HomeMy WebLinkAbout20233266.tiff RESOLUTION
RE: REGULATING, WARNING, AND GUIDING TRAFFIC DURING TEMPORARY
CLOSURE OF COUNTY ROAD 44 BETWEEN COUNTY ROAD 35 AND
U.S.HIGHWAY 85 FOR APPROXIMATELY ONE(1)MONTH,FOR ROADWAY AND
INTERSECTION IMPROVEMENTS
WHEREAS,the Board of County Commissioners of Weld County,Colorado,pursuant to
Colorado statute and the Weld County Home Rule Charter, is vested with the authority of
administering the affairs of Weld County,Colorado,and
WHEREAS,pursuant to C.R.S.§42-4-106(6)(a):
"...local authorities,with their respective jurisdiction may,for the
purpose of road construction and maintenance,temporarily close to
through traffic or to all vehicular traffic any highway or portion
thereof for a period not to exceed a specified number of work days
for project completion and shall,in conjunction with any such road
closure establish appropriate detours or provide for an alternative
routing of the traffic affected...",and
WHEREAS, pursuant to said statute and upon the basis of traffic and personnel
investigations, the Board has determined that conditions exist which make it necessary to
temporarily close County Road 44,between County Road 35 and U.S.Highway 85,to through
traffic and to regulate,warn and guide vehicular traffic by posting signs thereon,with said closure
being effective November 6,2023,for approximately one(1)month for roadway and intersection
improvements.
NOW,THEREFORE,BE IT RESOLVED that the Board of County Commissioners of Weld
County,Colorado,deems it necessary to regulate,warn and guide vehicular traffic on County
roads and any intersections thereof,and it hereby authorizes and orders the posting of such traffic
control devices as shall be reasonably necessary to regulate,warn and/or guide traffic thereon
for the safety of the general public and that said traffic control devices shall conform to the Federal
Manual on Uniform Traffic Control Devices.
BE IT FURTHER RESOLVED that the Board of County Commissioners of Weld County,
Colorado,does declare and establish that County Road 44, between County Road 35 and
U.S.Highway 85,be temporarily closed,with said closure being effective November 6,2023,for
approximately one (1) month for roadway and intersection improvements, and further,that
standard official traffic control devices shall be erected at said closure giving notice of the
restrictions.
cc•.So(RS),D,S Patcl.,C S P 2023-3266
l(/l4/23 EG0024
TEMPORARY CLOSURE—COUNTY ROAD 44
PAGE 2
The above and foregoing Resolution was,on motion duly made and seconded,adopted
by the following vote on the 1st day of November,A.D.,2023.
BOARD OF COUNTY COMMISSIONERS
WELD COUNTY,COLORADO
ATTEST: die/Leo
Mi man,Chair
Weld County Clerk to the Board
err .Bu ,Pro-Tem
BY •pOoKu`- -
Deputy Clerk to the Board
Scott K.Jam
.. *�. C
A -� Epp,., ORM: 4',�,�
'' �` e D.Ross
1302 ount ttorney j}ish' k�
I
Date of signature: I t`l`Z '� � � e
a•
2023-3266
EG0024
MEMORANDUM
TO:Clerk to the Board DATE:October 30,2023
m- �:_ r
FROM: Amy Mutchie,Public Works Department
SUBJECT:BOCC Agenda Item
Jalisco International Inc.,is requesting permission to close CR 44 between CR 35 and US 85 from
11/6/23 through 12/8/23 for final tie-ins at Niobrara Blvd for the CDOT flyover project.
See attached closure diagram.
2023-3266
M E&?0D24 0D24
www. invarion .com N
MHT 039e ' RDENT
TRAFFIC SERVICES. INC
NOT DRAWN TO SCALE
CR 44 CLOSURE MHT NO O39
3
N I O BA RA TD CR 35 DESCRIPTION CR 44 Closure ;
Niobara to CR 35
2O21 -012
Ardent No.
Phase 02
Designed by : Antonio
Ledeznia , TCS
Project: Us 85 8. Pecichar-ri
Grade Seper atior
Friend ROAD Project No. : NI-IPP 0853-10 .'
• ROAD . CLOSED - -- ( 2 1 OO6)
CLOSED
• ll ROAD -- Proj Owner: C2.. OO1-
CLOUD
MEA• _,
CL
Prime : Jalisco Intl Inc .
500'I . .. . . . .. . . . . .. . . . . . .. . . . .'
. COMMENTS
�fefififisififisif
.I.el�fffef ff f f�le!f!ff f!fi'.ff1.e.f1lfli.if f.1.i.1ii.fr. ,,.
fffff! !f! / .I .�..f1f . . ! ♦
• .f. Ife • � . . f . lflefefe
I�fffffffflfeff• fifes�f�e .. ! ♦f .f.f_.
-♦•.� , " This MHT shows the closure at CR 44 PH 01 East side realignment
500' 500' 1 "Flaggers my be moved or removed depending on the work as
.�; approved by the engineer.
• F• ROAD �� " This MHT is based on latest version of the MUTCD
►l CLOSED -4 " This MHT should be used with MHT 001 , MHT 008
kc�o , F+ — 41 " This MHT may be used with MHT's for this project
is
CLOSED • I " All signs and devices used to meet the requirements of NCHRP
niE 350
•Illit•
" The closure may be moved, lengthened or shortened depending on
fr! the work, as approved by the engineer or designee.
'Any conflicting Signs will be covered or removed
I
H •
f
Work Hours :
; one VJoik Hourb.
Mon -Fn 7am -5pm, other hours as
In current SB 85 location approved by the PM
it.;l:.cG at aI
Lane Closures
•NioeAR OETC CLOSURE SIGNING Single Lane lam - Spin
Other Hours as Approved by the PM
�P. 46
CR 46 —lb / egging
7a-Spin. Other hours as approved by
the PM
4O
0i
Manifest z �
T - _.,, CJ .Y , �.,
/ w
24 x Barrel 8 x Type III Bamcade MPH 30 35' 55 Legend
5 x M4-9 detour (L) 3 x ImLEFTARROW3 x R11-2 ROAD CLOSED 3 x W20-3 road dosed aheadTYPE URBAN URBANFRS • Barrel vMB VMB 2 PANEL
2 x M4-9 detour (R) 2 x VMB VMB 2 PANEL LOW LOW tR
Work Area
1 x M4-10 Detour M4-10L 1 x R11-4 R11-4 --
I x W20-2 detour ahead WIDTH 12' 12' 12' In current NB 85 location `i
4
! J
_L CSL ".N -J
A trJqEtAR DETOUR
MERGING 180 245' 660'
TAPER T T
. r CR 42 F
SHIFTING
TAPER 90' 123' 330' i - ....;,4
SHOULDR 50 82' 2
TAPER COMPANY NAME TITLE SIGNATURE
C?EV SPC 30 35' 55'
TAPER PREPARED BY
ARDENT TRAFFIC SERVICES Antonio D. Ledezma Pres / TCS
DEV SPC 60' 70' 110'
TANGENT
APPROVED BY
SIGN 100 100' 500'
SPACING
www. invarion .com N
ARDENT
MHT 039 TRAFFIC SERVICES, INC
NOT DRAWN TO SCALE
CR 44 CLOSURE MHT NO. 039
N I O BA RA TO C R 35 DESCRIPTION CR 44 Niobara too CR 35
Page 2 of 2 Ardent No. 2021 -012
021 -012
Antonio
Designed by :
Ledezrna , TCS
Project: US 85 S eF eckh-iAso
Grade Seperation
O853- 1 07
Project No. : (21 006)
.-)
t)
5 O Proj Owner: C EDOT
Prime : Jalisco Irnt.' 1 Inc .
COMMENTS
This MHT shows the closure at CR 44 PH 01 East side realignment
"Flaggers my be moved or removed depending on the work as
approved by the engineer.
" This MHT is based on latest version of the MUTCO
" This MHT should be used with MHT 001, MHT 008
This MHT may be used with MHT's for this project
" All signs and devices used to meet the requirements of NCHRP
350
" The closure may be moved, lengthened or shortened depending on
the work, as approved by the engineer or designee.
" Any conflicting Signs will be covered or removed
Work Hours :
Work Howe.
Mon -Fri lam-5pm, other hours as
approved by the PM
Lane Closures
Single Lane lam - 5pm
Other Hours as Approved by the PM
F lagging
?a - 5pm Other hours as approved by
iho PM
Manifest
24 x Barrel 8 x Type III Barricade
Legend
$ x M4-9 detour (L) 3 x ImLEFTARROW
3 x R11-2 ROAD CLOSED 3 x W20-3 road dosed ahead
Barrel — VMB VMB 2 PANEL
MPH 30 35' H
2 x M4-9 detour (R) 2 x VMB VMB 2 PANEL Work Area
1 x M4-10 Detour M4-10L 1 x R11-4 R11-4 TYPE URBAN URBAN FRWY
1 x W20-2 detour ahead LOW LOW
WIDTH •
MERGING
TAPER '
SHIFTING
TAPER iU
COMPANY NAME TITLE SIGNATURE
SHOULDR 221iTAPER PREPARED BY
DEV SPC
ARDENTTRAFFIC SERVICES Antonio D. Ledezma Pres / TCS _ ' '
TAPER 35' -
APPROVED BY
DEV SPC 70' 110'
TANGENT
SIGN Inn 100' 500'
SPACING
Hello