HomeMy WebLinkAbout20190268.tiffRESOLUTION
RE: ACTION OF BOARD CONCERNING USE BY SPECIAL REVIEW PERMIT,
USR18-0100, FOR A 1041 PERMIT FOR A MAJOR FACILITY OF A PUBLIC UTILITY
ONE (1) 230KV TRANSMISSION LINE EXTENDING APPROXIMATELY 21 MILES,
ONE (1) NEW SUBSTATION (GRAHAM CREEK) AND UPGRADES TO AN EXISTING
SUBSTATION (WAPA AULT SUBSTATION) IN THE A (AGRICULTURAL) ZONE
DISTRICT - PUBLIC SERVICE COMPANY OF COLORADO
WHEREAS, the Board of County Commissioners of Weld County, Colorado, pursuant to
Colorado statute and the Weld County Home Rule Charter, is vested with the authority of
administering the affairs of Weld County, Colorado, and
WHEREAS, the Board of County Commissioners held a public hearing on the 23rd day of
January, 2019, at the hour of 10:00 a.m., in the Chambers of the Board for the purpose of hearing
the application of Public Service Company of Colorado, 1800 Larimer Street, Suite 400, Denver,
Colorado 80202, for a Site Specific Development Plan and Use by Special Review Permit,
USR18-0100, for a 1041 Permit for a Major Facility of a Public Utility one (1) 230KV transmission
line extending approximately 21 miles, one (1) new substation (Graham Creek) and upgrades to
an existing substation (Wapa Ault Substation) in the A (Agricultural) Zone District on the following
described real estate, to -wit:
The transmission line will be located in Sections 2,
3, 4, 5, 6, 10, 15, 22, 26, 27 and 35, Township 7
North, Range 66 West; Sections 2, 11, and 12,
Township 6 North, Range 66 West; Sections 7, 15,
16, 17, 18, 22 and 27, Township 6 North, Range 65
West of the 6th P.M., Weld County, Colorado
WHEREAS, the Board heard all of the testimony and statements of those present and
reviewed the request of the applicant and, having been fully informed, finds that this request be
approved and the matter should be continued to May 22, 2019, at 10:00 a.m., to allow Public
Services Company of Company adequate time to comply with the terms of the Amended Waiver
Agreement and allow for the Planning Commission hearing continued to March 19, 2019.
NOW, THEREFORE, BE IT RESOLVED by the Board of County Commissioners of Weld
County, Colorado, that the abovementioned matter be, and hereby is, continued to May 22, 2019,
at 10:00 a.m.
c.G: PL .CC,(TP), aH(LC,), Pw(€;P/H8),
(3c),CA-I'PL/a.PPL REP
2019-0268
PL2623
RE: CONTINUANCE (USR18-0100) - PUBLIC SERVICE COMPANY OF COLORADO
PAGE 2
The above and foregoing Resolution was, on motion duly made and seconded, adopted
by the following vote on the 23rd day of January, A.D., 2019.
BOARD OF COUNTY COMMISSIONERS
WELD COUNTY, CO,LQRADO
ATTEST: datitoj .. 1. ,ii
Weld County Clerk to the Board
BY. O.
a i
puty Clerk to the Board
APP )IED AS
County A ttorney
Date of signature: narourct
Steve Moreno
arbara Kirkmeyer, !Chair
RECUSED
Mike Freeman, Pro-Tem
K. James
2019-0268
PL2623