HomeMy WebLinkAbout20231789.tiffRESOLUTION
RE: REGULATING, WARNING, AND GUIDING TRAFFIC DURING EXTENSION OF
TEMPORARY CLOSURE OF COUNTY ROAD 44 BETWEEN COUNTY ROAD 33 AND
U.S. HIGHWAY 85 FOR APPROXIMATELY AN ADDITIONAL TWO (2) WEEKS, FOR
UNANTICIPATED DELAYS DUE TO INCLEMENT WEATHER
WHEREAS, the Board of County Commissioners of Weld County, Colorado, pursuant to
Colorado statute and the Weld County Home Rule Charter, is vested with the authority of
administering the affairs of Weld County, Colorado, and
WHEREAS, pursuant to C.R.S. §42-4-106(6)(a):
"...local authorities, with their respective jurisdiction may, for the
purpose of road construction and maintenance, temporarily close to
through traffic or to all vehicular traffic any highway or portion
thereof for a period not to exceed a specified number of work days
for project completion and shall, in conjunction with any such road
closure establish appropriate detours or provide for an alternative
routing of the traffic affected...", and
WHEREAS, on the 5th day of June, 2023, pursuant to said statute and upon the basis of
traffic and personnel investigations, the Board determined that conditions exist which made it
necessary to temporarily close County Road 44, between County Road 33 and U.S. Highway 85,
to through traffic and to regulate, warn and guide vehicular traffic by posting signs thereon, with
said closure being effective June 12, 2023, for approximately two (2) weeks, through June 26,
2023, for roadway and intersection improvements, and
WHEREAS, on the 26th day of June, 2023, pursuant to said statute and upon the basis
of traffic and personnel investigations, the Board has determined that conditions exist which make
it necessary to extend said temporary closure of County Road 44, between County Road 33 and
U.S. Highway 85, with said extended closure being effective June 26, 2023, for approximately an
additional two (2) weeks through July 10, 2023, for unanticipated delays due to inclement weather,
and further, that standard official traffic control devices shall be erected at said closure giving
notice of the restrictions.
NOW, THEREFORE, BE IT RESOLVED that the Board of County Commissioners of Weld
County, Colorado, deems it necessary to regulate, warn and guide vehicular traffic on County
roads and any intersections thereof, and it hereby authorizes and orders the posting of such traffic
control devices as shall be reasonably necessary to regulate, warn and/or guide traffic thereon
for the safety of the general public and that said traffic control devices shall conform to the Federal
Manual on Uniform Traffic Control Devices.
cc: So (1,..s1,-.• spo ta., CS P
06/30/23
2023-1789
EG0024
EXTEND TEMPORARY CLOSURE - COUNTY ROAD 44
PAGE 2
BE IT FURTHER RESOLVED that the Board of County Commissioners of Weld County,
Colorado, does declare and establish that the closure of County Road 44, between County
Road 33 and U.S. Highway 85, be, and hereby is, extended, with said extended closure being
effective June 26, 2023, for approximately an additional two (2) weeks through July 10, 2023, for
unanticipated delays due to inclement weather, and further, that standard official traffic control
devices shall be erected at said closure giving notice of the restrictions.
The above and foregoing Resolution was, on motion duly made and seconded, adopted
by the following vote on the 26th day of June, A.D., 2023.
BOARD OF COUNTY COMMISSIONERS
WELD COUNTY, COLORADO
ATTEST:d i) f�',�A:�,� EXCUSED
Mik-___ eman, Chair
Weld County Clerk to the Board
BY:
AP
eputy Clerk to the Board
ounty Attorney
Date of signature: OCalon1(`01
Per L. B r k, Pro-Tem
Sc•tt K. James
Lori Saine
2023-1789
EG0024
MEMORANDUM
TO: Clerk to the Board DATE: June 22, 2023
FROM: Amy Mutchie, Public Works Department
SUBJECT: BOCC Agenda Item
Jalisco International Inc. is requesting permission to extend the closure of CR 44 between CR 33 and US
85 from 6/26/23 through 7/10/23 for roadway and intersection improvements for CDOT flyover project.
Completion was delayed due to weather.
Original closure date approved on 5/31/23 was for 6/12/23 through 6/26/23.
See attached closure diagram.
2023-1789
2Gooa9
www.invarion.com
,(C
ARDENT
TRAFFIC SERVICES. INC
in
LOSE
I ` ' rAre
I;
// /� 1,
/ ,//
/ '/ / /
CLI
F]
LIE rOUR alC3fiRiv
DETOUR
t
rSStF4
MPH
30
35
TYPE
URBAN
LOW
URBAN
LOW
FRWse
WIDTH
12'
t.2
'7'
MERGING
TAPER
130'
245'
560'
SHIFTING
TAPER
90'
123'
3 ii I
SHOULDR
TAPER
60'
82
220'
DEV SPC
TAPER
30'
35
55'
OEV SPC
TANGENT
60'
70
110'
SIGN
SPACING
100'
100'
500'
NOT DRAWN TO SCALE
MHT NO.
DESCRIPTION
Ardent No
Designed by:
Project:
Project No.:
031
CR 44 TEMP
CLOSURE
2021-012
Antonio
Ledezma, TCS
US 85 & Peckham
Grade Separation
NI -ARE' 0853-107
(21006)
Proj Owner: COOT
Prime: Jalisco Intl Inc.
COMMENTS
This MHT Shows the work are for the TEMP CR 44 Closure.
"•Flaggers my be moved or removed depending on the work as
approved by the engineer.
This MHT is based on latest version of the MUTCD TA 20 & 25
.. This MHT should be used with MHT 001. MHT 008
This MHT may be used with MHT's for this project
•• All signs and devices used to meet the requirements of NCHRP
350
" The closure may be moved. lengthened or shortened depending on
the work as approved by the engineer or designee.
Any conflicting Signs will be covered or removed
Work Hours:
Work Hours
Mon - Fri 7am - Sprn. other hours as
approved by the PM
Lane closures
Single Lane lam- Spin
Other Hours as Approved by the PM
Flagging
7a - Som. Other hours 36 approved by
the PM
Legend
[Jr {
Vizor. Anew
Manifest
1
9 x Cone
4 x Barrel
2 x M4-9 detour (RI
1 x M4-1DL Detour Left
1 x M4-9 Detour Straight
1 x R3-1 no right turn
1 x W20-3 road dosed ahead
5 x Type Ill Barricade
2x M4-9 detour (L)
2x R11-2 road dosed R11-2
lx M4 -10R Detour Right
lx R11-4 R11-4
1 x W20-2 detour ahead
COMPANY
NAME
TITLE
SIGNATURE
PREPARED BY
ARDENT TRAFFIC SERVICES
Antonio D. Ledezma
Pres / TCS
APPROVED BY
Ryan Idler
Peter Kubiak
Hello