Loading...
HomeMy WebLinkAbout730916.tiff e-NINGE ORDER N0. 2 DATE August 24, 1973 PROJECT PROSPECT VALLEY - KIOWA CREEK PROJECT NO. 73-1-CCA-0232 OWNER WELD COUNTY, COLORADO CONTRACTOR Goodell Brothers, Inc. DESCRIPTION OF CHANGE - That said Contract shall be changed in the following particulars: Additional 7,000 C.Y. of embankment be added to. O.E.P, item 5-47, due to elimination of low flow crossings. and that after the said changes shall have been made with additions and/or deletions are hereby directed to be a part of the original Contract, the agreement as shown by the original Contract together with the above-named additions and/or deletions shall consti- tute the agreement and Contract of the parties hereto. JUSTIFICATION Weld County Engineer CHANGE IN CONTRACT COST Item Description uaip Unit Unit Ct Total Cost 1 Embankment ,0 �� $ t.uuos $ 14,uuu.uv Total Amount This Change Order $ 14,000.00 Net of Previous Change Orders (+) (tc) $ 1,520.00 Original Contract Amount $ 115,700.00 Revised Total Contract Amount $ 131,220.00 CONTRACT TIME Original Completion Date 11/31/73 Previous Days Allowed 90 Days Allowed This Change Order u Revised Completion Date 11/31/73 Recommended: Approved: NELSON, HALEY, PATTERSON and QUIRK, INC. WELD COUNTY, COLORADO BY: if , ffr& cnia(e t 7)G Field Representative By: // Byron Ewing Date: �, GOOD H( . I . (Con act ) Approved: / roJect Manag By:\ eg-ez ��e ----- Date: ,E 2 0/7..) Date: 9 • /5/ "`777 730916 . . Hello