HomeMy WebLinkAbout20210663.tiffRESOLUTION
RE: APPROVE SITE SPECIFIC DEVELOPMENT PLAN AND USE BY SPECIAL REVIEW
PERMIT, USR20-0037, FOR ACCESSORY BUILDINGS WITH GROSS FLOOR AREA
LARGER THAN FOUR PERCENT (4°/0) OF THE TOTAL LOT AREA OF A LOT IN A
SUBDIVISION IN THE A (AGRICULTURAL) ZONE DISTRICT - DEAN PRINE AND
KELLI BECKVERMIT-PRINE
WHEREAS, the Board of County Commissioners of Weld County, Colorado, pursuant to
Colorado statute and the Weld County Home Rule Charter, is vested with the authority of
administering the affairs of Weld County, Colorado, and
WHEREAS, the Board of County Commissioners held a public hearing on the 10th day of
March, 2021, at the hour of 10:00 a.m., in the Chambers of the Board, for the purpose of hearing
the application of Dean Prine and Kelli Beckvermit-Prine, 5346 Fir Avenue, Erie, Colorado 80516,
for a Site Specific Development Plan and Use by Special Review Permit, USR20-0037, for
Accessory Buildings with gross floor area larger than four percent (4%) of the total lot area of a
lot in a subdivision in the A (Agricultural) Zone District, on the following described real estate,
being more particularly described as follows:
Lot 12, Block 3, Carmacar Ranchettes; being part of
Section 5, Township 1 North, Range 68 West of the
6th P.M., Weld County, Colorado
WHEREAS, at said hearing, the applicant was present, and
WHEREAS, Section 23-2-230 of the Weld County Code provides standards for review of
said Use by Special Review Permit, and
WHEREAS, the Board of County Commissioners heard all of the testimony and
statements of those present, studied the request of the applicant and the recommendation of the
Weld County Planning Commission and all of the exhibits and evidence presented in this matter
and, having been fully informed, finds that this request shall be approved for the following reasons:
1. The submitted materials are in compliance with the application requirements of
Section 23-2-260 of the Weld County Code.
2. The applicant has demonstrated that the request is in conformance with
Section 23-2-230.6 of the Weld County Code as follows:
A. Section 23-2-230.B.1 — The proposed use is consistent with Chapter 22
and any other applicable code provisions or ordinance in effect.
1) Section 22-2-30.C.2 states: "Establish residential development
options based on compatibility, proximity to municipalities, and
availability of services that reflect the desired density and character
of that location." The proposed building addition will not have a
negative impact on the character of the surrounding area. This
property is located in Carmacar Ranchettes, which is comprised of
residential lots ranging from one (1) to over 1.5 acres in size. The
CC 2 PL (c.c, Trio) , Pw ( Mk) EN -(u)
Cr�c6cl , �L
3/�t,Jaoa%
2021-0663
PL2792
SPECIAL REVIEW PERMIT (USR20-0037) — DEAN PRINE AND KELLI BECKVERMIT-PRINE
PAGE 2
proposed building addition is for personal use and will not generate
additional traffic to the property. The proposed building addition will
meet offsets and setbacks from adjacent property lines and road
rights -of -way and will not adversely impact the surrounding area.
B. Section 23-2-230.B.2 — The proposed use is consistent with the intent of
the A (Agricultural) Zone District.
1) The proposed Use of an Accessory Buildings with gross floor area
larger than four percent (4%) of the total lot area is permittable
under Section 23-3-60.A as a Use by Special Review Permit.
2) Section 23-3-10 — Intent, states: "Agriculture in the County is
considered a valuable resource which must be protected from
adverse impacts resulting from uncontrolled and undirected
business, industrial and residential land uses. The A (Agricultural)
Zone District is established to maintain and promote agriculture as
an essential feature of the county. The A (Agricultural) Zone District
is intended to provide areas for the conduct of agricultural activities
and activities related to agriculture and agricultural production, and
for areas for natural resource extraction and energy development,
without the interference of other, incompatible land uses." The
proposal meets the intent because this is located within an existing
agricultural zoned subdivision and is adjacent to other residential
lots with similar uses. The lot is not being utilized for agricultural
purposes and the proposed building addition will not impact existing
agricultural uses.
C. Section 23-2-230.B.3 — The uses which will be permitted will be compatible
with the existing surrounding land uses. The proposed use is in an area
that can support this development. The outbuilding is existing, and the
proposed building addition will not impact adjacent uses. No phone calls or
correspondence have been received from surrounding property owners
regarding this request.
D. Section 23-2-230.B.4 — The uses which will be permitted will be compatible
with future development of the surrounding area, as permitted by the
existing zoning and with the future development, as projected by
Chapter 22 of the Weld County Code and any other applicable code
provisions or ordinances in effect, or the adopted Master Plans of affected
municipalities. The site is located within the three (3) mile referral area of
the Town of Erie and the Town of Frederick. The Towns of Erie and
Frederick in the referral comments, dated December 22, 2020, and
December 15, 2020, respectively, indicated no concerns.
E. Section 23-2-230.B.5 — The application complies with Chapter 23, Articles
V and XI, of the Weld County Code. The property is not within the Geologic
Hazard Overlay District, Agricultural Heritage Overlay District, MS 4 Area,
2021-0663
PL2792
SPECIAL REVIEW PERMIT (USR20-0037) — DEAN PRINE AND KELLI BECKVERMIT-PRINE
PAGE 3
Airport Overlay District, or a Special Flood Hazard Area. Building Permits
issued on the property will be required to adhere to the fee structure of the
County -Wide Road Impact Fee, County Facility Fee, and Drainage Impact
Fee Programs.
F. Section 23-2-230.6.6 — The applicant has demonstrated a diligent effort to
conserve prime agricultural land in the locational decision for the proposed
use. This is a proposed building addition is in an existing residential
subdivision, not an agricultural area. The property is already covered by a
residence and outbuilding. No agricultural land is affected by this proposal.
G. Section 23-2-230.6.7 — The Design Standards (Section 23-2-240, Weld
County Code), Operation Standards (Section 23-2-250, Weld County
Code), Conditions of Approval and Development Standards can ensure
that there are adequate provisions for the protection of the health, safety,
and welfare of the inhabitants of the neighborhood and County.
NOW, THEREFORE, BE IT RESOLVED by the Board of County Commissioners of Weld
County, Colorado, that the application of Dean Prine and Kelli Beckvermit-Prine, for a Site Specific
Development Plan and Use by Special Review Permit, USR20-0037, for Accessory Buildings with
gross floor area larger than four percent (4%) of the total lot area of a lot in a subdivision in the
A (Agricultural) Zone District, on the parcel of land described above be, and hereby is, granted
subject to the following conditions:
1. Prior to recording the map:
A. The map shall be amended to delineate the following:
1) All sheets of the map shall be labeled USR20-0037.
2) The attached Development Standards.
3) The map shall be prepared in accordance with Section 23-2-260.D
of the Weld County Code.
4) Fir Avenue is a paved road and is designated on the Weld County
Functional Classification Map as a local road, which requires 60 feet
of right-of-way at full buildout. The applicant shall delineate and
label the future and existing right-of-way (along with the documents
creating the existing right-of-way) and the physical location of the
road on the site map or plat. All setbacks shall be measured from
the edge of the right-of-way. This road is maintained by Weld
County.
5) The applicant shall show and label the approved access locations,
approved access width and the appropriate turning radii on the site
plan. The applicant must obtain an Access Permit in the approved
locations prior to construction.
2021-0663
PL2792
SPECIAL REVIEW PERMIT (USR20-0037) — DEAN PRINE AND KELLI BECKVERMIT-PRINE
PAGE 4
6) The applicant shall show and label the drainage flow arrows.
7) The applicant shall show and label the parking and traffic circulation
flow arrows showing how the traffic moves around the property.
2. Upon completion of Condition of Approval #1 above, the applicant shall submit
one (1) electronic copy (.pdf) of the map for preliminary approval to the Weld
County Department of Planning Services. Upon approval of the map, the applicant
shall submit a Mylar map along with all other documentation required as Conditions
of Approval. The Mylar map shall be recorded in the office of the Weld County
Clerk and Recorder by the Department of Planning Services. The map shall be
prepared in accordance with the requirements of Section 23-2-260.D of the Weld
County Code. The Mylar map and additional requirements shall be submitted
within 120 days from the date of the Board of County Commissioners Resolution.
The applicant shall be responsible for paying the recording fee.
3. In accordance with Weld County Code Ordinance #2012-3, approved April 30,
2012, should the plat not be recorded within the required 120 days from the date
of the Board of County Commissioners Resolution, a $50.00 recording
continuance charge shall be added for each additional three (3) month period.
4. Prior to Construction:
A. The approved access locations shall be permitted prior to on -site
construction.
5. The Use by Special Review Permit is not perfected until the Conditions of Approval
are completed and the map is recorded. Activity shall not occur, nor shall any
building or electrical permits be issued on the property, until the Use by Special
Review plat is ready to be recorded in the office of the Weld County Clerk and
Recorder or the applicant has been approved for an early release agreement
2021-0663
PL2792
SPECIAL REVIEW PERMIT (USR20-0037) — DEAN PRINE AND KELLI BECKVERMIT-PRINE
PAGE 5
The above and foregoing Resolution was, on motion duly made and seconded, adopted
by the following vote on the 10th day of March, A.D., 2021.
BOARD OF COUNTY COMMISSIONERS
WELD COUNTY, COLORADO
ATTEST: v,�44/ ,, ..G,a„k
Weld County Clerk to the Board
BY:
Deputy Clerk to the Board
APPROVED A
Attorney
Steve ; oreno, Chair
Lori Sain
Date of signature: 3
2021-0663
PL2792
SITE SPECIFIC DEVELOPMENT PLAN
USE BY SPECIAL REVIEW PERMIT
DEVELOPMENT STANDARDS
DEAN PRINE AND KELLI BECKVERMIT-PRINE
USR20-0037
1. The Site Specific Development Plan and Use by Special Review Permit, USR20-0037, is
for Accessory Buildings with gross floor area larger than four percent (4%) of the total lot
area of a lot in a subdivision in the A (Agricultural) Zone District, subject to the
Development Standards stated hereon.
2. Approval of this plan may create a vested property right pursuant to Section 23-8-10 of
the Weld County Code.
3. The property owner or operator shall be responsible for controlling noxious weeds on the
site, pursuant to Chapter 15, Articles I and II, of the Weld County Code.
4. There shall be no parking or staging of vehicles on public roads. On -site parking shall be
utilized.
5. Any work that may occupy and/or encroach upon any County rights -of -way or easement
shall acquire an approved Right -of -Way Use Permit prior to commencement.
6. The historical flow patterns and runoff amounts on the site will be maintained.
7. Building Permits shall be required for any new construction or set up manufactured
structure, per Section 29-3-10 of the Weld County Code. A Building Permit application
must be completed and submitted. Buildings and structures shall conform to the
requirements of the various codes adopted at the time of permit application. Currently, the
following have been adopted by Weld County: 2018 International Building Codes, 2006
International Energy Code, 2017 National Electrical Code, and Chapter 29 of the Weld
County Code. A plan review shall be approved, and a permit must be issued prior to the
start of construction.
8. The property owner or operator shall be responsible for complying with the Design and
Operation Standards of Chapter 23 of the Weld County Code.
9. The Use by Special Review area shall be limited to the plans shown hereon and governed
by the foregoing standards and all applicable Weld County regulations. Substantial
changes from the plans or Development Standards, as shown or stated, shall require the
approval of an amendment of the Permit by the Weld County Board of County
Commissioners before such changes from the plans or Development Standards are
permitted. Any other changes shall be filed in the office of the Department of Planning
Services.
10. The property owner or operator shall be responsible for complying with all the foregoing
Development Standards. Noncompliance with any of the foregoing Development
Standards may be reason for revocation of the Permit by the Board of County
Commissioners.
2021-0663
PL2792
DEVELOPMENT STANDARDS (USR20-0037) — DEAN PRINE AND KELLI
BECKVERMIT-PRINE
PAGE 2
11. Construction or use pursuant to approval of a Use by Special Review Permit shall be
commenced within three (3) years from the date of approval, unless otherwise specified
by the Board of County Commissioners when issuing the original Permit, or the Permit
shall be vacated. The Director of Planning Services may grant an extension of time, for
good cause shown, upon a written request by the landowner.
12. RIGHT TO EXTRACT MINERAL RESOURCES STATEMENT: Weld County has some of
the most abundant mineral resources, including, but not limited to, sand and gravel, oil,
natural gas, and coal. Under Title 34 of the Colorado Revised Statutes, minerals are vital
resources because (a) the state's commercial mineral deposits are essential to the state's
economy; (b) the populous counties of the state face a critical shortage of such deposits;
and (c) such deposits should be extracted according to a rational plan, calculated to avoid
waste of such deposits and cause the least practicable disruption of the ecology and
quality of life of the citizens of the populous counties of the state. Mineral resource
locations are widespread throughout the County and people moving into these areas must
recognize the various impacts associated with this development. Oftentimes, mineral
resource sites are fixed to their geographical and geophysical locations. Moreover, these
resources are protected property rights and mineral owners should be afforded the
opportunity to extract the mineral resource.
13. The Weld County Right to Farm Statement, as it appears in Section 22-2-30.A.4.a of the
Weld County Code, shall be placed on the map and recognized at all times.