aNGE ORDER NO. � 1
DATE November 29 , 1973
PROJECT Road 8 Bridge PROJECT N0. 73-1-CCA-0227
OWNER Weld County, Colorado CONTRACTOR Eagle Construction Corporation
DESCRIPTION OF CHANGE - That said Contract shall be changed in the following particulars:
That Item No. 8 be added:
7.5 hours of Drag-line @ $40.00 per hour and
That Item No. 9 be added:
7.5 hour_ of Truck Use @ $14.00 per hour.
and that after the said changes shall have been made with additions and/or deletions are
here±v directed to be a part of the original Contract, the agreement as shown by the
original Contract together with the above-named additions and/or deletions shall consti-
tute the agreement and Contract of the parties hereto.
JUSTIFICATION
To provide a better embankment base for the relocated road on the west bridge approach.
CHANGE IN CONTRACT COST
Item Description
s Dragl ne Quantity Unit Unit Cost Total Cost
7.5 Hrs. $ 40.00 $ 300.00
9'' Truck 7.5 -firs $ 14.UU $ 105.00
$ $
Total Amount This Change Order $ 405.00
Net of Previous Change Orders (+) (-) $ .00
Original Contract Amount
Revised Total Contract Amount $ 66,52 .30
CONTRACT TIME $ 66,92 .�
original Completion Date 11/1/73 Previous Days Allowed 60
Days Allowed This Change Order o Revised Complet on Date 11/1/73
Recommended:
�P
Approved: licf i Cf'_,,�, . eic
NELSON, HALEY, PATTERSON and QUIRK, INC. WELD COUNTY, COLORADO
By: (Owner)
Field Representative By:
Date: EAGLE CONSTRU - ' J CORPORATION
Approved: .,_r_--40.---,,,..- .'. . ' ontract. ;#—
Project Manager g •
Date'- ///3d�p '�_: a- "C--re
Date: �� ,•• _ — .