HomeMy WebLinkAbout20202513.tiffMEMORANDUM
TO: Esther Gesick, Clerk to the Board
FROM: Ryan Rose, Chief Information Officer
SUBJECT: B2000119 North Campus Fiber Ring
PROJECT: IT -1090 2020 Fiber Redundancy
BOCC Approval Date: August 31, 2020
June 18, 2020
Bids were received and opened on June 18, 2020 for B2000119 North Campus Fiber
Ring. One (1) bid was received for $917,547.39. Attached is the bid tabulation for your
information.
The Information Technology staff reviewed all bid responses. Sturgeon Electric
Company from Henderson, CO proposed the lowest cost solution of $917,547.39 and
meets the needed functionality documented in the bid process.
Based on the above information, I recommend the Board award B2000119 North
Campus Fiber Ring to Sturgeon Electric Company for a total amount of $917,547.39.
03/9
DATE OF BID:
REQUEST FOR:
DEPARTMENT:
BID NO:
PROJECT:
PRESENT DATE:
APPROVAL DATE:
WELD COUNTY Dept. of Information Technology
PO Box 758 / 1401 North 17th Avenue, Greeley CO 80632
E-mail: AChuryk@weldgov.com
Phone: (970) 400-2555
Fax: (970) 304-6572
June 18, 2020
North Campus Fiber Ring
INFORMATION TECHNOLOGY
#B2000119
IT -1090 2020 Fiber Redundancy
August 17, 2020
August 31, 2020
Vendor Name
Total Bid Amount
Address
Sturgeon Electric Company
12150 East 112th Avenue
Henderson, CO 80640
$ 917,547.39
ids are being reviewed at this time by dept.**