Loading...
HomeMy WebLinkAbout20220178.tiffMEMORANDUM TO: Diana Aungst, Planning Services FROM: Mike McRoberts, P.E., Development Review DATE: October 29, 2021 SUBJECT: SUBJECT: PUDZ21-0003 DOB Farm PUD This proposal has been reviewed by Development Review on behalf of the Weld County Department of Public Works. Staff comments made during this phase of the application process may not be all-inclusive, as other issues may arise during the remaining application process. COMMENTS GENERAL PROJECT INFORMATION/LOCATION Project description: Change of Zone Request from the A (Agricultural) Zone District to the PUD (Planned Unit Development) Zone District for three (3) residential lots with Estate Zone District Use, and on -going oil and gas activities. Parcel number 105508300052 Proposed Development Access is from CR 39. ACCESS Development Review has reviewed the application materials related to access. The applicant is proposing that the existing permitted access location (AP18-00815 — Residential) onto County Road 39 be re -permitted as the "development access" for the proposed PUD's internal roadway. This location does not meet the minimum access spacing criteria specified in Table 1 below (PUD accesses are classified as intersections). However, no location along the parcel's County Road 39 frontage will meet the foregoing spacing criteria. For which reason, Development Review will accept the proposed intersection location. No access variance is needed. Sec. 8-14-30. Table 1 - Minimum Access Spacing Criteria (Feet) Access Element Arterial Collector Local Distance between intersections Signalized Unsignalized 2,640 1,320 N/A 1,320 N/A 330 Distance between accesses and intersections 660 660 330 Distance between access points 660 330 150 Distance between access points in subdivisions 660 330 75 Per Sec. 8-14-30.G., when there is a change in use of the access classification/type, or an increase in the amount of traffic using an access, a new access permit shall be required as a condition of the change in use. ROADS AND RIGHTS -OF -WAY County Road 39 is a paved road and is designated on the Weld County Functional Classification Map (Code Ordinance 2017-01) as a collector road, which requires 80 feet of right-of-way. The applicant shall delineate and label on the plat the existing and future rights -of -way and the physical location of the road. The creating documents for the existing right-of-way shall be provided on the plat. If the right-of-way cannot be verified it shall be dedicated or reserved per Weld County Code. Pursuant to the definition of setback in the Weld County Code, Sec. 23-1-90, the required setback is measured from the future right-of-way line. Be aware that physical roadways may not be centered in the right-of-way. This road is maintained by Weld County. Per Section 8-13-30.8, a Weld County Right -of -Way Use Permit is required for any project that will be occupying, constructing or excavating facilities within, and/or encroaching upon, any County rights -of -way or easement. Right -of -Way Use Permit instructions and application can be found at: https://www.weldgov.com/Government/Departments/Public-Works/Permits/Right-of-Way-Permits Weld County will not replace overlapping easements located within existing right-of-way or pay to relocate existing utilities within the County right-of-way. TRAFFIC Latest ADT on CR 39 counted 1,697 average daily trips with 21% trucks. The 8511 percentile speed is 59 mph. According to the applicant's traffic narrative, Lots 1 and 2 will have a combined total of 4 daily roundtrips of passenger vehicles, while Lot 3 will have approximately 2 pickup truck or tractor roundtrips per day. The applicant shall submit a revised Traffic Narrative if the intended use of Lot 3 has changed since the original traffic narrative was submitted. Note: The Institute of Transportation Engineers' Trip Generation Manual, uses 9.5 roundtrips/day to estimate roundtrips generated by one (1) single family home. Please use this estimate for residential lots if a revised narrative is required. INTERNAL ROADWAY All PUD lots shall have access from a privately maintained, internal roadway meeting the design standards of Chapter 8, of the Weld County Code. In addition, the roadway shall be located within a 60 -foot -wide public right-of-way, to be dedicated with the PUDZ plat. DRAINAGE REQUIREMENTS This project qualifies for an exception to stormwater detention (Exception 7) as defined by Section 8-11- 40.1, of the Weld County Code. No additional drainage information is needed. Historic Flows: The applicant will be required to maintain the historic drainage flow patterns and run-off amounts that exist on the property. CONSTRUCTION SCHEDULE At Final Plan, a construction schedule will be required with submittal. This shall show the approximate dates when construction of the development is proposed to start and finish. This shall describe the stages in which the development will be constructed, and the number of buildings or structures and the amount of common open space to be completed at each stage. UTILITY MAP At Final Plan, a Utility Map is required with submittal. The utility map shall show: gas lines, water, electricity (above or below ground), telecomm (if applicable), sewer (if applicable), utility and drainage easements with labels, culverts, detention areas and structures, and plans, profiles, and typical cross section drawings of streets. GRADING PERMIT A Weld County Grading Permit will be required if disturbing more than one (1) acre of land. Grading Permit applications are accepted after the planning process is complete (plat recorded). CONSTRUCTION STORMWATER PERMIT A Construction Stormwater Permit is also required with the State for disturbing more than 1 acre. Contact: Colorado Department of Public Health and Environment, Water Quality Control Division, 303-692-3575. CONDITIONS OF APPROVAL A. A revised Traffic Narrative is required if the intended of use for Lot 3 has changed since the original Traffic Narrative was submitted. B. The PUDZ plat shall be amended as detailed below: 1. County Road 39 is a paved road and is designated on the Weld County Functional Classification Map as a collector road which requires 80 feet of right-of-way at full buildout. Delineate and label the existing and future rights -of -way and the physical location of the road. Provide the creating document(s) for the existing right-of-way. (Development Review) 2. Delineate and label the proposed internal roadway. (Development Review) 3. Delineate and label the proposed 60 -foot -wide public right-of-way, to be dedicated with the PUDZ plat. (Development Review) 4. Show and label the approved access and appropriate turning radii. (Development Review) 5. Show and label the drainage flow arrows. (Development Review) Prior to Construction: If more than one (1) acre is to be disturbed, a Weld County Grading Permit will be required. (Development Review) DEVELOPMENT STANDARDS (NOTES ON THE PLAT) 1. The property owner or operator shall be responsible for controlling noxious weeds on the site, pursuant to Chapter 15, Article I and II, of the Weld County Code. (Development Review) 2. Weld County will not replace overlapping easements located within existing right-of-way or pay to relocate existing utilities within the existing County right-of-way. (Development Review) 3. The access on the site shall be maintained to mitigate any impacts to the public road including damages and/or off -site tracking. (Development Review) 4. Any work that may occupy and or encroach upon any County rights -of -way or easement shall acquire an approved Right -of -Way Use Permit prior to commencement. (Development Review) 5. The historical flow patterns and runoff amounts on the site will be maintained. (Development Review) 6. Weld County is not responsible for the maintenance of the internal (on -site) PUD roadway. (Development Review) WELD COUNTY DEPARTMENT OF PUBLIC HEALTH AND ENVIRONMENT c u rY 1555 North 17th Avenue, Greeley, CO 80631 www.weldhealth.org Memorandum To: Diana Aungst From: Lauren Light, Environmental Health Services Date: September 29, 2021 Re: PUDZ21 -0003 DOB Farm LLC Environmental Health Services has reviewed this Change of Zone Request from the A (Agricultural) Zone District to the PUD (Planned Unit Development) Zone District for two (2) residential lots with Estate Zone District Use, one (1) lot with Agricultural Zone District Uses (limited to a Solar Energy Facility), and on -going oil and gas activities. Central Weld County Water District will provide water and on -site wastewater treatment systems (OWTS) will provide sewer service. Engineer designed OWTS may be required due to the slow filtration rate of the soil on the site. Outstanding items identified from PUDK19-0004 have been addressed with this submittal. A report from Earth Engineering Company, Inc., dated June 10, 2019, was submitted. Environmental impacts were satisfactorily addressed. We recommend the following appear as notes on the Change of Zone plat: 1. Water service may be obtained from Central Weld County Water District. 2. The parcel is currently not served by a municipal sanitary sewer system. Sewage disposal may be by on -site wastewater treatment systems (OWTS) designed in accordance with the regulations of the Colorado Department of Public Health and Environment, Water Quality Control Division, and the Weld County Code in effect at the time of construction, repair, replacement, or modification of the system. 3. Activity or use on the surface of the ground over any part of the OWTS must be restricted to that which shall allow the system to function as designed and which shall not contribute to compaction of the soil or to structural loading detrimental to the structural integrity or capability of the component to function as designed. 4. During development of the site, all land disturbances shall be conducted so that nuisance conditions are not created. If dust emissions create nuisance conditions, at the request of Weld County Environmental Health Services, a fugitive dust control plan must be submitted. Health Administration Public Health & Environmental Health Communication, Emergency Preparedness Vital Records Clinical Services Services Education & Planning & Response Icic: 9/U 304 6410 Ice: 9/0 304 6420 Tele: 970-304-6415 Tele: 970-.304-6470 Tele: 970-304-6470 Fax: 9/U -30T-641'2 Fax: 5l0-304-6416 Fax: 970-304-6411 Fax: 970-304-6452 Fax: 970-304-6462 publicHeadth 5. If land development exceeds 6 months in duration, the responsible party shall prepare a fugitive dust control plan, submit an air pollution emissions notice application, and apply for a permit from the Colorado Department of Public Health and Environment. Diana Aungst From: Moss, Douglas C <mossd@wcsdrel.org> Sent: Tuesday, September 21, 2021 9:05 AM To: Diana Aungst Subject: Fwd: Attached Image Attachments: 3286_001.pdf Caution: This email originated from outside of Weld County Government. Do not click links or open attachments unless you recognize the sender and know the content is safe. ---------- Forwarded message --------- From: <donotreply@wcsdrel.org> Date: Tue, Sep 21, 2021 at 9:02 AM Subject: Attached Image To: Doug <mossd@wcsdrel.org> Diana, Please see the referral for DOB Farm LLC in regards to PUDZ21-0003. We have no conflicts since they already know they have to pay the fees from the previous referrals. Thanks and have a great day. Doug Moss Chief Financial & Operations Officer Weld County School District RE -1 14827 WCR 42 Gilcrest, CO 80623 970-350-4201 W 719-251-4527 C 970-737-2516 F 1 slut m'lt b .2 iaili Weld County Referral September 20, 2021 The Weld County Department of Planning Services has received the following item for review: Applicant: D 0 B Farm LLC Case Number: PUDZ21-0003 Please Reply By: October 18, 2021 Planner: Diana Aungst Project: Change of Zone Request from the A (Agricultural) Zone District to the PUD (Planned Unit Development) Zone District for two (2) residential lots with Estate Zone District Use, one (1) lot with Agricultural Zone District Uses (limited to a Solar Energy Facility), and on -going oil and gas activities Parcel Number: 105508300045-R5340308 Legal: LOT A 1AMRECX20-08-4792, BEING PART OF THE N2SW4 SECTION 8, T4N, R65W of the 6th P.M., Weld County, Colorado. Location: East of and adjacent to CR 39 and approximately one -quarter mile north of CR 46 The application is submitted to you for review and recommendation. Any comments or recommendation you consider relevant to this request would be appreciated. Please reply by the above listed date so that we may give full consideration to your recommendation. Any response not received before or on this date may be deemed to be a positive response to the Department of Planning Services. If you have any further questions regarding the application, please call the Planner associated with the request. Please note that new information may be added to applications under review during the review process. If you desire to examine or obtain this additional information, please call the Department of Planning Services. ❑ We have reviewed the request and find that it does / does not comply with our Comprehensive Plan because: El We have reviewed the request and find no conflicts with our interests. See attached letter. Doug Moss CFO -COO Signature Agency Weld County School District RE -1 Date 9/21/2021 Weld County Planning Dept. 1555 N. 17th Ave, Greeley, CO 80631 (970)-440-6100 (970)-304-6498 fax Weld County School District RE -1 Gilcrest • LaSalle • Platteville P.O. Box 157 14827 W.C.R. 42 Gilcrest, CO 80623 July 6, 2021 Diana Aungst Weld County Planning Department 1555 North 17th Avenue Greeley, CO 80631 RE: Case Number PUDK19-0004 Dear Diana: We have reviewed the application by D.O.B. Farm, LLC for PUDK 19-0004 and have the following comments: Weld County School District RE -1 has developed methodology for Land Dedication and/or In Lieu Payments. The current In Lieu Payment amount per single family unit is $1,054.20. Based on the information provided, it appears that there are plans to create 3 new lots on the parcel. Therefore, an in lieu payment in the amount of $3,162.60 is due to the school district prior to approval of the recorded exemption. The district is requiring that D.O.B. Farms make sure they follow the recommendation of the local fire protection district on the required width of road so that a fire truck and/or a school bus can safely turn around in the roadway. If you have any further questions please feel free to contact me. Respectfully, Doug Moss Chief Financial/Operations Officer BOARD OF EDUCATION KimChacon BenRainboltJr Naomi Nguyen Bridget Holcomb Pat Montoya Vacant President Vice President Secretary Treasurer Director Director Our Total Commitment is to Provide an Exemplary Education and Safe Environment for all Students December 11, 2020 SUBJECT: PUDK 19-0004 NAME: BOB FARM LLC LOCATION: LA SALLE, CO. The La Salle Fire Rescue District's Fire Prevention Division has completed a review of the above project. Currently, the Fire District has the following comments and/or requirements: 1. A water supply and hydrant system is required for this subdivision. 2. Access roads shall not be greater than 150 feet without a turn around or second point of access. 3. The roads shall be an all-weather surface capable of supporting 75,000 I.b.s. DOB Farm PUD follow-up Inbox Email from LaSalle Fire Dept Daryl Bohlender <dbohlender@gmail.com> Tue. Dec 15, 2020, 9:40 AM tojaramillofire, DeWayne Joe, I appreciated our conversation this morning. Per your request I wanted to clarify some of the details that were included in your letter to the county which I have attached. As a reference I have also attached a map which we recently provided to the county which shows approximate locations of the proposed structures and access points. 1. Water supply - With this being a small 3 lot PUD we were hoping to avoid the expense of a dedicated hydrant. I believe you were planning to have the captain determine where the closest hydrant is located or if a tender shuttle might suffice. As I mentioned we do also have a drainage ditch that adjoins the property in the southeast corner, and which usually has water flowing year-round, so perhaps that could suffice? 2. Access roads —The details about what is required in terms of the "150 feet without a turnaround.." would be helpful to us. 3. Road — I believe you had stated that paving would not be required, and that road base would suffice? I have cc'd my brother DeWayne on this since we are partners on this project. It probably would be beneficial for someone from the Fire Department to meet us at the site, and if that is desired just let us know. Thanks, Daryl Bohlender(970-216-4908) 2 Attachments LaSalle Fire PUDK... DOB Farm, Appl m... Joe Jaramillo <jaramillofire@aol.com> Thu, Dec 17, 2020, 10:09 AM to me Thanks for the email. I will follow up with Zach Hill at the department and either he or i will get back to you with an answer. Daryl Bohlender <dbohlender@gmail.com> Wed, Dec 23, 2020, 9:49 AM to Joe Good morning Joe, I'm just checking up to see if either you or Zach have a response yet for us. We're working hard to firm up as many of these details as we can before the end of the year so your part of it would be greatly appreciated! Thanks, Daryl jaramillofire <jaramillofire@aol.com> Wed, Dec 23, 2020, 10:35 AM to me The chief is on vacation and Zach will be in on Saturday when I will contact him. Sent from my T -Mobile 4G LTE Device Joe Jaramillo <jaramillofire@aol.com> Mon, Dec 28, 2020, 8:42 PM to me I talked to Zach he will talk to the Chief when he is back from vacation. ----Original Message ---- From: Daryl Bohlender <dbohlender@gmail.com> To: Joe Jaramillo <jaramillofire@aol.com> Sent: Wed, Dec 23, 2020 9:49 am Subject: Re: DOB Farm PUD follow-up Daryl Bohlender <dbohlender@gmail.com> Mon, Jan 11, 4:20 PM to DeWayne, Joe Good afternoon Joe, Has there any progress in getting answers from LaSalle Fire Dept regarding our PUD? Daryl Joe Jaramillo <jaramillofire@aol.com> Mon, Jan 11, 8:28 PM to me Sorry sir i have not heard back from Zach i believe he is working tomorrow so i will give him a call. Daryl Bohlender <dbohlender@gmail.com> Fri, Jan 22, 12:38 PM to DeWayne, Joe Hey Joe, just checking in once again to see what we can do to get an answer back from LaSalle Fire Dept on our PUD? Daryl Joe Jaramillo <jaramillofire@aol.com> to me Mon, Jan 25, 10:22 AM Daryl, after talking to the Fire Chief he will accept residential fire sprinkler systems for the homes instead of the required fire hydrant systems. The the access roads will still be required and will need to be installed before construction of the homes. Please give me a call if you have any questions about the fire sprinkler systems. Daryl Bohlender<dbohlender@gmail.com> to DeWayne, Joe Good morning Joe, Mon, Jan 25, 11:57 AM We appreciate your response about the residential fire sprinkler systems in the homes. Regarding the access roads, you have mentioned during a phone conversation that we had a few months ago that there is a requirement for "150 feet without a turnaround." I guess I'm still a little unclear what that means, so if that could be explained further it would be helpful to us. Thanks, Daryl Daryl Bohiender<dbohender@r11ail.cor11> to Joe, DeWayne Joe, Just to confirm our phone conversation: Mon, Jan 25, 2:41 PM • If the residences have a "fire sprinkler system", there would not be a requirement for the 150 foot turnaround, correct? • Regarding sprinkler systems I would anticipate a complete residential fire sprinkler system could be quite costly. You had mentioned that there are a variety of sprinkler system options (separate water tanks, etc), which I would appreciate learning more about. Is there any information you could send me? Or should we schedule a time to connect and discuss? Thanks! Daryl Bohlender<dbohlender@gmail.com> to Joe, DeWayne Hey Joe, I'm just checking in to see if you got the answers to my last email? Thanks, Daryl DeWayne Bohiender<drbohlender@gmaH.com> to me FYI, per my research, adding a home sprinkler system only adds about $1.501 sq foot. So at that (if correct) a 2000 sq ft house would only be $3000. Worth the protection. Wed, Feb 17, 4:30 PM Wed, Feb 17, 8:33 PM Daryl Bohiender<dbohender@r11aiI.cors> to DeWayne Thanks for the info. Joe Jaramillo <jaramillofire@aol.com> to me Thu, Feb 18, 5:59 AM Thu, Feb 18, 10:35 AM Daryl, the best way to understand the sprinkler system is to have a sprinkler contractor look at your house plans. They will give you a bid to design and install the system. I have included a list of fire protection contractors. Fire Sprinkler Cont... ❑ Daryl Bohlender <dbohlender@gmail.com> to Joe Good afternoon Joe, and I appreciate the sprinkler system contractors list. My other question was: If the residences have a "fire sprinkler system", there would not be a requirement for the 150 foot turnaround, correct? Thanks! Joe Jaramillo <jaramillofire@aol.com> to me You are correct a turn around is not needed. - Daryl Bohlender<dbohlender@gmail.com> to DeWayne, Joe Hey Joe, Thu, Feb 18, 2:33 PM Thu, Feb 18, 8:21 PM Fri, Feb 19, 12:38 PM We appreciate your response and are glad that is the answer! Have a great weekend! Daryl Reply Reply all Forward 111011 G II Email from Noble Chevron DOB PUD 3 messages Daryl Bohlender <dbohlender@gmail.com> Daryl Bohlender <dbohlender@gmail.com> Wed, Dec 9, 2020 at 1:44 PM To: ryan.antonio@chevron.com Ryan, Per our conversation I've attached a copy of the PUD Administrative Review that the county has requested comments from Chevron about. And per your request I have attached a copy of the plat. Let me know if you have any other questions. Thanks, Daryl 2 attachments �n PUDK19-0004 Administrative Review, highlights for Tim M.pdf 224K �n BOHLENDER LOT A 1AMRECX20-08-4792 All pages.pdf 76K Ryan Antonio <Ryan.Antonio@nblenergy.com> Thu, Dec 10, 2020 at 10:22 AM To: Daryl Bohlender <dbohlender@gmail.com> Daryl: Thank you for reaching out. As long as we have access and adequate workspace around our wells and production equipment as shown on the plat I don't have any concerns with the proposed PUD. If you need anything else, please let me know. Ryan Antonio [cIs1112YAI NRI From: Antonio, Ryan <ryan.antonio@chevron.com> Sent: Thursday, December 10, 2020 9:44 AM To: Ryan Antonio <Ryan.Antonio@nblenergy.com> Subject: FW: DOB PUD [Quoted text hidden] Daryl Bohlender <dbohlender@gmail.com> To: Ryan Antonio <Ryan.Antonio@nblenergy.com> Thank you! [Quoted text hidden] Thu, Dec 10, 2020 at 2:39 PM COLORADO dDivision of Water Resources Department of Natural Resources September 20, 2021 Diana Aungst, Planner II Weld County Department of Planning Services Transmission via email: daungstc weldgov.com Re: DOB Farm Planned Unit Development (2nd Letter) Case No. PUDZ21-0003 Part of the NW 1/4 SW 1/4 of Sec. 8, T4N, R65W, 6th P.M. Water Division 1, Water District 2 Dear Diana Aungst: We have reviewed the September 20, 2021 proposal to subdivide and rezone a 15.28 -acre parcel known as Lot A of Amended Recorded Exemption 1AMRECX20-08-4792 into 3 lots. Lots 1 and 2 will be approximately 2 acres and be used as residential lots. Lot 3 will be approximately 10.05 acres and be leased for used for agricultural uses, including use as a solar farm and for on -going oil and gas activities. This office previously provided comments for this planned unit development on March 23, 2020 (case no. PU DK19-0004). Water Supply Demand According to the Water Supply Information Summary provided by the applicant on October 1, 2020, the proposed water use and estimated demand for the residential lots are as follows: 0.3 acre- feet/year for household use, 0.25 acre-feet/year for irrigation use, and 0.1 acre-feet/year for the watering of livestock, for a total of 1.3 acre-feet/year for both residential lots. No water demand or water uses for Lot 3 was specified. Source of Water Supply The proposed water supply is service provided by the Central Weld County Water District (CWCWD). According to the letter dated May 24, 2021, the CWCWD can serve the development provided that all requirements set forth by the CWCWD are met. According to an email dated May 26, 2021 from Kathy Naibauer, this parcel has met these requirements to be eligible to receive service from the CWCWD. The CWCWD provided information about their water supplies in September of 2018. The CWCWD primarily relies on Colorado -Big Thompson (C -BT) water to supply retail water customers. As of September 2018, the CWCWD owned 5,832 C -BT units and 100 Windy Gap units. The yield of C -BT units and Windy Gap units varies from year to year based on conditions and storage. The dry year water yield is 3,800 acre-feet per year and the average yield is 4,800 acre-feet. In addition, the CWCWD continues to develop additional water supplies, including participating in the Northern Integrated Supply Project (NISP). According to the CWCWD, their current demand is 5,500 units with a commitment to serve 31 additional units. A review of our records showed well permit no. 11272-R located on the subject property. This well was registered on April 7, 1960 as an existing well used for irrigation and withdrawing from the alluvium. This well was later decreed as Kaufmen Well No. 2-11272 in Division 1 Water Court case 1313 Sherman Street, Room 821, Denver, CO 80203 P303 866 3581 www.colorado.gov/water Jared S. Polis, Governor I Dan Gibbs, Executive Director I Kevin G. Rein, State Engineer/Director •. './arc 4,. no. W-2038 for a pumping rate of 2.22 cfs and irrigation of 80 acres being the N %z SW'/4 Sec. 8, T 4N, R 65W, 6th P.M. This well is currently inactive and cannot be used for irrigation until it is covered under a water court -approved augmentation plan, a measuring device is installed, and a well test is performed by a certified well tester and submitted to the Division of Water Resources. State Engineer's Office Opinion Based upon the above and pursuant to section 30-28-136(1)(h)(I), C.R.S. and section 30-28- 136(1)(h)(II), C.R.S., the State Engineer's Office offers the opinion that the proposed water supply can be provided without causing material injury to existing water rights and the supply is expected to be adequate. If you, or the applicant, have any questions please contact Wenli Dickinson at 303-866-3581 x8206 or at Wenli.Dickinson@state.co.us. Sincerely, Joanna Williams, P.E. Water Resources Engineer Ec: Subdivision file no. 27076 Well Permit no. 11272-R Applicant (drbohlender@gmail.com) Submit by Email Weld County Referral September 20, 2021 The Weld County Department of Planning Services has received the following item for review: Applicant: D O B Farm LLC Please Reply By: October 18, 2021 Case Number: PUDZ21-0003 Planner: Diana Aungst Project: Change of Zone Request from the A (Agricultural) Zone District to the PUD (Planned Unit Development) Zone District for two (2) residential lots with Estate Zone District Use, one (1) lot with Agricultural Zone District Uses (limited to a Solar Energy Facility), and on -going oil and gas activities Parcel Number: 105508300045-R5340308 Legal: LOT A 1AMRECX20-08-4792, BEING PART OF THE N2SW4 SECTION 8, T4N, R65W of the 6th P.M., Weld County, Colorado. Location: East of and adjacent to CR 39 and approximately one -quarter mile north of CR 46 The application is submitted to you for review and recommendation. Any comments or recommendation you consider relevant to this request would be appreciated. Please reply by the above listed date so that we may give full consideration to your recommendation. Any response not received before or on this date may be deemed to be a positive response to the Department of Planning Services. If you have any further questions regarding the application, please call the Planner associated with the request. Please note that new information may be added to applications under review during the review process. If you desire to examine or obtain this additional information, please call the Department of Planning Services. O We have reviewed the request and find that it does / does not comply with our Comprehensive Plan because: We have reviewed the request and find no conflicts with our interests. See attached letter. Jill Carlson Signature Agency Colorado Geological Survey Date 10/19/2021 Weld County Planning Dept. 1555 N. 17th Ave, Greeley, CO 80631 (970)-440-6100 (970)-304-6498 fax COLORADO GEOLOGICAL SURVEY 1801 Moly Road Golden, Colorado 80401 October 19, 2021 Diana Aungst Location: Weld County Planning Department NW SW Section 8, 1555 N. 17th Ave. T4N, R65W, 6th P.M. Greeley, CO 80631 40.3248, -104.6952 Subject: PUDZ21-0003 — DOB Farm Change of Zone to PUD Weld County, Colorado; CGS Unique No. WE -20-0028-3 Dear Diana: Karen Berry State Geologist Colorado Geological Survey has reviewed the DOB Farm Change of Zonc referral. I understand the applicant currently proposes a Change of Zone from the A (Agricultural) Zone District to the PUD (Planned Unit Development) Zonc District for two residential lots with Estate Zone District Use, one lot with Agricultural Zone District Uses (limited to a Solar Energy Facility), and ongoing oil and gas activities. The referral documents include a Geologic Hazards and Mineral Extraction Evaluation Report, Proposed 3 -Lot PUD, 22240 County Road 39, La Salle (Earth Engineering Company, Inc. [EEC], June 18, 2019). CGS reviewed this site and EEC's 6/18/2019 report at PUD sketch plan in March 2020 (PUDK19-0004). The proposed PUD is substantially the same as previously rcvicwcd. The site is not undermined, is in an "Area of Minimal Flood Hazard," and is not exposed to any known or suspected geologic hazards that would preclude the proposed residential and solar uses. CGS therefore has no objection to approval of the PUD as proposed. Our March 2020 comments remain valid: EEC's Geologic Hazards and Mineral Extraction Evaluation Report contains a very general description of site geology and mineral resource potential based on available geologic mapping and NRCS soil survey data, which is typically valid for only the uppermost five feet below the ground surface. Mineral resource potential. According to the Atlas of Sand, Gravel, and Quarry Aggregate Resources, Colorado Front Range Counties (Schwochow et al, Colorado Geological Survey Special Publications 5-A, Plate 2, and 5-B, La Salle Quadrangle, 1974), the subject property is located near the southern edge of a mapped "T3" resource area. As noted by EEC (page 5) T3 is described as a stream terrace deposit potentially containing a sand resource. A depression shown on the La Salle quadrangle in the eastern portion of proposed Lots 1 & 2 and west of the Western Mutual Ditch indicates that some resource extraction may have already occurred, possibly related to construction of the ditch. The site's location near the edge of the mapped resource area indicates that any potential aggregate layer may be relatively thin. A determination of whether the property contains an economic mineral resource is outside the scope of CGS review. A site -specific investigation would be required to verify the presence or absence of a mineral resource. Potential geologic and geotechnical constraints. The site is underlain by Broadway alluvium (South Platte River -deposited sand and gravel). This soil type is typically not problematic from a geotechnical, or WE -20-0028_3 PUDZ21-0003 DOB Farm Zone Change to PUD 12:23 PM: 10/19/2021 Diana Aungst October 19, 2021 Page 2 of 2 foundation performance perspective. The surficial soils arc underlain at unknown depth by the Laramie Formation, consisting of potentially highly expansive shales and claystones interbedded with non -expansive sandstones, coal beds and lignites. Shales and claystones can exhibit significant volume changes in response to changes in water content. Expansive shale and claystone layers and lenses within a few feet of foundation bearing elevations can cause structural damage if not identified and mitigated. Perched water and shallow groundwater may be present or may develop post -construction. Corrosive soils. Although not discussed by Soilogic, NRCS Soil Survey data indicate that the site soils are moderately corrosive to uncoated steel. Disturbance tends to increase corrosivity. Epoxy -coated, fiberglass/composite, concrete, or otherwise corrosion -resistant or corrosion -proof basement window wells are recommended on lots where basements are planned and are determined to be feasible. Lot -specific gcotechnical investigation, testing, and analysis will be needed, once building locations have been determined and prior to building permit application, to (1) determine depths to bedrock and seasonal groundwater levels, (2) characterize soil and bedrock engineering properties such as density, strength, water content, and swell and consolidation/hydrocompaction potential, (3) evaluate the need for overexcavation or other mitigation measures to address potentially moisture -sensitive (expansive and collapsible) soils, expansive claystone bedrock and soft, low -strength lignite, (4) provide earthwork, foundation, floor system, subsurface drainage, and pavement recommendations for design, and (5) determine each lot's suitability for below -grade (basement) construction, if planned. Thank you for the opportunity to review and comment on this project. If you have questions or require additional review, please call me at (303) 384-2643, or c -mail carlson@mines.edu. Sincerely Jill Carlson, C.E.G. Engineering Geologist WE -20-0028_3 PUDZ21-0003 DOB Farm Zone Change to PUD 12:23 PM: 10/19/2021 Hello