through previous studies
that those areas along our major streams and reservoirs are the
principal areas of concern when considering the conservation of these
resources. It is these areas which contain a wide range of abundant
high quality resources. For example, sand and gravel deposits adjacent
to our major streams have been identified by the Colorado Geological
Survey as the most significant land form unit in the county in terms of
sand and gravel resources ( 14:25). The Weld County Mineral Resource
Extraction Plan states that it is especially important that these floodplain
sand and gravel deposits be protected from any use which would interfere
with their extraction ( 15:18). furthermore, water supplies for agricul-
tural and urban purposes are primarily located, stored and transported in
the major reservoirs, drainages and aquifers found in this county. In
addition, a wide range of wildlife species utilize these major water bodies
for resting, feeding and nesting purposes. Finally, most archeological
73
sites found to date in Weld County have been along our major drainage-
ways; and it is around the major water bodies where tree cover,
variable topography, and water (the three principle criteria conducive
to most major outdoor recreational activities) are found in this county.
Thus, special attention should be given to the placement of utility lines
and facilities in these resource areas.
1. Mineral Resource Areas
Weld County contains extensive deposits of sand, gravel
and low-sulfur coal; as well as more limited deposits of oil, gas and
low-grade uranium. Sand and gravel are basic to the construction of
our homes, schools, hospitals, churches, shopping centers, streets,
airfields, bridges, and electric generating plants. In addition, they
play important roles in the areas of sewage treatment, water infiltra-
tion, agriculture, landscaping, transportation, manufacturing,
recreation and petroleum production. Our coal, uranium, oil and
gas resources have also assumed greater significance in recent years
as energy supplies have dwindled. It must be realized that these
resources are the result of long geological processes, that their dis-
tribution is limited, that they cat be mined only where they occur
naturally, that they are essential to all kinds of construction, and
that proper steps must be taken to ensure that adequate supplies are
{ kept available to meet current as well as future demands. Further-
more,( it is the policy of Weld County, as stated in the Weld County
74
Mineral Extraction Plan, that:
"Access to future mineral resource development shall be
considered in all land use decisions. In accordance with
Colorado Statute, no Weld County governmental authority
which has control over zoning shall, by zoning, rezoning,
granting a variance, or other official action or inaction,
permit the use of any area known to contain a commercial
mineral deposit in a manner which would interfere with
the present or future extraction of such deposit by an
extractor. " (15:23)
a. Sand and Gravel Resources
The major concern of Weld County regarding public
utilities and sand and gravel resources is that the development or
extension of utility facilities will interfere with the extraction of
commercial sand and gravel deposits. Structures such as generating
plants, power poles, compressor stations, storage tanks, etc. ,
when located over a deposit, would effectively remove the underlying
sand and gravel from the available resource supply. Likewise, pipe-
lines and transmission lines would remove all deposits underlying
easement areas from the available resource supply. This potential
problem is of greatest concern in areas categorized as F-i Flood-
plain Deposits by the Colorado Geological Survey. F-1 Floodplain
deposits normally lie adjacent to the major drainageways located in
Weld County. Therefore, a pipeline or transmission line which ran
adjacent and parallel to a major stream containing such a deposit,
would create a significant conflict. In addition, the development of
major utility structures in such an area would create a conflict; the
75
larger the area required f.,r such structures the greater the problem
created. In general, the greatest concern lies with the conservation of
F-1 Floodplain deposits, because they are the highest quality and most
limited resource. However, concern for the protection of other cate-
gories of sand and gravel deposits is also important in Weld County.
b. Oil, Gas, Coal and Uranium Resources
A major concern of Weld County regarding public utilities
and our energy resources is that utility companies may inadvertently
create energy resource problems by placing new facilities over energy
deposits in such a manner as to make the resources unavailable for
their own energy supplies. For example, transmission lines and ease-
ments placed through uranium fields (to date, these fields have been
found along ancient stream beds in this county) may significantly inter-
fere with extraction of an ore which is used to produce electricity
carried by the transmission lines. This concern is greatest in areas
of potential strip mining operations since underground extraction and
well drilling operations would generally be less affected by above-
ground utility developments,. tr areas of potential underground mining,
it is the utility facilities themselves which are more likely to be im-
pacted as a result of subsidence created by future mining activities.
Therefore, the concern in such areas is more for the safety of pro-
posed utility facilities than it is for protection of the energy resource.
The probability of mining activities should at least be considered by
utility companies prior to locating their facilities in potential
underground mining areas. By doing this, it is possible to determine
if it is necessary to specially design structures to minimize the effects
of subsidence.
2. Wildlife Areas
Weld County contains numerous species of wildlife. Concen-
trations of most species are found along our river bottoms and in
areas surrounding our reservoirs. For example, mule deer numbers
are highest along the river bottoms; whitetail deer, quail, beaver,
waterfowl, pelicans, cranes, and many other species are localized
along the river bottoms or around our major reservoirs; bald eagles,
with few exceptions, are found only on the river bottoms and around
the larger irrigation reservoirs. Exceptions include moderate num-
bers of antelope and concentrations of a number of raptor species in
semi-arid rangeland areas of northern and eastern Weld County. For
example, the Crow Creek drainage, Chalk Bluffs, Pine Bluffs, and the
Pawnee Buttes areas of Weld County support one of the greatest popu-
lation of nesting raptors in North America, if not the world. Utility
facilities can pose special Lazards to a number of these species through
pollution or by the potential which exists for electrocution. As indi-
cated previously, diluted liquid waste discharges from nuclear genera-
tion plants have created problems for certain raptor species through
the "biological concentration" of radioactive minerals in the food
chain. Such problems, as well as others noted below, are a concern
77
in this county which should be taken into consideration and minimized
to the extent possible when utility facilities are proposed for develop-
ment.
a. Raptors
Electrocution is the principal hazard affecting those
species which use electric lines and support structures for perches.
Recent studies have documented electrocution losses of egrets, herons,
crows, ravens, and wild turkeys, but evidence shows that 90% of all
electrocution victims were golden eagles; that 98% of the eagles
electrocuted were young, inexperienced golden eagles that were just
learning to fly; and that most electrocutions took place during the
wintering period when peak populations of eagles and hawks were
present (16:1). This problem primarily occurs when a large bird
spans the distance between two conductors on an electric support -
structure with its wings, and as a result of not being grounded, takes
the voltage carried by the lines and dies. The problem occurs much
more frequently on distribution lines, because the support structures
are smaller and conductor spacing is therefore closer. However,
this problem can also occur on high voltage power lines whenever
conductors are placed in close proximity to each other. Techniques
to alleviate this problem involve placing conductors far enough apart
so that the wing span of large birds is less than the distance between
conductors. Utility companies have also found that placing the ground
78
wire above, rather than below, the energized wires assists in
minimizing the problem.
An additional problem, compounded by power lines and related
structures, concerns illegal shooting of raptors. Wildlife personnel
have indicated that raptors become easy targets when perched on power
lines located close to roadways. Birds of prey often use power poles
as perching and hunting sites especially in areas where trees and other
natural elevated sites are unavailable. Thus, in many areas of Weld
County,power poles are primary perching sites for raptors. In that
several areas of Weld County contain large concentrations of raptors,
especially during the winter nesting season, there is a special con-
- - cern for their protection. Therefore, any land use which may contri-
bute to the destruction of these birds of prey must be examined closely
in order to arrive at solutions which minimize their potential loss.
When it is not possible to avoid areas of raptor concentrations, the
most obvious solution to this problem is to place power lines away
from existing road right-of-ways, thus, making it more difficult for
shooters to get close easy shots at the birds. However, if such a
solution involves creation of greater impacts on surrounding land uses,
the trade-offs involved muse be given full consideration and the
approach acted upon which provides the most overall benefit.
79
b. Water Fowl
Electric transmission lines pose a special hazard to
water fowl when located in areas where these species concentrate.
Power lines are obstacles which interfere with their take-off and landing
patterns. The hazard becomes greatest for these species during periods
of low visibility, at which time they are more apt to inadvertently fly
into the lines. The problem occurs most frequently in areas where
power lines span major streams and reservoirs, or when power lines
are placed in close proximity to these water bodies. Because of large
concentrations of geese and ducks in Weld County, especially during
periods of migration, this problem should be taken into account when
locating electric transmission easements. Techniques to alleviate
the problem include: (1) flagging overhead lines with brightly colored
plastic streamers, and (2) placing power lines at a distance from
water bodies which minimizes interference with flight paths. Both
of these techniques, however, may create greater impacts than they
alleviate when weighed against agricultural and aesthetic concerns
noted in previous sections. Thus, although Weld County is concerned
about this problem, solutions to minimize any conflicts must be
examined closely before they are implemented, so that all trade-offs
involved are given full consideration.
111
c. Fish
Water pollution, either from construction operations or
from pipeline leaks, is a major concern of Weld County when consider-
ing the protection of local fish species. For example, during pipeline
construction activities, a common practice is to simply dig a ditch
across the bottom of a stream, weight the pipe with concrete, place it
in the ditch, and then to refill the ditch. This practice stirs up silt
and sediment which may increase water turbidity to a harmful level
for fish species which do exist in county streams. Additional prob-
lems arise when the stripping and vegetation for pipeline or electric
transmission easements, especially in floodplain areas, results in
conditions conducive to soil erosion during periods of intense rainfall.
Soil washed into streams and reservoirs by erosion can create the
same turbidity problem for fish as those noted above. The capacity
of the vegetation cover surrounding bodies of water or streams to
hold soils in place is a very important factor in the protection of these
water bodies and their fish population. Finally, oil and gas lines
crossing, or in close proximity to streams and reservoirs, could
seriously harm fish life, if the lines were to be washed out by flood
waters or were to otherwise develop leaks and spill oil or gas into
such water bodies.
It is acknowledged that most Weld County streams and reservoirs
are primarily used for agricultural purposes, and therefore basically
support only the more hardy warm water fishes. However, a number
81
of water bodies do support popular sport fishes, such as bass and pike,
and a few reservoirs are periodically stocked by the Colorado Division
of Wildlife. Thus, protection of fish is a realistic concern of the
county with reference to potential water pollution problems resulting
from development of utility facilities.
3. Cultural Resources
Historical sites, archaeological sites and scenic areas
exist as resources for the enjoyment, education and psychological
well being of the citizens of Weld County. These resources include
local landmarks, both natural and man-made, which can contribute to
an understanding of the past, provide local character and community
identity, and give a sense of direction to individuals and communities
as they grow. There are various cultural resources scattered through-
out Weld County. Examples of such resources include: Pawnee
Buttes, the Natural Fort, Wildcat Mound, Fort Vasquez, and Dent
archaeological site. In many cases, these sites are under private
ownership and may only be enjoyed for their scenic or educational
qualities from a distance or at the discretion of the local landowner.
Nevertheless, Weld County is concerned that such sites and areas be
maintained in a manner that will allow man to function in harmony with.
such resources so that they can remain as assets for future generations.
82
a. Archaeological Resources
The primary concern of Weld County related to the
development of utility facilities within areas containing archaeological
resources is that construction operations may damage or destroy the
resource. The basic problem which exists is that, in most cases,
the location of the resource itself is unknown. Archaeological sites
are often found by accident, although a trained archaeologist may un-
cover sites in areas of high probabilities. Areas of high probability
are identified based on geological stratas which have yielded site
discoveries in the local area or in other locales. Bulldozers and
ditch diggers used by utility companies in their construction operations
could easily destroy ancient artifacts and prehistoric bones and no one
would even realize it. In Weld County, to date, most archaeological
sites have been found on terraces along our major rivers. These
areas are the areas of high probability which are of greatest concern
in Weld County. This does not mean that discoveries which may be
uncovered outside such areas are of less concern. In fact, a discovery
made in an area or strata where no previous finds have occurred may
be of greater significance than a site uncovered in an area of high
probability.
b. Historic Sites
The primary concern of Weld County related to the
development of utility facilities around historic sites is to insure that
such development blend, to the extent possible, with the historic
83
resource. Lattice steel support structures in the vicinity of the
Hillsboro stagecoach stop, for example, would look completely out of
place, whereas structures designed to resemble old time telegraph
poles may blend in quite well. Weld County contains a variety of
historic sites which are now being inventoried and categorized. Many
of these are sites where an historic structure once stood or where a
historic event took place. In such cases, there is less concern about
potential aesthetic problems created by development of utility facilities,
than in areas where actual structures are still present.
c. Scenic and Recreational Resources
Weld County occupies over 4, 000 square miles in the
semi-arid Colorado piedmont section of the Great Plains Physiographic
Province. The topography is level to rolling uplands with stream
valley lowlands. In general, the lack of tree cover, variable topo-
graphy, and water provide the county with less than favorable conditions
for most popular outdoor recreational activities, both passive and
active. However, exceptions do exist, especially along the major
drainages where trees parallel the channels and where bluffs have
in some cases been carved out of the adjacent land mass. In other
spots the land mass has been eroded by streams which long ago dis-
appeared, taking with them the trees, but leaving behind scenic bluffs
and buttes which have been weathered by seasonal rains and winds and
stand guardian over the flatlands below. Because typical scenic and
84
recreational resources are not naturally bountiful in Weld County,
there is a concern that they be protected where they do exist to the
extent possible, for the enjoyment and education of present and future
residents of this jurisdiction. A concern of Weld County in reviewing
the potential development of utility facilities around these resources
is the possibility that such development will degrade their aesthetic
qualities.
85
D. Summary
This section has examined past and potential problems created
by development of public utility facilities in agricultural, community
development and other resource areas of Weld County. Major concerns
were expressed when such development created problems which con-
flicted with guidelines set forth in the Weld County Comprehensive Plan
or other county plans and regulations. Furthermore, this section
emphasized that such conflicts should be minimized to the extent pos-
sible, while realizing that Weld County could expect continued develop-
ment and expansion of major utility systems and facilities in the future.
Techniques and methods which have been developed or which are
available to minimize a number of problems and conflicts were also
presented. However, in some cases, no clear-cut techniques have
as yet been developed which can realistically be applied to the prob-
lems created by the development of new public utility facilities.
In any case, it must be realized that the production, generation,
transmission, processing, and distribution of energy resources can
have a negative impact on other resources and land uses which may
be of equal or greater importance. In order to minimize the negative
impacts on other land uses and resources, while still providing a means
86
for the development of our energy resources, a number of factors
must be given consideration as utility site selection is carried out.
Protection of agricultural lands and the production capabilities of
these lands, quality growth around incorporated communities, and
conservation of natural resources are basic concerns of Weld County,
as set forth in the Weld County Comprehensive Plan. Thus, agricul-
tural, urban, and conservation interests are major factors to be
considered when planning for and siting utility lines and facilities in
Weld County.
87
III. Policy Guidelines
III. Policy Guidelines
Energy resources such as electricity, oil, and gas are neces-
sary to maintain and continue the quality of life as we know it today.
Weld County contains oil and gas reserves which are produced, trans-
ported, and distributed to other regions, as well as within our own
County. Given this interdependence of various regions and jurisdictions
upon one another for energy supplies, it seems logical that national
and regional plans and guidelines should be developed which ensure
that such supplies continue to flow where and when they are needed.
However, such guidelines must take into consideration that structures
and facilities utilized in supplying needed energy have often been poorly
located and designed; wasting otherwise productive lands, creating
unnecessary and sometimes long-term problems for farmers and
ranchers, and adversely affecting land values around urban areas.
Thus, the following land use policy guidelines address, and attempt to
alleviate, the various conflicts which occur as facility siting takes
place in agricultural, urban, and conservation areas of Weld County.
Specifically, this section outlines the conflicts which may result
from the development of new power plants, electric transmission
systems, and pipeline systems; makes recommendations regarding
89
possible solutions to such conflicts, which should be given considera-
tion as projects are proposed in the various resource areas of the
county; and sets forth policy statements which will act as guidelines
to decision makers when new public utility facilities are proposed in
Weld County. Efforts should be made to adhere to these land use
guidelines whenever practical, realizing that economic and technologi-
cal factors must also be given due consideration.
90
A. Conflicts and Recommended Action
Utility companies strive to provide reliable service to consumers
at a reasonable cost. Their efforts have, in fact, achieved this goal in
most cases. However, the accomplishment of this goal has, in many
cases, been achieved at the expense of individual landowners who have
suffered reduced land values and reduced crop production. It would
seem more reasonable, that if the benefits of energy supplies are to be
shared by all consumers, that the costs should also be shared by all
consumers, rather than by a few unlucky individuals. Thus, solutions
which are recommended to alleviate land use conflicts will, in many
cases, be more costly to the utility companies and in turn to the general
consumer; however, these increased costs will be borne by all consumers,
not just by a few individuals as in the past.
Overall, it is the intent of this Plan to encourage utilities to locate
their facilities in those areas where the fewest negative impacts result
and where the loss of productive agricultural lands can be minimized.
For instance, by encouraging utilities to locate facilities on non-irrigated
lands as opposed to irrigated lands, this plan attempts to establish a
realistic approach to trade-offs which must occur between elements of
the overall resource base. In general, the goal to supply energy resources
iI
ninal Irr rvahrcttriri with rufrrein r to iln ovrrall impact nn agricultural
lands and uses, community growth areas, other resource bases and
the health, safety and welfare of the citizens of the County.
1 . Power Plants
In the previous chapter, a number of conflicts which may result
from development of power plants were presented. These conflicts
are outlined below:
a- Impacts on Agricultural operations and crop production:
1) Loss of Agricultural Lands
2) Loss of Agricultural Water
3) Pollution
b- Impacts on quality Community Growth:
1) Socio-economic impacts
2) Pollution
c- Impacts on Other Resources:
1) Interference with mineral resource extraction
2) Impacts on Wildlife
3) Impacts on Cultural Resources
The following sections summarize these conflicts and impacts,
and sets forth policies and/or guidelines to be utilized in reviewing
proposals for power plants which are to be located in Weld County.
92
a. Impacts on Agricultural Uses
Basically, a power plant is an industrial facility which
can be classified as a high water user. One of the major problems
associated with locating a power plant in Weld County, which is the
second most productive agricultural county in the nation, is that such
a facility may have significant impacts on agricultural water supplies.
If a plant were to be located on irrigated agricultural lands, prime
acreage would be directly lost for production of crops; if located on
non-irrigated land, prime irrigated land could be lost indirectly
because of diverted agricultural waters utilized by the plant. Regard-
less of location, crop production and range grasses could be adversely
affected by air or water borne contaminents emitted in power plant
waste discharges. In order to avoid such direct conflict with agricul-
tural operations, the following policies should be observed in decisions
involving the siting of power plants.
1) In order to ensure that prime agricultural lands are not
removed from crop production, power plants should be located
in non-irrigated, non-cropland areas.
2) In all power plant sitting Jecisions, the broad effects of trans-
ferring water from agricultural uses to other uses must be taken
into account and given consideration. More specifically, water
which is needed for power plant operations should not be drawn
from agricultural water supplies. In those instances where, for
lack of other alternatives, agricultural water supplies must be
93
utilized, the applicant should explore all possibilities available for
returning as much water as possible to agricultural uses once
power plant requirements are satisfied.
3) In all power plant siting decisions, the applicant or responsible
company will be encouraged to utilize the best available technology
for reducing plant emissions and for maintaining ambient air
quality standards. Where it is shown that a given proposal has
potential for causing crop damage or damage to human health
because contaminent emissions cannot be reduced to acceptable
levels with available technology, other alternativb site locations
must be considered. In all such proposals, "acceptable emission
levels" and "ambient air quality standards" will be based on
current standards set forth by the Colorado Department of Health
or the County of Weld.
b. Impacts on Communities
Another significant problem associated with power plant
siting in Weld County is the potential negative impacts such a facility
may have on the growth and welfare of our existing communities.
Depending on the size and type of facility proposed, substantial num-
bers of immigrant workers may settle near the plant site. In that the
Weld County Comprehensive Plan directs growth to existing towns,
those communities in close proximity to a power plant would be
affected by increased growth pressures. Socio-economic impacts such
94
as housing shortages and increased demands on local services thus
become primary concerns. For example, housing shortages can result
in inflated rents and market prices which could substantially affect
existing residents on fixed incomes, especially the elderly. Further,
demands on local services can result in overloads on medical, police,
fire, water, school and sewer capabilities which could substantially
affect the fiscal resources and budgets of local governments, especi-
ally in smaller communities.
Rate of growth is the factor which has the greatest influence on
the degree of severity of socio-economic impacts created by energy
development. The faster the rate of growth, the more severe the
impact. Thus, to ensure that socio-economic impacts resulting from
power plant development are not substantial, it is necessary that the
rate of growth be held to acceptable levels. Many of these impacts
could possibly be eliminated if it was possible to recruit the power
plant construction force from the area in which the plant was to be
located. In this manner, the number of individuals in the work force
requiring new housing and services would be minimized. Therefore,
it is recommended that the work force be recruited, as much as
possible, from the local area. This action could substantially alleviate,
if not prevent, any anticipated rate of growth problems likely to occur
as a result of an influx of immigrant workers and their families.
Another important factor to consider in alleviating socio-economic
impacts is the tax revenue generated by a power plant facility. Some
95
public utility companies, such as PRPA, are exempt from taxation.
Thus, revenues are not generated to offset costs to communities
induced by the develnpment of their facilities. Therefore, unless such
facilities are required by a given community to fulfill its own electrical
energy needs, the community may have to bear substantial service
costs and receive few, if any, benefits. In such cases, it would appear
to be more acceptable if power plant facilities are located within those
areas that utilize the electricity generated for their own electrical
requirements.
However, most public utility companies are tax payers. Revenues
generated from power plant developments are generally sufficient, in
the long-run, to offset the cost a community must bear as power plant
development occurs. Nevertheless, there are problems of timing and
geographic distribution of revenues which may affect individual commu-
nities. For instance, taxes imposed on power plants are available as
community revenue sources only after the projects are completed,
whereas impacts occur with the influx of construction workers and
their families. In addition, power plant facilities may be located in one
jurisdiction while major impacts created in neighboring jurisdic-
tions who do not receive any tax revenues to support additional service
costs.
Finally, as in agricultural areas, the potential which exists for
air pollution, as power plant development occurs, must be addressed
as power plant siting impacts our existing communities. The primary
96
concern in such considerations is to insure that acceptable contaminant
emission levels and ambient air quality standards are established and
maintained to protect the health of the general public. Thus, in all
decisions concerning the siting and development of power plants, the
potential impacts of air pollution and the applicability of current air
quality standards and regulations will be fully evaluated with reference
to the desirability and feasibility of such proposals being approved.
In order to minimize the impacts discussed above, related to
power plant siting and development, the following policies will be
considered and utilized in reviewing and assessing proposals for the
location of such utilities.
1) Prior to approval of any such plant proposal, it shall be
determined that the nature and location or expansion of the pro-
posed power plant facility will not create an expansion of the
demand for government services beyond the reasonable capacity
of an impacted community or the County to provide such services.
Where it is anticipated that such an expansion of the demand for
services will occur beyond the reasonable capacity of the County,
or a community to provide such services, the applicant must
clearly show how such impacts will be mitigated prior to approval
of the proposal by the County.
2) Where a proposed power plant is to be located in an area where
a sufficient housing supply is unavailable for the anticipated
immigrant construction force, the applicant for the
97
location of such a facility must present plans showing how housing
will be provided for such workers without creating major negative
impacts on existing housing supplies and existing residents in the
impacted communities.
3) Prior to approval of any such plant siting proposal, it shall
be determined that the nature and location or expansion of the
facility will not significantly deteriorate air quality in the impact
area and that the facility will meet Colorado Department of
Health and Weld County air quality standards.
c. Impacts on Mineral, Wildlife and Cultural Resources
Additional problems which may result from locating a
power plant in Weld County are the potential negative impacts such a
facility may have on existing mineral, wildlife and cultural resources.
Collectively, these resources would most likely be impacted to the
greatest extent if such a facility were to be built adjacent to our larger
streams. Individually, these resources may be impacted to varying
degrees in areas and sites which are scattered throughout the county.
Extensive deposits of sand and gravel have been mapped and
categorized in Weld County by the Colorado Geological Survey. These
deposits range from the highest quality F-1 Floodplain deposits found
along our major streams, to the low quality E-3 Eolian (wind blown)
sands found in the more isolated eastern sections of the county.
Valley, Terrace, Alluvial and Upland sand and gravels are intermediate
98
quality categories located in various areas of the county. According
to State Statute (14:3), Weld County cannot, through any official action
or inaction, allow the development of areas underlain by commercial
mineral deposits in a manner which would interfere with the future
extraction of those deposits. Therefore, before power plants can be
located over mineral deposits, such deposits must be determined non-
commercial.
In order to alleviate conflicts between mineral resource deposits
and the location of power plant facilities, various steps may be taken.
Two are of importance in the initial stages of developing such pro-
posals. First, utility companies should ensure in the early stages of
site review, that the properties in question are not underlain by com-
mercial mineral deposits. Initial indications of the presence of such
deposits may be gained through communication with such agencies as
the Colorado Geological Survey or the Weld County Department of
Planning Services. Second, when preliminary evidence indicates such
deposits exist, further exploration work should be undertaken to con-
clusively determine whether such deposits are "commercially extract-
able" within the definitions set g:-rth by Colorado Statute. Finally, if
such deposits do exist, it is important that the utility company consider
the policies set forth, regarding development of uses over such
deposits, in the Weld County Mineral Resource Extraction Plan.
Wildlife resources and potential impacts on such resources are
additional factors which must be given consideration as power plant
99
development occurs. It has been indicated by local wildlife officials
that the major streams and reservoirs of Weld County are the areas of
greatest significance to wildlife populations. These areas support the
greatest number of wildlife species, as well as the greatest populations
of individual species found in Weld County. However, there are other
areas important to individual species of wildlife. The most important
antelope habitat in Weld County is the rangelands of northern Weld
County which support moderate populations of this species. In addition,
the Chalk Bluffs, Pine Bluffs, Pawnee Buttes and Crow Creek drainage
areas support concentrated populations of nesting raptors.
It is important that the conservation of such resources and the
mitigation of impacts on such resources is given full consideration as
power plant facilities are developed. Coordination with the Colorado
Division of Wildlife, as well as with local wildlife groups is important
in securing information relevant to how impacts on these resources can
be minimized as facility development occurs.
Finally, archaeological, historic and scenic sites are cultural
resources of Weld County which must be considered as power plant
siting proposals are developed. Areas adjacent to our major streams
contain the heaviest concentration of these resources; primarily be-
cause of the presence of water, which exists in these areas as a limited
resource, in an otherwise semi-arid climate. The Plains Indians and
more ancient cultures camped and hunted along these streams because
they provided areas for hunting and ready supplies of drinking water.
100
For essentially the same reasons, men built trails and forts along
these streams, and later established farming settlements in these
areas because of the availability of irrigation water for crops. Further-
more, in an otherwise flat, treeless region, these streams support
tree cover and provide areas for aesthetic enjoyment where scenic
bluffs have been carved out along their banks. Thus, our major streams
are very significant areas for scenic resources in Weld County.
Other important cultural resources are scattered throughout
the County. For example, the Pawnee Buttes are significant historic
landmarks located in the rangelands of northeastern Weld County which
are important for their scenic beauty. The Natural Fort, located in
Western Weld County, is an unusual geological formation of scenic
quality which was the site of an historic Indian battle between the Crow
and Blackfoot Nations. Determination of the best approach(es) to
minimize harmful effects to such resources should be coordinated with
the Weld County Landmark Committee and other agencies. In general,
the siting of power plants should be accomplished in areas where
impacts on our cultural resources can be avoided as much as possible.
In those cases where it is no*. c,-?ctical to completely avoid such
resources, measures should be developed to mitigate impacts on such
resources as much as possible.
in order to mitigate and/or minimize the impacts on Weld County' s
mineral and cultural resources as power plant development occurs,
the following policies shall apply to the review of proposals for
101
location or expansion of power plant facilities in Weld County.
1) Prior to approval of any proposal for the location or expan-
sion of a power plant facility, it shall be determined that the pro-
posal is in compliance with the Weld County Mineral Resource
Extraction Plan.
2) Prior to the approval of any proposal for the location or
expansion of a power plant facility, it shall be determined that the
nature and location or expansion of the facility will not adversely
interfere with any significant wildlife habitat and will not
adversely affect any endarttzered wildlife species, unique natural
resource, historic landmark and/or archaeological site within
the impact area.
2. Electrical Transmission Systems
The development or extension of electrical transmission
facilities may also result in conflicts with existing land uses and
resources. Potential conflicts were set forth in the previous chapter
and noted in the following outline:
a-• Impacts on Agricu]t;.ral Operations and Crop Production
1 ) Interference with irr. tation systems
2) Interference with efficient operation of farm machinery
3) Creation of weed sources
4) Creation of trespass problems
5) Crop losses
102
6) Interference with crop dusting operations
h- Impact on Community Growth Areas
1) Lower land values
2) Weed sources
3) Waste of land
4) Aesthetic degradation
5) Radio and television interference
c- Impacts on Other Resources
1) Interference with mineral resource extraction
2) Impacts on wiir'1i.fe resources
3) Impacts on cultural resources
a. Impacts on Agricultural Uses
Electrical transmission lines are primarily strung
on aboveground support structures. One of the major problems
associated with locating a power line in Weld County is that these
aboveground facilities can create an obstacle affecting the efficiency
of agricultural operations, with long-range implications. Support
structures placed in irrigatee fl ?rs interfere with the distribution of
irrigation waters. Placed in crup and areas, they interfere with the
operation of seeding, cultivation, and harvesting equipment. In
addition, weeds may grow around these structures and beneath guy
wires, sending their seeds into adjacent fields where they grow and
compete with crops. in their efforts to reduce the size of such weed
103
patches, farmers often get too close to the support structures and guy
wires which results in damaged equipment. Hunters and other recre-
ationists observing public utility easement signs often enter fields and
ranchlands at such locations under the impression that adjacent land-
owners do not need to be contacted because the easement is "public"
property. In addition, pilots often have difficulties maintaining a
constant speed and altitude while maneuvering their planes around
transmission lines during cropdusting operations.
In order to mitigate and/or minimize impacts on agricultural
land as transmission facility (lc,veiopment occurs, the following
policies shall apply to the review of proposals for the location or
expansion of electrical transmission facilities in Weld County.
1) In reviewing proposals for the location of electrical
transmission facilities, it will be the policy of Weld,County to
encourage that such facilities be located in non-irrigated,
non-cropland areas. In those instances where such facilities
must be located in irrigated, cropland areas, it will be the
policy of Weld County to encourage the location of such facilities
in existing right-of-ways. in those instances where county
road right-of-ways are to be utilized for the placement of
structures, Weld County will encourage the use of single -
pole support structure that are to be placed a minimum of twelve
feet from the Mhuuldl r o± exietiing roads.
104
2) In those instances where the use of existing right-of-ways
is not feasible, all structures shall be placed in alternative
locations in such a manner that negative impacts on farm opera-
tions and irrigation systems are minimized to the greatest extent
feasible. In the placement of such structures the applicant will
be expected to coordinate as closely as possible with effected
landowners to ensure that negative impacts are minimized.
3) In the review of all proposals for transmission lines, it
will be the policy of Weld County to encourage the use of single-
pole support structures, ' ienever practical, in order to mini-
mize impacts on cropland areas. In addition, Weld County will
encourage the use of self-supporting power poles which do not
require the placement of guy-wires in cropland areas.
4) Transmission line easement routes which cross land parcels
at a diagonal will be discouraged except in those instances
where:
a) Such placement is necessary in order to alleviate
interference with agricultural operations, and where
b) Such placement ,\ 'd not negatively affect agricultural
operations or land va'ues.
5) It will be the policy of Weld County to encourage that
management of utility easements and corridors be conducted
105
in such a manner as to minimize the problems associated with
trespassing. For example, easement and corridor identification
signs should establish when public access to such areas is and
is not allowed.
6) In the review of all applications for electrical transmission
facilities, it will be the policy of Weld County to encourage
facility design which will minimize the negative impacts on crop
dusting operations which may be necessary to produce crops on
lands adjacent to such facilites.
7) In those cases where it is technologically and economically
feasible, it will be the policy of Weld County to encourage the
placement of electrical transmission lines underground. In
cases where such placement is feasible, established guidelines
for underground pipelines will apply to the placement of electrical
transmission lines.
106
h. Impacts on Communities
Another major problem regarding the location of trans-
mission lines in Weld County is that these lines and associated facilities,
because of their appearance, may have a negative impact on land values,
especially around populated areas. Substations, power poles, and lines
are generally regarded by most people as lacking aesthetic qualities.
Many feel that such facilities degrade the surrounding landscape and
interfere with scenic views. Many locations in Weld County offer a
panoramic view of the Rocky Mountain frontrange. Past proposals
to locate transmission lines in areas which may degrade such a view
from residential sites have resulted in strong protest from local
residents, as well as developers and other individuals desiring to
construct homes in the affected area. In that the Weld County Compre-
hensive Plan directs growth to incorporated communities, the growth
areas around these communities are the major areas of concern
regarding this problem. However, areas around existing rural
subdivisions and rural residence are also important areas of concern
regarding aesthetics and should not be neglected.
107
In order to ensure that impacts on land values resulting from the
placement of power lines are not substantial, it is necessary that they
project an acceptable appearance or that they be placed underground.
Impacts on land values created by aboveground facilities could be sub-
stantially alleviated if appropriate design and landscaping techniques
were utilized, and if these facilities were located in such a manner
that they did not interfere with community growth patterns. In
addition, placement of said facilities on the east side of incorporated
communities and other areas of concentrated population would reduce
the number of cases where interference with scenic mountain views
occurred.
Additional problems regarding the placement of electrical trans-
mission facilities around populated areas and local residences involve
"wasted" easements and power line interference with radio and tele-
vision reception. As noted in the previous chapter, weed patches are
generally concentrated around the base of power line support structures
in rural areas, primarily because the remainder of the easement area
is used for agricultural purposes. However, in communities, entire
transmission line easements are often a source of weeds because such
easements are not used for any other purpose. These "wasted" ease-
ments spread weeds to adjacent lawns and properties which landowners
must then spend time and money to remove in order to maintain their
properties in a quality condition. Furthermore, many individuals are
leary of purchasing property close to transmission line easements
108
because of suspected interference with radio and television reception
from the power lines during periods of bad weather. Thus, properties
adjacent to power line easements are often less desirable than would
otherwise be the case.
In order to lessen such undesirable impacts on adjacent land-
owners, it is necessary that an acceptable ground cover be established
on power line easements or that such easements be utilized for addi-
tional beneficial uses. Furthermore, utility companies should assist
adjacent landowners in correcting poor radio and television reception
resulting from power line interference. In any case, proposals for
the siting and development of power lines will be evaluated with refer-
ence to whether or not a satisfactory program for mitigation of adverse
impacts has been presented.
The following policies will be considered and utilized in reviewing
and assessing proposals for the location of electrical transmission
lines and associated facilities in and around populated areas of Weld
County.
1) Prior to approval of any substation or transmission line
siting proposal, it shall be determined that the nature and loca-
tion or expansion of such facilities comply with the intent and
provisions of applicable Weld County plans and the development
plans of affected communities.
2) Prior to the approval of any substation or transmission line
siting proposal, it shall be determined that all reasonable
109
alternatives to the proposed action which may serve to protect
the welfare and property of surrounding landowners have been
adequately assessed, and that the proposed action represents
the best interests of the people of Weld County.
c. Impacts on Mineral, Wildlife and Cultural Resources
Electric transmission facilities and easements can also
have negative impacts on other land use resources. Interference with
the extraction of mineral resources is one important problem which
should be avoided whenever possible. Utility structures located over
mineral deposits can effectively eliminate accessibility to the under-
lying resource. In addition, overhead lines can interfere with the
large equipment used in mining operations and create a safety hazard
for workers.
Techniques which reduce the magnitude of such impacts on future
mining activities should be implemented in those instances where
utility companies cannot completely avoid mineral resource areas in
their transmission line siting proposals. Preferably, easements pro-
posed through mineral resource areas would be located within existing
right-of-ways, since these locations already preclude mining activities.
In other cases, the route selection process should give preference to
locations through lower grade deposit areas; and, when it is necessary
to traverse high grade deposit areas, to select the shortest route
possible. In addition, support structures should be designed to
110
ullkata.!ifl flip nH , le ,,f ;ri Art—np 'at ;;''trn}.l:il underground
mining. In areas of potential strip mining, lines should be placed at
heights which will not interfere with mining equipment and create
safety hazards.
Electric transmission lines can also create impacts on wildlife
resources, if designed or located improperly. Techniques to alleviate
these problems were noted in the previous chapter; at this time, how-
ever, it is emphasized that the major problem is the potential for
electrocuting birds of prey. A study conducted in another region pointed
out that young golden eagles were the principal victims of transmission
line electrocutions (16:1). Weld County contains large concentrations
of various raptor species, including golden eagles, especially during
the winter nesting season. Thus, large numbers of young golden eagles
are present during certain times of the year. In areas of raptor con-
centration, it is especially important that utility companies consider
this problem and eliminate it to the extent feasible when constructing
their facilities in Weld County. In order to help minimize this prob-
lem, it is recommended that power lines avoid raptor nesting areas to
the extent practical or design power line facilities using techniques
similar to those noted in the publication Suggested Practices for
Raptor Protection on Power Lines (16:2).
Weld County' s cultural resources are an additional concern which
must be considered prior to development of transmission lines and
associated facilities. The two major problems created by transmission
111
line facilities regarding these resources is that; one, they reduce the
quality of scenic and historic sites, especially when designed and
located improperly; and two, construction operations can destroy or
disturb archaeological, historic and scenic resources to a significant
extent.
An analogous example of improper location and destructive con-
struction operations is the routing of Interstate 25 through the middle
of the Natural Fort in northwestern Weld County. Although transmission
line construction operations through the Natural Fort would probably
not require extensive removal of the rock formations, as was the case
with the Federal highway right-of-way, overhead power lines and
associated facilities would probably create a greater aesthetic impact.
In any case, further destruction and degradation of our cultural re-
sources should be prevented to the extent possible.
In cases where cultural resources cannot be avoided, it is
recommended that transmission lines and facilities should be screened
to the extent possible, or otherwise designed, so that they blend with
the surrounding landscape. Additionally, in the vicinity of archeologi-
cal areas of high probability, utility companies should employ the
assistance and advice of qualified agencies and professionals in deter-
mining alternative methods to minimize potential impacts.
The following policies will be considered and utilized in review-
ing and assessing proposals for the development of electrical trans -
mission lines and associated facilities in order to mitigate impacts on
112
Weld County' s mineral, wildlife and cultural resources.
1) Prior to approval of any proposal for the location or expansion
of electrical transmission facilities, it shall be determined that
the proposal satisfactorily complies with the intent and purpose
of this plan and other applicable plans and regulations of this
jurisdiction; specifically, the Weld County Mineral Resource
Extraction Plan and appropriate sections of the Weld County
Zoning Resolution.
2) Prior to the approval of any proposal for the location or
expansion of substations and electrical transmission facilities,
it shall be determined that, one, the proposal will not interfere
with any significant wildlife habitat, mineral resource area or
. cultural resource area; or two, that measures are set forth in
the proposal which adequately mitigate adverse impacts on any
wildlife species, mineral resource area, unique natural re-
source, historic landmark and/or archaeological site within the
affected area.
3. Gas and Oil Pipeline Systems
Problems created for other land uses and resources by new
development or extension of pipeline systems are generally of a short-
range nature because the pipes themselves are placed underground.
However, associated aboveground facilities, such as compressor
stations and storage tanks, may have long-range impacts similar to
113
those created by electrical transmission facilities. Although these
similar impacts were not re -emphasized to any great depth in the
previous chapter, they are included in the following outline which
identifies potential conflicts created by pipeline system development
on existing land uses and resources.
a- Impacts on Agricultural Operations and Crop Production
1) Disruption of irrigation systems
2) Crop loss and reduced production
3) Fence damage and livestock movement
4) Trash and cut utility service lines
5) Loss of prime agricultural land
6) Water and wind erosion
b- Impacts on Quality Community Growth
1) Development patterns
2) Safety
c- Impacts on Other Resources
1) Interference with mineral resource extraction
2) Wildlife impacts
3) Impacts on cultural resources
a. Impacts on Agricultural Uses
Pipelines and associated facilities primarily impact
other land uses during the period of time required to construct the
lines. Thus, construction techniques will largely determine the severity of
114
impacts which will be encountered. In agricultural areas, construction
operations generally create the biggest problems when pipelines are
placed through irrigated croplands during the growing season; however,
significant problems can also be created when pipelines are placed
through rangelands because of the fact that it takes a long time for
construction scars to heal over in these semi-arid areas which experi-
ence high winds and little water.
In cropland areas, crops can be destroyed, irrigation ditches cut
and topsoil displaced by pipeline ditching operations. Later, subsidence
can occur along these newly constructed pipelines, which may displace
irrigation waters, especially if water tamping techniques have not been
used. If aboveground facilities are constructed in such areas, the
ground is either lost to crop production or such facilities become an
obstacle to the operation of farm machinery. In addition, the area
immediately around such facilities may become a source of weeds which
compete with crops, resulting in reduced yields and a degraded product.
In rangeland areas, potential water and wind erosion problems
are created whenever vegetation is stripped from the surface, as
occurs during pipeline ditching operations or when constructing above -
ground facilities. As previously noted, it often takes years for natural
vegetation to be re -established in these semi-arid areas. Therefore,
it is extremely important to quickly re -establish suitable ground cover
by artificial methods once construction operations are completed in
order to minimize potential water and wind erosion problems.
115
Additional problems are created in rangeland areas when utility
company survey parties fail to notify landowners about their activities,
when construction operations damage fences and utility service lines,
and when trash is left behind after operations are completed. Ranchers
must spend time and money, in such areas, identifying trespassers,
rounding up cattle, repairing service line connections and fences,
and picking up trash. Many of these problems are generally uncalled
for and can be avoided; nevertheless, past complaints affirm that such
problems are not uncommon. In the future, it is recommended that
utility companies inform landowners of their activities, inquire about
the location of existing underground utility service lines and other
facilities, carry out trash generated as a result of construction
activities, and provide temporary gates when it is necessary to cut
fences during construction operations. Such measures will minimize
interference with the daily activities of affected landowners, avoid
damages to their utility hook-ups, assure that livestock does not get
into roadways or adjacent fields, and generally alleviate hard feelings.
In order to avoid or lessen impacts on agricultural operations and
production capabilities which may result from construction of pipeline
facilities, the following policies should be observed in decisions
involving the siting of such facilities.
1) Utility companies shall be encouraged to locate aboveground
facilities in non-cropland areas to the extent possible, especially
avoiding irrigated arras. This action will assure that prime
116
lands are not directly lost for production of agricultural crops,
will minimize any interference with farm machinery, and will
minimize weed problems to the greatest extent possible.
21) In those instances where it is necessary for pipeline ease -
ments to traverse cropland areas, utility companies shall be
encouraged to conduct construction activities prior to or after
the growing season and to place their pipe at a depth which does
not interfere with plowing operations. These actions will assure
that crop yields are maintained to the greatest extent possible.
3) In those instances where it is necessary for pipeline ease-
ments to traverse irrigated areas, utility companies shall be
encouraged to bore under, rather than cut, irrigation ditches.
However, if pipeline construction activities must necessarily
take place during the growing season, boring operations shall be
postponed and temporary lines placed over irrigation ditches
until crops have been harvested.
4) Utility companies shall he encouraged to use ditching tech-
niques which replace topsoils on the surface regardless of the
location proposed for pipeline easements. This action will assure
that crop yields as well as reclamation measures are not affected
by sterile soil horizons.
5) Natural or adopted plant species suitable for grazing purposes
shall be re -established by utility companies along pipelines and
associated facilities constructed through rangeland and other
117
grazing areas. This action requires that seeding of appropriate
grasses and forbs be followed with efforts which assure that the
vegetation is finally established. This will minimize problems
associated with wind and water erosion in such areas.
b. Impacts on Communities
In and around community growth areas, pipeline place-
ment and construction activities can also create problems. Major
problems involve impacts on development patterns and safety of resi-
dents. Pipelines emplaced at shallow depths or at locations which
interfere with local community plans and projects can create significant
problems in these areas. These problems are compounded if the pipe
standards used are not on a par with proposed densities as set forth
in community development plans. In addition, aboveground utility
facilities can create problems similar to those of electrical trans -
mission facilities with reference to reduced land values because of
their general appearance. In order to minimize potential conflicts
such as those delineated above it is necessary that pipeline utility
companies observe the following guidelines.
].) Prior to approval of any pipeline or oil and gas storage area
siting proposal, it shall be determined that the nature and loca-
tion or expansion of such facilities comply with the intent and
provisions of applicable Weld County plans and the development
plans of affected communities. Such action shall include
118
coordination with local officials regarding any local capital
improvement projects or plans which may be affected by the
siting proposal.
L) Prior to the approval of any oil and gas storage area or pipe -
line siting proposal, it shall be determined that all reasonable
alternatives to the proposed action which may serve to protect
the welfare and property of surrounding landowners have been
adequately assessed and that the proposed action represents the
best interests of the people of Weld County.
3) Aboveground pipeline facilities shall be designed to blend in
with surrounding and proposed land uses, or otherwise screened
from view. This action will assist in minimizing negative
impacts on surrounding land values.
4) Pipelines shall be buried to depths which are reasonably safe
from accidental cuts caused by machinery used in constructing
streets and other urban facilities.
5) Pipe standards shall be used which are in keeping with densi-
ties proposed in community growth plans. This action will
assure that impacts on community growth patterns are minimized.
c. Impacts on Mineral, Wildlife and Cultural Resources
Pipeline easements and associated facilities can also
have impacts on other resources and land uses. Interference with
extraction of the extensive coal, sand and gravel resources found in
119
Weld County is a likely impact which must be given consideration as
pipeline development occurs. Pipelines traversing mineral resource
areas can affectively eliminate underlying deposits from being extracted
and can interfere with adjacent mining operations. It is important that
pipeline development proposals avoid commercial mineral deposits as
much as possible; and that measures be developed to mitigate impacts
and conserve commercial deposits when it is not practical to com-
pletely avoid such resource areas. Preferably, pipeline easements pro-
posed through mineral resource areas should be located within existing
right-of-ways, since these locations have,in general, precluded mining
activities. In addition, the route selection process should give preference
to locations through lower grade deposit areas. In those instances where
it is necessary for easements to traverse high grade mineral deposits,
the shortest route possible should be selected.
Potential impacts on wildlife resources are an additional concern
which must be given consideration as pipeline development occurs. Oil
spills and gas leaks from corroded pipes or lines washed out by flood-
waters, and increased sediment infiltration of water bodies from
ditching operations or from erosion of pipeline easements are potential
problems which could cause harm to fish and to wildlife habitat. In
that this concern is most likely to create problems in and around water
bodies, it is important to insure that acceptable pipeline construction
and reclamation measures are established to protect water habitats.
At stream crossings, it is recommended that pipelines be placed at
120
depths which reasonably assure that they will not be washed out by
floodwaters; and that ditching techniques be used which maintain water
turbidity within levels that will not significantly affect any fish species
present. Moreover, in any area where water resources could be
affected by pipeline construction activities or by oil and gas spills, it
is recommended that the most efficient pipe corrosion prevention tech-
niques be used and that utility companies quickly re-establish vegeta-
tion on their easement areas. These actions will assure that siltation
and pollution of water bodies, serving as wildlife habitat, is prevented
to the extent possible.
Finally, cultural resources must be considered when proposing
to construct pipeline facilities in Weld County. Damage to archaeologi-
cal artifacts, historic sites and scenic formations is a likely possibility
as pipeline development occurs. Therefore, areas containing known
cultural resources should be avoided whenever it is practical to locate
pipelines elsewhere. In addition, oil and gas storage facilities or other
aboveground facilities which may intrude upon scenic vistas should be
screened to the extent possible and otherwise designed to blend in with
the surrounding landscape. in the vicinity of archaeological areas of
high probability, utility companies should employ the assistance and
advice of qualified agencies and professionals in determining alternative
methods of protecting ancient artifacts, prehistoric bones, etc. , from
damage by construction activities.
121
In any case, the following policies shall apply to the review of
proposals for location of pipelines and associated facilities in Weld
County.
1) Prior to approval of any proposal for the location or expansion
of a pipeline or oil and gas storage facility, it shall be determined
that the proposal is in compliance with the Weld County. Mineral
Resource Extraction Plan.
2) Prior to the approval of any proposal for the location or expan-
sion of a pipeline or oil and gas storage facility, it shall be
determined that the nature and location or expansion of such
facility will not adversely interfere with any significant wildlife
habitat and will not adversely affect any endangered wildlife
species, unique natural resource, historic landmark and/or
archaeological site within the impact area.
122
B. Summary and Conclusions
In the overall effort to maintain an adequate supply of electricity,
oil and natural gas, provisions must be made for the development of
new facilities to meet the increasing demands of a growing population.
Weld County recognizes many of the problems faced by utility companies
in their necessary efforts to develop new and expanded electrical gener-
ating plants, oil and gas storage facilities and transmission systems;
however, the utilities industry does not exist in a vacuum. Rather,
their presence and the energy they supply is closely related to other
valuable resources and essential land uses such as agricultural lands
and water supplies. Thus, development of major utility facilities and
energy supply must be closely considered within the full context of land
use goals, objectives and policies in Weld County today; more specifically,
within the framework of the Weld County Comprehensive Plan.
In order to achieve this integration, and to recognize the inter-
relationships between the va;r ous elements of Weld County' s resource
base, the following guidelines will be used in evaluating proposals to
develop major utility facilities:
1) The protection of the county' s prime agricultural lands for
agricultural use is the primary goal of the Weld County
123
Comprehensive Plan. Since the county' s irrigated lands are
the most productive lands for agricultural use, and since major
utility facilities can seriously impact these lands, development
of such facilities will be discouraged in prime irrigated agri-
cultural areas:
a) When other alternatives are feasible, or
b) Unless development techniques are to be utilized
which adequately mitigate long-term interference
with farming operations and crop production.
2) Proposed major utility facilities requiring substantial water
supplies will be discouraged unless such water is either:
a) Procured from a source which will not affect existing
irrigated lands, or
b) Procured from existing agricultural water sources and
returned after use in such a manner that existing
irrigated lands are basically unaffected.
3) As an overall approach, major utility facilities will be en-
couraged to locate in non-cropland areas rather than in cropland
areas. In locating facilities in non-cropland areas, utility
companies will be expected to utilize development, design and
reclamation standards which will minimize negative impacts
on such areas. These policies are based on the assumption
that the impacts caused by development of major utility
124
facilities in non-cropland areas will be less severe than similar
impacts in cropland areas. This assumption is supported by three
basic factors. In general, non-cropland areas are more sparsely
populated; thus fewer impacts result on surrounding residential
uses. Second, non-cropland areas are generally less productive
on a per/acre basis; thus economic impacts are less severe when
such lands are removed from production. Finally, the impacts
on agricultural operations in non-cropland areas are generally
less severe since these areas in general do not require the use
of large farm machinery and lack sophisticated water distribution
systems.
4) The location of major public utility facilities in identified
resource conservation areas will be discouraged unless develop-
ment, design and reclamation standards are utilized which adequately
mitigate the negative impacts created by the location of these
facilities in such areas. Resource conservation areas include
lands underlain by the County' s most significant sand and gravel
resources, significant cultural resources sites, and those areas
which support large concentrations of raptors and other wildlife
species. It is important that these areas, which contain valuable
and/or limited resources be protected, to the extent possible,
from impacts which would deplete, destroy or otherwise lessen
the value of such resources.
125
5) When the location of major utility facilities is proposed
within the comprehensive planning area of one or more Weld
County incorporated communities, it shall be determined prior
to the approval of the application, that:
a) The proposal is consistent with the applicable town
comprehensive plans, and
b) That the design of the proposal mitigates negative
impacts on the area in question to the greatest extent
feasible.
Finally, in all new major utility facility developments, the
impacts on the general public, as well as affected lands, must be con-
sidered in project design. It is the intent of the plan to insure that such
considerations are indeed realities.
126
Sources Cited
Sources Cited
1. Session Laws of Colorado 1974, Second Regular Session. Areas
and Activities of State Interest. Chapter 106, Article 7, Para-
graph 204(6).
2. Yakich, Eli, Jr., Public Service Company of Colorado. Letter
to Roy Jost, Planner, Weld County Planning Commission, Greeley,
Colorado, September 12, 1975.
3. Capener, J. Paul, U. S. Bureau of Reclamation, interviewed by
Roy Jost, Denver, Colorado, September 3, 1975.
4. Nagel, Theodore J. , and Vassell, Gregory S. , "Power Plant
Siting Requirements." Planning, February, 1973, pp. 24-26.
5. Colorado Land Use Map Folio. Selected Energy Resources and
Pipelines. Colorado Land Use Commission: Denver, Colorado,
January, 1974.
6. U. S. Bureau of the Census, "Census of Agriculture, 1969,
Volume V. Special Reports. " Part 12. Ranking Agricultural
Counties. U. S. Government Printing Office, Washington, D. C. ,
February, 1973.
7. Board of County Commissioners, Weld County, Colorado. "Weld
County Comprehensive Plan. " County Master plan adopted by
the Board, Greeley, Colorado, September, 1973.
8. Board of County Commissioners, Weld County, Colorado. "Weld
County Zoning Resolution. " County Zoning regulations adopted
by the Board, Greeley, Colorado, May 1961, as amended.
9. The Denver Post, April 24, 1977.
10. Korrin, M., Department of Atmospheric Science, Colorado State
University, interviewed by Roy Jost, telephone, Greeley,
Colorado, June 6, 1977.
11. Public Service Company of Colorado. Air Solutions? Informational
booklet available through the Information Department of Public
Service Company of Colorado, Denver, Colorado, January, 1974.
128
12. U. S. Department of Housing and Urban Development. Rapid
Growth From Energy Projects. A study prepared under the 701
Comprehensive Planning Program in cooperation with the Federal
Energy Administration, U. S. Government Printing Office, 1976.
13. Western Systems Coordinating Council. Environmental Guide-
lines. Guidelines developed by environmental committee and
offered to member utility companies Rosemead, California:
Southern California Edison Company, December 3, 1971.
14. Department of Natural Resources. Sand, Gravel, and Quarry
Aggregate Resources of the Colorado Front Range Counties.
Colorado Geological Survey: Denver, Colorado, 1974.
15. Board of County Commissioners, Weld County, Colorado. "Weld
County Extraction Plan." Amendment to County Master Plan
adopted by the Board, Greeley, Colorado, July, 1975.
16. Raptor Research Foundation, Inc. Suggested Practices for Raptor
Protection on Powerlines. Provo, Utah: Department of Zoology,
BYU, June, 1975.
129
Appendix/ Regulations
APPENDIX
AMENDMENTS TO THE WELD COUNTY ZONING RESOLUTION
Under the Weld County Zoning Resolution, major public utility
facilities shall be permitted upon the granting of a Public Utilities Per-
mit by the Board of County Commissioners in those zoning districts
outlined below in Table A-1.
TABLE A-1
Zone Districts Allowing Development of
Major Public Utility Facilities
Facility Zone District
Substation All districts
Transmission line All districts
Pipeline All districts
Oil and Gas Storage Areas Agricultural and
Industrial
Power Plant Industrial
Prior to submittal of a Public Utilities Permit application,
applicants are strongly encouraged to coordinate their intentions with
the Weld County Department of Planning Services and, through public
meetings, to inform potentially affected landowners and other con-
cerned citizens of their intentions. Such actions will help ensure that:
1) Applicants are informed of county policy regarding the site
selection process;
2) Applicants are made aware of reasonable alternatives which
should be considered;
3) Applicants are informed of specific problems, objections,
and concerns of affected individuals regarding their develop-
ment proposal; and
131
4) Applicants are assisted in determining if additional informa-
tion may be required.
This information will expedite the application process and avoid
rehearings. Previous applications have been tabled at hearings be -
cause they were in direct conflict with the Weld County Comprehensive
Plan; various alternative locations were not considered and required
study; underground irrigation systems were overlooked; or sufficient
information regarding a variety of factors had not been submitted as
required. If applicants coordinate closely with the Weld County Planning
Staff and conduct public meetings, such delays can be avoided.
Public Utility Permits are not a requirement for minor facilities
such as: substation sties not directly connected with transmission lines
carrying over 69 KV of electricity; oil and gas storage facilities with
capacities under 100, 000 gallons or 50 million cubic feet; oil and gas
pipelines 10 inches diameter; or electric transmission lines under 70 KV
capacity. Request for facilities larger than those noted above and for
power plants are subject to the additional requirements of Section 6. 8
of the Weld County Zoning Resolution. Section 6. 8, which follows, is
a new amendment declared to be necessary for the immediate protection
of the health, safety and welfare of the inhabitants of Weld County.
132
Section 6. 8 Site Selection and Construction of Major Facilities of a
Public Utility
1 . General and Introductory Provisions
A. Purpose and Intent - The purpose and intent of the regulations
contained in this section are:
(1) To encourage planned and orderly land use development;
(2) To encourage uses of land and other natural resources
which are in accordance with their character;
(3) To conserve soil, water, and agricultural resources;
(4) To protect the beauty of the landscape;
(5) To promote the efficient and economic use of public
resources;
(6) To regulate the site selection and construction of major
facilities of a public utility to prevent significant deteriora-
tion or degradation of existing air and water quality in the
state;
(7) To regulate the site selection and construction of major
facilities of a public utility so as to avoid direct conflict
with existing land uses and adopted city, county, regional,
and state master plans; and
(8) To promote the health, safety and welfare of the inhabitants
of the area and the county.
B. Authority
These regulations are adopted pursuant to inter alia, Z4-65. 1 -101,
et. seq. , 29-20 -101 , et. sea. , 30 -28-101 , et. seq. , C. R. S.
1973, as amended.
C. Applicability
These regulations shall apply to all new site selections of major
facilities of public utilities within the unincorporated lands of
Weld County subsequent to the adoption of these regulations. These
regulations shall also apply to any expansion, enlargement, or
extension of major facilities of public utilities after the adoption
of these regulations.
133
D. Relationship of Regulations to Other Requirements
Nothing in these regulations shall be construed as exempting
an applicant for a permit from any other requirements of
Weld County or state or federal laws and regulations. An
application for a public utilities permit under these regula-
tions may be filed concurrently with any other permit or
applications required under this resolution or other regula-
tions of Weld County. If it is necessary to rezone the property,
then the rezoning application shall be submitted concurrently
with the public utilities permit application.
E. Prohibition of Site Selection and Construction of a Major
Facility of a Public Utility Without Permit
(1) No person may locate or construct a major facility
of a public utility in Weld County without first obtaining
a public utilities permit pursuant to these regulations.
(2) No building permit for a major facility of a public
utility will be approved without the applicant first ob-
taining approval of a Public Utilities Permit pursuant
to these regulations.
F. Relationship to Zoning Districts
Major facilities of a public utility as identified below shall be
permitted to locate in the zoning districts outlined below once
a Public Utilities Permit has been obtained pursuant to these
regulations.
Facility Zone District
Substation All Districts
Electric Transmission Line All Districts
Pipeline All Districts
Oil and Gas Storage Areas Agricultural and
Industrial
Power Plant Industrial
1 34
G. Permit Process
(1) Duties of the Department of Planning Services
a. the Weld County Department of Planning Services
shall be responsible for processing all applications
for a major facility of a public utility in the unin-
corporated area of Weld County. The Department
shall also have the responsibility of insuring that all
application submittal requirements are met prior to
initiating any official action as listed below.
b. Upon determination that a submitted application is
complete, the staff of the Department of Planning
Services shall:
1) Set a Planning Commission hearing date not less
than thirty (30) days nor more than sixty (60)
days after the complete application has been
submitted.
2) Arrange for a public notice of the hearing by the
Planning Commission to be published once in a
newspaper serving the general area of the request
a minimum of ten (10) days prior to the hearing
date.
3) Notify all owners of property within 500 feet of
the parcel under consideration a minimum of ten
(10) days in advance of the Planning Commission
hearing except for applications for an electric
transmission line or gas pipeline which is more
than one (1) mile in length in which case it is the
responsibility of the applicant to advertise the
hearing at least once in a newspaper(s) serving
the general area of the request a minimum of ten
(10) days prior to the hearing date. The advertise-
ment shall be at least one-half page in size and
shall contain a map displaying the proposed alterna-
tive routes along with a description of the hearing
time, date, and location. The number, form, and
content of the advertisement(s) shall be approved
by the Director of the Department of Planning Ser-
vices prior to publication.
135
4) Refer the application to the following agencies,
when applicable, for their review and comment.
The agencies named shall respond within twenty-
one (21) days after the mailing of the application by
the County. The failure of any agency to respond
within twenty-one (21) days may be deemed to be a
favorable response to the proposal. Such agencies
may request and be granted additional time for
review of such proposals upon approval by the
Director of the Department of Planning Services.
The reviews and comments solicited by Weld
County are intended to provide the County with
information on the proposal. The Planning Com-
mission and Board of County Commissioners may
consider all such reviews and comments, and may
solicit additional information if such information
is deemed necessary. The reviews and comments
submitted by a referral agency are recommendations
to the County. The authority and responsibility for
making the decision to approve or deny the proposal
rests with the officials of Weld County.
a) The Planning Commission of any town and/or
county whose boundaries are within three (3)
miles of the proposed site(s) or if the proposed
site(s) is located within any town' s compre-
hensive planning area.
b) Weld County Planning Commission member(s)
representing the geographic district in which
the proposed site is located.
c) Weld County Department of Law for checking
the legal description of the proposed site.
d) Weld County Department of Health Services
e) Weld County Department of Engineering
Services
f) Colorado Geological Survey
g) Colorado State Department of Highways
h) U. S. Forest Service
i ) Any irrigation ditch company with facilities
136
within or adjacent to the site(s) under
consideration.
j ) All utility companies with underground lines
which might be affected by the development.
k) All special service districts who will need
to provide service to the development such
as education, fire protection, police pro-
tection, water, and sewer.
1) State Engineer, Division of Water Resources
m) Soil Conservation Service
n) Colorado Land Use Commission
o) Any other agencies or individuals whose
review the Director of the Department of
Planning Services deems necessary.
5) Prepare staff comments and recommendations for
presentation at the Planning Commission hearing,
addressing all aspects of the application, its
conformance with the Weld County Zoning Resolu-
tion, the Weld County Comprehensive Plan, and
comments received from agencies to which the
proposal was referred.
c. The Department of Planning Services shall arrange
for the office of the Weld County Clerk and Recorder
to record the plans approved by the Board of County
Commissioners.
(2) The Planning Commission shall hold a hearing to
consider the application for the Public Utilities Permit.
The Commission shall make a recommendation to the
Board of County Commissioners. Prior to making
a recommendation on an application for a Public
Utilities Permit, the Planning Commission shall
determine whether the proposal is in conformance with:
a. Section A - Purpose and Intent, of these regula-
tions, and
b. Section 3 - Standards, of these regulations.
137
The SecrrLrry of the Planning Commission shall
forward the official recommendation to the Clerk
to the Board of County Commissioners within ten
(10) days after said recommendation has been made.
If the Planning Commission recommendation is
conditional upon the applicant completing certain
specified items prior to the publication of the notice
for the hearing by the Board of County Commissioners,
then the ten (10) day period shall commence upon
submission of the items by the applicant to the Director
of the Department of Planning Services.
(3) Duties of the Board of County Commissioners
a. Upon receipt of the Planning Commission recom-
mendation, the Clerk to the Board shall:
1) Set a Board of County Commissioners' public
hearing for consideration of the proposal
within sixty (60) days after receiving the
Planning Commission recommendation.
2) Arrange for notice of said meeting to be
published once in a newspaper of general
circulation in Weld County. The date of
publication shall be at least ten (10) days
prior to the hearing.
3) Notify surrounding property owners in con-
formance with Section 1 . G. (1)b. 3) of these
regulations.
b. The Board of County Commissioners shall hold a
public hearing to consider the application and to
take final action thereon. In making a decision
on a Public Utilities Permit, the Board shall:
1) Consider the recommendation of the Planning
Commission;
2) Determine whether the proposal complies with
Section 1. A - Purpose and Intent, of these
regulations; and
3) Determine whether the proposal complies with
Section 3 - Standards, of these regulations.
138
The Board of County Commissioners shall ap-
prove an application for a major facility of a
public utility only if the request complies with
Section 1.A - Purpose and Intent and with
Section 3 - Standards of these regulations.
2. Application for Permit
A. Any person seeking to locate and construct a major facility
of a public utility in Weld County shall apply for a Public
Utilities Permit on the forms provided by the Weld County
Department of Planning Services. The application forms
shall be accompanied by the supporting documents required
by these regulations.
B. Fee - Any application for a permit to locate and construct
a major facility of a public utility shall be accompanied by
certified funds to cover the cost of processing the application
in the amount of $150. 00. The $150. 00 fee covers part of
the cost of processing the application and is non-refundable.
C. To minimize expenditures of time and money by all con-
cerned, the Department of Planning Services encourages
applicants to confer with the staff once a written summary state-
ment of the project, as outlined below, has been completed.
This consultation between the applicant and the Department of
Planning Services Staff will provide a forum for identifying
problems and issues which need to be addressed in the de-
tailed report.
D. Submission Requirements
Fifteen (15) copies of the application for a public utilities per-
mit shall be submitted by the applicant to the Department of
Planning Services. An application for a public utilities permit
shall contain the following information in such form as pre -
scribed by the Department of Planning Services.
(1) Applicant' s name and telephone number.
(2) Address of applicant and general office.
(3) Summary statement of the project, to include when
applicable:
139
a. Source, capacity, destination and type of facilities,
support structures, lines, etc. involved.
b. Number and description of alternative locations
or routes considered with a synopsis emphasizing
reasons for favoring a particular site or route.
c. Procedures, including reclamation measures, land-
scaping, buffering techniques, and/or multiple -
uses, to be employed in efforts to mitigate any
adverse impacts.
d. Size of the work force, both temporary and per-
manent, involved.
e. An outline of the planned construction and operation
_ schedule to include the number of stages and timing
of each.
f . A synopsis of the water requirements, if any, to
include the quality and quantity needed for each pro-
posed use, proposed source(s), proposed storage
facilities, proposed points of diversion, proposed
treatment system, and proposed distribution system.
g. A summary of the fuel requirements, if any, to
include the type and quantity needed, proposed
source(s), and proposed storage facilities.
h. A description of the proposed location(s) and method(s)
of disposal of all forms of waste.
(4) A detailed report shall be submitted which includes
information on the following items:
a. A complete description of the propsed facilities
including the source, capacity, destination, type
of structures, etc. , which are involved.
b. A complete analysis of the alternative routes or
sites considered to include in each case:
1) Reasons for consideration;
2) Types of agricultural and other land uses affected;
140
3) Construction cost of the proposed alternatives;
4) Impacts on mineral resources;
5) Impacts on wildlife habitat;
6) Impacts on historical, archaeological, and scenic
resources;
7) Visual impacts created by above ground facilities;
8) A description of any geologic hazards which
could adversely affect the development; and
9) Advantages and disadvantages of the alternatives
considered.
c. A description of the preferred alternative route or site
and reasons why it is favored.
d. Procedures to be employed in mitigating any adverse
impacts of the proposed routes or sites.
e. An outline of the planned construction and operation
schedule to include the number of stages and timing
of each.
f . Information of any public meeting(s) conducted to
include the location(s), date(s), time(s), attendance,
and method of advertising.
g. A description of the hazards, if any, of fire, explosion
and other dangers to the health, safety and welfare of
employees and the general public.
h. A description of emergency procedures to be followed
in case of a reported failure or accident involving
the proposed facility. Such outline should include
actions, if any, required of public officials, including
fire and police officials, and the names and telephone
numbers of appropriate company officials to notify
if an accident or failure should occur.
i . A description of the method or procedures to be em-
ployed to avoid or minimize the impacts on irrigated
agricultural land.
141
j . A discussion of how the proposal conforms with the
guidelines of the Weld County Comprehensive Plan
with particular emphasis on the Public Utilities Section
of the Plan.
k. A discussion of the proposal for maintenance of the
facility so as to prevent fugitive dust, soil erosion,
and the growth of noxious weeds.
1 . A drainage report outlining the method of preventing
surface runoff from exceeding the historical flow.
m. Additional information needed for Transmission Lines
and Oil and Gas Pipe Lines:
1) A discussion of the feasibility of utilizing any
existing utility line corridors.
2) A list of the names and addresses of all the
various utility companies which have existing
underground utility lines underlying the alterna-
tive routes.
n. Additional information needed for Power Plant site
proposals:
1) Detailed information concerning water require-
ments to include the quantity and quality needed
for the use, proposed source(s), proposed
storage facilities, proposed point(s) of diversion,
proposed treatment system, and proposed distri-
bution system.
2) A description of the fuel requirements to include
the type and quantity needed, proposed source(s),
and proposed storage facilities.
3) A description of the location(s) and method(s) of
disposal of all forms of waste.
4) A description of the type of transportation
facilities needed to service the facility.
5) An outline of the types and numbers of operating
and construction equipment to be employed.
142
6) A description of the size of the work force, both
temporary and permanent, to be involved in the
construction and operation of the facility.
7) A discussion of the proposal for providing
temporary and permanent housing to accommodate
the work force. The description shall outline the
number, type, and location of the proposed building
dwellings.
8) An estimate of the anticipated tax revenues to be
generated by the project for local government and
special districts.
9) A letter from each utility company indicating
their intention and ability to serve the development.
10) A list of the names and addresses of all the local
governments and special districts which would be
affected by the development.
11) A discussion of the anticipated overall impact on
local governments and special district service
capabilities, including: education, police pro-
tection, fire protection, water, sewer, health
services and road maintenance services.
12) A description of the program proposed by the
applicant to meet the costs of providing necessary
facilities and services which a particular service
entity does not have the financial capability of
providing.
13) A discussion of the potential air and water pollution
impacts which may be created by the facility along
with proposed pollution control measures. This
discussion should include any meteorological or
climatological conditions which would cause the
facility to create negative impacts on surrounding
land uses.
14) A description of any routine haul routes identifying
the roads and bridges involved and the weight of
the loads.
143
15) Any other information determined to be necessary
by the Board of County Commissioners or their
authorized representative to ensure the protection
of the health, safety and welfare of the inhabitants
of Weld County.
(5) Drawing Requirements
a. Facilities Plan Map(s) for Substation Sites, Oil and Gas
Storage Areas, and Power Plant Sites
1) General Requirements
a) Fifteen (15) copies of these maps shall be
submitted concurrently with the written
application
b) Maps shall be delineated in drawing ink on
mylar or other drafting media approved by
_ the Director of Planning Services in the
following size: Twenty-four (24) inches by
thirty-six (36) inches.
c) The maps shall be prepared and certified
by a land surveyor registered in the State of
Colorado.
2) Vicinity Map
a) The purpose of the Vicinity Map is to show
the location of the proposed site in relation
to the surrounding area within three (3)
miles.
b) The proposed site shall be identified on the
vicinity map. The vicinity map shall also
identify the zone districts, subdivisions, water
bodies, transportation facilities, and towns
within a three (3) mile radius.
3) Site Plan
The Site Plan shall:
144
a) 11e• 'Irawn at a scale of I inch. 100 feel. This
scale may be reduced or enlarged upon ap-
proval of the Director of Planning Services.
b) Include the property under application as well
as features within 500 feet of the parcel
boundaries.
c) Include a certified boundary survey of the
property. Bearings and distances of all
perimeter boundary lines shall be indicated
outside the boundary line.
d) Show the existing topography of the site at
ten (10) feet contour intervals, as solid lines,
and the proposed topography of the site at
ten (10) feet contour intervals as dashed lines.
e) Show the name and location of all streams,
including normally dry streams, ponds or
other bodies of water, existing structures,
roads, bridges, irrigation ditches, oil and
gas wells, utility lines, landscape features,
and easements.
f) Show in detail the size and location of any
proposed structures or associated facilities
such as access drive(s), parking area(s),
landscaped area(s), and fencing.
g) Include such additional information as may
be required by the Board of County Commissioners
to satisfactorily explain the general charac-
teristics of the proposed facility.
4) Legend
The legend shall include:
a) A certified boundary survey of the property.
The description shall include the total
acreage of the surveyed parcel.
145
b) Development standards governing the loca-
tion, design, construction, and operation of
the proposed facility. It is recommended
that the first draft of the development standards
be placed on separate 82 x 11" typed sheets.
This will prevent additional drafting if changes
must be made as the application is reviewed.
c) Certificates:
1 - Surveyor' s Certificate;
2 - Certificate of Responsibility to be
signed by the landowner;
3 - Planning Commission Certificate;
4 - Certificate of Approval by the Board
of County Commissioners; and
5 - Clerk and Recorder' s Certificate.
d) Title, scale, and north arrow.
e) Date, to show revision dates if applicable.
b. Utility Line Plan Map(s) for Electric Transmission
Lines, and Oil and Gas Pipelines
1) General Requirements
a) Utility Line Plan Map(s) shall be submitted
in two stages:
1 - Alternate Route Map Set, and
2 - Selected Route Map Set.
b) Fifteen copies (15) of the Alternate Route
Map Set shall be submitted concurrently
with the written application.
c) The Selected Route Map Set shall be sub-
mitted for recordation after approval of a
route by the Board of County Commissioners.
146
2) Alternate Route Map Set shall:
a) Include a vincinity map which displays the
location of all the alternative routes within
Weld County in relation to towns, major
water features, and major transportation
features. The vicinity map shall be pre-
pared at a suitable scale on a sheet 24 x 36"
in size. The vicinity map shall function as
a map index for the detailed route maps shown
on the U. S. G. S. Topographic Quadrangle
Maps.
b) Include a route map showing the proposed
alternate routes through Weld County. The
routes shall be shown on a 1:24, 000 scale
U. S. G. S. Topographic Quandrangle Map(s).
The centerline of each of the proposed alter-
nate routes shall be displayed on the route
map. The route map shall also show the
areas of irrigated and non-irrigated agri-
cultural land use as well as future land use
designations for the areas around the towns
which have adopted Master Plans. In addition,
the 1 :24, 000 U. S. G. S. Topographic base map
shall be updated to accurately depict any
significant new man-made features within one
mile of any of the proposed routes.
c) Include such additional information as may
be required by the Board of County Commis-
sioners or their duly authorized representative.
3) Selected Route Map Set shall:
a) Be submitted on a sheet(s) 24 x 36" in size.
b) Be drafted in drawing ink on mylar or other
drafting media approved by the Director of
Planning Services.
c) Include a vicinity map at a suitable scale
which displays the location of the approved
route within Weld County and its relationship
to towns, major water features, and major
transportation features.
147
d) Include a detailed route map showing the
approved route through Weld County. The
approved route shall be displayed on a
1:24, 000 scale U. S. G. S. Topographic Quad-
rangle(s). The map(s) shall display the
centerline of the approved route and all of
the features depicted on the U. S. G. S.
Topographic Quadrangle within one (1) mile
on each side of the approved route. The
base map shall be updated to include any
significant new man-made features within
one (1) mile on each side of the approved
route.
e) Include a legend consisting of the following
items:
1 - Development standards governing the
location, design, construction, and
operation of the proposed facility.
2 - Certificates as follows:
a - Certificate of Responsibility of the
landowner;
b - Planning Commission Certificate;
c - Certificate of Approval by the
Board of County Commissioners; and
d - Clerk and Recorder' s Certificate.
3 - Title, scale, and north arrow.
4 - Such additional information as may be
required by the Board of County Com-
missioners to satisfactorily explain the
general requirements of the facility as
approved.
148
Amendments to Section 12. 2 - Terms and Words:
(58) "Applicant" tneans any individual, partnership, corporation,
association, company, or other public or corporate body, in-
cluding the federal government or federal entity, and includes
any political subdivision, agency, instrumentality, or corpora-
tion of the state.
(59) "Appurtenant facilities" means any buildings, structures or
other property which are clearly incidental to, and custom-
arily found in connection with major facilities of public utilities
and are operated and maintained for the benefit or convenience
of the occupants, employees, customers or visitors of such
major facilities. Appurtenant facilities as defined herein re -
lates only to those facilities which are constructed at the same
time as the major facility itself.
(60) "Major facilities of a public utility" means:
(a) Transmission lines, power plants, and substations of elec-
trical utilities, including extensions, expansions, and/or
enlargements thereof.
(b) Pipelines and storage areas of utilities providing natural
gas or other petroleum derivatives, including extensions,
expansions, and/or enlargements thereof.
(61) "Pipelines" mean any pipeline and appurtenant facilities designed
for, or capable of, transporting natural gas or other petroleum
derivatives of ten (10) inches diameter or larger which creates
a hoop stress of 20 percent or more at their specified minimum
yield strength.
(62) "Power plant" means any electrical generating facility with an
energy generating capacity of fifty (50) megawatts or more, and
any facilities appurtenant thereto, or any expansion, extension,
or enlargement thereof increasing the existing design capacity
of the facility by fifty (50) megawatts or more.
(63) "Master plan" (or comprehensive plan, or general plan) means
a plan for the physical development of the state, a county, region,
or municipality, as defined by 24-32 -203(1)(e), 24-65-104(1)(a)(b),
30 -28-106(3)(a)(b)(c), 30 -28-107, and 31 -23-106(1)(a)(b)(c)(d),
C. R. S. 19i3, or by charter or ordinance of a home-rule municipality.
149
(64) "Public Utility"means:
(1) The term "public utility" includes every common carrier,
pipeline corporation, gas corporation, electrical corporation,
telephone corporation, telegraph corporation, water corpora-
tion, person, or municipality operating for the purpose of
supplying the public for domestic, mechanical, or public uses
and every corporation, or person declared by law to be affected
with a public interest. Nothing in this definition shall be
construed to apply to irrigation systems, the chief or principal
business of which is to supply water for the purpose of irriga-
tion or to exemptions provided for in the constitution of the
State of Colorado relating to municipal utilities.
(2) Every cooperative electric association, or nonprofit electric
corporation or association, and every other supplier of
electrical energy, whether supplying electric energy for the
use of the public or for the use of its own members, is also
a public utility.
(65) "Site selection" means the process for determining the location of
major facilities of a public utility or the expansion, extension or
enlargement of existing major facilities of a public utility.
(66) "Substation" means any facility designed to provide switching,
voltage transformation, or voltage control required for the trans-
mission of electricity which has an incoming or outgoing line
which is more than 69 KV.
(67) "Transmission lines" mean any electric transmission line
carrying more than 69 KV and appurtenant facilities which
emanate from a power plant or substation and terminate at a
substation.
(68) "Storage area" means any facility, including appurtenant facilities,
designed to store fifty million cubic feet or more of natural gas
or similar petroleum derivatives, or one hundred thousand
barrels or more of liquid petroleum derivatives.
3. Standards
The Board of County Commissioners may approve an application
for site selection and construction or expansion of a major facility
of a public utility only if all requirements of these regulations are
met, and the application is consistent with the following standards:
150
A. Reasonable efforts have been made to avoid irrigated cropland
or to minimize the impacts on such lands in those cases where
avoidance is impractical.
B. The facility will not have an undue adverse effect on existing
and future development of the surrounding area as set forth
in applicable Master Plans.
C. The design of the proposed facility mitigates negative impacts
on the surrounding area to the greatest extent feasible.
D. The site shall be maintained in such a manner so as to control
soil erosion, fugitive dust, and the growth of noxious weeds.
E. The applicant has agreed to implement any reasonable measures
deemed necessary by the Board of County Commissioners to
insure that the health, safety, and welfare of the inhabitants
of Weld County will be protected and to mitigate or minimize
any potential adverse impacts from the proposed facility.
F. The proposed facility will be supplied by an adequate water
supply which has been evaluated with reference to the impacts
of the use of such supply on agricultural uses. All reasonable
steps have been taken by the applicant to minimize negative
impacts on agricultural uses and lands.
G. All reasonable alternatives to the proposal have been ade-
quately assessed and the proposed action is consistent with
the best interests of the people of Weld County and represents
a balanced use of resources in the affected area.
H. It has been determined that the nature and location or expansion
of a proposed power plant facility will not create an expansion
of the demand for government services beyond the reasonable
capacity of an impacted community or the County to provide such
services. Where it is indicated that such an expansion of the
demand for services will occur beyond the reasonable capacity
to provide such services, the applicant must clearly show how
such impacts will be mitigated prior to approval of the proposal
by the County.
I . It has been determined that the nature and location or expansion
of the facility will not significantly deteriorate air quality in the
affected area and that the facility will meet Colorado Department
of Health and Weld County air quality standards.
151
J . The nature and location of the facility or expansion thereof
will not impair the water rights of any upstream, downstream,
or adjacent communities or other water users without due
compensation.
K. Adequate electric, gas, telephone, water, sewage, and other
utilities exist or can be developed to service the site.
L. The nature and location for expansion of the facility will not
unreasonably interfere with any significant wildlife habitat
and will not unreasonably affect any endangered wildlife
species, unique natural resource, historic landmark and/or
archaeological site within the affected area.
M. The applicant' s engineer has certified that the drainage plans
developed for, and to he implemented on the site, will prevent
surface drainage from leaving the site which would exceed
historic runoff flows.
N. There are no geological hazards present which cannot be
overcome through proper engineering design and construction
techniques. The proposal complies with the requirements, if
applicable, of the Weld County Supplementary Regulations con-
cerning Geologic Hazards.
O. The development of the proposed facility will not preclude the
development of any commercial mineral deposit. Further, the
proposal is in compliance with the Weld County Mineral Resource
Extraction Plan.
P. Where a proposed power plant is to be located in an area where
a sufficient housing supply is unavailable for the anticipated
immigrant construction force, the applicant for the location of
such a facility must present plans showing how housing will be
provided for such workers without creating major negative
impacts on existing housing supplies and existing residents in
the impacted communities,
Q. The proposal complies with the policy guidelines set forth in
the Weld County Publi.c Utilities Plan.
R. The proposal complies with the requirements, if applicable, of
the Weld County Supplementary Regulations concerning Geologic
Hazards and Flood Plains.
152
Hello