_.,ANGE ORDER N0. 3
DATE 12/14/73
PROJECT ROAD 29 BRIDGE O.E.P #5-37 PROJECT NO. 73-1-CCA-O229
OWNER WELD COUNTY, COLORADO CONTRACTOR THOR CONSTRUCTION COMPANY
DESCRIPTION OF CHANGE - That said Contract shall be changed in the following particulars:
That estimated quantities will be changed to measured "in place" quantities.
and that after the said changes shall have been made with additions and/or deletions are
hereby directed to be a part of the original Contract, the agreement as shown by the
original Contract together with the above-named additions and/or deletions shall consti-
tute the agreement and Contract of the parties hereto.
JUSTIFICATION
For accounting purposes, the estimated contractural quantities are being changed to final
"in place" quantities.
•
CHANGE IN CONTRACT COST
Item Description Quantity Unit Unit Cost Total Cost
See attached sheet.
$ $
Total Amount This Change Order -3,331.00
a Orders +
Net of Previous Chan $
Change t ) t ) $ 1,200.00
Original Contract Amount $ 40,737. 1 )
Revised Total Contract Amount $ 38,606. 50
CONTRACT TIME
original Completion Date 12/15/73 Previous Days Allowed 130
Days Allowed This Change Order o ._ Revised Completion Date 12/15/73
Recommended: Approved:
J �
NELSON, HALEY, PATTERSON and QUIRK, INC. WELD COUNTY, COLORADO
By: (Owner)
Field Representative By:
Date: THOR CONSTRUCTION COMPANY
("//� `- - (Contractor)2 '
Approved: _�' c i
Project Plan ger BY: tt_,%,7/2-
Date:_ > �.
2/ —71 Dates , '—
730933
/0"-N 'A-6\
CHANGE ORDER NO. 3
PROJECT _ROAD 29 BRIDGE O.E.P #5-37 DATE: 12/14/73
CONTRACTOR THOR CONSTRUCTION COMPANY PROJECT N0. 73--1-CCA-0229
Amount
Item Description Quantity Unit Unit Price Add + Delete -
2 10BP42 Bearing Piles -307 L.F. 15.00 4,605.00
3 Embankment +560 C.Y. 2.25 1,260.00
6 12" C.M.P. + 2 L.F. 7.00 14.00
Subtotal 1,274.00 4,605.00
Total $ -3,331.00