HomeMy WebLinkAbout20211315.tiffRESOLUTION
RE: REGULATING, WARNING AND GUIDING TRAFFIC DURING THE EXTENSION OF
TEMPORARY CLOSURE OF COUNTY ROAD 6 BETWEEN COUNTY ROADS 13
AND 19 FOR APPROXIMATELY AN ADDITIONAL THREE WEEKS, FOR
UNANTICIPATED DELAYS DUE TO WEATHER
WHEREAS, the Board of County Commissioners of Weld County, Colorado, pursuant to
Colorado statute and the Weld County Home Rule Charter, is vested with the authority of
administering the affairs of Weld County, Colorado, and
WHEREAS, pursuant to C.R.S. §42-4-106(6)(a):
"...local authorities, with their respective jurisdiction may, for the
purpose of road construction and maintenance, temporarily close to
through traffic or to all vehicular traffic any highway or portion
thereof for a period not to exceed a specified number of work days
for project completion and shall, in conjunction with any such road
closure establish appropriate detours or provide for an alternative
routing of the traffic affected...", and
WHEREAS, the Board, pursuant to said statute and upon the basis of traffic and personal
investigations, has determined that conditions exist which make it necessary to temporarily close
said County Road to through traffic and to regulate, warn and guide vehicular traffic by posting
signs thereon.
NOW, THEREFORE, BE IT RESOLVED that the Board of County Commissioners of
Weld County, Colorado, deems it necessary to regulate, warn and guide vehicular traffic on
County roads and any intersections thereof, and it hereby authorizes and orders the posting of
such traffic control devices as shall be reasonably necessary to regulate, warn and/or guide traffic
thereon for the safety of the general public and that said traffic control devices shall conform to
the Federal Manual on Uniform Traffic Control Devices.
BE IT FURTHER RESOLVED that the Board of County Commissioners of Weld County,
Colorado, does declare and establish that the temporary closure of County Road 6, between
County Roads 13 and 19, be extended, with said extended closure being effective May 4, 2021,
for approximately an additional three (3) weeks through May 28, 2021, for unanticipated delays
due to weather, and further, that standard official traffic control devices shall be erected at said
closure giving notice of the restrictions.
cc..So(Rs) D:sp -ch, CSP
OS/2.5/2(
2021-1315
EG0024
Lori Sai
EXTEND TEMPORARY CLOSURE — COUNTY ROAD 6
PAGE 2
The above and foregoing Resolution was, on motion duly made and seconded, adopted
by the following vote on the 17th day of May, A.D., 2021, nunc pro tunc March 8, 2021.
BOARD OF COUNTY COMMISSIONERS
WELD OUNTY, COLORADO
ATTEST: dea44)•Xd�fD%�
Weld County Clerk to the Board
BY:
N IA
Deputy Clerk to the Board
Stev
APPD AS
=;;,01. �i Ike Freeman
oun
y
rney
Date of signature: o5/?S/21
2021-1315
EG0024
MEMORANDUM
TO: Clerk to the Board DATE: May 12, 2021
FROM: Amy Mutchie, Public Works Department
SUBJECT: BOCC Agenda Item
Request to extend the closure of WCR 6 between WCR 13 and WCR 19 thru 5/28/2021 for road construction due
to weather delays.
See attached closure diagrams.
2021-1315
o5/I_7
ECooati
it
DETOUR
WCR 6113 to 19 scheduled for FDR, CTB, pave project spring 2021.
Bridge replacement scheduled to finish 3/12/2021
Culvert replacements scheduled all 3 miles beginning 2/22/2021
culverts: 13 to 15 thru 3/5/21. 15 to 17 thru 3/19/21. 17 to 19 yet to be determined
Pavement milling scheduled to begin 2/22/2021
FDR. CTB. Pave to begin in conjunction of completed prep work
Road scheduled to reopen May 5, 2021.
o w:7a
rn:
1
J 1 -
-y+
anol3a
0
w
0
sass
DETOUR
1
www.invarion.c
PROJECT # HRP-80
ROAD CLOSURE DESCRIPTION
WCR 6 between WCR 13 and WCR 19
closed 2/22/2021 thru 5/4/2021
for culvert replacements all 3 mile
5" asphalt removal, CTB treated base
Repave with new asphalt
WCR 6 between WCR 17 and WCR 19
will remain closed for continued
bridge replacement work thru 3/12/21
NOTICE TO PUBLIC
Road signs and barricaded
Message boards to be used
DETOUR ROUTE
West bound traffic:
WCR 19 between WCR 6 and WCR 8 1 mile paved
WCR 8 between WCR 19 and WCR 13 3 mile gravel
WCR 13 between WCR 6 and WCR 8 1 mile paved
East bound traffic:
WCR 13 between WCR 6 and WCR 4 1 mile paved
WCR 4 between WCR 13 and WCR 19 3 mile gravel
WCR 19 between WCR 6 and WCR 4 1 mile paved
NOTES:
ADT of WCR 6 is: 3190/2018
Culverts replaced are irrigation: with new 15" & 18" RCPA
Mag Chloride to be used for dust control
Culverts are 50' and .2 east of WCR 15 on WCR 6
Prepared by: Lee Stephen
3/1/2021