HomeMy WebLinkAbout730911 1ANGE ORDER N0. v 6
DATE September 19, 1973
PROJECT MASTERS-HARDIN AREA PROJECT NO. 73-1-CCA-0228
OWNER WELD COUNTY, COLORADO CONTRACTOR Loveland Excavation
DESCRIPTION OF CHANGE - That said Contract shall be changed in the following particulars:
That a cattleguard that was at the intersection of County Road No. 87 and the K-4 Ranch
Road (Item 5-21A) shall be relayed.
and that after the said changes shall have been made with additions and/or deletions are
hereby directed to be a part of the original Contract, the agreement as shown by the
original Contract together with the above-named additions and/or deletions shall . consti-
tute the agreement and Contract of the parties hereto.
JUSTIFICATION
This damage was overlooked during the original O.E.P. Survey and repairs were okayed by
the O.E.P. on their second survey of the area.
•
CHANGE IN CONTRACT COST
Item Description Quantity Unit Unit Cost Total Cost
12 Cattleguard, Relay 1 L.S.. $ 600.00 $ 600.00
-- $ $
Total Amount This Change Order $ 600.00
Net of Previous Change Orders (+) (-) $ 22,274.40
Original Contract Amount $ 55.062.50
Revised Total Contract Amount $ 77,936. 90
CON RACT TIME
Original Completion Date 9/10/73 Previous Days Allowed 78
Days Allowed This Change Order 0 Revised Comple�t�ion Date 9/10/73
Recommended: Approve 7 � a/ azd
NELSON, HALEY, PATTERSON and QUIRK, INC.
8y: (Owner)
Field Representative By:
Date:
,� (Co actor)
Approved:. fl-z-7-274,--5.--E—"Z /�
rojec "—Manager By:
� '
Date: 2c)7 Date: