HomeMy WebLinkAbout20232290.tiffRESOLUTION RE: REGULATING, WARNING, AND GUIDING TRAFFIC DURING EXTENSION OF TEMPORARY CLOSURE OF COUNTY ROADS 74 AND 33 INTERSECTION FOR APPROXIMATELY AN ADDITIONAL FOUR (4) MONTHS, DUE TO LAWSON CONSTRUCTION COMPANY FALLING SIGNIFICANTLY BEHIND SCHEDULE WITH UNANTICIPATED DELAYS WHEREAS, the Board of County Commissioners of Weld County, Colorado, pursuant to Colorado statute and the Weld County Home Rule Charter, is vested with the authority of administering the affairs of Weld County, Colorado, and WHEREAS, pursuant to C.R.S. §42-4-106(6)(a): "...local authorities, with their respective jurisdiction may, for the purpose of road construction and maintenance, temporarily close to through traffic or to all vehicular traffic any highway or portion thereof for a period not to exceed a specified number of work days for project completion and shall, in conjunction with any such road closure establish appropriate detours or provide for an alternative routing of the traffic affected...", and WHEREAS, on the 3rd day of April, 2023, pursuant to said statute and upon the basis of traffic and personnel investigations, the Board determined that conditions existed which made it necessary to temporarily close the intersection of County Roads 74 and 33, to through traffic and to regulate, warn and guide vehicular traffic by posting signs thereon, with said closure being effective April 17, 2023, for approximately four (4) months, through August 14, 2023, for a roundabout construction project, and WHEREAS, on the 7th day of August, 2023, pursuant to said statute and upon the basis of traffic and personnel investigations, the Board has determined that conditions continue to exist which make it necessary to extend said temporary closure of the intersection of County Roads 74 and 33, with said extended closure being effective August 14, 2023, for approximately an additional four (4) months through December 1, 2023, as a result of Lawson Construction Company falling significantly behind schedule due to unanticipated delays, and further, that standard official traffic control devices shall be erected at said closure giving notice of the restrictions. CC So(RA Dzsro.+ch, CSP 037io%3 2023-2290 EG0024 EXTEND TEMPORARY CLOSURE - INTERSECTION OF COUNTY ROADS 74 AND 33 PAGE 2 NOW, THEREFORE, BE IT RESOLVED that the Board of County Commissioners of Weld County, Colorado, deems it necessary to regulate, warn and guide vehicular traffic on County roads and any intersections thereof, and it hereby authorizes and orders the posting of such traffic control devices as shall be reasonably necessary to regulate, warn and/or guide traffic thereon for the safety of the general public and that said traffic control devices shall conform to the Federal Manual on Uniform Traffic Control Devices. BE IT FURTHER RESOLVED that the Board of County Commissioners of Weld County, Colorado, does declare and establish that the closure of the intersection of County Roads 74 and 33, be, and hereby is, extended, with said extended closure being effective August 14, 2023, for approximately an additional four (4) months through December 1, 2023, as a result of Lawson Construction Company falling significantly behind schedule due to unanticipated delays, and further, that standard official traffic control devices shall be erected at said closure giving notice of the restrictions. The above and foregoing Resolution was, on motion duly made and seconded, adopted by the following vote on the 7th day of August, A.D., 2023. BOARD OF COUNTY COMMISSIONERS WELD COUNTY, COLORADO ATTEST: ditifv,t) JC o%6k, Weld County Clerk to the Board BY: Deputy Clerk to the APPROVED AS TO FOR /1 4 Ass .County A torney Date of signature: ng/I0/23 Mi Leman, Chair erry L. Bu'', Pro-Tem c . James XCUSED evin D. Ross Lori Saine 2023-2290 EG0024 MEMORANDUM TO: Clerk to the Board DATE: August 3, 2023 FROM: Amy Mutchie, Public Works Department SUBJECT: BOCC Agenda Item Weld County Public Works is requesting approval to extend the road closure on Weld County Road 74 and Weld County Road 33 due to the contracting company (Lawson Construction) falling significantly behind schedule. The original closure dates were April 17, 2023 thru August 14, 2023, Weld County Public Works would like to extend this road closure to December 1, 2023. See attached closure diagram. 2023-2290 BOARD OF COUNTY COMMISSIONERS PASS -AROUND REVIEW PASS -AROUND TITLE: Intersection Closure Extension for WCR33/74 Roundabout Project DEPARTMENT: Public Works DATE: July 31, 2023 PERSONS REQUESTING: Don Dunker, Michael Bedell, and Amy Mutchie Brief description of the problem/issue: The WCR33/74 Roundabout Project requires full closure of the intersection to accommodate the ongoing roadway construction. The project was bid with this in mind, and the closure period described in the bid specifications is April 17 through August 14, 2023. The following surrounding roads are being utilized as signed detour routes; 31, 35, 72, and 76. Unfortunately, a series of circumstances and challenges during construction have led to the construction contractor (Lawson Construction) falling significantly behind the planned schedule. Public Works currently estimates the closure period will need to be extended to December 1, 2023. Lawson Construction will be assessed $7,800 per day in liquidated damages, starting on August 15, 2023, and continuing until such time as the intersection is deemed safe to be reopened to the public. What options exist for the Board? (Include consequences, impacts, costs, etc. of options): • Allow the requested intersection closure extension so ongoing construction can continue. This item will he placed on the next available BOCC agenda for approval. • Request a work session to discuss. Recommendation: Staff recommends approval of the intersection closure extension as planned. Approve Recommendation Perry L. Buck, Pro-Tem Mike Freeman, Chair Scott K. James Kevin D. Ross Lori Sai ne Schedule Work Session Other/Comments: gig goUZ'+ Karla Ford From: Sent: To: Subject: yes Lori Saine Weld County Commissioner, District 3 1150 0 Street PO Box 758 Greeley CO 80632 Phone: 970-400-4205 Fax: 970-336-7233 Email: Isaine@weldgov.com Website: www.co.weld.co.us In God We Trust Lori Saine Tuesday, August 1, 2023 2:41 PM Karla Ford RE: Please Reply - PW #2 P -A Intersection Closure Ext. WCR 33/74 Roundabout Project Confidentiality Notice: This electronic transmission and any attached documents or other writings are intended only for the person or entity to which it is addressed and may contain information that is privileged, confidential or otherwise protected from disclosure. If you have received this communication in error, please immediately notify sender by return e-mail and destroy the communication. Any disclosure, copying, distribution or the taking of any action concerning the contents of this communication or any attachments by anyone other than the named recipient is strictly prohibited. From: Karla Ford <kford@weld.gov> Sent: Tuesday, August 1, 2023 12:35 PM To: Lori Saine <Isaine@weld.gov> Subject: Please Reply - PW #2 P -A Intersection Closure Ext. WCR 33/74 Roundabout Project Importance: High Please advise if you approve recommendation. Thank you. Karla Ford ( Office Manager, Board of Weld County Commissioners 1150 0 Street, P.O. Box 758, Greeley, Colorado 80632 :: 970.336-7204 :: kford@weldgov.com :: www.weldgov.com 1 WCR 78 LEGEND _- WCR 74 EASTBOUND DETOUR ROUTE WCR 74 WESTBOUND OF TOUR R0UrE .:NQPQM PROJECT LIMITS DETOUR 4 e44 -9e. WCR 76 I END DETOUR: WCR 74 1 N re V Computer File Information OETOUR M4 -9R PROJECT LMMTs ROAD CLOSED TO THRU TRAFFIC R1144 istirr Art S / "ir W20 -2D WCR 72 1!//. Kit//. ROAD CLOSED TO THRU TRAFFIC R11-04 DETOU (WCR ROAD CLOSED TO THRU TRAFFIC ROAD CLOSED en ft V M4 -St Pa.\ R AND TRAFFIC CONTROL PLAN 74 - EAST/WEST CLOSURE) NT TO SCALE I DETOUR 4OU M4-94. H (901 ROAD CLOSED TO THRU TRAFFIC END DETOUR 03 t) Cramo Ca 1D/212022 trma*. CLW La L c Ow 10,210022 Mum's. CL W 3 art W reoltn Dtbelmoes4 r. s..vJ riesi u dortrinenttaz,c»a, ^zit DrairtS rte in WCR 33 DETOUR DWG 4aoCAt Venal l 202' Salt AS soap Jnes E-c$si Index of Revisions Comn ents: WELD COUNTY As Constructed PUBLIC WORKS DEPARTMENT 1111 H STREET P O 00X 7S8 GREELEY, CO. eopa2-0158 PHONE (970) 3564000 FAX: (970) 3044497 No Revisions: Revised: WCR 74 / 33 INTERSECTION WCR 74 DETOUR PLAN Des+q+v CL'�`r Project No./Code Void: Deluder: CLW PROJ 23044. itSTU C030-0/8 GR-55 Stec &Jost Scot Star an 4; V .rr. ' d' rr' 724 LEGEND WCR 33 NORTHBOUND DETOUR ROUTE WCR 33 SOUTHSOLN0 DETOUR ROUTE PROJECT LIMITS WCR 76 WCR 74 DETOUR 4 M41L I oei ct U! DETOUR DETOUR WCR 72 r Ce t, DETOUR M44R W20-1 DETOUR M14 -9R PROJECT LMMTS ROAD CLOSED TO THRU TRAFFIC R11-04 !/n. • n sae r/!'// W20-20 DETOUR irt4.AR -4\1END DETOUR DETOUR + ROAD CLOSED TO THRU TRAFFIC R11-04 R11-2 Computer Re Information Ovate Das 1 OQ 12022 4N+Yc CLW Lan Modeled Dee 10e21,2022 Whale. CLW F.f psv,, 21 n1rctre r as,rr+g swoosZe Id Pao aot sir ►iaa+e WCR 33DETOUR OVYO MoUI3 Veneer,. Sage AS NOTED Jets Index of Revisions Dale Ca rnenti WELD COUNTY ///!. !/ r///I EATON As Constructed 0) 1 � DETOUR AND TRAFFIC CONTROL. PLAN IWCR 33 - NORTH/SOUTH CLOSURE) NOT TO SCALE • PUBLIC WORM PARTUE N1111 G&1ET CO WO) 356-4000 EP Etr0)3dtbt97 No Revisions WCR 74 / 33 INTERSECTION WCR 33 DETOUR PLAN 01 Project No./Code PROJ: 23044, #8TU C030-078 Revised: Descrier CLW Void: Delaier: &SI Wait CLW Sheet Subset. GR-55 Sheet Number 188 d 224 Hello