HomeMy WebLinkAbout730940.tiff n ,-,\
CHANGE ORDER N0. 1
DATE October 31, 1973
PROJECT PAINTER RANCH ROAD PROJECT NO. 73-1-CCA-0231
OWNER WELD COUNTY, COLORADO CONTRACTOR GOODELL BROTHERS, INC.
DESCRIPTION OF CHANGE - That said Contract shall be changed in the following particulars:
That 2,350 L.F. of snow fencing be installed on O.E.P. Items Nos . 5-24, 100 L.F. ; 5-25, 200
L.F. ; 5-26, 1,650 L.F. ; 5-27, 400 L.F. Also, that 530 wood fence posts be added to O.E.P
item #5-26.
and that after the said changes shall have been made with additions and/or deletions are
hereby directed to be a part of the original Contract, the agreement as shown by the
original Contract together with the above-named additions and/or deletions shall consti-
tute the agreement and Contract of the parties hereto.
JUSTIFICATION
The Weld County Engineer has determined that the extra items are needed to protect the roadway
from snow. Agreement was reached with landowners in the area concerning the fence posts
needed to strengthen the fence.
CHANGE IN CONTRACT COST
Item Description Quantity Unit Unit Cost Total Cost
az_ Wooden fence posts 530 -a. $ 5.00 $ 2,650.00 .
13_ Snow fnnrn 2,350 L.F. $ 1.75 $ 4,112.50
_ $ $
Total Amount This Change Order $ + 6,762.50
Net of Previous Change Orders (+) (-) $ -o-
Original Contract Amount $ 75,383.00
Revised Total Contract Amount $ 82,145.50
CONTRACT TIME
Original Completion Date 10/30/73 Previous Days Allowed 60
Days Allowed This Change Order 15 Revised `Comal e ion Date 1 /15/73
Recommended: Approved: /2 1Z-9 aaft�
NELSON, HALEY, PATTERSON and QUIRK, INC. WELD COUNT LORADO
By: kohl- /Ctcmcw PAAAAc
Field Representative By.
Date: Watt. • 6, /97,3 t6 HERS, IN .
�- Con ra r
Approved: C.c. o't //g�Q�
Pro 'ect Manager '� By: 2�-�
Date: �< G�?� Date:
730940