HomeMy WebLinkAbout730913 _.;NGE ORDER N0. 8
•
•
DATE September 19, 1973
PROJECT PIASTERS-HARDIN AREA PROJECT N0. 73-1-CCA-0228
OWNER WELD COUNTY, COLORADO CONTRACTOR LOVELAND EXCAVATING
DESCRIPTION OF CHANGE - That said Contract shall be changed in the following particulars:
That the measured "in place" quantities be increased by 112 tons of gravel surfacing
overlooked in previous measurements.
•
and that after the said changes shall have been made with additions and/or deletions are
hereby directed to be a part of the original Contract, the agreement as shown by the
original .Contract together with the above-.named additions and/or deletions shall consti-
tute the agreement and Contract of the parties hereto.
. JUSTIFICATION
Measurements reported by Kotu Kumar Phull , Weld County Engineering Consultant's
Field Representative.
CHANGE IN CONTRACT COST
Item Description . Quantity Unit Unit Cost Total ,Cost
3 Gravel Surfacing Ii [ tuns 2, 0 $ 280.00
Total Amount This Change Order $ 280.00
Net of Previous Change Orders (+) (X) $ - 22,268. 15
Original Contract Amount $ 55,062. 50
Revised Total Contract Amount $ 77,610.65
CONTRACT TIME
Origina Completion Date 9/10/73 Previous Days Allowed 78
Days Allowed This Change Order 0 Revised Comple ion Date 9/10/73
Recommended: Approved: �� /�
(� 1
NELSON, HALEY, PATTERSON and QUIRK, INC. WELD COUNTY ,COLORADO
(Owner)
By: k&t, mom. t�ivu f�c
Field Representative By:
Date: Oct . Z4, /.973 LOVELAND EXCAVATING
(Con ctor)
Project Manager By: •
Date: `0/Z ft/?-03 Date: