HomeMy WebLinkAbout20210521.tiffMEMORANDUM
TO: Esther Gesick, Clerk to the Board February 24, 2021
FROM: Ryan Rose, Chief Information Officer
SUBJECT: B2100049 Coroner Facility Cabling
PROJECT NAME: COR-952 Coroner Move to the Ambulance Building
BOCC Approval Date: March 10, 2021
Bids were received and opened on February 17, 2021 for B2100049 Coroner Facility
Cabling. Three (3) bids were received ranging from $21,116.60 to $37,946.92. Attached
is the bid tabulation for your information.
The Information Technology staff reviewed all bid responses Sturgeon Electric
Company Inc. out of Henderson, CO proposed the lowest cost solution of $21,116.60
and meets the needed functionality documented in the bid process.
Based on the above information, I recommend the Board award B2100049 Coroner
Facility Cabling to Sturgeon Electric Company Inc., for a total amount of $21,116.60.
boa., - o� a
DATE OF BID:
REQUEST FOR:
DEPARTMENT:
BID NO:
PROJECT NAME:
PRESENT DATE:
APPROVAL DATE:
WELD COUNTY Dept. of Information Technology
PO Box 758 / 1401 North 17th Avenue, Greeley CO 80632
E-mail: AChuryk@weldgov.com
Phone: (970) 400-2555
Fax: (970) 304-6572
February 17, 2021
Coroner Facility Cabling
INFORMATION TECHNOLOGY
# B2100049
COR-952 Coroner Move to the Ambulance Building
February 24, 2021
March 10, 2021
Vendor Name
Total Bid Amount
Address
Sturgeon Electric Company Inc.
12150 East 112th Ave.
Henderson, CO 80640
$ 21,116.60
American Datapath Inc.
4251 S. Natches Ct, Unit M
Sheridan, CO 80110
$ 24,470.00
Clover Technologies
920 W. 10th St.
Pueblo, CO 81003
$ 37,946.92
ids are being reviewed at this time by dept.**
2021-0521