On July 28, 2023, the Air Pollution Control Division will begin a 30 -day public notice period for Noble
Energy, Inc. - STOCKLEY T4N-R64W-S15 L01. A copy of this public notice is enclosed.
Thank you for assisting the Division by posting a copy of this notice in your office. A public copy of
this notice is required by Colorado Air Quality Control Commission regulations. The notice must be
available for public inspection for a period of thirty (30) days from the beginning of the public notice
period. Please reference the public notice for instructions on submitting comments.
4300 Cherry Creek Drive S., Denver, CO 80246-1530 P 303-692-2000 www.colorado.gov/cdphe
Jared Polls, Governor I Jill Hunsaker Ryan, MPH, Executive Director
L4,O
I LIL0Z3
r✓ : r?L('i t M.4), 1-4 t.C35(LL),
Tuu C .Izi / e.K 11).r I r t4) D(() +,4)
131120Z-3
2023-2195
CMl74M
41'---0 Notice of a Proposed Project or Activity Warranting Public
Comment
Air Pollution Control Division
Website Title: Noble Energy, Inc. - STOCKLEY T4N-R64W-S15 L01 - Weld County
Notice Period Begins: July 28, 2023
Notice is hereby given that an application for a proposed project or activity has been submitted to the
Colorado Air Pollution Control Division for the following source of air pollution:
Applicant: Noble Energy, Inc.
Facility: STOCKLEY T4N-R64W-S15 L01
Well Production Facility
SWSW quadrant of Section 15, Township 4N, Range 64W
Weld County
The proposed project or activity is as follows: Noble is requesting to combine points 123-9685-001, 123-
5273-001, and 123-9686-001 into one point (123-9685-001) and cancel the other 2 points upon issuance of
this permit. Point 123-9685-001 was previously covered under a GP01, and they are requesting to change
coverage to a traditional construction permit. The request also includes a decrease in the combined
permitted throughput, and a change to state default emission factors. The facility is in the severe ozone
nonattainment area and is synthetic minor for VOC NANSR, PSD, and OP programs
The Division has determined that this permitting action is subject to public comment per Colorado
Regulation No. 3, Part B, Section III.C due to the following reason(s):
• the source is requesting a federally enforceable limit on the potential to emit in order to avoid other
requirements
The Division has made a preliminary determination of approval of the application.
A copy of the application, the Division's analysis, and a draft of Construction Permit 23WE0292 are available
on the Division's website at https://www.colorado.gov/cdphe/air-permit-public-notices
The Division hereby solicits submission of public comment from any interested person concerning the ability
of the proposed project or activity to comply with the applicable standards and regulations of the
Commission. The Division will receive and consider written public comments for thirty calendar days after
the date of this Notice. Comments may be submitted using the following options:
Use the web form at https://www.colorado.gov/cdphe/air-permit-public-notices. This page also
includes guidance for public participation
Send an email to cdphe_apcd_airpermitcomments®state.co.us
Send written comments to our mailing address:
Air Pollution Control Division - Oil Et Gas Unit
Colorado Department of Public Health and Environment
4300 Cherry Creek Drive South, APCD-SS-B1
Denver, Colorado 80246-1530
2.02 1 I a
COLORADO
DapaxtmentafPublie
Health 6 :;„11 nmext
NOTE: Comments submitted to the division will be uploaded to an online document repository and will be
accessible to the public. Your comments and the division's responses are not considered confidential and will
be publicly accessible, including your name and any other personal information you provide in your
comments.
2.02 2 Is
COLORADO
Department of Public
Health b Envtronment
Hello