HomeMy WebLinkAbout20222935.tiffUSE BY SPECIAL REVIEW PERMIT STAFF COMMENTS Planner: Diana Aungst Case Number: USR22-0022 Owner: Arthur Griffiths 9216 County Road 48.5, Johnstown, CO 80534 Agent: CBEP Solar 5, LLC c/o Zach Brammer PO Box 1225, Sterling, CO 80751 Hearing Date: October 4, 2022 Request: A Site Specific Development Plan and Use by Special Review Permit for a Solar Energy Facility (SEF) outside of subdivisions and historic townsites in the A (Agricultural) Zone District. Legal Being part of the N2S2 and SW4SW4 of Section 3, T4N, R67W, of the 6th P.M., Weld County, Description: Colorado Location: North of and adjacent to State Highway 60 and approximately 0.75 miles west of State Highway 257 Acreage: Parcel boundary: +/- 37.46 acres Parcel No. 1059-03-3-00-001 Solar array: +/- 28.5 acres The criteria for review of this Special Review Permit are listed in Section 23-2-220 and Section 23-4-1030 of the Weld County Code. The Department of Planning Services' staff has received referral responses with comments from the following agencies: ➢ PDC Energy Inc., referral dated August 30, 2022 ➢ Colorado Parks and Wildlife, September 14, 2022 ➢ Weld County Oil and Gas Energy Department, referral dated August 8, 2022 ➢ Front Range Fire Rescue, referral dated August 13, 2022 and August 30, 2022 ➢ Weld County Office of Emergency Management, referral dated August 19, 2022 ➢ Little Thompson Water District, referral dated August 25, 2022 and August 26, 2022 ➢ Weld County Department of Public Health and Environment, referral dated August 11, 2022 ➢ Colorado Department of Transportation, referral dated August 30, 2022 and September 19, 2022 ➢ Weld County Department of Planning Services — Development Review, referral dated August 8, 2022 The Department of Planning Services' staff has received referral responses without comments from the following agencies: ➢ City of Greeley, referral dated August 3, 2022 ➢ Weld County Sheriff's Office, referral dated August 2, 2022 ➢ West Greeley Conservation District, referral dated August 8, 2022 ➢ Northern Colorado Water Conservancy, referral dated August 31, 2022 ➢ State of Colorado, Division of Water Resources, referral dated August 12, 2022 ➢ Weld County Department of Planning Services - Code Compliance, referral dated August 4, 2022 USR22-0022 — Griffiths Page 1 of 15 The Department of Planning Services' staff has not received responses from the following agencies: ➢ Town of Milliken ➢ Town of Johnstown ➢ Great Western Railway ➢ Weld County School District RE -5J ➢ Big Thompson and South Platte Ditch CASE SUMMARY: The applicant, CBEP Solar 5, LLC., is requesting a Use by Special Review Permit for a Solar Energy Facility (SEF), known as the Griffiths #1 Solar Project. The SEF will be a five (5) -megawatt (5 MW AC) facility that will encompass about 28.5 acres and will consist of 14,500 solar modules mounted about five (5) feet above the existing grade on single -axis trackers. The subject property is 37.46 acres of land that is privately owned by Mr. Arthur Griffiths. The single -axis trackers allow the panels to track the sun from east to west over the course of the day. The Solar Energy Facility will also include forty (40) inverters mounted on steel posts or beams, two (2) concrete -pad mounted transformers, other ancillary equipment, an access road, and a perimeter game fence with gates. About five (5) utility poles will be installed that will connect the Solar Energy Facility to the existing Xcel Energy distribution line on the south side of the property. The maximum height of the solar panels is twenty-five (25) feet as measured from the highest grade below each solar panel to the highest extent of the solar panel rotation. Construction activities will take place Monday through Saturday from 7:00 a.m. to 6:00 p.m. Once the construction phase is completed the site will be visited 1-2 times per year between 7:00 a.m. and 7:00 p.m. as needed for routine maintenance and any emergency maintenance. There will also be a team of shepherds that will visit the property on a daily basis in the Spring, Summer, and Fall during daylight hours. There will be a maximum of 500 sheep on the site at any one time for vegetation management. Disturbed areas not covered with gravel as part of the Solar Energy Facility design will be reseeded with native seed to revegetate disturbed areas and hold soil in place, minimizing fugitive dust impacts during operations. All electrical cables on the improved area shall be buried, except for direct current string wires that connect between solar collectors, direct current collection circuits between rows of solar arrays that are no more than four (4) feet above grade crossings, substations, switchyards, and circuit voltages greater than 34.5 kilovolts. A supervisory control and data acquisition (SCADA) system will remotely monitor and control the Solar Energy Facility 24 hours per day. The SCADA system will transmit Solar Energy Facility data and control signals over the internet. A temporary laydown area will be located on the north side of the proposed solar array. One (1) temporary construction trailer will be located on -site during construction as well as two (2) storage containers to store parts, tools, and equipment. Once in operation, there will be no outdoor stockpiling, uncovered storage, or waste areas. There applicant has proposed two access points onto the site. A northern one from County Road 48.5 and a southern one from State Highway 60. There will be a seven (7) -foot tall game fence around the Solar Energy Facility. The applicant is proposing woven mesh fabric or similar screening on the along the southern and eastern boundaries of the to provide additional screening of the site and to mitigate potential glare. Staff is recommending that the fence either be wood, metal, or vinyl and not include mesh fabric. The eastern, southern, and western boundaries of the Solar Energy Facility will include pollinator habitats that will provide additional screening. This pollinator habitat will be irrigated by a drip irrigation system that the landowner is installing on the property for the irrigation of sheep forage and consists of native plants that will require very little maintenance. There will be no lighting on the Solar Energy Facility after construction is completed. The need for lighting during construction is expected to be limited because the majority of construction activities will occur during USR22-0022 — Griffiths Page 2 of 15 daylight hours. If lighting is needed during construction, lights will be positioned and/or shielded from oncoming traffic and residences in the vicinity of the Solar Energy Facility site. Cutoff -type luminaires would be used where practicable. According to the email received on September 15, 2022, the cutoff -type luminaries will be powered by a Honda EU2200 generator or equivalent. The Honda EU2200 generator produces a maximum of 57 dB per the Honda website. According to the applicant the decibels would decrease to 50 dB from just 2.5 feet away. Section 14-9-40 of the Weld County Code states that the residential noise levels from 9:00 p.m. to 7:00 a.m. are limited to 50 dB. Since the residences in the area are greater than 2.5 feet from the generator no noise mitigation is proposed. Decommissioning/reclamation will commence within twelve (12) months after power production has permanently ceased and will be completed within twelve (12) months. Decommissioning of the Solar Energy Facility will include removal of all above and below -ground infrastructure, including the arrays, inverter structures, concrete foundations and pads, and electrical infrastructure. All fences, graveled areas and access roads shall be removed unless landowner agreement to retain is presented, in writing, in which the property owner agrees for this to remain. The property shall be restored to a condition reasonably similar to its condition prior to development of the 5 MW AC SEF. Grading and re -vegetation will comply with all applicable rules and regulations. Exclusions from the Decommissioning Plan include planting trees, removing internal site roads, and re -grading to previous conditions. All non -utility owned equipment, conduits, structures, fencing, and foundations to a depth of at least three (3) feet below grade shall be removed. Decommissioning activities will follow the Colorado Department of Transportation best management practices (BMPs) for erosion and sediment control and stormwater management that are applied during Solar Energy Facility construction, or any new BMPs relevant at the time. The land was irrigated and used for crops until 2022. In 2022, the landowner leased their water to a neighbor and planted a sheep -friendly seed mix in order to establish the pasture ahead of the sheep grazing that is set to begin next year. The landowner is designing and installing a new irrigation system and the irrigation of the land is expected to resume next year. There will be a maximum of 500 sheep on the site at any one time for vegetation management. CBEP Solar 5, LLC and the property owner are working together to install a drip irrigation system alongside the Solar Energy Facility so that the land can continue to be irrigated throughout the duration of the Solar Energy Facility's life. The land will retain its agricultural use through sheep grazing. Water for the sheep will be provided by the property owner's Little Thompson Water District account and will be transported from the landowner's residence on the property to the north to the Solar Energy Facility via a water trailer. The facility is unmanned and no water or sewage disposal service is proposed. Bottled water and portable toilets will be provided during construction. DEPARTMENT OF PLANNING SERVICES' STAFF RECOMMENDS THAT THIS REQUEST BE APPROVED FOR THE FOLLOWING REASONS: 1. The submitted materials are compliant with the application requirements of Section 23-2-260 of the Weld County Code. 2. It is the opinion of the Department of Planning Services' staff that the applicant has shown compliance with Section 23-2-220 of the Weld County Code as follows: A. Section 23-2-220.A.1. -- The proposed use is consistent with Chapter 22 [Weld County Comprehensive Plan] and any other applicable code provisions or ordinance in effect. Section 22-2-10.C. states: "Promoting Economic Growth and Stability. Land use policies have a significant impact economic conditions in the County and should be structured to encourage economic prosperity. To ensure the continued strength of Weld County's economy, land use processes and decisions based on this plan [Comprehensive Plan] shall be consistent and promote financially responsible growth." USR22-0022 — Griffiths Page 3 of 15 This Solar Energy Facility will provide construction jobs and energy to Weld County. These functions directly support economic prosperity. This Solar Energy Facility, being a power - generating facility, will add variety, stability and redundancy to the existing electrical grid. Traditional energy resources are tied to commodity markets and can vary in demand and output. This Solar Energy Facility can complement and support the economy during times of fluctuating oil and gas activity. 22-2-30.C. Harmonize development with surrounding land uses. The adjacent land will experience minimal nuisance from the SEF, which is an unmanned energy development facility. The residences in the area are more than five hundred (500) feet from the facility. Additionally, the applicant is proposing screening and landscaping options along State Highway 60. B. Section 23-2-220.A.2. -- The proposed use is consistent with the intent of the A (Agricultural) Zone District. Section 23-3-10. — Intent, of the Weld County Code states, "Agriculture in the County is considered a valuable resource which must be protected from adverse impacts resulting from uncontrolled and undirected business, industrial and residential land uses. The A (Agricultural) Zone District is established to maintain and promote agriculture as an essential feature of the County. The A (Agricultural) Zone District is intended to provide areas for the conduct of agricultural activities and activities related to agriculture and agricultural production, and for areas for natural resource extraction and energy development, without the interference of other, incompatible land uses." This code section supports the installation of the subject Solar Energy Facility, which is an energy development. The facility will provide power to be utilized by residences, businesses and farming operations in Weld County. Section 23-3-40.FF. — Uses by special review, of the Weld County Code includes, "Solar Energy Facilities (SEF'S), being more than five (5) acres in size but less than one -hundred sixty (160) acres in the Near/Urban Area as shown on Appendix 21-B, or being more than five (5) acres but less than three -hundred twenty (320) acres in the Ag/Rural Area as shown on Appendix 21-B." This code section allows the applicant to apply for the subject Solar Energy Facility, being located in the Near/Urban Area as shown by map in Appendix 21-B. Per Section 23-1-90 of the Weld County Code, a "Solar Energy Facility" means: "a commercial facility whose primary purpose is to supply electricity and consists of one or more solar arrays and other accessory structures, equipment, including substations, switchyards, battery storage, electrical infrastructure, generators, transmission lines, communications infrastructure, and other appurtenant structures and/or facilities." The SEF will encumber approximately twenty-eight and a -half (28.5) acres and qualifies as an SEF USR. This USR facility will also include two (2) storage containers for construction and operation usage, being Accessory Uses, permitted by Section 23-3-30.B of the Weld County Code. C. Section 23-2-220.A.3 -- The uses which will be permitted will be compatible with the existing surrounding land uses. The adjacent unincorporated lands to the north and south are zoned A (Agricultural) the lands to the west are zoned 1-3 (Heavy Industrial). Despite the zoning the surrounding uses are agricultural in nature except for the property east of and adjacent to the subject property which is the Town of Johnstown's Wastewater Treatment Plant. Colorado Sweet Gold Industrial Park with an 1-3 (Heavy Industrial) zoning is located southwest of the site. There are three (3) rural USR22-0022 — Griffiths Page 4 of 15 residences in the area with the closet one being about 1,100 feet to the north. This residence is owned by the property owner. The two (2) other residences are no closer than 1,400 feet. The Great Western Railroad is on the south boundary between the site and State Highway 60. There are no residential dwellings closer than five hundred (500) feet. There are eight (8) USRs within one (1) mile of the site. USR-823 for 230kV electric transmission lines is west of and adjacent to the site. USR-1281 for a 150 -foot -tall telecommunications tower, USR-1142 fora recreational facility, MUSR18-0003 fora substation and 115 kV antennas, and USR-222 (SUP -222) for spray ponds are located south of the site. USR-1706 for a 16 -inch natural gas pipeline, USR-52 (CUP -52) for a golf course (Mad Russian), and USR-1277 for herbal products processing are all located north of the site. The application materials state that there are two (2) options being considered for access to the site the first one is access from the southern side of the parcel from State Highway 60. This access location involves the crossing of a railroad line owned/operated by Great Western Railroad. The applicant shall contact the Railroad to determine if a crossing agreement is required. Additionally, accessing from State Highway 60 requires a Colorado Department of Transportation (CDOT) access permit. An email received from CDOT on August 30, 2022 states that this USR should not use the State Highway 60 access for their traffic and that the Access Control Plan shows this access as a field access and that is what it needs to remain - for agricultural purposes. The second access is from the northern side of the neighboring property from County Road 48.5. The proposed access from County Road 48.5 is located at an existing unpermitted access point and will involve traversing the parcel due north of the subject property that is currently under the same ownership. An easement may be required for this crossing either now or in the future if ownership changes. The applicant will be required to obtain an access permit for the access location on County Road 48.5. Weld County Department of Planning Services staff sent notice to six (6) surrounding property owners within 500 feet of the proposed USR boundary. No written correspondence or telephone calls were received. The proposed use is in an area that can support this development and the Development Standards and the Conditions of Approval will assist in mitigating the impacts of the facility on the adjacent properties and ensure compatibility with surrounding land uses and the region. D. Section 23-2-220.A.4 -- That the uses which would be permitted will be compatible with future development of the surrounding area as permitted by the existing zoning and with the future development as projected by Chapter 22 of this Code or master plans of affected municipalities. The site is located within the Coordinated Planning Agreement Area (CPA) for the Towns of Johnstown and Milliken. As part of the pre -application process the municipalities were sent a Notice of Inquiry (NOI). The Town of Johnstown submitted a Notice of Inquiry dated March 14, 2022, with a letter attached that listed four (4) Conditions of Approval including a request for dedication of right-of-way, clear identification of the thirty (30) foot sanitary sewer easement and coordinating with the Town and the Town's Utility Department if the applicant intends to utilize the access point from State Highway 60. Mr. Zach Brammer with Cloud Break Energy (the authorized agent) replied to the Town of Johnstown's request to annex with an email dated March 29, 2022. The email states, "I [Mr. Zach Brammer] had the chance to meet with the landowner, and he is potentially interested in annexing the property into Johnstown, but he needs some time to think through the decision and consider all of his options (Milliken was also interested in annexing). So the plan he and I came up with is that we are going to continue permitting the solar projects with Weld County while he and his family figure out the pros/cons of annexation (at some point, he will likely be USR22-0022 — Griffiths Page 5 of 15 reaching out to you to set up another meeting to discuss) and then make the final annexation decision after our USR process with Weld is complete." The email goes on the state. "So, for the time being, we are going to continue pursuing a USR permit from Weld. I will be sure all of the items we discussed are included in the site plans." The authorized agent also sent an email to the Town of Milliken with similar content dated March 17, 2022. Planning Staff reached out to both Milliken and Johnstown and the towns stated that they are not asking for pre -annexation agreements. The site is located within the three (3) mile referral area of the Towns of Johnstown and Milliken and the City of Greeley. The City of Greeley submitted referral agency comments dated, August 3, 2022, stating that they have no concerns and that the site is located outside of Greeley's Long Range Expected Growth Area. The Towns of Johnstown and Milliken did not submit referral agency comments. The site is located within the future land use areas for both the Town of Johnstown and the Town of Milliken. The 2021 Johnstown Area Comprehensive Plan identifies this site as Medium Intensity / Density Development (MDI) and Greenway. Johnstown's Comprehensive Plan states that the intent and desired character of the MDI will generally be characterized by a more balanced, and wider -ranging mix of land uses - incorporating walk-up apartment buildings, townhomes, small lot (3,500-5,000 SF) attached and detached single-family housing, in close proximity to neighborhood -scale shopping, personal services, restaurants, small medical facilities, and facilities such as libraries and recreational centers. MDI areas may also occur along arterials and other major corridors and may serve as the next layer away from the High Density/Intensity areas they may neighbor, as a transition to lower density neighborhoods. MDI's will offer complete neighborhoods with a diversity of shops and services, including schools and civic facilities, within walking or biking distance from residential areas; and offer good walking connections along with larger -scale multi -modal trails. Commercial uses may be developed as stand-alone sites or be grouped in small 10 to 20 -acre centers or campuses. Johnstown's Downtown would be ideal for this level of development. Reuse and redevelopment of existing structures may occur, with historic residences and structures changing to offices, boutiques, or personal services with alley -served parking. Commercial centers in an MDI will feature more walkability, perhaps offering covered arcades or awnings, pedestrian -scaled signage, shade trees and nice landscaping that helps slow traffic and break-up parking areas, and enjoyable outdoor spaces to gather. Rooftop and sidewalk patios, along with courtyard plazas offer patrons enjoyable places to meet and eat, gather and chat with friends. Residential neighborhoods will provide a range of housing options and provide street and trail connections to adjacent neighborhoods. Housing will be encouraged to provide porches that extend closer to the sidewalks, and garages that are alley -loaded or setback to offer a safer, slower, and more interesting streetscape. Future considerations may include accessory dwelling or carriage house units to increase affordability and diversity. These are great neighborhoods to encourage and accommodate a diversity of lifestyles and income ranges and allow active-agers to remain in Johnstown once larger family homes and yards may be less desirable The Greenway area is primarily intended for floodplain areas, as established by the adopted FIRM/FEMA maps and studies. These areas are natural areas for flooding - to capture and channel stormwater in large storm events, offer high habitat and ecosystem value, and should be avoided when considering areas for new development or redevelopment to protect life, property, and natural assets. These areas offer opportunities for conservation of natural areas and landscapes, as well as low impact recreational trails. Greenways may also be located adjacent to irrigation ditches, reservoirs, wetlands, and other ecologically -significant areas. USR22-0022 — Griffiths Page 6 of 15 The greenway/floodplain areas include natural open space, trails, and river access. While sections of this land use may be on private land, efforts should be made to increase and maintain public access and to enhance connections for regional recreation and wildlife movement. With a recommended use as passive recreation. According to the Framework Plan for the Town of Milliken included, in the Town's Comprehensive Plan dated February 2016, the site is designated in the Future Land Use Category of `Agriculture'. The Town of Milliken's Comprehensive Plan states that Agriculture is primarily used for farming, ranching, and other agriculturally related uses and secondarily used for low density (rural) residential. The Agriculture Land Use Category contain areas that are not anticipated to be developed within the 20 -year planning horizon, provide for the continuation of agricultural uses within the context of both market demand and the desires of individual property owners, and limits residences to those for owners/operators of the agricultural enterprise. The Colorado Department of Transportation requested an email from the applicant concerning the traffic at the intersection of CR 48.5 and HWY 257. This email has been submitted to CDOT. CDOT has stated that no access to this site should come off of State Highway 60. E. Section 23-2-220.A.5 -- That the application complies with Articles V and XI of this Chapter if the proposal is located within an overlay zoning district or a special flood hazard area identified by maps officially adopted by the county. The property is not located within any overlay district officially adopted by the County, including A -P (Airport) Overlay District, 1-25 Overlay District, Geologic Hazard Overlay District, MS4 - Municipal Separate Storm Sewer System area, Special Flood Hazard Area, Historic Townsites Overlay District, or Agricultural Heritage Overlay District. Building Permits issued on the lot will be required to adhere to the fee structure of the County - Wide Road Impact Fee Program, County Facility Fee and Drainage Impact Fee Programs. F. Section 23-2-220.A.6 -- The applicant has demonstrated a diligent effort to conserve prime agricultural land in the locational decision for the proposed use. The proposed facility is located on approximately 10 acres of soils designated as "Farmland of Statewide Importance" with low slope (1-3%) Vona sandy loam soils and on approximately 28 acres of soils designated as "Prime Farmland if Irrigated (Soils Erodibility)" with low slope (1- 3%) Olney fine sandy loam per the USDA Natural Resources Conservation Service (NRCS) Custom Soil Report prepared March 25, 2021. The proposed use of the property for an SEF will not remove topsoil from the property. After the life of the SEF the land may be returned to historic uses. The land was irrigated and used for crops until 2022. In 2022, the property owner leased their water to a neighbor and planted a sheep -friendly seed mix in order to establish the pasture ahead of the sheep grazing that is set to begin next year. The landowner is designing and installing a new irrigation system and the irrigation of the land is expected to resume next year. G. Section 23-2-220.A.7 -- There is adequate provisions for the protection of the health, safety, and welfare of the inhabitants of the neighborhood and County. The Design Standards (Section 23-2-240, Weld County Code), Operation Standards (Section 23-2-250, Weld County Code), Conditions of Approval and Development Standards can ensure that there are adequate provisions for the protection of health, safety, and welfare of the inhabitants of the neighborhood and County. USR22-0022 — Griffiths Page 7 of 15 This recommendation is based, in part, upon a review of the application materials submitted by the applicant, other relevant information regarding the request, and responses from referral entities. THE DEPARTMENT OF PLANNING SERVICES' STAFF RECOMMENDATION FOR APPROVAL IS CONDITIONAL UPON THE FOLLOWING: 1. Prior to recording the map: A. The applicant shall address the requirements of the Town of Johnstown, as stated in the Notice of Inquiry response letter date March 14, 2022. Evidence of such shall be submitted in writing to the Weld County Department of Planning Services. (Department of Planning Services) B. The applicant shall address the requirements of Front Range Fire Rescue, as stated in the referral response dated August 13, 2022 and August 30, 2022. Evidence of such shall be submitted in writing to the Weld County Department of Planning Services. (Department of Planning Services) C. The applicant shall address the requirements of the Colorado Parks and Wildlife, as stated in the referral response dated September 14, 2022. Evidence of such shall be submitted in writing to the Weld County Department of Planning Services. (Department of Planning Services) D. The applicant shall address the requirements of the Colorado Department of Transportation, as stated in the email dated September 19, 2022. Evidence of such shall be submitted in writing to the Weld County Department of Planning Services. (Department of Planning Services) E. Should the applicant pursue an access point off of State Highway 60 the applicant shall: 1) Submit an approved access permit from CDOT for the access off of State Highway 60. (Department of Planning Services) 2) Submit documentation from Great Western Railroad (GWRR) that states that GWRR has no concerns with the applicant crossing the tracks to access the subject property. (Department of Planning Services) F. The applicant shall attempt to address the concerns of PDC Energy Inc., as stated in the referral response dated August 30, 2022. Evidence of such shall be submitted in writing to the Weld County Department of Planning Services. (Department of Planning Services) G. The applicant shall acknowledge the advisory referral comments of the Weld County Oil and Gas Energy Department, as stated in the referral response dated August 8, 2022. Evidence of such shall be submitted in writing to the Weld County Department of Planning Services. (Department of Planning Services) H. The applicant shall acknowledge the advisory referral comments of the Little Thompson Water District, as stated in the referral response dated August 25, 2022 and August 26, 2022. Evidence of such shall be submitted in writing to the Weld County Department of Planning Services. (Department of Planning Services) I. The applicant shall submit to the Department of Planning Services an updated Landscaping and Screening plan. (Department of Planning Services) J. A Road Maintenance Agreement (Construction) is required at this location. Road maintenance includes, but is not limited to, dust control and damage repair to specified haul routes during construction. (Development Review) K. The map shall be amended to delineate the following: USR22-0022 — Griffiths Page 8 of 15 1) All sheets of the map shall be labeled USR22-0022. (Department of Planning Services) 2) The attached Development Standards. (Department of Planning Services) 3) The map shall be prepared per Section 23-2-260.D and Section 23-4-1030 of the Weld County Code. (Department of Planning Services) 4) Show and label the required setbacks, in accordance with Section 23-4-1030.C.3 of the Weld County Code. (Department of Planning Services) 5) Show and label any existing and proposed solar facility installations and electrical equipment, power lines, structures, temporary work trailers, storage containers (limited to two (2) per Section 23-3-30.B of the Weld County Code), storage areas and miscellaneous improvements, as applicable. Clearly indicate which items are temporary for use during construction and which items are permanent. (Department of Planning Services) 6) Show and label the required fencing, gates and any emergency and site identification signage, in accordance with Section 23-2-240.A.12 and Section 23-4-1030.C.6 of the Weld County Code. Include fence and sign specification details on the map. Refer to the Weld County Sign Code, as amended. (Department of Planning Services) 7) Show and label the location of the trash collection areas, if applicable. Include specification details on the USR map. Refer to Section 23-2-240.A.13. of the Weld County Code for design criteria. (Department of Planning Services) 8) Show and label any on -site lighting, if applicable. All lighting shall be downcast and shielded so that light rays will not shine directly onto adjacent properties. Include lighting specification details on the USR map. Refer to Section 23-2-250.D. of the Weld County Code for design criteria. (Department of Planning Services) 9) Show and label the Big Thompson and South Platte Ditch. (Department of Planning Services) 10) Show and label the setback radiuses for existing oil and gas tank batteries, wellheads, and encumbrances, if applicable. Setback requirements are located in Section 23-3-70.E. of the Weld County Code. (Department of Planning Services) 11) Show and label any planned oil and gas surface development areas, corridors, access roadways, etc. as part of any executed Surface Use Agreement. (Department of Planning Services) 12) Show and label all recorded easements and rights -of -way on the map by book and page number or reception number and recording date. (Department of Planning Services) 13) County Road 48.5 is a gravel road and is designated on the Weld County Functional Classification Map as a local road which requires 60 feet of right-of-way at full buildout. The applicant shall delineate and label on the site map or plat the future and existing right-of- way (along with the documents creating the existing right-of-way) and the physical location of the road. All setbacks shall be measured from the edge of right-of-way. This road is maintained by Weld County. (Development Review) 14) Show the Colorado Department of Transportation (CDOT) right-of-way on the plat along with the documents creating the right-of-way. (Development Review) 15) Show and label the existing proposed access point onto County Road 48.5 and the usage USR22-0022 — Griffiths Page 9 of 15 type (Agriculture, Residential, Commercial/Industrial, or Oil and Gas). Development Review will review the access location as a part of the plat submittal. (Development Review) 16) Show and label the drainage flow arrows. (Development Review) 2. Upon completion of Condition of Approval #1 above, the applicant shall submit one (1) electronic copy (.pdf) of the map for preliminary approval to the Weld County Department of Planning Services. Upon approval of the map the applicant shall submit a Mylar map along with all other documentation required as Conditions of Approval. The Mylar map shall be recorded in the office of the Weld County Clerk and Recorder by the Department of Planning Services. The map shall be prepared in accordance with the requirements of Section 23-2-260.D of the Weld County Code. The Mylar map and additional requirements shall be submitted within one hundred twenty (120) days from the date of the Board of County Commissioners Resolution. The applicant shall be responsible for paying the recording fee. (Department of Planning Services) 3. In accordance with Appendix 5-J of the Weld County Code, should the map not be recorded within the specified timeline from the date the administrative review was signed, a $50.00 recording continuance fee shall be added for each additional 3 -month period. (Department of Planning Services) 4. The Use by Special Review is not perfected until the Conditions of Approval are completed and the map is recorded. Activity shall not occur, nor shall any building or electrical permits be issued on the property, until the Use by Special Review map is ready to be recorded in the office of the Weld County Clerk and Recorder or the applicant has been approved for an early release agreement. (Department of Planning Services) 5. Prior to Construction: A. The applicant shall submit an irrevocable standby letter of credit, bond, or alternate form of security in an amount sufficient to fund the estimated decommissioning/reclamation costs required by Section 23-4-1030.B.4 of the Weld County Code, for acceptance and approval by the Weld County Board of County Commissioners. Once approved, the Decommissioning and Reclamation Plan shall be updated to include the approved security information. (Department of Planning Services) B. The approved access and tracking control shall be constructed prior to on -site construction. (Development Review) C. If more than one (1) acre is to be disturbed, a Weld County Grading Permit will be required. (Development Review) 6. Prior to Operation: A. The applicant shall develop an Emergency Action and Safety Plan with the Weld County Office of Emergency Management and the Windsor -Severance Fire District. The plan shall be reviewed on an annual basis by the Facility operator, the Fire District, and the Weld County Office of Emergency Management. Submit evidence of acceptance to the Weld County Department of Planning Services. (Office of Emergency Management) USR22-0022 — Griffiths Page 10 of 15 SITE SPECIFIC DEVELOPMENT PLAN USE BY SPECIAL REVIEW PERMIT DEVELOPMENT STANDARDS Arthur Griffiths USR22-0022 1. A Site -Specific Development Plan and Use by Special Review Permit, USR22-0022, for a Solar Energy Facility (SEF) outside of subdivisions and historic townsites in the A (Agricultural) Zone District, subject to the Development Standards stated hereon. (Department of Planning Services) 2. Approval of this plan may create a vested property right pursuant to Section 23-8-10 of the Weld County Code. (Department of Planning Services) 3. The facility is unmanned and will operate year-round, according to the application materials. Limited maintenance personnel may visit the site once operational. (Department of Planning Services) 4. The property owner or operator shall provide written evidence of an approved Emergency Action and Safety Plan on or before March 15th of any given year signed by representatives for the Fire District and the Weld County Office of Emergency Management to the Department of Planning Services. (Department of Planning Services) 5. Height limitation. Ground -mounted solar collectors shall not exceed twenty-five (25) feet in height, measured from the highest grade below each solar panel to the highest extent of the solar panel rotation per Section 23-4-1030.C.1 of the Weld County Code, as amended. (Department of Planning Services) 6. Glare. A SEF shall be designed, located or placed so that concentrated solar glare from its solar collectors will not be directed toward or onto nearby properties or roadways at any time of the day per Section 23-4-1030.C.2 of the Weld County Code, as amended. (Department of Planning Services) 7. Setbacks. The Improved Area of the SEF shall conform to the setback requirements of the underlying zone. Additionally, the improved area must be at least five hundred (500) feet from existing residential buildings and residential lots of a platted subdivision or planned unit development. The residential setback requirement may be reduced if appropriate screening through landscape or an opaque fence is installed, or upon submittal to Weld County of a waiver or informed consent signed by the residence owner agreeing to the lesser setback. If landscaping or opaque fencing is substituted for setback, a landscaping plan or fencing plan shall first be submitted to and approved by the Department of Planning Services per Section 23-4-1030.C.3 of the Weld County Code, as amended. (Department of Planning Services) 8. Dust mitigation. The operators of the SEF shall continuously employ the practices for control of fugitive dust detailed in their accepted Dust Mitigation Plan per Section 23-4-1030.C.4 of the Weld County Code, as amended. (Department of Planning Services) 9. Underground cables. All electrical cables on the improved area shall be buried, except for direct current string wires that connect between solar collectors, direct current collection circuits between rows of solar arrays that are no more than four (4) feet above grade crossings, substations, switchyards, and circuit voltages greater than 34.5 kilovolts (where necessary) per Section 23-4- 1030.C.5 of the Weld County Code, as amended. (Department of Planning Services) 10. Fencing. The SEF shall be enclosed with a security fence as approved pursuant to the Fencing Plan. Appropriate signage shall be placed upon such fencing that warns the public of the high voltage therein per Section 23-4-1030.C.6 of the Weld County Code. All signs shall adhere to the adopted Weld County Sign Code, as amended. (Department of Planning Services) USR22-0022 — Griffiths Page 11 of 15 11. Stormwater management. The Operator of the SEF shall comply with the approved Final Drainage Report and the required Storm Drainage Criteria pursuant to Chapter 8, Article XI of this Code. Ground -mounted solar collector systems shall be exempt from impervious surface calculations if the soil under the collectors is designated hydrologic A or B soil groups by the Natural Resources Conservation Service per Section 23-4-1030.C.7 of the Weld County Code, as amended. (Department of Planning Services) 12. Existing irrigation systems. The nature and location or expansion of the SEF must not unreasonably interfere with any irrigation systems on or adjacent to the solar facility per Section 23-4-1030.C.9 of the Weld County Code, as amended. (Department of Planning Services) 13. The site shall adhere to the accepted Decommissioning and Reclamation Plan. Per Section 23-4- 1030.B.4.h of the Weld County Code, as amended, Weld County shall have the right to draw upon the irrevocable standby letter of credit, or other form of financial security, to pay for decommissioning in the event that the holder has not commenced decommissioning/reclamation activities within ninety (90) days of the Board of County Commissioners' order or resolution directing decommissioning/reclamation. (Department of Planning Services) 14. The site shall be maintained in accordance with the accepted Property Maintenance Plan. (Department of Planning Services) 15. The site shall be maintained in accordance with the accepted Lighting Plan. (Department of Planning Services) 16. Sources of light shall be shielded so that light rays will not shine directly onto adjacent properties where such would cause a nuisance or interfere with the use on the adjacent properties in accordance with the plan. Neither the direct, nor reflected, light from any light source may create a traffic hazard to operators of motor vehicles on public or private streets. No colored lights may be used which may be confused with, or construed as, traffic control devices. (Department of Planning Services) 17. The property owner or operator shall be responsible for controlling noxious weeds on the site, pursuant to Chapter 15, Article I and II, of the Weld County Code. (Development Review) 18. The access to the site shall be maintained to mitigate any impacts to the public road, including damages and/or off -site tracking. (Development Review) 19. Any work that may occupy and or encroach upon any County rights -of -way or easement shall acquire an approved Right -of -Way Use Permit prior to commencement. (Development Review) 20. The Property Owner shall comply with all requirements provided in the executed Road Maintenance Agreement. (Development Review) 21. The historical flow patterns and runoff amounts on the site will be maintained. (Development Review) 22. During construction, all liquid and solid wastes (as defined in the Solid Wastes Disposal Sites and Facilities Act, 30-20-100.5, C.R.S.) shall be stored and removed for final disposal in a manner that protects against surface and groundwater contamination. (Department of Public Health and Environment) 23. During construction, no permanent disposal of wastes shall be permitted at this site. This is not meant to include those wastes specifically excluded from the definition of a solid waste in the Solid Wastes Disposal Sites and Facilities Act, 30-20-100.5, C.R.S. (Department of Public Health and Environment) USR22-0022 — Griffiths Page 12 of 15 24. During construction, waste materials shall be handled, stored, and disposed in a manner that controls fugitive dust, fugitive particulate emissions, blowing debris, and other potential nuisance conditions. The facility shall operate in accordance with Chapter 14, Article 1 of the Weld County Code. (Department of Public Health and Environment) 25. Fugitive dust and fugitive particulate emissions shall be controlled throughout the duration of construction of the facility. (Department of Public Health and Environment) 26. During construction, adequate toilet facilities and handwashing units shall be provided. Portable toilets shall be serviced by a cleaner licensed in Weld County, contain hand sanitizers, be screened from public view, and removed when construction is completed. 27. The operation shall comply with all applicable rules and regulations of State and Federal agencies and the Weld County Code. (Department of Public Health and Environment) 28. Building permits shall be required for any new construction or setup of a manufactured structure (buildings and/or structures) per Section 29-3-10 of the Weld County Code. A building permit application must be completed and submitted. Buildings and structures shall conform to the requirements of Chapter 29 of the Weld County Code, and the adopted codes at the time of permit application. Currently, the following have been adopted by Weld County: 2018 International Building Codes; 2018 International Energy Code; 2020 National Electrical Code. (Department of Planning Services) 29. The property owner or operator shall be responsible for complying with the Design and Operation Standards of Chapter 23 of the Weld County Code. (Department of Planning Services) 30. Necessary personnel from the Weld County Departments of Planning Services, Public Works, and Public Health and Environment shall be granted access onto the property at any reasonable time in order to ensure the activities carried out on the property comply with the Conditions of Approval and Development Standards stated herein and all applicable Weld County regulations. 31. The Use by Special Review area shall be limited to the plans shown hereon and governed by the foregoing standards and all applicable Weld County regulations. Substantial changes from the plans or Development Standards, as shown or stated, shall require the approval of an amendment of the Permit by the Weld County Board of County Commissioners before such changes from the plans or Development Standards are permitted. Any other changes shall be filed in the office of the Department of Planning Services. 32. The property owner or operator shall be responsible for complying with all of the foregoing Development Standards. Noncompliance with any of the foregoing Development Standards may be reason for revocation of the Permit by the Board of County Commissioners. 33. Construction or use pursuant to approval of a Use by Special Review Permit shall be commenced within three (3) years from the date of approval, unless otherwise specified by the Board of County Commissioners when issuing the original Permit, or the Permit shall be vacated. The Director of Planning Services may grant an extension of time, for good cause shown, upon a written request by the landowner." 34. A Use by Special Review shall terminate when the use is discontinued for a period of three (3) consecutive years, the use of the land changes or the time period established by the Board of County Commissioners through the approval process expires. The landowner may notify the Department of Planning Services of a termination of the use, or Planning Services staff may observe that the use has been terminated. When either the Department of Planning Services is notified by the landowner, or when the Department of Planning Services observes that the use may have been terminated, the Planner shall send certified written notice to the landowner asking that the landowner request to vacate the Use by Special Review Permit." USR22-0022 — Griffiths Page 13 of 15 35. RIGHT TO EXTRACT MINERAL RESOURCES STATEMENT: Weld County has some of the most abundant mineral resources, including, but not limited to, sand and gravel, oil, natural gas, and coal. Under title 34 of the Colorado Revised Statutes, minerals are vital resources because (a) the state's commercial mineral deposits are essential to the state's economy; (b) the populous counties of the state face a critical shortage of such deposits; and (c) such deposits should be extracted according to a rational plan, calculated to avoid waste of such deposits and cause the least practicable disruption of the ecology and quality of life of the citizens of the populous counties of the state. Mineral resource locations are widespread throughout the County and people moving into these areas must recognize the various impacts associated with this development. Often times, mineral resource sites are fixed to their geographical and geophysical locations. Moreover, these resources are protected property rights and mineral owners should be afforded the opportunity to extract the mineral resource. 36. WELD COUNTY'S RIGHT TO FARM STATEMENT: Weld County is one of the most productive agricultural counties in the United States, typically ranking in the top ten counties in the country in total market value of agricultural products sold. The rural areas of Weld County may be open and spacious, but they are intensively used for agriculture. Persons moving into a rural area must recognize and accept there are drawbacks, including conflicts with long-standing agricultural practices and a lower level of services than in town. Along with the drawbacks come the incentives which attract urban dwellers to relocate to rural areas: open views, spaciousness, wildlife, lack of city noise and congestion, and the rural atmosphere and way of life. Without neighboring farms, those features which attract urban dwellers to rural Weld County would quickly be gone forever. Agricultural users of the land should not be expected to change their long-established agricultural practices to accommodate the intrusions of urban users into a rural area. Well -run agricultural activities will generate off -site impacts, including noise from tractors and equipment; slow -moving farm vehicles on rural roads; dust from animal pens, field work, harvest and gravel roads; odor from animal confinement, silage and manure; smoke from ditch burning; flies and mosquitoes; hunting and trapping activities; shooting sports, legal hazing of nuisance wildlife; and the use of pesticides and fertilizers in the fields, including the use of aerial spraying. It is common practice for agricultural producers to utilize an accumulation of agricultural machinery and supplies to assist in their agricultural operations. A concentration of miscellaneous agricultural materials often produces a visual disparity between rural and urban areas of the County. Section 35-3.5-102, C.R.S., provides that an agricultural operation shall not be found to be a public or private nuisance if the agricultural operation alleged to be a nuisance employs methods or practices that are commonly or reasonably associated with agricultural production. Water has been, and continues to be, the lifeline for the agricultural community. It is unrealistic to assume that ditches and reservoirs may simply be moved "out of the way" of residential development. When moving to the County, property owners and residents must realize they cannot take water from irrigation ditches, lakes, or other structures, unless they have an adjudicated right to the water. Weld County covers a land area of approximately four thousand (4,000) square miles in size (twice the size of the State of Delaware) with more than three thousand seven hundred (3,700) miles of state and County roads outside of municipalities. The sheer magnitude of the area to be served stretches available resources. Law enforcement is based on responses to complaints more than on patrols of the County, and the distances which must be traveled may delay all emergency responses, including law enforcement, ambulance, and fire. Fire protection is usually provided by volunteers who must leave their jobs and families to respond to emergencies. County gravel roads, no matter how often they are bladed, will not provide the same kind of surface expected from a paved road. Snow removal priorities mean that roads from subdivisions to arterials may not be cleared for several days after a major snowstorm. Services in rural areas, in many cases, will not USR22-0022 — Griffiths Page 14 of 15 be equivalent to municipal services. Rural dwellers must, by necessity, be more self-sufficient than urban dwellers. People are exposed to different hazards in the County than in an urban or suburban setting. Farm equipment and oil field equipment, ponds and irrigation ditches, electrical power for pumps and center pivot operations, high speed traffic, sand burs, puncture vines, territorial farm dogs and livestock, and open burning present real threats. Controlling children's activities is important, not only for their safety, but also for the protection of the farmer's livelihood. USR22-0022 — Griffiths Page 15 of 15 September 1, 2022 DEPARTMENT OF PLANNING SERVICES 1555 N 17th AVE GREELEY, CO 80631 WEBSITE: www.weldgov.com E-MAIL: daungst@co.weld.co.us PHONE: (970) 400-3524 FAX: (970) 304-6498 Zach Brammer PO BOX 1255 Sterling, CO 80751 Subject: USR22-0022 - A Site Specific Development Plan and Use by Special Review Permit for a Solar Energy Facility (SEF) outside of subdivisions and historic townsites in the A (Agricultural) Zone District. On parcel(s) of land described as: PT N2S2 AND SW4SW4 Section 3, T4, R67W of the 6th P.M., Weld County, Colorado. Dear Applicants: I have scheduled a meeting with the Weld County Planning Commission on October 04, 2022 at 12:30 p.m. A subsequent hearing with the Board of County Commissioners will be held on October 26, 2022 at 10:00 a.m. Both hearings will be held in the Hearing Room, Weld County Administration Building, 1150 O Street, Greeley, Colorado. The property owner and/or authorized agent must be in attendance to answer any questions the Planning Commission members or Board of County Commissioners may have. Colorado Revised Statute, C.R.S.24-65.5-103 (adopted as part of H.B.01-1088) requires notification of all mineral estate owners 30 days prior to any public hearing. The applicant needs to provide the Weld County Planning Department with written certification indicating the above requirement has been met. A representative from the Department of Planning Services will be out to the property a minimum of ten days prior to the hearing to post a sign, adjacent to and visible from a publicly maintained road right-of-way which identifies the hearing time, date, and location. In the event the property is not adjacent to a publicly maintained road right-of-way, one sign will be posted in the most prominent place on the property and a second sign posted at the point at which the driveway (access drive) intersects a publicly maintained road right-of-way. The Department of Planning Services' staff will make a recommendation concerning this application to the Weld County Planning Commission and will be included in the staff report one week prior to the scheduled Planning Commission hearing. You may view the staff report at https://accela- aca.co.weld.co.us/CitizenAccess Respectfully, )k/k/S2k,CtifIlikea, Diana Aungst Planner Diana Aungst From: Zach Brammer <zach@cloudbreakenergy.com> Sent: Tuesday, September 27, 2022 2:37 PM To: Diana Aungst Cc: Rosie Stewart Subject: USR22-0022/Griffiths 1 - Little Thompson Water District Referral Comment Acknowledgement Caution: This email originated from outside of Weld County Government. Do not click links or open attachments unless you recognize the sender and know the content is safe. Hi Diana, I have read all of the referral comments from LTWD for USR22-0022 and I understand their comments. Thanks, Zach Zach Brammer Co -Founder I COO Cloudbreak Energy Partners CLOUDBREAK'" i O: (970) 425-3175 I C: (970) 580-5652 W zach@cloudbreakenergy.com fl cloudbreakenergy.com 218 S 3rd Street, Sterling, CO 80751 1 Diana Aungst From: Zach Brammer <zach@cloudbreakenergy.com> Sent: Tuesday, September 27, 2022 1:45 PM To: Diana Aungst Cc: Rosie Stewart Subject: USR22-0022/Griffiths - CPW Referral Comments Caution: This email originated from outside of Weld County Government. Do not click links or open attachments unless you recognize the sender and know the content is safe. Hi Diana, We have reviewed the referral comments in the letter from CPW dated September 14, 2022. We understand their recommendations and will incorporate their recommendations, as applicable, to the Griffiths #1 Solar Project (USR22- 0022). Thanks, Zach Zach Brammer Co -Founder I COO Cloudbreak Energy Partners CLOUDBREAK' • O: (970) 425-3175 I C: (970) 580-5652 • zach@cloudbreakenergy.com fl cloudbreakenergy.com • 218 S 3rd Street, Sterling, CO 80751 1 Diana Aungst From: Zach Brammer <zach@cloudbreakenergy.com> Sent: Tuesday, September 27, 2022 1:20 PM To: Diana Aungst Cc: Rosie Stewart Subject: USR22-0002/Griffiths - Removal of Proposed Highway 60 Access Caution: This email originated from outside of Weld County Government. Do not click links or open attachments unless you recognize the sender and know the content is safe. Hi Diana, Based on CDOT's comments, we will no longer be pursuing an access on Highway 60 as part of USR22-0002. We will only be using an access from County Road 48.5. Thanks, Zach Zach Brammer Co -Founder I COO Cloudbreak Energy Partners CLOUDBREAK'" L O: (970) 425-3175 I C: (970) 580-5652 O zach@cloudbreakenergy.com fl cloudbreakenergy.com • 218 S 3rd Street, Sterling, CO 80751 1 Diana Aungst From: Zach Brammer <zach@cloudbreakenergy.com> Sent: Tuesday, September 27, 2022 1:53 PM To: Diana Aungst Cc: Rosie Stewart Subject: USR22-0022/Griffiths 1 - OGED Referral Comment Acknowledgement Caution: This email originated from outside of Weld County Government. Do not click links or open attachments unless you recognize the sender and know the content is safe. Hi Diana, I have read the referral comments from the Weld County Oil & Gas Energy Department dated August 8, 2022 and I understand these comments. Thanks, Zach Zach Brammer Co -Founder I COO Cloudbreak Energy Partners CLOUDBREAK'" L O: (970) 425-3175 I C: (970) 580-5652 O zach@cloudbreakenergy.com fl cloudbreakenergy.com • 218 S 3rd Street, Sterling, CO 80751 1 Diana Aungst From: Sent: To: Cc: Subject: Attachments: Zach Brammer <zach@cloudbreakenergy.com> Tuesday, September 13, 2022 3:16 PM Diana Aungst Rosie Stewart; Alec Shobe Re: USR22-0022 solar - number of modules and lighting Screen Shot 2022-09-13 at 3.05.43 PM.png; Weld County Noise Ordinance.pdf Caution° This email originated from outside of Weld County Government. Do not click links or open attachments unless you recognize the sender and know the content is safe. Hi Diana, Apologies for my delayed response on these items. It took me a while to track down the correct generators that we will be using on the property during construction. My answers are listed below: 1. What is the power source for these lights? If it is a generator how will the noise be mitigated? o Our lights will mainly be powered by electric batteries that will not generate noise. In the rare cases that we are doing work that requires more lighting we will power the lighting using a Honda EU2200 generator or an equivalent generator. The Honda EU2200 generator produces a maximum of 57 dB of noise, as demonstrated in the attached screenshot from Honda's website. 57 dB of noise is less than the nighttime limit within construction areas according to section Sec. 14-9-40 of the Weld County Code. From just 2.5 feet away, the generator would only be producing 50 dB of noise, which is equivalent to the Code's limit for residential properties. Our project is more than 2.5 feet away from any residences. Based on the limited noise generated by these generators, no noise mitigation will be necessary. 2. How many solar modules are proposed? The questionnaire states 14,500 and the USR map states 11,112. o 14,430 solar modules are proposed, so the questionnaire stating approximately 14,500 is correct. We are currently adjusting the USR map based on feedback from FRFR and we will be sure that the number of modules is corrected in the next draft. Please let me know if you have any additional questions! Thanks, Zach On Thu, Sep 8, 2022 at 12:44 PM Diana Aungst <daungst@weldgov.com>wrote: Hi Zach: Just a couple of questions: 1. The lighting plan states that: "If lighting is needed during construction, lights will be positioned and/or shielded from oncoming traffic and residences in the vicinity of the project site, as necessary. Cutoff -type luminaires would be used where practicable. Individual light sources would not exceed 150,000 lumens 1 per light source (typical of a 1250W metal halide light) and would project 0.1 lumen or less at property lines. Unnecessary lighting will not be used. Lights would not exceed 24 feet in height. Any lighting needed for construction is not shown in the dimensioned elevation drawing of the USR Map due to its temporary nature." What is the power source for these lights? If it is a generator how will the noise be mitigated? 2. How many solar modules are proposed? The questionnaire states 14,500 and the USR map states11,112. Please let me know. H -- A ' .) AIM+ 0ti many iany solar modules, panels, - arr-ays are proposed? As discussed in the Panning Qe Project will consist ot approximately 14,500 solar modules. S #1 SOLAR PR0JE PARCEL ID# 105903300001 COUNTY OF WELD, STATE OF COLO'ADO VICINITY M A P Regards, Diana Aungst Planner Weld County Department of Planning Services 1555 N. 17th Avenue - Greeley, Colorado 80631 D: 970-400-3524 O: 970-400-6100 MAD RUSSIAN SUBDIVISION CASE #: PARCEL #: 105903300 ZONE DISTRICT: A (AC PROPERTY ADDRESS: S PROPERTY AREA: 37.4( SOLAR GARDEN AREA: LEASE AREA: 37.46 AC SYSTEM SIZE: 5M ac TOTAL MODULES: 11,1 INVERTER. RACK: CHIN MOUNTING SYSTEM: A SOILS: OLNEY FINE SA ESTIMATED CC'NSTR.UC DWG. NO., TITLE C-001 TITLE SHEE E!E C-002 GENERAL tig C -O03 PROPERTY 8 C-101 EXISTING C C-102 EXISTING C-103 PHASING PL C-104 PHASING Pt C-201 SITE PLAN C-202 SITE PLAN ii C-301 PRE DRAIN/5 C-302 POST DRAM C-400 DETAILS ream F F N rF rI FT2 Fax: 970-304-6498 3 daungst@ weld_gov. corm www. weldgov. coat Confidentiality Notice: This electronic transmission and any attached documents or other writings are intended only for the person or entity to which it is addressed and may contain information that is privileged, confidential or otherwise protected from disclosure. If you have received this communication in error, please immediately notify sender by return e-mail and destroy the communication. Any disclosure, copying, distribution or the taking of any action concerning the contents of this communication or any attachments by anyone other than the named recipient is strictly prohibited. Zach Brammer Co -Founder I COO Cloudbreak Energy Partners CLOUDBREAK7" O: (970) 425-3175 I C: (970) 580-5652 zach@cloudbreakenergy.com cloudbreakenergy.com 218 S 3rd Street, Sterling, CO 80751 4 9/13/22, 3:04 PM Sec. 14-9-40. - Maximum permissible noise levels. Weld County, CO Charter and County Code A. Sound levels shall be measured as provided for in Section 14-9-50 below. B. Sound levels are hereby established for each type of property during specific hours of the day. Any sound level which exceeds the level set for a type of property at any time of day is prohibited. Land Use Maximum (dB(A)) a.m. Noise - 9:00 (dB(A)) 9:00 a.m. Maximum p.m. Noise 7:00 p.m. - 7:00 Residential Property or Commercial Area 55 dB(A) 50 dB(A) Industrial Area or Construction Activities 80 dB(A) 75 dB(A) Nonspecified Areas 55 dB(A) 50 dB(A) C. Between the hours of 9:00 p.m. and 7:00 a.m., the noise levels set forth above may be exceeded by up to ten (10) decibels for up to fifteen (15) minutes in a one -hour period. D. Vehicles operating in the public right-of-way are subject to the following maximum noise levels: Vehicle Class (GVWR) Speed m.p.h. Maximum Limit or less Noise 35 zone in Speed m.p.h. Maximum Limit zone Noise over in 35 (MGWR) any Manufacturer's motor combination vehicle over 10,000 gross of vehicles vehicle pounds weight (4,536 towed by kg), rating such or 86 90 about:blank 1/2 9/13/22, 3:04 PM Weld County, CO Charter and County Code Any other motor vehicle or any combination 80 84 of vehicles towed by any motor vehicle, including but not limited to automobiles, motorcycles, vans or light trucks, with a gross vehicle weight rating (GVWR) less than 10,000 pounds (4,536 kg) E. No person shall operate, anywhere in the County, any vehicle that is not equipped with a muffler in constant operation which is properly maintained to prevent noise in excess of that set forth in this Section; nor shall any person operate, in unincorporated Weld County, any vehicle having a muffler that has been equipped or modified with a cutoff, bypass or similar device or modification. (Weld County Code Ordinance 2008-4) about:blank 2/2 POWER EQUIPMENT norkina. GENERATORS v LAWN RDEN 440t PUMPS v SNOW BLOWERS 9 Find a Dealer QSearch Support ort Special Offers Financing Home • ) e.nerators EU220th v Features vr Specs v Accessories v Applicatfrr _- v Manuals How to Videos v Reviews v Questions Where to Buy T Ti. mss• -LP Ts.v I. 7 4 7 'fir - DC Output Starting System Fuel Tank apacity Run Time per Tankful Dimensions (L x W x H) Noise Level Dry Weight Residential Warranty Commercial Warranty NA Recoil .95 gal :2hr cdr rated load 81 hrs (ail/4 load 20.0'1x 11.4' 1 :7 7 dB(A) rated load 4.1tdB(A) 1/4 load 47.Elb. . 3 Years 3 Years Diana Aungst From: Zach Brammer <zach@cloudbreakenergy.com> Sent: Tuesday, August 16, 2022 10:04 AM To: Diana Aungst Subject: Re: USR22-0022 Griffiths farmland Caution: This email originated from outside of Weld County Government. Do not click links or open attachments unless you recognize the sender and know the content is safe. Hi Diana, The reasons why Mr. Griffiths wants to install the solar facility include, but are not limited to, the following: 1. Financial Sustainability - solar leases generate significantly more income than farming, which will allow the Griffiths to keep the land for generations. By pairing sheep grazing with the solar project, the Griffiths family can keep the land agriculturally productive and financially sustainable. Mr. Griffiths is making a change to ensure that the property remains profitable and remains in his family for years to come. 2. Energy Security - generating enough electricity on his land to power thousands of local homes was very interesting to Mr. Griffiths. 3. Community Benefits - Mr. Griffiths likes how Xcel's Solar*Rewards Community Program allows local residents to potentially save money on their electricity bills without needing to install a solar project on their roof or put any money down. Let me know if you have any additional questions! Thanks, Zach On Tue, Aug 16, 2022 at 7:09 AM Diana Aungst <daungst@weldgov.com>wrote: Hi Zach: I know Mr. Griffiths has historically been farming his property. Can you tell me why now he wants to install the solar facility? Thanks, Diana Aungst Planner 1 Weld County Department of Planning Services 1555 N. 17th Avenue - Greeley, Colorado 80631 D: 970-400-3524 O: 970-400-6100 Fax:970-304-6498 daungst@weldgov.com www. weldgov. corn 00 Confidentiality Notice: This electronic transmission and any attached documents or other writings are intended only for the person or entity to which it is addressed and may contain information that is privileged, confidential or otherwise protected from disclosure. If you have received this communication in error, please immediately notify sender by return e-mail and destroy the communication. Any disclosure, copying, distribution or the taking of any action concerning the contents of this communication or any attachments by anyone other than the named recipient is strictly prohibited. Zach Brammer Co -Founder I COO Cloudbreak Energy Partners CLOUDBREAK' • 0: (970) 425-3175 I C: (970) 580-5652 len zach@cloudbreakenergy.com ?� cloudbreakenergy.com • 218 S 3rd Street, Sterling, CO 80751 2 Hello