HomeMy WebLinkAbout20232241.tiffRESOLUTION RE: APPROVE NON-REFUNDABLE QUOTE LETTER FOR RELOCATION OF HIGH PRESSURE GAS PIPELINE METER STATION FOR COUNTY ROAD 41 AND STATE HIGHWAY 52 INTERSECTION PROJECT AND AUTHORIZE CHAIR TO SIGN - XCEL ENERGY WHEREAS, the Board of County Commissioners of Weld County, Colorado, pursuant to Colorado statute and the Weld County Home Rule Charter, is vested with the authority of administering the affairs of Weld County, Colorado, and WHEREAS, the Board has been presented with a Non -Refundable Quote Letter for the Relocation of a High Pressure Gas Pipeline Meter Station for the County Road 41 and State Highway 52 Intersection Project between the County of Weld, State of Colorado, by and through the Board of County Commissioners of Weld County, on behalf of the Department of Public Works, and Xcel Energy, with further terms and conditions being as stated in said quote letter, and WHEREAS, after review, the Board deems it advisable to approve said quote letter, a copy of which is attached hereto and incorporated herein by reference. NOW, THEREFORE, BE IT RESOLVED by the Board of County Commissioners of Weld County, Colorado, that the Non -Refundable Quote Letter for the Relocation of a High Pressure Gas Pipeline Meter Station for the County Road 41 and State Highway 52 Intersection Project between the County of Weld, State of Colorado, by and through the Board of County Commissioners of Weld County, on behalf of the Department of Public Works, and Xcel Energy, be, and hereby is, approved. BE IT FURTHER RESOLVED by the Board that the Chair be, and hereby is, authorized to sign said quote letter. The above and foregoing Resolution was, on motion duly made and seconded, adopted by the following vote on the 2nd day of August, A.D., 2023. BOARD OF COUNTY COMMISSIONERS WELD COUNTY, COLORADO ATTEST: d„,,A4A)C� JClto•(4, Weld County Clerk to the Board BY: eputy Clerk to the Boar APPROVED AS TO FOR A • -County Attorney Date of signature: O$/Io/23 cc:PW(CH/ER/DD) OS/3(/23 40, rts man, Chair i!l P • erry/' B; ck, Pro-Tem Scot K. James 7 evin D. Ross 257,4.A. Lori Saine 2023-2241 EG0081 Cri-vxc iz4 I BOARD OF COUNTY COMMISSIONERS PASS -AROUND REVIEW PASS -AROUND TITLE: WCR 41 / SH 52 Intersection Project Xcel Energy High Pressure Gas Relocation Non-refundable Quote Letter DEPARTMENT: Public Works DATE: 7/5/23 PERSON REQUESTING: Don Dunker, and Cutis Hall Brief description of the problem/issue: WCR 41 / SH 52 Intersection Project will install a left turn lane on the WCR 41 north and south legs of the intersection. Wider shoulders and larger radii at the corners will also be installed. The intersection design was shifted to the east to avoid a house at the SW corner and a Western Midstream 20" process waterline, 8" gas line and 12" gas line next to the existing west ROW line. As a result, the shift to the east requires an Xcel Energy High Pressure Gas metering station at the NE corner to be relocated from its current location further east. Xcel Energy has provided staff with a cost estimate of $1,658,490.40 to do this relocation. The cost of acquiring ROW, easements for the process waterline and gas lines on the west side of the existing road is expected to cost more than $1.7 million. Xcel has also indicated in the email that the non -refund letter needs to be signed by the County to agree to this amount. The 2023 budget to do this relocation is currently at $1,100,000 which indicates an additional $558,490.40 would be required if the BOCC agrees to the relocation cost. This project has a CDOT/CMAQ grant for $953,445. What options exist for the Board? (Include consequences, impacts, costs, etc. of options): Option 1: The Board may choose to recommend approval of the Xcel Energy relocation cost and sign the letter. Option 2: The Board may choose to request Public Works staff to schedule a work session to discuss the issue. Recommendation: To keep the project moving forward and on schedule, Staff recommends the BOCC approve option 1 above which is to approve the Xcel relocation cost of $1,658,490.40 and sign the letter. Perry L. Buck, Pro -Tern Mike Freeman, Chair Scott K. James Kevin D. Ross Lori Saine 3/2, Approve Schedule Rec,pounendation Work Session 4917136 Pages: 2 of 4 08/24/2023 12:22 PM R Fee:$0.00 Carly Koppes, Clerk and Recorder, Weld County , CO uIII MittUPI JAM IiiiMari Dlf II Other/Comments: 2023-2241 E oO I Xce/Energy June 16, 2023 Don Dunker County Engineer 1 150 O St. Greeley, CO 80631 Subject: Request For High Pressure Gas relocation at 40.080794', -104.678150°, Hudson, Colorado Dear Don Dunker, I have completed the engineering design and cost estimate to provide High Pressure Gas relocation based upon information you have provided. This design is based upon High Pressure Gas relocation, as shown on the enclosed drawing. The cost to provide the requested High Pressure Gas relocation is $1,658,491.00, which is non-refundable. If the Applicant elects to have the Company advance the Construction Payment for the duration of the construction period, Applicant will be billed by the Company in accordance with the Company's tariffs, within 30 days after the construction of the Extension is complete. The Applicant shall pay the Company within ninety (90) days after the Construction Completion date. This proposal is contingent upon the following: • Alt work performed during our normal work hours. • Obtaining "Right -of -Way" at no cost to us. • Obtaining permits as needed. • No frost, in the ground, during construction or agreeing to pay for additional costs during frost conditions. • There is an additional charge to open the transformer. • Providing final grade elevations, at our equipment locations. • Grade at trench location to be within 6 inches of the final grade. If necessary our right-of-way agent will mail the right-of-way or easement documents to the appropriate landowners for their signature. This proposal is contingent upon receiving easements at no cost to us. Our right-of-way agent will need a copy of the Warranty Deed, the legal description, and the site drawing in order to prepare the easement for the landowner's signature. NOTE: You must personally contact the local telephone company, the local cable TV company and/or any other utility company to arrange for the installation and payment of any costs of their facilities if they need to be relocated or disconnected along with the relocation. If you accept the above costs and system design, please sign and date the second page of this letter and return this document to Public Service Company of Colorado, at the address shown below. After the signed and dated documents are received, a work order will be issued and Revision January 28, 2022 Non-refundable Quote Letter PA 4917136 Pages: 3 of 4 08/24/2023 12:22 PM R Fee:$0.00 Carly III IYU��IIGiJT N Clerk and Recorder, !'ihi4 4� �' J�I� 6411111 a oar -02,2 I released so your project can be placed on the construction schedule. When payment is due if a check is sent via the new payment process we are unable to accept checks with any sort of Lien Waiver because our Tariffs do not make an allowance for PSCo to accept checks printed or stamped with a lien waiver. Our current lead-time to begin work after receiving the signed documents is approximately 24 weeks. You will be notified of the week that our construction is scheduled to begin as soon as it is available. This proposal will be valid until July 07, 2023. If you have any questions regarding this project, please call me at (970)690-9080. Sincerely, Delaney Morgan Gas Engineering HP Mailing address: 1 123 W 3rd Ave Denver, CO 80223 Name: Timothy O'Connor Title: EVP, Chief Operation Officer Re: High Pressure Gas, relocation, 40.080794°, -104.678150° I have reviewed and approve of the enclosed design. I accept the cost of $1,658,491.00 and this amount will be paid to Xcel Energy within 90 days of the construction completion date. The Construction Cost stated above does not include special items such as but not limited to frost or rock conditions. In the event the Company encounters any special items during construction, the Company shall bill Applicant for such special items as a non-refundable contribution in aid of construction. I will send a signed copy of this letter with the applicable agreements. Date: AUG 0 2 2023 *Customer Signature: Mike Freeman, Chair Title: Board of Weld County Commissioners Mailing address: 1150 "0" Street Greeley, CO 80631 * Confidential Information Revision January 28, 2022 Non-refundable Quote Letter PA 4917136 Pages: 4 of 4 08/24/2023 12:22 PM R Fee:$0.00 Carly Koppes, Clerk and Recorder, Weld County , CO VIII fFJIRILdal4TIPAMJIM 0 MPhil '111.1.'444k 11 III 2 .92%1,3 —a 2 LA/ From: To: Cc: Subject: Date: Attachments: Morgan, De anev N port Dunker Cinde Wright RE: WCR 41 & HWY 52 (GH-3 Relocation Thursday, June 22, 2023 1:07:17 PM jmage001,png ( ution : This email originated from outside of Weld County Government. Do not click links or open attachments unless you recognize the sender and know the content is safe. Hi Don, Unfortunately after speaking with upper management, this is as detailed of a breakdown as we can go. We are replacing like for like on this station, and any upgrading will come at Xcel Energy's cost. Best Regards, Delaney Morgan Xcel Energy Staff Gas Pipeline Engineer, Gas Transmission Engineering 1123 W. 3rd Ave Denver, CO 8O223 (97O)69O-9O8O From: Don Dunker <ddunker@weld.gov> Sent: Wednesday, June 21, 2023 10:50 AM To: Morgan, Delaney N <Delaney.N.Morgan@xcelenergy.com> Cc: Cinde Wright <cwright@weld.gov> Subject: RE: WCR 41 & HWY 52 (GH-3 Relocation EXTERNAL - STOP & THINK before opening links and attachments. Do you have a break down for each main category shown below? This is the information my Board of County Commissioner will want to see. Thanks, Don From: Morgan, Delaney N <Delaney.N,Morganc xcelernergy.corn> Sent: Wednesday, June 21, 2023 10:21 AM To: Don Dunker <ddunkerTweld.gov> Cc: Cinde Wright <cwr'ghtweld.gov> Subject: RE: WCR 41 & HWY 52 (GH-3 Relocation Caution: This email originated from outside of Weld County Government. Do not click links or open attachments unless you recognize the sender and know the content is safe. Good morning, Below is a breakdown based on Ancillary, Engineering, and construction of each component of this relocation as well as material cost. Let me know if you need any additional information. Ancillary Support Services $ 353,284.01 Project Management & Planning $ 353,284.01 Engineering Services $ 152,131.85 Design & Constructability Support $ 152,131.85 Construction Services $1,153,074.55 Materials $ 305,087.48 Removal Building, (Exisitng Fencing) T -G, Meter Set, $ 85,000.00 T -O Valve & HP line Relocaion $ 161,394.42 Meter Building, Station Fence Install Gravel, (Meter Set, Acess Road $ 601,592.65 Total Cost $ 1,6580490.40 Best Regards, Delaney Morgan Xcel Energy Staff Gas Pipeline Engineer, Gas Transmission Engineering 1123 W. 3rd Ave Denver, CO 80223 (970)690-9080 From: Don Dunker <ddunk! weld.gov, Sent: Wednesday, June 21, 2023 9:50 AM To: Morgan, Delaney N <Delaney,N.Morganaxcelenergy.com> Cc: Cinde Wright <cwright(cOweld.gov> Subject: RE: WCR 41 & HWY 52 (GH-3 Relocation i _ EXTERNAL - STOP & THINK before opening links and attachments Hi Delaney, I need the backup data as to how you derived at the $1.658M. It needs to show Weld is only paying for like for like or 4" gas line for a 4" gas line. Please let me know if you have questions. Thanks, Don Dunker, P.E. Weld County, County Engineer From: Morgan, Delaney N <Delaney.N.Morgar•Cbxcefenefgy.cotn> Sent: Tuesday, June 20, 2023 8:20 AM To: Don Dunker <ddunkerPwe d.gov> Subject: WCR 41 & HWY 52 (GH-3 Relocation This email originated from outside of Weld County Government. Do not click links or open attachments unless you recognize the sender and know the content is safe. Good Afternoon, Attached is the non -refund letter requiring your signature. Let me know if you need any additional information. Delaney Morgan Xcel Energy Staff Gas Pipeline Engineer, Gas Transmission Engineering 1123 w 3rd Ave Denver, Co 80223 (970)690-9080 reern: droller Wr er < .y ; r,.; ,y,_ . ;_y_11> Sent. Monday, April 25, 2012 3'25 PM Tot 8Cl-Co <.. cv.t..• Cis Morn. Ka My <1.t.a-=S,:-,Y►Lt.Ctett.SC :.s: Don Ou tart <3!a'.a:.ior :astns feats Martian ca Subjoelt FW' WCA 41 and State Highway 52 Intersection LXf (NNA1, 'rum .4 1)f •rK t•." s '. I a, last *ecerrater we put in a request for Info/melon regard kit a valve suUon at the NE corner of lwy 52 and WCR 4 I n Weld County- We did not receive any Information at thst tnse, however we decided to proceed as if we could more the Writ natant to IM n M We are now moving forward vnth the design of the Intersection and would file to touch base With you on the protect r ne protect is going to to decried by in roust County staff this war, with `tOW and Jetity re+uubun occurring in 2O23 Please let us know who our print of contact is for the protect. If we cou d get a rough cost estimate and scope of wort( involved with retocaturg the station, we would appreciate 4 Thank you Grids Prom Croat Wright $inti Tuesday. December Al. 2021 12:US PM Tot as. csatat r't'Ct:tt WOW,: WCR 41 and State Highway 52 Morsection Please see the attached request ktr info rotation regarding a valve station in the NE corner of the intersection Thank yrxi I Devon FnQlneer (PE) t,S%tl %'rte P*j %.t •1. Grotty. CC 40631 (Mt 400.3719 - owe 19701342-9549 - cad Wa Conn den deity Notke: this electronic transmission .md any ittacerd documents or other writings are Intended only forth" person or entity to Mich It is addressed and may contain information that is privileged, confidential or otherwise protected from d:sciasure If you have received this cornmwdcathy in error. please lelrnedtetety notify strider by return e-mail and destroy she communication Any disclosure, copying, dlianbution or the taking of any action concerning the con ttnts of this torimunkatkin or any attachments by anyone other than the named rnoplent is stric+Jyrenhi it.d CaleSalny,.` 1W tr�ada►at A rtv: MO la and San Mglawy Si halt e.er tiare.utar, ILS..L t I t, atn)1:e t:0 ara Imp flu's tail rsamtS wi rem 'owl burn 7trrt ►har'1t Onde From: Hill, Rnhert M<Rnhrrt IU it:Ilfj@Xee'{.rr•rgycoin> Sant: Monday, lune 27, 20210:53AM to: Cinde Wright . cwrighttOweldgov come Cs: Don Dunker <ddunker@weldgov.com>; TraceAnderson <tarderxin@weldgov corn pi; Ifolder, Andrew P <Andrew P He der)xccienergy corn) Sublet[: RE. WCR 41 and State Highway 52 intersection Mr awlwiplat ee1ear•.al.e,itia11e..ag/iar 'flOlt rtciillriovi.}nn3.ies boa ir alias JIM Ilk m.yt'rcIto torkrAN! MoWl,Mc.elIn+riah Mande. I was honing to get something to you much sooner I rn refining our estimate, but we're tooting at between 5500t to 5800k to reitxe:e our statiun and piping within tx.ir sire That doesn't include land acquisition We have a federal rule that requires us to have uui erneiger:cy isuIati xa valves at east 15ft from the buildirig, so although we can nxot the pining anti pat up wane bollards fairly easily, we would ultimately have to move the entire regutalo•/mater station further to the east as well This is also a transfer panic between Xcer and Atmos so thel/tl need to reconligure their piping un the north side. of Me site ell get you a hetler Oclimate by the and of the week hut hopefully this belts let me know if you hap any Questions Thanks. Rob HII P E PMP *oaf Energy I Naaponalble By Nature Sr On Transmission Engineer, HPGE 1123 Wee 3rd Ave , Denver, CO 80223 P 303-571.338 C: 830.89D-9049 tcr331 f sf act Ja ccca From: Cinde Wright< 1phtts dagia.tct> Sant: Wednesday, April 7'/, 101217:31 PM To: Hill, Robert M <kcircii 1! t • • ot.ce,r.r.c aDSs2' Cc: purr Dunker <Ijt:,,tikcl('eetektzc', imp: Trace Anuerson <lca"; a'. kas' er c_r•> Sublaci: R): OCR 4 t and State Highway 52 Intersection You Oral ale pa teal Da • snag a ■ 44sn, irio Irootsbassetteel LXTtW4AL t tIO'iflG •rs clerir•f roc• •irn3..la n;• fl3/4100 Sorry IN; is confusing COOT has a project that is mstaiing the traffic signal lights at the Intersection (this year) Wetd county Is designing a separate protect to add felt turning lanes on both legs of WfR 41 Our project is starting the Jesigtt this year with ROW being purchased and utility relocations to he done in 2023, and roadway ccnstrt'ction :n 2024 I think the correspondence that you forwarded to us was regarding the COOT protect We have been conrd:nal.ng with COOT on the traffic light locations so that we don't have to r2loCate them when our proiectgocs in As your email stated with the C001 protect. they are ,yorking within the existing ROW for the traffic pale locations and the Xcel gas valve station isn't affected by their protect The County's roadway widening protect will affect the gas valve station because we decided to push the roadway to the east (there is an enstirg residence and large gas I nes to the wrst of the intersection we nerd to avoid) I've attached a drawing showing our preliminary layout and you can see how the Xccl valve station is affected Wald you lot tit know whit the implications would he to move the fac.lity to the east approximately 20' 30'? Could ,ere get an approximate cost at relocating the facility? From what I have laid out for the intersection, the building and valves west of the 'structure would be most affected As the design progresses, we can provide more detailed drawings thank ycul Cinde D ,err ■ ? s's)c ". V , cixoft v., >t * 4- ` C a ynrynsm•.-up:nsac,ecet•• )tkUItlarS,Snows•:tAranirnAt•i'r'e.iseSO•r•FGt•tos..-,:*ta,wv..y.eann er.,••rwp•u.w.a".**•tellb• .ksna.wuswa,'••1Ra4Nstialas tug of r • be it :s a ueN 1.i -•,r. -••.,. t 13 w`>wCa. — w -raw.." a-...\rwr . • ...v ' .t r. •� .I >Y - a• • tw, age -ego (, ta• • ',aat I►sv\ •r• aeons ti t9• a it • m * . i :a. w.-st. a gassy is 1.••• r,w (awn r,.,, r 9 .N.:.•:.14 ... • • • + a gco a'd•• •- s: • Cl •.I) !A:. .; '.••Sit ' :3:b.n111 iv 'r•••rt al(O1 P1r1•r 4 &M;3:*;s .is7a�e1'a? ►i' - -%I •e .2.- "4.. 'bar. 1••.%V'r•' . • . • • • a • • • • •••. . ' • . , • ' 1 .• •'t ' • . . 1 r • • ' 1 I Air \ , . 1 • 1// • •• r I 1 . • • • • +♦ I ••• ir . . 1 • •r• • • • ••' • • • 4• - . . • . • I 3 • 'e r♦ • •w. ••r ' • : • 4,11.1 • . • • .•• • • • Q a 1. • ...071 11.14,41 14V Fiero: Itiit, Robert M <1,•y0 •1• S tatuttr.:rDS' Sant Wert rwcday, April 71, It12A tkAO AM Ts: Pnr:rasdoretots<t7/1aa.fry- titALCUCautibt Horn, Kelly <ItilttbL:`:is:t.t:.11di-CYi: >" Conde Wright <cHrrtbht1 at djw u r eon DaA n: ti•wo: ,c stC%_uttsCC'), Tact ta+fen o <I.Rjc'avtaart ►'r Len Cc:O'Shea, Mrdlael K < MicaujjActili i r-tr fl, A+>- Ward, April 1 c*t.0 r "':a tiy. tclr-yacc.; Welch. Mark E c vas r MN. r warp •true Iubjeet: RE• WCR 41 and State H,ghway52 Intersection Cwear MbmsdongwrwFite 3+biborWelilCwntyGureemsat Iheeld/citladscrevcw.uatl-talsiwla•1rnrecevieaSe1a4oandLaee:►eua4aua;she was informed Xcel didn't need to perform this review arymore by your engtneerins consultant (see Die attached e mail) Will rh•s need to be re..ewed again? Ihank,, 'lob N►:.P Jtcsa Enarpy I ResDoesINe Sy fWlute Sr. 3as irencmisslon Engineer, HPGE 1173 Wes 3rd Ave . Owner, CO. 80223 P 303.371-3346 C: 630-89O-904$ i:Atsl Li:• Clitartsltrr..Ora_ Fromr Err'oactunents < agagt • • tt ,v • ) Sat Tuesday, April 26, 20222:38 PM To: Horn, Kelty<I•t..a:.L::s2latv'.Ciitssr;Ctnde Wright < rc, EhiliCyabir,Qu11rr Don Dunker<•tiunAv' Alyce:rigur,cratt : Likmittil6Cetlataillahrj, Hitt. Robert 1Ae ft:L +,yp rligsit+rf-re, v Cc(flned.MichaelK<4ts.'rr't3Stiestntrrilserer•.Ward.Agr4J<AeaiOn'Qwrrare.Le tWelch,Mark F<VIES. t ►YrdH.lnettnp :>• Subset* RE' WCR 41 and State kkthwey 51 intersection Hello Ihis encroachment 4546 was assigned to Rob i tiff an Jan 4. 1O22. i sent the rn:tiel intake emit, to cw.r;ht@wetdkmr curt an that same day Y": s ; - world yrxo please tollaw up with Conde' Thant yarn, Kseta Aoffnisyst Kee Energy 1 Rnpon [sole 8y Nalurs tier Otnttieu Irian; sp.Welal 1123 W 3'd Ave Denver. CO 60223 P: (103) 5714313 C: Aai2atistlnslniltataWastern Fromm Horn. Kelly <ttlair irlttrn tr> Sat: Tuesday, April 26, 2072 A:15 AM Tar uncle Wright <; wrlgnrnigringer' cc,;._ • Don lbrnker <;+yjynrlpr yyg)ttltg'LL;tlnfr; trdr tiete'tu gem Cc O'Shea, Michael K<'!!I'tl`.trs:7k^tAstten •tit* s.v• ►ialtitte ee. ItICIA • tlett2atteitilit6C:L-CilLiferna. Ward. April 1 <lluy„Q vtSogftraj cn>; Welch, Mark r <Mrs,Letigstt ititt{aettill +,i Subfest: RI: WCR 41 and State Highway 52 intersection Good morning Cinch', As 1 stated in December 2021 I am not *e contact nor am quati!ied to assist you with your CDO- protect to relocate the high pressure gat gencml:soon lines At that time I was told to refer you to Mike O'Shea the Manager of Gas Transmission Engineering department I have cc's nfrtt Mod I am forwarding you, coned with your attached application and site print to him Please teach ott to him !or assistance on your project Thank you, kany Horn xcel thargy P+anner Dully S La/out Engrnemry 1460 W ft A6ti Aryeda.(O.80003 Pr 363.425 1966 Cat JO) 356-8670 1 ttisha !S*t*'S'aU4L., Houstan Aragon From: Sent: To: Cc: Subject: Don Dunker Friday, July 28, 2023 9:37 AM Houstan Aragon Curtis Hall Fwd: WCR 41 & HWY 52 (GH-3 Relocation Houstan, Here is the response from Xcel gas see below. It is okay to sign the non refundable quote etter. Let me know if you have more questions. Thanks, Don Sent from my iPhone Begin forwarded message: From: "Morgan, Delaney N" <Delaney.N.Morgan@xcelenergy.com> Date: July 28, 2023 at 7:15:19 AM MDT To: Don Dunker <ddunker@weld.gov> Cc: Cinde Wright <cwright@weld.gov>, Curtis Hall <chall@weld.gov> Subject: RE: WCR 41 & HWY 52 (GH-3 Relocation Caution. This email originated from outside of Weld County Government. Do not click links or open attachments unless you recognize tl sender and know the content is safe. Hi Don, This letter should be still good to sign. Thanks, Delaney Morgan Xcel Energy Stan Gas Pipeline Engineer, Gas Transmission Engineering 1123 W. 3rd Ave Denver, CO 80223 (970)690-9080 From: Don Dunker <ddunker@weld.gov> Sent: Thursday, July 27, 2023 4:46 PM To: Morgan, Delaney N <Delaney.N.Morgan@xcelenergy.com> Cc: Cinde Wright <cwright@weld.gov>; Curtis Hall <chall@weld.gov> Subject: RE: WCR 41 & HWY 52 (GH-3 Relocation EXTERNAL - STOP & THINK before opening links and attachments. Delaney, The non-refundable quote letter you sent to get signed says it is only good through 07/07/23 and must be signed before that date. I am just now able to get it on the Board of County Commissioner agenda are we still okay to sign it? The Clerk to the Board is asking the question they process all agendas and need to know asap. Thanks, Don Dunker, P.E. Weld County, County Engnieer From: Morgan, Delaney N <Delaney.N.Morgan@xcelenergy.com> Sent: Thursday, June 22, 2023 1:07 PM To: Don Dunker <ddunker@weld.gov> Cc: Cinde Wright <cwright@weld.gov> Subject: RE: WCR 41 & HWY 52 (GH-3 Relocation Caution: This email originated from outside of Weld County Government. Do not click links or open attachments unless you recognize tl sender and know the content is safe. Hi Don, Unfortunately after speaking with upper management, this is as detailed of a breakdown as we can go. We are replacing like for like on this station, and any upgrading will come at Xcel Energy's cost. Best Regards, Delaney Morgan Xcel Energy Staff Gas Pipeline Engineer, Gas Transmission Engineering 1123 W. 3rd Ave Denver, CO 80223 (970)690-9080 From: Don Dunker <ddunker@weld.gov> Sent: Wednesday, June 21, 2023 10:50 AM To: Morgan, Delaney N <Delaney.N.Morgan@xcelenergy.com> Cc: Cinde Wright <cwright@weld.gov> Subject: RE: WCR 41 & HWY 52 (GH-3 Relocation EXTERNAL - STOP & THINK before opening links and attachments. Do you have a break down for each main category shown below? This is the information my Board of County Commissioner will want to see. Thanks, Don From: Morgan, Delaney N <Delaney.N.Morgan@xcelenergy.com> Sent: Wednesday, June 21, 2023 10:21 AM To: Don Dunker <ddunker@weld.gov> Cc: Cinde Wright <cwright@weld.gov> Subject: RE: WCR 41 & HWY 52 (GH-3 Relocation Caution: This email originated from outside of Weld County Government. Do not click links or open attachments unless you recognize tl sender and know the content is safe. Good morning, Below is a breakdown based on Ancillary, Engineering, and construction of each component of this relocation as well as material cost. Let me know if you need any additional information. Ancillary Support Services $ 353,284.01 Project Management & Planning $ 353,284.01 Engineering Services $ 152,131.85 Design & Constructability Support $ 152,131.85 Construction Services $ 1,153,074.55 Materials $ 305,087.48 Removal T-O, Meter Set, Building, (Exisitng Fencing) $ 85,000.00 Valve & HP Line Relocaion $ 161,394.42 1-0 Meter Station Install (Meter Set, $ 601,592.65 Building, Fence,Gravel, Acess Road) Total Cost $ 1,658,490.40 Best Regards, Delaney Morgan Xcel Energy Staff Gas Pipeline Engineer, Gas Transmission Engineering 1123 W. 3rd Ave Denver, CO 80223 (970)690-9080 From: Don Dunker <ddunker@weld.gov> Sent: Wednesday, June 21, 2023 9:50 AM To: Morgan, Delaney N <Delaney.N.Morgan@xcelenergy.com> Cc: Cinde Wright <cwright@weld.gov> Subject: RE: WCR 41 & HWY 52 (GH-3 Relocation EXTERNAL - STOP & THINK before opening links and attachments. Hi Delaney, I need the backup data as to how you derived at the $1.658M. It needs to show Weld is only paying for like for like or 4" gas line for a 4" gas line. Please let me know if you have questions. Thanks, Don Dunker, P.E. Weld County, County Engineer From: Morgan, Delaney N <Delaney.N.Morgan@xcelenergy.com> Sent: Tuesday, June 20, 2023 8:20 AM To: Don Dunker <ddunker@weld.g.ov> Subject: WCR 41 & HWY 52 (GH-3 Relocation Caution: This email originated from outside of Weld County Government. Do not click links or open attachments unless you recognize tl sender and know the content is safe. Good Afternoon, Attached is the non -refund letter requiring your signature. Let me know if you need any additional information. Delaney Morgan Xcel Energy Staff Gas Pipeline Engineer, Gas Transmission Engineering 1123 W. 3' I Ave Denver, CO 80223 (970)690-9080 Contract Form New Contract Request Entity Information. Entity Name. XCEL ENERGY Entity ID* O00000400 Contract Name. Contract ID WCR 41 , SH 52 INTERSECTION PROJECT XCEL ENERGY HIGH 7241 PRESSURE GAS RELOCATION NON-REFUNDABLE QUOTE LETTER Contract Lead. DRUNKER Contract Status CTB REVIEW ❑ New Entity? Contract Lead Email ddunkerOco.weld.co.us Parent Contract ID Requires Board YES Department Project GR-59 Contract Description" XCEL ENERGY HAS PROVIDED STAFF WITH A COST ESTIMATE OF $1,658,490.40 TO RELOCATE THIS METERING STATION OUT OF THE WAY FOR OUR WCR 41 AND SH 52 INTERSECTION PROJECT, THIS QUOTE LETTER IS A NON-REFUNDABLE LETTER WHICH NEEDS SIGNED BY THE BOCC. Contract Description 2 Contract Type AMENDMENT Amount. 51,658,490.40 Renewable. NO Automatic Renewal NO Grant IGA Department PUBLIC WORKS Department Email CM- PublicWorks?nweldgay.corn Department Head Email CM-PublicWorks- DeptHeadNweldgov,com County Attorney GENERAL COUNTY ATTORNEY EMAIL County Attorney Email CM - C OU NTYATTOR N EY@WELDG O1/.COM Requested BOCC Agenda Date 07, 26,+2023 Due Date 07:22;2023 Will a work session with BOCC be required?* NO Does Contract require Purchasing Dept. to be included? YES Bid/RFP#* GR-60 tf this is a renewal enter previous Contract ID If this is part of a MSA enter MSA Contract ID Note: the Previous Contract Number and Master Services Agreement Number should be left blank if those contracts are not in OnBase Contract Dates Effective Date Review Date. 0711 5,2024 Renewal Date Termination Notice Period Contact Information Committed Delivery Date Expiration Date* 07/17,2023 Contact Info Contact Name Contact Type Contact Email Contact Phone lI Contact Phone 2 Purchasing Purchasing Approver CHERYL PATTELLI Approval Process Department Head Finance Approver .CURTIS HALL CHERYL PATTELLI Purchasing Approved Date 07/27;2023 Legal Counsel BRUCE BARKER DH Approved Date Finance Approved Date Legal Counsel Approved Date 07,=26=2023 07,26;`2023 07/2712023 Final Approval BOCC Approved BOCC Signed Date BOCC Agenda Date 08/02,=2023 Originator DDUNKER Tyler Ref # AG 080223 Hello