HomeMy WebLinkAbout730919.tiff es... ' `ANGE ORDER N0. 5
DATE August 28, 1973
PROJECT Prospect Valley PROJECT N0. 73-1-CCA-0232
OWNER Weld County, Colorado CONTRACTOR Goodell Brothers, Inc.
DESCRIPTION OF CHANGE - That said Contract shall be changed in the following particulars:
That 5 tons of asphalt be added to bridge approaches on O.E.P. Item 5-51 at a thickness
of 5",
and that after the said changes shall have been made with additions and/or deletions are
hereby directed to be a part of the original Contract, the agreement as shown by the
original Contract together with the above-named additions and/or deletions shall consti-
tute the agreement and Contract of the parties hereto.
JUSTIFICATION
Original asphalt on approaches washed out due to flood. The 5 tons of asphalt needed
is to replace the original asphalt.
CHANGE IN CONTRACT COST
Item Description Quantity Unit Unit Cost Total Cost
_5_ Asphalt - 5" _IL__ Tons $ 12.00 $ 180.00
$
— $ $
--- $ $
Total Amount This Change Order + $ 18 0.00
Net of Previous Change Orders (+) (gl $ sn 320.00
Original Contract Amount $ 115,700.00
Revised Total Contract Amount $ 168,200.00
CONTRACT TIME
Original Completion Date 11-30-73 Previous Days Allowed 90
Days Allowed This Change Order o Revised ComplE)� Date -80-73
Recommended: Approv ELD '1 DO `Li
NELSON, HALEY, PATTERSON and QUIRK, INC.
By: o �— � Ewing (Owner
aC Tice le d Representative By:
Date: S Jj3 :4
GOODS L BROTHER INC.
Approved:
(Contrac r
roje Manager BY: $.>2.4-144---
Date: 04/�/ Zs Date: