HomeMy WebLinkAbout730910.tiff umANGE ORDER N0. 5
DATE September 18, 1973
PROJECT MASTERS - HARDIN PROJECT N0. 73-1-CCA-0228
OWNER WELD COUNTY, COLORADO CONTRACTOR LOVELAND EXCAVATING
DESCRIPTION OF CHANGE - That said Contract shall be changed in the following particulars:
The northwest wingwall on O.E.P. Item No. 5-20 and one section of the deck on the north
end of the bridge per same item, shall be repaired.
and that after the said changes shall have been made with additions and/or deletions are
hereby directed to be a part of the original Contract, the agreement as shown by the
original Contract together with the above-named additions and/or deletions shall consti-
tute the agreement and Contract of the parties hereto.
JUSTIFICATION
Field Order No. 1 : Verbal authorization by the County Engineer to the field inspector.
CHANGE IN CONTRACT COST
Item Description Quantity Unit Unit Cost Total Cost
10 Wingwall Repair 1 TS▪ $ 300.00 $ 3UUMU
11 Deck Repairs T T.T• $ 5L.UU $ 5t.UU
Total Amount This Change Order $ + 352.00
Net of Previous Change Orders (+) (40 $ 21 ,922.40
Original Contract Amount $ 55,062.50
Revised Total Contract Amount $ 77,336.90
CONTRACT TIME
Original Completion Date 8/31/73 Previous Days Allowed 68
Days Allowed This Change Order 10 Revised Complexion Date 9/10/73
Recommended: Approved: Th\aei,t ai iii,
NELSON, HALEY, PATTERSON and QUIRK, INC. WELD COUNTY, COLORADO
(Owner)
BY: /CDS. n rybQn. Pic(
Fie l . Representative By:
Date: S'e.ot• S, /91�9�,w.�
2/Contr ,,ct_e_irtor)
Approved:
roject Manager By: '
Date: x}//7/73 Date: %jV>3>