HomeMy WebLinkAbout20211003.tiff7
BOARD OF COUNTY COMMISSIONERS
PASS -AROUND REVIEW
PASS -AROUND TITLE: BOCC Agenda Item - Approve Improvements and Road Maintenance Agreement for:
Pedro Saucedo — MUSR14-0023
DEPARTMENT: Public Works DATE: March 30, 2021
PERSON REQUESTING: Jazmyn Trujillo -Martinez
Brief description of the problemlissue:
The Department of Public Works received a request from the applicant, Pedro Saucedo, requesting that the
Board of County Commissioners consider approving the Improvements and Road Maintenance Agreement for
(MUSR14-0023). No collateral is required with this agreement.
Weld County Public Works, Planning Services and .the County Attorney's Office have reviewed the above
mentioned signed original document and observed the following:
• All Public Works related items, of the "Improvements & Road Maintenance Agreement According To
Policy Regarding Collateral For Improvements", are found to be acceptable.
• This Agreement complies with the terms of the Use by Special Review Permit Resolution, as signed
by the Board of County Commissioners.
What options exist for the Board? (include consequences, impacts, costs, etc. of options):
1. Have this BOCC Hearing item be placed on the next available agenda as part of the Consent Agenda.
2. Have this BOCC Hearing item be placed on the next available agenda as part of the Regular Agenda.
Recommendation:
Option 1. The Departments of Public Works, Planning Services and the County Attorney's Office are
recommending approval of the Improvements & Road Maintenance Agreement According To Policy Regarding
Collateral For Improvements for MUSR14-0023, and that this item be placed on the next regularly scheduled
BOCC Hearing, as part of the Consent Agenda.
Approve Schedule
Recommendation Work Session Other/Comments:
Perry L. Buck _______
Mike Freeman YhF
Scott K. James, Pro -Tern
Steve Moreno, Chair
Lori Saine
GIB, Pw(DA/sm/rL/ta) PL(KR/Ko)
2021-1003
IMPROVEMENTS & ROAD MAINTENANCE AGREEMENT ACCORDING TO
POLICY REGARDING COLLATERAL FOR IMPROVEMENTS
Pedro Saucedo — MUSRl4-0023
THIS AGREEMENT is made this b'day of i41L , 202, by and between Pedro
Saucedo, whose address is 15463 Barley Avenue, Fort Lupton, Colorado 80621, hereinafter referred to as
"Property Owner," authorized to do business in the State of Colorado, and the County of Weld, a body
corporate and politic of the State of Colorado, by and through its Board of County Commissioners, whose
address is 1150 "O" Street, Greeley, Colorado 80631 hereinafter referred to as "County."
WITNESSETH:
WHEREAS, Property Owner is the owner of the following described property in the County of
Weld, Colorado:
Lot A of Recorded Exemption RE -4224; being part of the
El/2 NW1/4 of Section 22, Township 2 North, Range 66
West of the 6th P.M., Weld County, Colorado
hereinafter referred to as "the Property," and
WHEREAS, Property Owner has received the Director of Planning Services conditional approval
of MUSRl4-0023, and
WHEREAS, Property Owner acknowledges that the final approval of MUSRl4-0023 is conditional
upon Property Owner's funding and/or construction of the off -site road maintenance and improvements
(if/when triggered) as described in this Agreement and depicted in the following incorporated exhibits:
Exhibit A — Future Off -Site Improvements Costs of Construction, to be attached pursuant to Part I, B.3.0,
below, if/when triggered
Exhibit B — Future Off -Site Improvements Construction Schedule, to be attached pursuant to Part I, B.4.0,
below, if/when triggered
Exhibit C — Construction Plans, to be attached when triggered pursuant to Part I, A., below
Exhibit D — Plat Map, and
WHEREAS, Property Owner acknowledges they may not operate as described in MUSR14-0023
until said improvements have been completed and accepted by County, and
WHEREAS, Property Owner acknowledges that pursuant to the provisions of Weld County Code
Sec. 23-2-290, the failure to commence construction of the improvements outlined herein within three (3)
years of being triggered, may result in the revocation or suspension of MUSRl4-0023, upon consideration
and order of the Board of County Commissioners, and
NOW, THEREFORE, IN CONSIDERATION OF the foregoing and of the promises and covenants
contained herein, the parties hereto promise, covenant and agree as follows:
Pedro Saucedo — MUSRl4-0023 — IA20-0010
Page 1 of 12
tea/ -/060
PART I: SITE SPECIFIC PROVISIONS
A. Off -Site Improvements (as required by the County Code): The Property Owner shall be
responsible for the construction of certain off -site safety improvements as identified in the Administrative
Approval — Staff Report, which may include, but are not limited to: construction of adequate turning radii
of sixty (60) feet at the main entrances and exits which extend into County road Rights -of -Way (ROW)
connecting to the County road system, and off -site drainage and signage installations, as indicated on the
accepted Exhibit D and future Exhibit C, as required. On -Site improvements that create more run-off than
the historical amount may require off -site drainage improvements to roads and ROW. Any approved access
point(s) improvements will include standard County approved tracking control, and may include a double
cattle guard set (one right after the other), placed back to back across the entire width of the access, to
ensure a complete revolution of the truck tires in order minimize the tracking of mud and debris onto the
adjacent County road.
B. Future Off -Site Improvements:
1.0 Traffic Triggers. When the traffic associated with the Minor Amended Use by Special Review
Permit reaches certain safety thresholds as set forth in this agreement, the Property Owner shall design and
construct required road improvements based on the amount of traffic being generated by the site. The
Property Owner's development does not currently meet the traffic safety triggers requiring the
improvements specified below; however, off -site or phased improvements may be warranted in the future.
1.1 Property Owner shall be required to design, obtain right-of-way, relocate utilities, and
construct said auxiliary lanes into their site if/when all traffic to/from the Property meets the
following traffic triggers:
• Design and construct a paved roadway along CR 20 from CR 31 to CR 37 or
participate in proportional share of county determined paving whenever traffic
exceeds gravel capacity or becomes a safety hazard to traveling public.
• Property Owner shall design and construct a left deceleration/turn lane on CR 20
whenever traffic exceeds 10 vehicles per hour (VPH) turning left into the Property
for an average daily peak hour.
• Property Owner shall design and construct a right deceleration/turn lane on CR 20
whenever traffic exceeds 25 VPH turning right into the Property for an average
daily peak hour.
• Property Owner shall design and construct a right acceleration lane on CR 20
whenever traffic exceeds 50 VPH turning right out of the Property for an average
daily peak hour.
• Property Owner shall design and construct a left acceleration lane on CR 20
whenever such a lane would be a benefit to the safety and operation of the roadway.
The County, in its sole discretion, shall determine if a left acceleration lane is
required.
2.0 Property Owner's Responsibilities regarding Future Triggers. Property Owner is solely responsible
for the cost and construction of required improvements. These responsibilities may include but are not
limited to the following, as applicable: design, surveys, utility locates, acquisition of ROW, dedication of
ROW, ROW and Access Permits and fees, coordination with oil and gas operators and facilities and affected
irrigation facilities and utilities, traffic control, and project safety during construction. Property Owner shall
Pedro Saucedo — MUSR 14-0023 - IA20-0010
Page 2 of 12
obey a.11 applicable regulations issued by OSHA, CDOT, CDPHE, and other federal, State, or County
regulatory agencies.
3.0 Cost of Construction Exhibit. When any trigger is met, the Property Owner shall submit Exhibit A
within six (6) months of being notified regarding the need for the triggered improvements, indicating the
cost of construction estimates (engineer's estimate) to detail the costs used in determining the collateral
requirement for the development. Construction costs must be obtained through a registered Colorado
Engineer. A registered Colorado Engineer must sign and stamp the construction cost exhibit for sites that
have project collateral. New or additional collateral may be required for the triggered improvements. If
required, collateral shall be submitted at the same time as Exhibit A. Exhibit A shall be attached to this
Agreement and incorporated herein once approved by the County.
4.0 Construction Schedule Exhibit. When any trigger is met, the Property Owner shall submit
Exhibit B within six (6) months of being notified regarding the need for the triggered improvements,
indicating the construction schedule, and including completion date for the improvements. Property owner
shall not commence construction of improvements prior to approval of the Construction Plans and receipt
of the appropriate Grading Permit, Access Permit, and/or ROW Permit. Property Owner shall complete all
improvements in accordance with the construction schedule exhibit. The construction of the triggered
improvements shall be completed within the specified timeframe, which may not exceed three (3) years
from the date the trigger is first met and shall be completed as follows: Year I design deadline; Year 2
ROW/Utilities; Year 3 Construction. Property Owner shall collateralize 100% of the cost of the
construction improvements, including design, right-of-way, and utility relocation cost within six months of
being notified of meeting the triggers. Exhibit B shall be attached to this Agreement and incorporated
herein once approved by the County.
5.0 Collateral. Collateral for improvements may be required by the Board of County Commissioners,
hereinafter referred to as the BOCC. Collateral is accepted and released by the BOCC pursuant to the Weld
County Code. Additional information about collateral is outlined in Part II.B of this Agreement.
6.0 As -Built Plans. "As -built" plans shall be submitted at the time the letter requesting release of
collateral is submitted or once the Property Owner has completed improvements as described in Part II.B,
Subsection 3.2.3, of this Agreement. Property Owner shall also provide an electronic copy of the as -built
drawings. The as -built drawings shall be stamped, signed, and dated by a licensed and registered
Professional Land Surveyor or Professional Engineer.
E_
o
o t
o
O
N0 RN
� f
LL 0
•a a $C
�IMlY t
dNo�
-V
N a�
ID
NmaM
C. Haul Routes: The Property Owner shall be financially responsible for its proportional share of the
associated costs for maintaining and/or improving designated haul/travel routes.
1.0 Haul/Travel Routes. The following roads are designated as haul/travel routes for the Property:
1) East and West on CR 20
2.0 Haul Trucks/Traffic shall enter and exit the site at the approved access(es) on CR 20 and travel
east -west to the nearest paved road for further dispersal. Any County roads used by MUSR14-0023 traffic
may become part of the established haul/travel routes.
3.0 Weight Limits. No travel vehicles may exceed CDOT required specifications for pounds -per -axle
and axle configurations, unless overweight permits have been applied for and granted.
4.0 Temporary Deviations. In unusual or rare occasions, if projects mandate deviation from the above -
mentioned haul/travel route for a limited period (six months or less), the Weld County Department of Public
Pedro Saucedo — MUSR14-0023 — IA20-0010
Page 3 of 12
Works may authorize, in writing, the deviation. In that circumstance, haul/travel vehicles will utilize paved
County roads whenever possible. A deviation from the established haul/travel route lasting more than six
(6) months, or requests for one (1) or more deviations within a twelve (12) -month period shall authorize
the County to change the haul/travel routes designated herein, and provide notice to the Property Owner.
5.0 Haul Route Signage. Property Owner shall install travel route signs, if applicable, as per Manual
of Uniform Traffic Control Devices standards, at all exit points of the Property which can be clearly seen
by drivers leaving the facility and which clearly depict County approved travel routes.
6.0 No Deviation from Permitted Haul Routes. Except as authorized by the BOCC pursuant to this
Agreement, no use of any roads other than those specifically authorized for use in this Agreement is
permitted without the prior written amendment of this Agreement.
D. Maintenance Requirements:
1.0 Off -site recurring maintenance, if applicable, as required:
2.0 Dust Control. Property Owner shall be financially responsible for its proportional share of dust
control on unpaved designated haul/travel routes after commencement of operation. The amount and extent
of dust control will be determined by site -specific conditions at the time, as determined exclusively by
County personnel. Dust abatement along the relevant haul/travel routes is expected to occur approximately
two to five times per year. Dust abatement is required for roads with more than 200 vehicles per day, per
section 8-6-100 of the Weld County Code.
3.0 Repair. Property Owner shall be financially responsible for its proportional share of excavation,
patching, and pavement repair on designated haul/travel routes. The amount and extent of repair and paving
measures will be determined by site -specific conditions at the time, as determined exclusively by County
personnel.
4.0 Need for Immediate Repairs: In the event of damage to a designated haul/travel route by project
traffic that causes an immediate threat to public health and safety or renders the road impassible
("Significant Damage"), County shall, after inspection, notify Property Owner of such Significant Damage.
Property Owner shall identify the repair required and shall consult with County on the extent, type, timing,
materials and quality of repair (i.e. temporary versus permanent) within twenty-four (24) hours after receipt
of such notice and shall commence such repair within forty-eight (48) hours after receipt of such notice. If
• Property Owner identifies Significant Damage prior to receiving notice thereof from County, Property
Owner may commence repair of such Significant Damage and shall concurrently notify County of the
o=
extent, type, timing, materials and quality of repair (i.e. temporary versus permanent).
U
5.0 Repair of Road: On or before December 31, of the calendar year in which County staff has
determined through site analysis and/or pavement testing that a particular haul/travel route road portion will
89 require paving measures in order to protect the public health, safety, and welfare, and the County has
mom budgeted sufficient funds for the following calendar year to pay its share of the Off -Site
�3 Improvement/Repair Costs, County shall notify Property Owner in writing that the Off -Site
= Improvements/Repairs shall be undertaken. Within ninety (90) days of its receipt of County's notice of the
need to undertake the road maintenance repairs and/or improvements, Property Owner shall submit Off -Site
Construction Plans and Cost Estimates to County for review. Property Owner shall have sole responsibility
as p� for the completion of the repairs and/or improvements on or before December 15, of the year following
dN a County's notice of the need for repairs.
ma Y ZE Pedro Saucedo — MUSR 14-0023 — IA20-0010
ermaj& Page 4 of 12
5.1 In County's sole discretion, County may undertake the repairs and/or improvements.
Property Owner's payment for its Proportionate Share of the road repairs/improvements will be
calculated as determined in this Agreement. Property Owner will be invoiced accordingly for those
proportional share costs.
6.0 Calculation of Property Owner's Proportional Share of Costs. The County shall notify Property
Owner of County's preliminary determination and assessment of Property Owner's proportional share of
costs of maintenance, repair, or improvements to Property Owner's designated haul/travel routes. Prior to
County's final determination and assessment, County shall provide Property Owner with a reasonable
opportunity to review, comment upon and supplement County's data, collection methodology, and
determinations. The County shall review and consider Property Owner's input prior to making a final
determination and assessment. The County shall have sole responsibility for determination of Property
Owner's proportional share of costs. Property Owner agrees to pay such proportional share of costs within
thirty (30) days of receiving an invoice from County.
7.0 Road Inspection. County may conduct a road inspection annually, or as needed, with the
cooperation of Property Owner and all other Property Owners and/or Lessees who are required by County
to participate in road improvement/maintenance agreements for the haul routes designated in this
Agreement. As a result of the inspection, County, in its sole discretion, shall determine actual conditions
and shall further determine what road repair/improvement/maintenance work is to be performed during that
construction season. Notification to the Property Owner of the required roadway repairs will be given as
soon as the data becomes available.
8.0 Notification. The County shall notify Property Owner of County's preliminary determination and
assessment of Property Owner's proportionate share of costs of maintenance, repair, or improvements to
Property Owner's designated haul/travel routes. Prior to County's final determination and assessment,
County shall provide Property Owner with a reasonable opportunity to review, comment upon and
supplement County's data, collection methodology, and determinations. The County shall review and
consider Property Owner's input prior to making a final determination and assessment.
PART II: GENERAL PROVISIONS
A. Engineering and Construction Requirements:
1.0 Engineering Services. Property Owner shall furnish to County, at its own expense, all engineering
services in connection with the design and construction of the off -site improvements and all on -site
drainage -related structures if required by any Municipal Separate Storm Sewer System (MS4) permit, as
identified on the accepted Construction Plans and according to the construction schedule set forth in the
construction schedule exhibits. The required engineering services shall be performed by a Professional
Engineer and Land Surveyor registered in the State of Colorado, and shall conform to the standards and
criteria established by the County for public improvements. The required engineering services shall consist
of, but not be limited to: surveys, designs, plans and profiles, estimates, construction supervision, and the
o2 submission of necessary documents to the County.
r1�3�2.0 Rights -of -Way and Easements. Before commencing the construction of any off -site improvements
herein agreed upon for public ROW or easements, Property Owner shall acquire, at its sole expense, good
and sufficient ROW and easements made necessary for the improvements. The County will not exercise
eminent domain on behalf of Property Owner. All such ROW and easements for the construction of roads
max m to be accepted by the County shall be conveyed to the County on County -approved forms and the documents
°!'— of conveyance shall be furnished to the County for acceptance with express written authority of the BOCC
and recording.
N Q
in o — Pedro Saucedo — MUSR14-0023 - IA20-0010
Nma Page 5 of 12
3.0 Construction. Property Owner shall furnish and install, at its own expense, the improvements (and
any drainage -related structures including those required by any MS4 permit) identified on the accepted
Exhibits and shall be solely responsible for the costs listed on the cost of construction exhibits, with the
improvements being completed also in accordance with the schedule set forth in the construction schedule
exhibits. The BOCC, at its option, may grant an extension of the time of completion set forth in construction
schedule exhibits stated herein upon application by the Property Owner. Said construction shall be in strict
conformance to the plans and drawings accepted by the County and the specifications adopted by the
County.
4.0 Testing. Property Owner shall employ, at its own expense, a qualified testing company previously
approved by the County to perform all testing of materials or construction; and shall furnish copies of test
results to the County. if County discovers inconsistencies in the testing results, Property Owner shall
employ at its expense a third party qualified testing company approved by County. Such third party shall
furnish the certified results of all such testing to the County. At all times during said construction, the
County shall have the right to test and inspect material and work, or to require testing and inspection of
material and work at Property Owner's expense. Any material or work not conforming to the approved
plans and specifications, including but not limited to damages to property adjacent to the construction plan
area shall be repaired, removed or replaced to the satisfaction of the County at the expense of Property
Owner.
5.0 Construction Standards. Design and construction of all off -site improvements shall conform to the
current version of CDOT's "Standard Specifications for Road and Bridge Construction" and the Weld
County Engineering and Construction Guidelines.
6.0 Traffic Control. Prior to any construction in County and/or State ROW, and as a condition of
issuance of any ROW or Access Permit, the Property Owner shall submit a traffic control plan for County
review. During construction, appropriate safety signage shall be posted in accordance with the then -current
version of the Manual of Uniform Traffic Control Devices.
B. Collateral:
1.0 General Requirements for Collateral. Property Owner shall provide to County the necessary
collateral to guarantee all of Property Owner's obligations under this Agreement: (1) Project Collateral is
required for completion of off -site improvements, as described in this Agreement; (2) Warranty Collateral
is required for all off -site improvements during the two-year warranty period. Collateral acceptance and
• release is governed by the Weld County Code.
0�7
1.1 Project Collateral shall be submitted to guarantee completion of off -site improvements
identified in the Exhibits. Project Collateral must be submitted in an amount equal to 100% of the
value of the improvements, as calculated in the cost of construction exhibits. Project Collateral
omust be submitted at the time of execution of the Agreement, unless otherwise directed by the
Board of County Commissioners. In the event that Property Owner fails to adequately complete
NO3s the required improvements, County may, in its sole discretion, access Project Collateral for the
.�� purpose of completing such improvements. It may be necessary to provide additional collateral in
.� •a the event the cost estimate is older than three (3) years. No work shall commence until project
o•L�
mLL a collateral has been submitted and accepted by County.
° 1.2 Warranty Collateral shall be submitted and held by the County until release after the two-
year warranty period following the County's initial approval of the improvements. Warranty
0-N Collateral shall be in an amount equal to 15% of Project Collateral. In the event that Property Owner
a �
a
mN$ Pedro Saucedo — MUSR14-0023 - IA20-0010
Nm a Page 6 of 12
��L
fails to adequately complete or repair improvements during the warranty period, County may, in
its sole discretion, access Warranty Collateral for the purpose of completing such improvements.
2.0 Form of Collateral. Collateral may be in the form of a letter of credit, a surety bond, or a cash
deposit, subject to the requirements and restrictions of Section 2-3-30 of the Weld County Code, as that
section may be amended from time to time.
3.0 Release of Collateral. Collateral shall be released in accordance with Section 2-3-30 of the Weld
County Code. For collateral release, the Planning Department conducts inspections for on -site
improvements, and the Department of Public Works conducts inspections for off -site improvements.
3.1 Timing of Release. Project Collateral may be released upon completion of all
improvements required by the Exhibits after initial approval by the County. Warranty Collateral
shall be withheld by County at the time of release of Project Collateral, or may be submitted
separately by Property Owner. Warranty Collateral may be released upon the approval of the
County at the end of the two-year warranty period.
3.2 Request for Release of Collateral. Prior to release of collateral by Weld County for the
entire project or for a portion of the project, the Property Owner must present a Statement of
Substantial Compliance from an Engineer registered in the State of Colorado. The Statement of
Substantial Compliance shall state that the project or a portion of the project has been completed
in substantial compliance with accepted plans and specifications documenting the following:
3.2.1 The Property Owner's Engineer or his representative has made regular on -site
inspections during the course of construction and the construction plans utilized
are the same as those accepted by Weld County.
3.2.2 For the improvements to public rights -of -way or easements, test results must be
submitted for all phases of this project as per Colorado Department of
Transportation (CDOT) Schedule for minimum materials sampling, testing and
inspections found in CDOT Materials Manual.
3.2.3 "As -built" plans shall be submitted at the time the letter requesting release of
collateral is submitted or at such time as the Property Owner has completed
improvements as shown on the Exhibit C and/or Exhibit D, and shall be stamped
• and approved by an Engineer registered in the State of Colorado, if an Engineer
was initially required for the project. The Property Owner's Engineer shall certify
that the project "as -built" is in substantial compliance with the plans and
specifications as approved, or that any material deviations have received prior
written acceptance from the County Engineer.
3.3 County's Response to Request for Release of Collateral. Following a written request for
release of collateral, County personnel will inspect the improvements as provided in this
�m3 Agreement. Upon approval, the Board of County Commissioners may release said collateral.
C. Acceptance of Improvements:
O
�3
as "� 1.0 Acceptance of Off -Site Improvements: Upon completion of the off -site improvements, Property
dN Owner shall contact the Weld County Department of Public Works and request an inspection of such
In improvements. Upon request, County personnel will initiate the inspection, approval, and acceptance
m� t process.
N a
mNx ~ Pedro Saucedo — MUSR14-0023 — IA20-0010
A Page 7 of 12
L-
2.0 Inspection, Approval, and Acceptance Process:
2.1 Upon completion of construction of all off -site improvements as described in the
Construction Plans, Property Owner shall submit to the Weld County Department of Public Works
a Statement of Substantial Compliance by Property Owner's Engineer along with "as -built"
drawings as required in subsection B.3.2.3, above, and shall request County inspection of the
Off -Site Improvements. County personnel shall then inspect the improvements. If the County
determines the improvements were not constructed in accordance with the Construction Plans, the
County shall direct the Property Owner to correct the deficiencies. If the County determines the
improvements were constructed in accordance with the Construction Plans, the County shall
initially approve the Off -Site Improvements.
2.2 Two -Year Warranty Period. Such initial approval begins the two-year warranty period.
Upon completion of the two-year warranty period, County Public Works personnel shall, upon
request by the Property Owner, inspect the subject improvements, and notify the Property Owner
of any deficiencies. If any deficiencies are discovered, the Property Owner shall correct the
deficiencies. County personnel shall re -inspect the improvements after notification from the
Property Owner that said deficiencies have been corrected. If the County personnel finds that the
improvements are constructed according to County standards, he or she shall approve the
improvements. Such final approval shall authorize the Property Owner to request the Board of
County Commissioners to release the Warranty Collateral.
2.3 Placement of Improvements into Service Prior to County Approval. If requested by the
Property Owner and agreed by the County, portions of the improvements may be placed in service
when completed according to the schedule shown on the construction schedule exhibit, but such
use and operation shall not alone constitute an approval or acceptance of said portions of the
improvements. County may, at its option, issue building permits for construction for which the
improvements detailed herein have been started but not completed according to the schedule shown
on the construction schedule exhibit, and may continue to issue building permits so long as the
progress of work on the improvements is satisfactory to the County, and all terms of this Agreement
have been faithfully kept by Property Owner.
D. Permits: The Operator is required to apply for and receive all permits required by the County or
any other applicable local, State, or federal permit, including but not limited to:
1.0 Access Permits. Operator shall not use any access onto any County road unless and until an access
permit has been issued by the Department of Public Works. Public Works may condition the issuance of an
updated access permit on the amendment of this Agreement if the updated access permit authorizes the use
x of an additional access point, or if there is a change in use of the current access point, as permitted by Article
XIV of Chapter 8 of the Weld County Code.
3
2.0 Right -of -Way (ROW) Permits. Per Article XII of Chapter 8 of the Weld County Code, any work
occurring within County ROW requires a ROW permit issued by the Department of Public Works. No work
shall occur without said ROW permit.
L _
ooL� 3.0 Transport Permits. Per Article XV of Chapter 8 of the Weld County Code, a Weld County
LLV�
Transport Permit is required for Extra -legal vehicles using Weld County roadways to ensure the operation
•a and movement of Extra -legal Vehicles and Loads occurs in a safe and efficient manner.
�C1. E. Enforcement and Remedies:
NU
O �y
"a p�
N a!
mN o �ti Pedro Saucedo — MUSR14-0023 — IA20-0010
Naafi Page 8 of 12
�mc�i�
1.0 Violation of Terms of Agreement. If in County's opinion, Property Owner has violated any of the
terms of this Agreement, County shall notify Property Owner of its belief that the Agreement has been
violated and shall state with specificity the facts and circumstances which County believes constitute the
violation. Property Owner shall have fifteen (15) days within which to either cure the violation or
demonstrate compliance. If, after fifteen (15) days have elapsed, County believes in good faith that the
violation is continuing, County may consider Property Owner to be in breach of this Agreement.
2.0 Remedies for Breach by Property Owner. In the event that County determines that Property Owner
has violated the terms of this Agreement, and has failed to correct said violation, County may exercise any
or all of the following remedies, or any other remedy available in law or equity.
2.1 Access and Use of Collateral. County may access and use collateral to address the issues
specific to the violation. For example, the County may access and use Project Collateral in order to
complete improvements as required by the Construction Plans, when such improvements have not
been completed in accordance with the Construction Schedule.
2.2. Withholding Permits. County may "lock" any or all lots within the Property, which
precludes the continued issuance of building permits, zoning permits, septic permits, or any other
permit issued by any department of the County.
2.3 Court Action. County may seek relief in law or equity by filing an action in the Weld
District Court or Federal District Court for the District of Colorado, except that no such civil action
or order shall be necessary to access collateral for the purpose of completing improvements as
described above.
2.4 Revocation of USR Permit. Property Owner acknowledges that failure to comply with the
terms of this Agreement constitutes cause to revoke MUSR14-0023, and County may exercise this
option in its sole discretion by proceeding with revocation under the then current provisions of the
Weld County Code.
3.0 Termination of Agreement. This Agreement shall terminate upon the earliest of the following
events:
3.1 Failure to Commence. County may terminate this Agreement upon or after revocation of
the underlying land use approval under Weld County Code Section 23-2-290. However, County
may still exercise all necessary activities under this Agreement that the County determines
necessary' to protect the health, safety, and welfare of the residents of Weld County.
3.2 Cessation of all Permit Related Activities. Termination of this Agreement shall occur upon
Property Owner's complete cessation of all activities permitted by the USR and Minor Amended
USR including any clean up or restoration required. A partial cessation of activities shall not
0
constitute a Termination of this Agreement, nor shall County's issuance of a partial release/vacation
constitute a Termination. Unless informed in writing by the Property Owner of cessation of
Cm3
activities, and verified by the County, cessation shall only be presumed if the County determines
that MUSR14-0023 has been inactive for three (3) years. Property Owner shall not be entitled to a
LL
release of Project or Warranty Collateral unless and until the improvements required by this
Agreement are completed.
aML
3.3 Execution of Replacement Agreement. This Agreement shall terminate following County's
dN �—
execution of a new Improvements Agreement with a new property owner or operator who has
CONY 1
Pedro Saucedo — MUSR 14-0023 - IA20-0010
NCO ?
Page 9 of 12
�B =
�BV-
purchased the Property or has assumed the operation of the business permitted by the USR, and
intends to make use of the rights and privileges available to it through the then existing USR.
3.4 Revocation of USR. This Agreement shall terminate following County's revocation of
Property Owner's USR, except that the Property Owner shall only be released from this Agreement
after the successful completion of all improvements required under this Agreement, which may be
completed by County after accessing Property Owner's collateral if Property Owner fails to
complete such improvements.
F. General Provisions:
1.0 Successors and Assigns.
1.1 Property Owner may not delegate, transfer, or assign this Agreement in whole or in part,
without the prior express written consent of County and the written agreement of the party to whom
the obligations under this Agreement are assigned. Consent to a delegation or an assignment will
not be unreasonably withheld by County. In such case, Property Owner's release of its obligations
shall be accomplished by County's execution of a new Improvements Agreement with the
successor owner of the property.
1.2 County's rights and obligations under this Agreement shall automatically be delegated,
transferred, or assigned to any municipality which, by and through annexation proceedings, has
assumed jurisdiction and maintenance responsibility over all roads affected by this Agreement.
2.0 Severability. If any term or condition of this Agreement shall be held to be invalid, illegal, or
unenforceable by a court of competent jurisdiction, this Agreement shall be construed and enforced without
such provision, to the extent that this Agreement is then capable of execution within the original intent of
the parties.
3.0 Governmental Immunity. No term or condition of this contract shall be construed or interpreted as
a waiver, express or implied, of any of the immunities, rights, benefits, protections or other provisions, of
the Colorado Governmental Immunity Act §§24-10-101 et seq., as applicable now or hereafter amended.
4.0 Amendment or Modification. Any amendments or modifications to this agreement shall be in
writing and signed by both parties.
5.0 No Third -Party Beneficiary_ It is expressly understood and agreed that the enforcement of the terms
and conditions of this Agreement, and all rights of action relating to such enforcement, shall be strictly
reserved to the undersigned parties and nothing in this Agreement shall give or allow any claim or right of
action whatsoever by any other person not included in this Agreement. It is the express intention of the
undersigned parties that any entity other than the undersigned parties receiving services or benefits under
this Agreement shall be an incidental beneficiary only.
6.0 Board of County Commissioners of Weld CountyApproval. This Agreement shall not be valid
4. until it has been approved by the Board of County Commissioners of Weld County, Colorado or its
mLL O designee.
O
b� 7.0 Choice of Law/Jurisdiction. Colorado law, and rules and regulations established pursuant thereto,
•0.0
shall be applied in the interpretation, execution, and enforcement of this Agreement. Any provision included
d U� or incorporated herein by reference which conflicts with said laws, rules and/or regulations shall be null
a and void. In the event of a legal dispute between the parties, the parties agree that the Weld County District
—w
a.
N a
mNY Pedro Saucedo — MUSR14-0023 — IA20-0010
Nar Page 10 of 12
Court or Federal District Court for the District of Colorado shall have exclusive jurisdiction to resolve said
dispute.
8.0 Attorneys' Fees/Legal Costs. In the event of a dispute between County and Property Owner,
concerning this Agreement, the parties agree that each party shall be responsible for the payment of attorney
fees and/or legal costs incurred by or on its own behalf.
9.0 Release of Liability. Property Owner shall indemnify and hold harmless the County from any and
all liability loss and damage County may suffer as a result of all suits, actions, or claims of every nature
and description caused by, arising from, or on account of the design and construction of improvements, and
pay any and all judgments rendered against the County on account of any such suit, action or claim, and
notwithstanding section 8.0 above, together with all reasonable expenses and attorney fees incurred by
County in defending such suit, action or claim whether the liability, loss or damage is caused by, or arises
out of the negligence of the County or its officers, agents, employees, or otherwise except for the liability,
loss, or damage arising from the intentional torts or the gross negligence of the County or its employees
while acting within the scope of their employment. All contractors and other employees engaged in
construction of the improvements shall maintain adequate worker's compensation insurance and public
liability insurance coverage, and shall operate in strict accordance with the laws and regulations of the State
of Colorado governing occupational safety and health.
10.0 Binding Arbitration Prohibited. Weld County does not agree to binding arbitration by any extra-
judicial body or person. Any provision to the contrary in this Agreement or incorporated herein by reference
shall be null and void.
11.0 Authority to Sign. Each person signing this Agreement represents and warrants that he or she is
duly authorized and has legal capacity to execute and deliver this Agreement. Each party represents and
warrants to the other that the execution and delivery of the Agreement and the performance of such party's
obligations hereunder have been duly authorized and that the Agreement is a valid and legal agreement
binding on such party and enforceable in accordance with its terms. If requested by the County, Property
Owner shall provide the County with proof of Property Owner's authority to enter into this Agreement
within five (5) days of receiving such request.
12.0 Acknowledgment. County and Property Owner acknowledge that each has read this Agreement,
_ understands it and agrees to be bound by its terms. Both parties further agree that this Agreement, with the
attached or incorporated Exhibits, is the complete and exclusive statement of agreement between the parties
and supersedes all proposals or prior agreements, oral or written, and any other communications between
the parties relating to the subject matter of this Agreement.
O
13.0 Notwithstanding any other provision contained in this Agreement, for any conflict or potential
conflict between any term in this Agreement and the Resolution of the Board of County Commissioners
approving the underlying land use permit, the provisions of the Board's Resolution shall control. In the
m� event of a discrepancy between this agreement and the Weld County Code in effect at the time of the
agreement, the terms of the Weld County Code shall control.
0
ovo_I:
r1LLO
Y
.+vy
N ar
N0 Pedro Saucedo — MUSR14-0023 - IA20-0010
���— Page 11of12
�Bo�
PROPERTY OWNER: Pedro Saucedo
By: /c4c .� i-/6 i
Name:
Title:
STATE OF COLORADO
County of Weld
Date
ss.
The foregoing instrument was acknowledged before me this day of___________
202(,by PedVp.SCEuC O
WITNESS my hand and official seal.
=VALVERDE
N tar Public
0
N69
LAV
WELD COUNTY:
AT'
We
)ARD OF COUNTY COMMISSIONERS
ELD COUNTY, COLORADO
eve Moreno, Chair
APR 0 7 2021
Pedro Saucedo — MUSR 14-0023 - IA20-0010
Page 12 of 12
o2ocf_1063
Entity Information
Entity Narne * Entity ID * ❑ New Entity?
SAUCEDO, PEDRO X00028474
Contract Name *
IMPROVEMENTS AND ROAD MAINTENANCE AGREEMENT
MUSR14-0023 PEDRO SAUCEDO
Contract Status
CT6 REVIEW
Contract ID
4617
Contract Eead
JTRUJILLOMARTINEZ
Contract Lead Email
jtru j i ll om arti n e z@weidgov. c
om
Parent Contract ID
Requires Board Approval
YES
Department Project #
Contract Desorption *
IMPROVEMENTS AND ROAD MAINTENANCE AGREEMENT MUSR14-0023 PEDRO SAUCEDO NO COLLATERAL REQUIRED
Contract Description 2
Contract Type *
Department
Requested BOCC Agenda Due Date
AGREEMENT
PUBLIC WORKS
Date* 04 03 ;2021
04/072021
Amount*
Department Email
$0.00
CM-
Will a work session with BOCC be required?*
PublicWorks cweldgov.corn
NO
Renewable
NO
Department Head Email
Does Contract require Purchasing Dept. to be included?
CM-PublicWorks-
NO
Automatic Renewal
DeptHeadgweldgov.com
Grant
County Attorney
BOB CHOATE
IGA
County Attorney Email
BCHOATE &CO. WELD.CO. U S
if this is a renewal enter previous Contract ID
If this is part of a MSA enter MSA Contract ID
Note- the Previous Contract Number and Master Services Agreement Number should be left blank if those contracts are not in
OnRase
Contract Dates
Effective Date
Termination Notice Period
Contact Information
Review Date * Renewal Date
0407!2022
Committed Delivery Date Expiration Date*
04:07/2023
Contact Info
Purchasing
Purchasing Approver
CONSENT
Approval Process
Department Head
JAY MCDONALD
DH Approved Date
04/01,/2021
Final Approval
BOCC Approved
BOCC Signed Date
BOCC Agenda Date
04,/07'2021
Originator
JTRUJ LLOMARTINEZ
Purchasing Approved Date
04/01 x`2021
Finance Approver
CONSENT
Finance Approved Date
04/01/2021
Tyler Ref
AG 040721
Legal Counsel
CONSENT
Legal Counsel Approved Date
04/01/2021
Hello