HomeMy WebLinkAbout730920.tiff Chang�rder No. 6
Date September 5, 1973
•
PROJECT Prospect Valley-Kiowa Creek AreaPROJECT N0. 73-1-CCA-0232
OWNER Weld County, Colorado CONTRACTOR ' Goodell Bros.
DESCRIPTION OF CHANGE - That said Contract shall be changed in the following particulars :
Quantities enumerated below are to be added because of errors in estimates and
the change from glow-flow" crossjngs to 72" CL( .P. culverts. quantities per O.E. P.
item, 5-31 , 9 tbns; 5-47, 300 ons; 5-48, 366 tons; 5-49, 175 tons.
and that after the said changes shall have been made with additions and/or deletions are
hereby directed to be a part of the original Contract, the agreement as shown by the
original Contract together with the above-named additions and/or deletions shall constitute
the agreement and Contract of the parties hereto
JUSTIFICATION:
These extra quantities are needed to provide a neat, matching repair with existing
sections. Field Order No. 1 , L.E. Martin, Inspector.
CHANGE IN CONTRACT COST:
Item Description Quantity Unit Unit Cost Total Cost
2 Gravel Surfacing 85_0_ Tons 5.00 4250.00
Total Amount this change order $ 4,250.00
Net of Previous Change Orders (+) (-) $ 50,500.00
Original Contract Amount $ 115,700.00 _
Revised Total Contract Amount $ 170,450.00
CONTRACT TIME:
Completion Date October 31 , 1973
Previous Days Allowed 90
Days Allowed This Change Order 0
Revised Completion Date October 31 , 1973
Recommended: Approve f t��t ed , r1�
NELSON, HALEY, PATTERSON and QUIRK, INC.
(Owner)
By: o
Field-Representative By:
C(p/n_.vtractor)
Date: 1 73By: NI
e
Approved: trazzecm,
�i��
Project M nager Date:
Date: Vie 7�
730920