Loading...
HomeMy WebLinkAbout20240551.tiff es) Xcel R 1800 La rimer Street Denver , CO 80202 June 23 , 2023 Kim Ogle , Principal Planner Weld County Planning Department 1155 N 17th Ave . Greeley , Colorado 80631 RE : 1041 , Use by Special Review , and Site Plan Review Permit Applications for Colorado ' s Power Pathway Dear Mr . Ogle , P ublic Service Company of Colorado , a Colorado corporation conducting business as Xcel Energy ( Xcel Energy ) , is seeking approval of an Areas and Activities of State Interest ( 1041 ) Permit , Use by S pecial Review ( USR ) Permit , and Site Plan Review ( SPR ) Permit for Major Facilities of Public U tility or Public Agency from Weld County to construct and operate a portion of Colorado ' s Power P athway ( Pathway ) located in Weld County . Pathway is a $ 1 . 7 to $ 2 billion investment to improve the state ' s electric grid and enable future renewable energy development around the state . Pathway will increase electric reliability , boost the regional economy , and create jobs during construction . P athway includes the installation of approximately 550 to 610 miles of new 345 - kilovolt ( kV ) double - circuit transmission line ; four new electric substations ; and expansion , equipment additions , or e quipment upgrades at four existing electric substations . P athway will be constructed in five segments , with an optional sixth segment , with each new or e xpanded electric substation serving as endpoints for the transmission line segments : • Fort St . Vrain — Canal Crossing ( Segment 1 ) • Canal Crossing — Goose Creek ( Segment 2 ) • Goose Creek — May Valley ( Segment 3 ) • May Valley — Tundra ( Segment 4 ) • Tundra — Harvest Mile ( Segment 5 ) • May Valley — Longhorn ( Extension ) In March 2021 , Xcel Energy filed a Certificate of Public Convenience and Necessity ( CPCN ) Application with the Colorado Public Utilities Commission ( CPUC ) describing the purpose , need , and public benefits of constructing Pathway . In February 2022 , the CPUC provided verbal approval , and in June 2022 , it provided written approval of the CPCN for Segments 1 - 5 , and conditional approval for the Extension based on a determination that Pathway is in the public interest . While the CPUC determines the need for Pathway , it does not determine the location of the components ; the location and land use permissions will be granted through easement negotiations with landowners and land use permits in the applicable jurisdictions where Pathway components will be located . P referred transmission line routes and substation sites for Pathway have been selected after completion of routing and siting studies , coordination with permitting entities , and conducting public outreach . P athway facilities proposed in Weld County subject to the 1041 Permit Application include 38 miles of new 345 - kV double - circuit electric transmission line in new right - of - way ( ROW ) and a 67 . 6 - acre laydown area ( referred to as the Cervi Yard ) . The proposed route in Weld County is generally located in central Weld County in an east - west direction . The proposed route subject to the 1041 P ermit Application is east of Platteville and crosses Interstate 76 near Roggen . P athway facilities proposed in Weld County subject to the USR Permit Application include 9 . 1 miles of new 345 - kV double - circuit transmission line within the ROW permitted under USR - 1236 ; the relocation of 4 . 5 miles of existing 230 - kV electric transmission line into new ROW and the relocation of 4 . 5 miles of existing 230 - kV electric transmission line within the USR - 1236 ROW to accommodate engineering requirements for Pathway crossing of the existing transmission lines within the USR - 1236 ROW ; and a 59 . 4 - acre laydown area ( referred to as the Sarchet Yard ) . The proposed route subject to the USR Permit Application is north of Platteville and crosses U . S . Highway 85 near Platteville . P athway facilities proposed in Weld County subject to the SPR Permit Application include equipment additions to Xcel Energy ' s existing Fort St . Vrain Substation within a 28 . 9 - acre parcel . The equipment additions at the Fort St . Vrain Substation are adjacent to the existing Xcel Energy Fort St . Vrain Generating Station at 9379 Weld County Road 34 , northwest of Platteville . P roject representatives met with County staff on October 5 , 2022 , for the Pre - Application Meeting during which Xcel Energy provided information about Pathway and responded to questions from County representatives . The 1041 Permit Application was prepared per the requirements outlined in Chapter 21 , Article II of the Weld County , Colorado , Charter and County Code and 1041 Use by S pecial Review ( USR ) Procedural Guide Major Facility of a Public Utility . The USR Permit Application was prepared per the requirements outlined in Chapter 23 , Article II , Division 5 of the Weld County , Colorado , Charter and County Code and Use by Special Review ( USR ) Procedural Guide . The SPR Permit Application was prepared per the requirements outlined in Chapter 23 , Article II , Division 3 of the Weld County , Colorado , Charter and County Code and Site Plan Review ( SPR ) Procedural Guide . These Applications were also prepared pursuant to guidance and discussion provided during the Pre - Application Meeting attended by representatives of Weld County and Xcel nergy on October 5 , 2022 . We look forward to working with you during the permit process . If you need any additional information , please feel free to contact me by telephone at ( 303 ) 285 - 6533 or email at jennier . l . chester@xcelenergy . com ; Cory Miller at ( 303 ) 571 - 7759 or cory . r . miller@xcelenergy . com ; or our environmental consultant Stephanie Phippen with Tetra Tech Inc . at ( 303 ) 980 - 3515 or stepha n ie . ph i ppen © tetratech . com . S incerely , . Jennifer Chester Xcel Energy S iting & Land Rights , Manager Telephone : ( 303 ) 285 - 6533 jennifer . l . chester@xcelenergy . com Xcei nergr COLORADO ' S POWER PATHWAY WELD COUNTY SITE SELECTION AND CONSTRUCTION OF MAJOR FACILITIES OF A PUBLIC UTILITY JUNE 2023 COLORADO ' S POWER PATHWAY i Application Submittal Requirements ( Sec . 21 - 3 - 330 ) Location i n this Permit Re •_ uirement A _ • • ication A . hese application submittal requirements shall apply to all applications for a development permit for a major facility of a public utility , except for requirements which have been waived as provided in these Section 1041 Regulations . B . Submittal requirements for all applications for a development permit for a major facility of a public utility , where applicable : Sec . 2 1 The following are general requirements for any map or plan required hereunder . Minimum requirements include : Sec . 2 . 1 , Attachment A a . The name of the proposed development or use and total number of acres under consideration . b . Because all maps and plans may be used for public presentation , the map scale and size should be large enough for effective presentation and should accurately illustrate the application . c . he name , address and telephone number of the applicant , designer , engineer , surveyor and any other consultants of the applicant . d . Date of preparation , revision box , written scale , graphic scale and north arrow for each map . 2 . The applicant must provide the following information concerning title of the project site , which shall be the entire proposed Sec . 1 . 4 , Sec . 6 . 8 , alignment or corridor under consideration at the time of the application for transmission line and pipeline projects : Attachment G a . The names and addresses of all surface property owners of the project site and within one thousand three hundred twenty ( 1 , 320 ) feet of the boundaries of the property proposed to be physically disturbed , except for transmission line or pipeline projects , for which the names and addresses of all surface property owners for five hundred ( 500 ) feet on either side of the centerline of the proposed alignment shall be provided . b . he planned access to the project site and the means the applicant intends to use to obtain a legal right to utilize such access , including copies of any access or right - of- way agreements which have been entered into by the date of the application for such access . c . The names and addresses of persons or entities with an interest in any real property proposed to be physically disturbed or crossed by the activity or development which is the subject of the application , excluding mineral interests but including those holding mortgages , judgments , liens , easements , contract rights , rights - of- way , reservations , exceptions or other encumbrances , at least to the extent shown in the records of the County Clerk and Recorder or of which applicant has actual knowledge . d . The names and addresses of mineral interest holders with an interest in any real property proposed to be physically disturbed or crossed by the activity or development which is the subject of the application in the case of projects to be constructed more than ten ( 10 ) feet below the surface , excluding foundation structures for above - ground transmission lines , at least to the extent shown in the records of the County Clerk and Recorder and County Assessor . In addition , the applicant shall provide a certificate stating the process by which the applicant compiled such information , when such information was compiled and the steps which were taken to ensure the accuracy of the information . The County will require that the information be compiled and verified in a manner reasonably designed to ensure the accuracy of such information but shall not require the use of title insurance or attorney ' s title opinions . he County will require that the last search for such information have been updated no later than ten ( 10 ) days before the date that the application is submitted , and that such information be updated again no later than ten ( 10 ) days before the public hearing on the application . 3 . Section 1041 Permit Map : Sec . 2 . 1 , Attachment D a . The map shall be delineated on reproducible material approved by the Department of Planning Services . b . The dimensions of the map shall be thirty - six ( 36 ) inches wide by twenty - four ( 24 ) inches high . COLORADO ' S POWER PATHWAY Location in this Permit Requirement Application c . The map shall include certificates for the property owner ' s signature ( excepting linear facilities ) , the Planning Commission , the Board of County Commissioners and the Clerk to the Board . The required content of the certificates is available from the Department of Planning Services . d . Vicinity Map . A vicinity map shall be drawn on the Use by Special Review Permit Plan Map . ' Attachment A , Attachment D i . The exact scale of the vicinity map shall be determined at the time of the preapplication conference , taking into consideration the type and size of the proposed project , as well as the type and complexity of the information to be mapped . ii . The vicinity map shall delineate all of the required information within a one - half- mile radius of the property ( one thousand [ 1 , 000 ] feet for linear facilities ) proposed for the Section 1041 Permit . iii . The following information shall be shown on the vicinity map : a . Section , township and range . b . Scale and north arrow . c . Outline of the perimeter of the parcel proposed for the site . ( For linear facilities , the proposed centerline and width of any corridor to be considered for the Section 1041 Permit . ) d . The general classifications and distribution of soils over the parcel under consideration . Soil classification names and agricultural capability classifications must be noted in the legend . ( These requirements are generally not applicable to linear facilities ) . e . Locations and names of all key roads , irrigation ditches and water features . f . Location of all residences within a one - half- mile radius , existing and proposed accesses to the property proposed for the facility ( excepting linear facilities ) , any abutting subdivision outlines and names , and the boundaries of any adjacent municipality . g . Any other relevant information within a one - half - mile distance of the perimeter property proposed for the facility as may be reasonably required by the County to meet the intent and purpose of this Chapter . 4 Plot Plan . A plot plan of the facility area shall be drawn on the Section 1041 Permit Map . Attachment D a . The exact scale of the plot plan shall be determined at the time of the preapplication conference , taking into consideration the type and size of the proposed project , as well as the type and complexity of the information to be mapped . b . The plot plan shall outline the boundaries of the parcel being considered for the facility . c . he plot plan shall include the location and identification of all of the following items which are presently existing within a two - hundred - foot radius of the boundaries of the Section 1041 Permit area as well as within the area itself ; it shall also include the proposed features and structures of the facility ( some of the following may not be applicable to linear facilities ) : i . All public rights - of - way of record , including names . ii . All existing and proposed structures . iii . All utility easements or rights - of - way for telephone , gas , electric , water and sewer lines . iv . Irrigation ditches . v . Adjacent property lines and respective owners ' names ( may be shown on vicinity map instead ) . vi . All hydrographic features including streams , rivers , ponds and reservoirs ( including names ) . vii . Topography at two - foot contour intervals or at intervals as determined necessary by the Planning Department . ( Linear facilities shall include appropriate topographic data derived from USGS maps or an equivalent database . ) COLORADO ' S POWER PATHWAY Location in this Permit Requirement Application viii . Location of areas of moderate or severe soil limitations as defined by the Natural Resources Conservation Service or by a soil survey and study prepared by a soils engineer or scientist for the uses and associated structures proposed for the parcel . ix Location and design of storm water management devices or structures ( excepting linear facilities ) . x Complete traffic circulation and parking plan showing locations and sizes ( excepting linear facilities ) . xi . Location , amount , size and type of any proposed landscaping , fencing , walls , berms or other screening . ( Linear facilities shall provide information regarding revegetation and reclamation . ) xii . Location of any flood hazard , geologic hazard or mineral resource areas . xiii Such additional information as may be reasonably required by the Department of Planning Services , the Panning Commission or the Board of County Commissioners in order to determine that the application meets the requirements of this Chapter and the policies of _ Chapter 22 of this Code and any other applicable Code provision or ordinance in effect . 5 . The following items and information : Sec . 2 . 2 . a a . Description of the present use and zoning . b . A sketch or map showing the following : Not applicable i . If a power plant is proposed , the area within ten ( 10 ) miles from the site . ii . For transmission lines or pipelines , provide a map showing all existing transmission lines ( 115 kV or greater ) for Sec . 2 . 2 . b a distance of two ( 2 ) miles beyond any reasonable alternative studied . c . For upgrades of existing transmission lines ( 115 kV or greater ) , provide a sketch showing all existing transmission Sec . 2 . 2 . c lines and pipelines within one ( 1 ) mile on either side of the proposed alignment . d . For all other major facilities of a public utility , provide a sketch showing the area within five ( 5 ) miles of the site if Sec . 2 . 2 . d another major facility is proposed . e . Type of facility - specify where applicable : Sec . 2 . 2 . e i . The voltages and lengths of transmission lines . ii . Power source and generating capacity . iii . The functions and sizes of substations . iv . For pipeline projects , the diameters and lengths of pipelines . v . The capacities of the storage tanks and types of petroleum derivative to be stored . vi . Corridor locations . vii . Service area . viii . Resource area ( e . g . , source of power being generated or transmitted , source of petroleum derivative being transported ) . ix . Describe applicable support facilities ( e . g . , pollution control , parking areas , landscaping , etc . ) to be provided . f . Projected development schedule : Sec . 2 . 2 . f i . Estimate maximum number of employees , number of shifts and employees per shift during the construction , operation and maintenance phases of the project . ii . Specify any future phases or extensions of the facility and relationship of the facility ( if currently foreseen ) to larger programs and plans . iii . Specify timetable for planning ( e . g . , federal permits , other state permits , local zoning , etc . ) . iv . Estimate beginning and completion of construction and beginning of operation of facility . g . Hazards and emergency _ procedures : Sec . 2 . 2 . 9 COLORADO ' S POWER PATHWAY iv Location in this Permit Requirement Application i . Describe hazards , if any , of fire , explosion and other dangers to the health , safety and welfare of employees and the general public . ii . Describe hazards , if any , of environmental damage and contamination due to materials used at or activities taking place at the proposed facility . iii . Describe emergency procedures to be used in the event of fire , explosion or other event which may endanger the public health , safety and welfare . iv . Describe any prevalent natural hazards that will affect or be affected by development , and describe mitigating measures to be taken to reduce danger due to such natural hazards . h . Name , address and telephone number of the applicants . Sec . 2 . 2 . h i . Name and address of the fee owners of the property proposed for the Section 1041 Permit , if different from above . Sec . 2 . 2 . i j . Legal description of the property under consideration . Sec . 2 . 2 . j k . Total acreage of the parcel , right - of- way or corridor under consideration . Sec . 2 . 2 . k I . Existing land use of the parcel , right - of - way or corridor under consideration . Sec . 2 . 2 . 1 m . Existing land uses of all properties adjacent to said parcel , right - of - way or corridor . Sec . 2 . 2 . m n . Present zone and overlay zones , if appropriate . Sec . 2 . 2 . n o . Signatures of the applicant and fee owners or their authorized legal agent . Sec . 2 . 2 . o 6 . Summarization of major natural and socioeconomic environmental constraints as they affect the site selection and Sec . 2 . 3 construction of the facility as proposed . 7 . Summarization of the effects of the proposed site selection and construction upon the natural and socioeconomic Sec . 2 . 4 environment of the impact area as applicable to submission requirements . Included should be an analysis of impacts upon agricultural productivity and agricultural resources and upon vested water rights . 8 . Analysis of the long - term effects of the proposed site selection and construction upon the physical and socioeconomic Sec . 2 . 5 development of the impact area . 9 . A description of a program to minimize and mitigate adverse impacts and to maximize the positive impacts of the Sec . 2 . 6 proposed site selection and construction . 10 . Analysis of nonstructural alternatives to the project such as conservation of energy use , no development or management Sec . 2 . 7 ( different scheduling , conservation programs , facility design , land trades , etc . ) , if applicable . 11 . Analysis of reasonable structural alternatives to the project such as alternate locations and routes , alternative types of Sec . 2 . 8 facilities , use of existing d • hts - of - wa , Joint use of ri • hts - of - wa with other utilities and upgrading of existing facilities . 12 . Analysis of air and water pollution impacts and control alternatives . Sec . 2 . 9 13 . Analysis of design alternatives concerning access , landscaping , architectural controls and so forth . Sec . 2 . 10 14 . Submission of a proposed form of development agreement to meet costs of affected political subdivisions in the project Sec . 2 . 11 area of providing new or upgraded services and facilities necessary to serve the proposed project . 15 . Analysis of hydrologic , atmospheric , geologic , pedologic , biotic , visual and noise impacts . Sec . 2 . 12 16 . Surface and subsurface drainage analysis . Sec . 2 . 13 17 . A Decommissioning Plan . Adequate financial assurance to cover the decommissioning of the facility may be required as a Sec . 2 . 14 condition of approval of the Decommissioning Plan . 18 . Any other information required by the Board or the Planning Department and communicated to the applicant at the Sec . 2 . 15 preapplication conference . This limitation shall not preclude the Board from requesting the applicant to provide additional information during the public hearing on the application , in order to provide which the applicant shall be granted reasonable continuances if the applicant so requests . COLORADO ' S POWER PATHWAY Location in this Permit Requirement Application C . Specific submittal requirements . These additional requirements shall be imposed on the applicant by the Planning Department , in such Department ' s sole discretion , if the Planning Department determines that the need for the additional information is warranted by the size and scope of the proposed project in order for the Board of County Commissioners to make an informed decision on the application . It is the intention of these Regulations that the following information shall be required only if the proposed project is of such size and scope that it is reasonably likely to have significant environmental or social impacts on the County residents or lands . 1 . Detailed description of the need for the proposed development or activity , including but not limited to : Sec . 3 . 1 a . The present population of the area to be served and the total population to be served when the project is operating at Sec . 3 . 1 . a full capacity . b . The predominant type of users or communities to be served by the proposal . Sec . 3 . 1 . b c . The percentage of the design capacity at which the current system is now operating . Sec . 3 . 1 . c d . The relationship of the proposal to the applicant ' s Ion + - ran + e plannin + and capital improvements pro + rams . Sec . 3 . 1 . d e . A description of why public convenience and necessity require a facility of the size and nature proposed . Sec . 3 . 1 . e f . A description of the user needs and user patterns to be fulfilled by the proposed project . Sec . 3 . 1 . f g . A description of the relationship of the project to other existing and planned utility facilities of a similar nature , other Sec . 3 . 1 . g communication or energy generation and transmission facilities , local government capital improvement programs and special district expansion _ programs . 2 . Environmental Impact Analysis Sec . 3 . 2 a . Land use : Sec . 3 . 2 . a i . Describe the relationship of the project to local land use , policies and comprehensive plans and to policies and Sec . 3 . 2 . a . 1 plans adopted or under preparation by federal , state , regional or other affected local governmental agencies . ii . Detail the agricultural productivity capability of the land affected bar the proposal ( SCS classification ) . Sec . 3 . 2 . a . 2 iii . Specify how the proposed development will utilize existing easements or rights - of - way for any associated Sec . 3 . 2 . a . 3 distribution or collector networks . b . Information regarding other utility facilities . Sec . 3 . 1 . b i . A map showing each existing major facility of a public utility within the County of the type proposed for Sec . 3 . 1 . b . 1 development . c . Water resources : Sec . 3 . 2 . c i . On the map of the base area , or another appropriate map , indicate any flood plain associated with the proposal . Sec . 3 . 2 . c . 1 Documentation of the historical flooding activity should be included . Detail potential , adverse impacts related to the associated f oodplain . ii . Describe the potential adverse effects of the proposal upon plant and animal life dependent upon the water Sec . 3 . 2 . c . 2 resources in question . d . Significant environmentally sensitive factors : Sec . 3 . 2 . d i . Identify and locate on a map of appropriate scale the juxtaposition of any of the following features present in the Sec . 3 . 2 . d . 1 proposed development or activity and its vicinity , and detail the potential impact of the proposal upon each feature : a ) Marshlands and wetlands . Sec . 3 . 2 . d . 1 b ) Groundwater recharge areas , if applicable . Sec . 3 . 2 . d . 1 c ) Potential natural hazards . Sec . 3 . 2 . d . 1 d ) Forests and woodlands . Sec . 3 . 2 . d . 1 COLORADO ' S POWER PATHWAY vi Location in this Permit Requirement Application e ) Critical wildlife habitat . Sec . 3 . 2 . d . 1 f ) Public outdoor recreation areas . Sec . 3 . 2 . d . 1 g ) Unique areas of geologic , historic or archeological importance . Sec . 3 . 2 . d . 1 e . Visual aesthetics and nuisance factors : Sec . 3 . 2 . e i . Identify key locations where the facility can be viewed from and its proximity to residences , simulate the Sec . 3 . 2 . e . 1 appearance of the facility , and identify noise pollution or obnoxious odors which may stem from the proposal . ii . Where significant , map or describe area within view of project . Sec . 3 . 2 . e . 2 iii . Describe proposed mitigation strategy . Sec . 3 . 2 . e . 3 f . Transportation impacts : Sec . 3 . 2 . f i . Describe what impacts the proposal will have upon transportation patterns in the area intended to be served or Sec . 3 . 2 . f . 1 affected by the proposal . ii . Describe the potential impact on roads within the County . Sec . 3 . 2 . f . 2 iii . Identify improvements required to any roads within the County in order to serve the project adequately . Sec . 3 . 2 . f . 3 g . Less damaging alternatives : Sec . 3 . 2 . g i . If the Planning Department determines that the nature or extent of the proposal involves the potential for Sec . 3 . 2 . g . 1 significant environmental damage or warrants examination of specific , less environmentally damaging alternatives , the Planning Department may request that the Board require the applicant evaluate and present information on such alternatives as part of the application . ii . Required information on alternatives may include , but shall not necessarily be limited to , information on the Sec . 3 . 2 . g . 2 environmental impacts and cost - effectiveness of the alternatives in relationship to the proposal presented . 3 . Applicants seeking a permit for the site selection and construction of transmission lines or substations shall submit the Sec . 3 . 3 following additional documents and information : a . Computer modeled electromagnetic field measurements within the proposed transmission line easement for that Sec . 3 . 3 . a portion of transmission line between substations or transition sites ; and b . Measures taken to comply with the concept of prudent avoidance with respect to planning , siting , construction and Sec . 3 . 3 . b operation of transmission lines , which may be those steps taken to comply with the Colorado Public Utilities Commission ' s Rule 18 ( 1 ) , or similar authority , for projects where other similar authority is applicable . D . Waiver of submittal requirements . Specific submittal requirements may be waived by the Planning Department , as provided in Sec . 4 these Section 1041 Regulations . COLORADO ' S POWER PATHWAY vii 1041 Use by Special Review ( USR ) Procedural Guide Application Submittal Requirements Checklist Location in this Permit Requirement A • plicalon 1041 Use by Special Review ( USR ) Procedural Guide Application Submittal Requirements Checklist A copy of the pre - application meeting minutes provided by Planning Services . Attachment Q Application form . Attachment I Authorization form , if applicable . Section 6 . 3 Incorporation documents if the owner is a business entity ( LLC , etc . ) , or trust documents . Attachment R Completed Questionnaire . Attachment C A certified list of names , addresses and the corresponding Parcel Identification Number ( s ) assigned by the County Assessor Attachment G of the owners of property ( the surface estate ) within 1 , 320 feet of the property , except for transmission line projects , for which surface property owners for 500 feet on either side of the centerline of the proposed alignment , and to interest holders ( excluding mineral interests ) in any real property proposed to be physically disturbed or crossed by the activity or development which is the subject of the application . The source of such list shall be the records of the County Assessor , or an ownership update from a title or abstract company or attorney , derived from such records or from the records of the County Clerk and Recorder . If the list was assembled from the records of the County Assessor , the applicant shall certify that such list was assembled within 30 days of the application submission date . The names and addresses of any owner , operator , or user of any irrigation ditch , lateral , or pipeline that traverses the Attachment S property , if applicable . A copy of an agreement with the mineral owners associated with the subject property , if applicable . Such agreement shall Section 6 . 8 stipulate that the oil and gas activities on the subject property have been adequately incorporated into the design of the site or shall provide written evidence that an adequate attempt has been made to mitigate the concerns of the mineral owners on the subject property . A copy of the most recent deed to the property and , if the applicant is not the property owner , evidence of interest in the Section 6 . 9 subject land held by the applicant , such as a lease agreement , trust documents , Statement of Authority , or similar evidence . A Certificate of Conveyances ( Chain of Title ) form provided by the Department of Planning Services and completed by a Title Section 6 . 10 Insurance or Abstract Company . The date of certification of the form must be within 30 days of the date of application . A signed Statement of Taxes from the County Treasurer showing no delinquent property taxes for the area referred to in the Attachment T application materials . A copy of a document showing evidence of adequate water supply ( e . g . , well permit or letter from water district ) . Section 6 . 12 A copy of a document showing evidence of adequate methods of sewage disposal ( e . g . , on - site wastewater treatment Section 6 . 13 system ( OWTS ) ( septic )_permit ) . A signed Notice of Inquiry from a municipality or municipalities if the site is located within an Intergovernment Agreement Section 6 . 14 ( IGA ) boundary or a Coordinated Planning Agreement ( CPA ) boundary , if applicable . A drainage report , preliminary drainage study , or drainage narrative , as determined by Development Review . Attachment E , Engineering Question 3 A traffic study or traffic narrative including a traffic control plan , as determined by Development Review . Section 6 . 16u Attachment C , Engineering Question 1 A sign plan detailing type , size and number of desired signs with images following the standards set forth in Chapter 23 , Section 6 . 17 Article IV , Division 2 and Appendices 23 - C through E , if applicable . A nuisance abatement plan , if applicable . Section 6 . 18 A landscape and screening plan , if applicable . Section 6 . 19 COLORADO ' S POWER PATHWAY viii Location in this Permit Requirement Application A decommissioning plan , if applicable . Adequate financial assurance to cover the decommissioning of the facility may be Attachment J required as a condition of approval . A draft emergency incident action plan , if applicable . Section 6 . 21 , Attachment U A noise study including a noise abatement plan documenting the methods to be utilized to meet the applicable noise Attachment O standard , if applicable . A soil report of the site prepared by the Natural Resource Conservation Service or by a soils engineer or scientist . In those Attachment V instances when the soil report indicates the existence of moderate or severe soil limitations for the uses proposed , the applicant shall detail the methods to be employed to mitigate the limitations . Community meeting sign - in sheet , minutes , and summary ( optional ) . Attachment W The application fee ( $ 10 , 000 ) . Note : Fees are non - refundable and due when the application is determined to be complete . Application fee will be paid Fees are set by the Board of County Commissioners . County Staff is not authorized to negotiate fees and cannot , under any when application circumstance , waive , reduce , or amend the fees set forth in the Weld County Planning Fee Schedule . determined to be complete Investigation fee , due only if this is a violation case . ( 50 % of the application fee . ) Section 6 . 26 The planned access to the project site and the means the applicant intends to use to obtain a legal right to utilize such Section 1 . 4 , Section 6 . 8 , access , including copies of any access or right - of- way agreements which have been entered into by the date of the Attachment D application for such access . The names and addresses of persons or entities with an interest in any real property proposed to be physically disturbed or Attachment G crossed by the activity or development which is the subject of the application , excluding mineral interests but including those holding mortgages , judgments , liens , easements , contract rights , rights - of- way , reservations , exceptions or other encumbrances , at least to the extent shown in the records of the County Clerk and Recorder or of which applicant has actual knowledge . The names and addresses of mineral interest holders with an interest in any real property proposed to be physically Section 6 . 28 disturbed or crossed by the activity or development which is the subject of the application in the case of projects to be constructed more than 10 feet below the surface , excluding foundation structures for above - ground transmission lines , at least to the extent shown in the records of the County Clerk and Recorder and County Assessor . In addition , the applicant shall provide a certificate stating the process by which the applicant compiled such information , when such information was compiled and the steps which were taken to ensure the accuracy of the information . The County will require that the information be compiled and verified in a manner reasonably designed to ensure the accuracy of such information , but shall not require the use of title insurance or attorney ' s title opinions . The County will require that the last search for such information have been updated no later than 10 days before the date that the application is submitted , and that such information be updated again no later than 10 days before the public hearing on the application . 1041 USR map . The applicant shall submit the draft map for preliminary approval to the Department of Planning Services in Attachment D electronic ( . pdf ) format . Upon approval , the applicant shall submit a 24 " x 36 " map on Mylar . A sketch or map showing the following : Pathway is not a power i . If a power plant is proposed , the area within 10 miles from the site . plant ii . For transmission lines , provide a map showing all existing transmission lines ( 115 kV or greater ) for a distance of 2 miles Attachment F beyond any reasonable alternative studied . iii . For upgrades of existing transmission lines ( 115 kV or greater ) , provide a sketch showing all existing transmission lines Attachment F and pipelines within 1 mile on either side of the proposed alignment . iv . For all other major facilities of a public utility , provide a sketch showing the area within 5 miles of the site . _ Not applicable v . Indicate any floodplains , if required . Attachment L COLORADO ' S POWER PATHWAY ix Location in this Permit Requirement Application A map showing each existing major facility of a public utility within the County of the type proposed for development , if Attachment F required . If required , identify and locate on a map of appropriate scale the juxtaposition of any of the following features present in the Attachment M ; Attachment proposed development or activity and its vicinity , and detail the potential impact of the proposal upon each feature : C , Supplemental Question i . Marshlands and wetlands . 15 . d . i ii . Groundwater recharge areas , if applicable . Attachment C , S upplemental Question 15 . d . ii iii . Potential natural hazards . Attachment C , S upplemental Question 15 . d . iii iv . Forests and woodlands . Attachment B ; Attachment L ; Attachment C , S upplemental Question 15 . d . iv v . Critical wildlife habitat . Attachment B ; Attachment C , Supplemental Question 15 . d . v ✓ i . Public outdoor recreation areas . Attachment C , S upplemental Question 15 . d . vi ✓ ii . Unique areas of geologic , historic or archeological importance . Attachment V ; Attachment C , Supplemental Question 15 . d . vii COLORADO ' S POWER PATHWAY x Use by Special Review Questionnaire ( " 1041 Questionnaire " ) Location in this Permit Requirement A • plicalon Supplemental Questions for 1041 Major Facilities of Public Utilities 1 Describe the type of facility . Specify where applicable : Attachment C , a . The voltages and lengths of transmission lines . Supplemental Question 1 . a b . Power source and generating capacity . Attachment C , Supplemental Question 1 . b c . The functions and sizes of substations . Attachment C , Supplemental Question 1 . c d . The capacities of storage tanks and types of petroleum derivative to be stored . Attachment C , Supplemental Question 1 . d e . Corridor locations . Attachment C , Supplemental Question 1 . e f . Service area . Attachment C , Supplemental Question 1 . f g . Resource area ( e . g . , source of power being generated or transmitted ) . Attachment C , Supplemental Question 1 . g h . Applicable support facilities ( e . g . , pollution control , parking areas , landscaping , etc . ) to be provided . Attachment C , Supplemental Question 1 . h 2 . Describe the projected development schedule . Specify where applicable : Attachment C , a . Estimated maximum number of employees , number of shifts and employees per shift during the construction Supplemental Question 2a b . Any future phases or extensions of the facility and relationship of the facility ( if currently foreseen ) to larger programs Attachment C , and plans . _ Supplemental Question 2b c . Timetable for planning ( e . g . , federal permits , other state permits , local zoning , etc . ) . Attachment C , _ Supplemental Question 2c d . Estimated beginning and completion of construction and beginning of operation of facility . Attachment C , _ Supplemental Question 2d 3 . Describe hazards and emergency procedures . Specify where applicable : Attachment C , a . Hazards , if any , of fire , explosion and other dangers to the health , safety and welfare of employees and the general Supplemental Question 3a public . b . Hazards , if any , of environmental damage and contamination due to materials used at or activities taking place at the Attachment C , proposed facility . Supplemental Question 3a c . Emergency procedures to be used in the event of fire , explosion or other event which may endanger the public health , Attachment C , safety and welfare . Supplemental Question 3a d . Any prevalent natural hazards that will affect or be affected by development , and describe mitigating measures to be Attachment C , taken to reduce danger due to such natural hazards . Supplemental Question 3a 5 . Summarize the effects of the proposed site selection and construction upon the natural and socioeconomic environment of Attachment C , the impact area as applicable to submission requirements . Included should be an analysis of impacts upon agricultural Supplemental Question 5 productivity and agricultural resources and upon vested water rights . 6 . Include analysis of the long - term effects of the proposed site selection and construction upon the physical and Attachment C , socioeconomic development of the impact area . Supplemental Question 6 COLORADO ' S POWER PATHWAY xi Location i n this Permit Requirement Application 7 . Include a description of a program to minimize and mitigate adverse impacts and to maximize the positive impacts of the Attachment C , proposed site selection and construction . Supplemental Question 7 8 . Include analysis of nonstructural alternatives to the project such as conservation of energy use , no development or Attachment C , _ management ( different scheduling , conservation programs , facility design , land trades , etc . ) , if applicable . Supplemental Question 8 9 . Include analysis of reasonable structural alternatives to the project such as alternate locations and routes , alternative types Attachment C , of facilities , use of existing rights - of - way , joint use of rights - of- way with other utilities , and upgrading of existing facilities . Supplemental Question 9 10 . Include analysis of air and water pollution impacts and control alternatives . Attachment C , Supplemental Question10 11 . Include analysis of design alternatives concerning access , landscaping , architectural controls , and so forth Attachment C , Supplemental Question 11 12 . Include analysis of hydrologic , atmospheric , geologic , pedologic , biotic , visual and noise impacts . Attachment C , Supplemental Question 12 13 . Include surface and subsurface drainage analysis . Attachment C , _ Supplemental Question13 14 . Applicants seeking a permit for the site selection and construction of transmission lines or substations shall submit the Attachment C , following additional documents and information : Supplemental a Computer modeled electromagnetic field measurements within the proposed transmission line easement for that portion Question 14 . a of transmission line between substations or transition sites ; and b . Measures taken to comply with the concept of prudent avoidance with respect to planning , siting , construction and Attachment C , operation of transmission lines , which may be those steps taken to comply with the Colorado Public Utilities Supplemental Commission ' s Rule 18 ( 1 ) , or similar authority , for projects where other similar authority is applicable Question14 . b 15 . Specific submittal requirements . The following information may also be required : Attachment C , a . Detailed description of the need for the proposed development or activity , including but not limited to : Supplemental i . The present population of the area to be served and the total population to be served when the project is operating Question15 . a . i at full capacity . ii . The predominant type of users or communities to be served by the proposal . Attachment C , S upplemental Question15 . a . ii iii . The percentage of the design capacity at which the current system is now operating . Attachment C , S upplemental Question15 . a . iii iv . The relationship of the proposal to the applicant ' s long - range planning and capital improvements programs . Attachment C , S upplemental Question15 . a . iv v . A description of why public convenience and necessity require a facility of the size and nature proposed . Attachment C , S upplemental Question 15 . a . v vi . A description of the user needs and user patterns to be fulfilled by the proposed project . Attachment C , S upplemental Question 15 . a . vi COLORADO ' S POWER PATHWAY xii Location i n this Permit Requirement Application vii . A description of the relationship of the project to other existing and planned utility facilities of a similar nature , other Attachment C , communication or energy generation and transmission facilities , local government , capital improvement programs Supplemental and special district expansion programs . Question 15 . a . 1 . vii b . Environmental impact analysis — land use . Attachment C , i . Describe the relationship of the project to local land use , po icies and comprehensive plans and to policies and Supplemental plans adopted or under preparation by federal , state , regional or other affected local governmental agencies . Question15 . b . i ii . Detail the agricultural productivity capability of the land affected by the proposal ( SCS classification ) . Attachment C , S upplemental Question15 . b . ii iii . Specify how the proposed development will utilize existing easements or rights - of- way for any associated Attachment C , distribution or collector networks . Supplemental Question15 . b . iii c . Environmental impact analysis — water resources . Attachment C , i . Documentation of the historical flooding activity should be included . Detail potential , adverse impacts related to the Supplemental associated floodplain . Question15 . c . i ii . Describe the potential adverse effects of the proposal upon plant and animal life dependent upon the water Attachment C , resources in question . Supplemental Question15 . c . ii d . Environmental impact analysis — significant environmentally sensitive factors . Detail the potential impact of the proposal Attachment C , upon each feature : Supplemental i . Marshlands and wetlands . Question15 . d . i ii . Groundwater recharge areas , if applicable . Attachment C , S upplemental Question15 . d . iii . Potential natural hazards . Attachment C , S upplemental Question15 . d . iii iv . Forests and woodlands . Attachment C , S upplemental Question15 . d . iv v . Critical wildlife habitat . Attachment C , S upplemental Question15 . d . iv vi . Public outdoor recreation areas . Attachment C , S upplemental Question 15 . d . vi vii . Unique areas of geologic , historic or archeological importance . Attachment C , S upplemental Question15 . d . vii e . Environmental impact analysis — Visual aesthetics and nuisance factors . Attachment C , S upplemental Question15 . e . i COLORADO ' S POWER PATHWAY xiii Location i n this Permit Requirement Application i . Identify key locations where the facility can be viewed from and its proximity to residences , simulate the appearance Attachment C , of the facility , and identify noise pollution or obnoxious odors which may stem from the proposal . Supplemental Question15 . e . ii ii . Where significant , map or describe areas within view of project . Attachment C , S upplemental Question15 . e . iii iii . Describe proposed mitigation strategy . Attachment C , Supplemental Question15 . f f . Environmental impact analysis — Transportation impacts . Attachment C , S upplemental Question 15 . f . i i Describe what impacts the proposal will have upon transportation patterns in the area intended to be served or Attachment C , affected by the proposal . Supplemental Question15 . f . ii ii . Describe the potential impact on roads within the County . Attachment C , S upplemental Question151 . iiii iii . Identify improvements required to any roads within the County in order to serve the project adequately . Attachment C , S upplemental Question 15 . f . iv g Environmental impact analysis — less damaging alternatives . If the Planning Department determines that the nature or Attachment C , extent of the proposal involves the potential for significant environmental damage or warrants examination of specific , Supplemental less environmentally damaging alternatives , the Planning Department may request that the Board require the applicant Question15 . g evaluate and present information on such alternatives as part of the application . Required information on alternatives may include , but shall not necessarily be limited to , information on the environmental impacts and cost - effectiveness of the alternatives in relationship_ to the proposal presented . Planning Questions 1 Explain , in detail , the proposed use of the property . Include , at a minimum , the following : Attachment C , Planning Question 1 a . Current or previous use of the land , if any . Attachment C , Planning Question 1 . a b . Describe the uses surrounding the site and explain how the proposed use is compatible with them . Attachment C , Planning Question 1 . b c . Describe the proximity of the proposed use to residential structures . Attachment C , Planning Question 1 . c d . Describe the hours and days of operation ( e . g . Monday thru Friday 8 : 00 a . m . to 5 : 00 p . m . ) . Attachment C , Planning Question 1 . d e . List the types , number , and uses of the proposed structures to be erected . Attachment C , Planning Question 1 . e f . Describe the size of stockpile , storage or waste areas to be utilized , if any . Attachment C , Planning Question 1 . f COLORADO ' S POWER PATHWAY xiv Location i n this Permit Requirement Application g . Describe the method and time schedule of removal or disposal of debris , junk and other wastes associated with the Attachment C , Planning proposed use . Question 1 . g h . Include a time table showing the periods of time required for the construction of the operation . Attachment C , Planning Question 1 . h i . Describe the type of lot surface proposed and the square footage of each type ( e . g . asphalt , gravel , landscaping , dirt , Attachment C , Planning grass , buildings ) . Question 1 . i j . How many parking spaces are proposed ? How many handicapped ( ADA ) parking spaces are proposed ? Attachment C , Planning Question 1 . j k . Describe the proposed screening for all parking and outdoor storage areas . Attachment C , Planning Question 1 . k I . Describe the existing and proposed landscaping for the site . Attachment C , Planning Question 1 . 1 m . Describe the type of fence or other screening proposed for the site . Attachment C , Planning Question 1 . m n . Describe reclamation procedures to be employed as stages of the operation are phased out or upon cessation of the Attachment C , Planning activity . Question 1 . n o . Describe the proposed fire protection measures . Attachment C , Planning Question 1 . o 2 . Explain how this proposal is consistent with the Weld County Comprehensive Plan . Attachment C , Planning Question 2 3 . Explain how this proposal is consistent with the intent of the zone district in which it is located . ( Intent statements can be Attachment C , Planning found at the beginning of each zone district section in Article III of Chapter 23 . ) Question 3 4 . Explain how this proposal will be compatible with future development of the surrounding area or adopted master plans of Attachment C , Planning affected municipalities . Question 4 5 . Explain how this proposal complies with Article V and Article XI of Chapter 23 if the proposal is located within any Overlay Attachment C , Planning Zoning District ( Airport , Geologic Hazard , or Historic Townsites Overlay Districts ) or a Special Flood Hazard Area identified Question 5 by maps officially adopted by the County . 6 . If the proposed use is to be located in the A ( Agricultural ) Zone District , explain your efforts to conserve prime agricultural Attachment C , Planning land in the locational decision for the proposed use . Question 6 7 Explain whether this proposal interferes with the protection of the health , safety and welfare of the inhabitants of the Attachment C , Planning n eighborhood and the County . Question 7 Environmental Health Questions 1 . What is the drinking water source on the property ? If utilizing a drinking water well include either the well permit or well permit Attachment C , application that was submitted to the State Division of Water Resources . If utilizing a public water tap include a letter from the Environmental Health Water District , a tap or meter number , or a copy of the water bill . Question 1 2 . What type of sewage disposal system is on the property ? If utilizing an existing septic system provide the septic permit Attachment C , n umber . If there is no septic permit due to the age of the existing septic system , apply fora septic permit through the Environmental Health Department of Public Health and Environment prior to submitting this application . If a new septic system will be installed Question 2 please state " a new septic system is proposed . " Only propose portable toilets if the use is consistent with the Department of Public Health and Environment ' s portable toilet policy . COLORADO ' S POWER PATHWAY xv Location i n this Permit Requirement Application 3 . If storage or warehousing is proposed , what type of items will be stored ? Attachment C , Environmental Health _ Question 3 4 . Describe where and how storage and / or stockpile of wastes , chemicals , and / or petroleum will occur on this site . Attachment C , Environmental Health Question 4 5 . If there will be fuel storage on site , indicate the gallons and the secondary containment . State the number of tanks and Attachment C , gallons per tank . Environmental Health Question 5 6 . If there will be washing of vehicles or equipment on site , indicate how the wash water will be contained . Attachment C , Environmental Health Question 6 7 . If there will be floor drains , indicate how the fluids will be contained . Attachment C , Environmental Health Question 7 8 . Indicate if there will be any air emissions ( e . g . painting , oil storage , etc . ) . Attachment C , Environmental Health Question 8 9 . Provide a design and operations plan if applicable ( e . g . composting , landfills , etc . ) . Attachment C , Environmental Health Question 9 10 . Provide a nuisance management plan if applicable . Attachment C , Environmental Health _ Question 10 11 . Additional information may be requested depending on type of land use requested . Attachment C , Environmental Health Question 11 Engineering Questions 1 . Include a traffic narrative with the information below . A traffic impact study may be required . Improvements to adjacent Attachment C , Engineering streets / roads may be necessary to provide adequate safe and efficient transportation to and from the site . An Improvements Question 1 . a Agreement may be required . a . The projected number of vehicle trips ( average per day , maximum per day , peak hour data ) to and from the site and the type of vehicles ( passenger , semi - truck , etc . ) . b . Describe how many roundtrips / day are expected for each vehicle type : Passenger Cars / Pickups , Tandem Trucks , Semi - Attachment C , Engineering Truck / Trailer / RV ( Roundtrip = 1 trip in and 1 trip out of site ) Question 1 . b c . Describe the expected travel routes for site traffic . Attachment C , Engineering Question 1 . c d . Describe the travel distribution along the routes ( e . g . 50 % of traffic will come from the north , 20 % from the south , 30 % Attachment C , Engineering from the east , etc . ) Question 1 . d e . Describe the time of day that you expect the highest traffic volumes to and from the site . Attachment C , Engineering Question 1 . e COLORADO ' S POWER PATHWAY xvi Location i n this Permit Requirement Application 2 . Describe where the access to the site is planned . Attachment C , Engineering Question 2 3 . Drainage Design : Design and construction of a detention pond as described in an approved Drainage Report is required Attachment C , Engineering unless the project falls under an exception to stormwater detention requirements per code . ( See below . ) Does your site Question 3 . a qualify for an exception to stormwater detention ? If so , describe in a drainage narrative the following : a . Which exception is being applied for ? Include supporting documentation . b . Does the water flow onto the property from an offsite source ? If so , from where ? Attachment C , Engineering Question 3 . b c . Describe where the water flows to as it leaves the property . Attachment C , Engineering Question 3 . c d . Describe the direction of flow across the property . Attachment C , Engineering Question 3 . d e . Describe the location of any irrigation facilities adjacent to or near the property . Attachment C , Engineering Question 3 . a f . Describe any previous drainage problems with the property . Attachment C , Engineering Question 3 . f 4 . If your site does not qualify for an exception , the following applies : Attachment C , Engineering a . A Drainage Report summarizing the detention pond design with construction drawings and maintenance plan shall be Question 4 . a completed by a Colorado Licensed Professional Engineer and adhere to the drainage related sections of the Weld County Code . b . The Drainage Report must include a certification of compliance , which can be found under the Development Review Attachment C , Engineering webpage on the Planning and Zoning website , stamped and signed by the PE . Question 4 . b c . See the attached Drainage Report Review Checklist . Attachment C , Engineering Question 4 . c Building Questions 1 . List the type , size ( square footage ) , and number of existing and proposed structures . Show and label all existing and Attachment C , Building proposed structures on the USR drawing . Label the use of the building and the square footage . Question 1 2 . Explain how the existing structures will be used for this USR . Attachment C , Building Question 2 3 . List the proposed use ( s ) of each structure . Attachment C , Building Question 3 COLORADO ' S POWER PATHWAY xvii CONTENTS 1 Introduction 1 1 . 1 Estimated Pathway Schedule 4 1 . 2 Pathway Activities Prior to Submittal of Application 7 1 . 2 . a Public Outreach 7 1 . 2 . b Transmission Line Routing & Substation Siting Studies 8 1 . 3 Regulatory Framework 10 1 . 4 Description of Facility 10 1 . 4 . a Transmission Line 11 1 . 4 . b Transmission Line Access 13 1 . 4 . c Temporary Construction Areas 13 1 . 4 . c . 1 Staging / Laydown Areas 13 1 . 4 . c . 2 Conductor Stringing Areas 14 1 . 4 . d Areas for Other Construction Activities 14 1 . 4 . e Construction Process 15 1 . 4 . e . 1 Construction Phases 15 1 . 4 . e . 2 Transmission Line Construction 15 1 . 4 . e . 3 Construction Staffing , Vehicles , and Equipment 16 2 Application Submittal Requirements ( 21 - 3 - 330 ) ( B ) 18 2 . 1 Section 1041 Permit Map ( 21 - 3 - 330 ( B ) ( 3 ) and 21 - 3 - 330 ( B ) ( 4 ) ) 18 2 . 2 Project Information ( 21 - 3 - 330 ( B ) ( 5 ) ) 18 2 . 2 . a Present Use and Zoning ( 21 - 3 - 330 ( B ) ( 5 ) ( a ) ) 18 2 . 2 . b Map of Existing Transmission Lines ( 21 - 3 - 330 ( B ) ( 5 ) ( b ) ) 18 2 . 2 . c Sketch Map of All Existing Transmission Lines and Pipelines Within One Mile on Either Side of the Proposed Alignment ( 21 - 3 - 330 ( B ) ( 5 ) ( c ) ) 18 2 . 2 . d Sketch Map of Utility Facilities within Five Miles of Proposed Facility ( 21 - 3 - 330 ( B ) ( 5 ) ( d ) ) 18 2 . 2 . e Type of Facility ( 21 - 3 - 330 ( B ) ( 5 ) ( e ) ) 18 2 . 2 . f Projected Development Schedule ( 21 - 3 - 330 ( B ) ( 5 ) ( 0 ) 18 2 . 2 . g Hazards and Emergency Procedures ( 21 - 3 - 330 ( B ) ( 5 ) ( g ) ) 19 2 . 2 . h Name , Address , and Telephone Number of the Applicant ( 21 - 3 - 330 ( B ) ( 5 ) ( h ) ) 19 2 . 2 . i Name and Address of the Fee Owners of the Property ( 21 - 3 - 330 ( B ) ( 5 ) ( 0 ) 19 2 . 2 . j Legal Description of the Property Under Consideration ( 21 - 3 - 330 ( B ) ( 5 ) (D ) 19 2 . 2 . k Total Acreage of the Parcel , Right - of- Way or Corridor Under Consideration ( 21 - 3 - 330 ( B ) ( 5 ) ( k ) ) 19 COLORADO ' S POWER PATHWAY xviii 2 . 2 . 1 Existing Land Use of the Parcel , Right - of- Way or Corridor Under Consideration ( 21 - 3 - 330 ( B ) ( 5 ) ( 1 ) ) 19 2 . 2 . m Existing Land Uses of All Properties Adjacent to Said Parcel , Right - of- Way or Corridor ( 21 - 3 - 330 ( B ) ( 5 ) ( m ) ) 20 2 . 2 . n Present Zone and Overlay Zones ( 21 - 3 - 330 ( B ) ( 5 ) ( n ) ) 20 2 . 2 . o Signatures of the Applicant and Fee Owners or Their Authorized Legal Agent ( 21 - 3 - 330 ( B ) ( 5 ) ( o ) ) 20 2 . 3 Summarization of Major Natural and Socioeconomic Environmental Constraints ( 21 - 3 - 330 ( B ) ( 6 ) ) 20 2 . 4 Summarization of the Effect upon the Natural and Socioeconomic Environment of the Impact Area ( 21 - 3 - 330 ( B ) ( 7 ) ) 20 2 . 5 Analysis of the Long - Term Effects of the Proposed Site Selection and Construction upon the Physical and Socioeconomic Development of the Impact Area ( 21 - 3 - 330 ( B ) ( 8 ) ) 21 2 . 6 Description of a Program To Minimize and Mitigate Adverse Impacts and To Maximize Positive Impacts ( 21 - 3 - 330 ( B ) ( 9 ) ) 21 2 . 7 Analysis of Nonstructural Alternatives to the Project ( 21 - 3 - 330 ( B ) ( 10 ) ) 21 2 . 8 Analysis of Reasonable Structural Alternatives to the Project ( 21 - 3 - 330 ( B ) ( 11 ) ) 21 2 . 9 Analysis of Air and Water Pollution Impacts and Control Alternatives ( 21 - 3 - 330 ( B ) ( 12 ) ) 21 2 . 10 Analysis of Design Alternatives Concerning Access , Landscaping , Architectural Controls ( 21 - 3 - 330 ( B ) ( 13 ) ) 21 2 . 11 Proposed Form of Development Agreement ( 21 - 3 - 330 ( B ) ( 14 ) ) 22 2 . 12 Analysis of Hydrologic , Atmospheric , Geologic , Pedologic , Biotic , Visual and Noise Impacts ( 21 - 3 - 330 ( B ) ( 15 ) ) 22 2 . 13 Surface and Subsurface Drainage Analysis ( 21 - 3 - 330 ( B ) ( 16 ) ) 22 2 . 14 Decommissioning Plan ( 21 - 3 - 330 ( B ) ( 17 ) ) 22 2 . 15 Additional Information ( 21 - 3 - 330 ( 6 ) ( 18 ) ) 22 3 Specific Submittal Requirements ( 21 - 3 - 330 ) ( C ) ) 22 3 . 1 Need for the Proposed Development or Activity ( 21 - 3 - 330 ( c ) ( 1 ) ) 22 3 . 1 . a Present Population and Total Population to Be Served ( C ) ( 1 ) ( a ) 22 3 . 1 . b Predominant Type of Users or Communities to Be Served ( C ) ( 1 ) ( b ) 23 3 . 1 . c Percentage of the Design Capacity of Current System ( C ) ( 1 ) ( c ) 23 3 . 1 . d Relationship of the Proposal to the Applicant ' s Long - Range Planning and Capital Improvements Programs ( C ) ( 1 ) ( d ) 23 3 . 1 . e Public Convenience and Necessity for Proposed Project ( C ) ( 1 ) ( e ) 23 3 . 1 . f User Needs and User Patterns to Be Fulfilled ( C ) ( 1 ) ( 0 23 COLORADO ' S POWER PATHWAY xix 3 . 1 . g Relationship to Other Existing and Planned Utility or Energy Generation and Transmission Facilities , Local Government Capital Improvement Programs , or Special District Expansion Program ( C ) ( 1 ) ( g ) 23 3 . 2 Environmental Impact Analysis ( 21 - 3 - 330 ( C ) ( 2 ) ) 24 3 . 2 . a Land Use ( C ) ( 2 ) ( a ) ) 24 3 . 2 . a . 1 Relationship of Project to Local Land Use , Policies , and Comprehensive Plans ( C ) ( 2 ) ( a ) ( i ) 24 3 . 2 . a . 2 Agricultural Productivity Capability of the Land Affected by the Proposal ( C ) ( 2 ) ( a ) ( ii ) 24 3 . 2 . a . 3 Use of Existing Easements or Rights - of- Way for Associated Distribution or Collector Networks ( C ) ( 2 ) ( a ) ( iii ) 24 3 . 2 . b Information Regarding Other Utility Facilities ( C ) ( 2 ) ( b ) 24 3 . 2 . b . 1 Map each Existing Major Facility of a Public Utility of the Type Proposed for Development ( 5 ) ( C ) ( 2 ) ( b ) ( i ) 24 3 . 2 . c Water Resources ( C ) ( 2 ) ( c ) ) 24 3 . 2 . c . 1 Map of Floodplains and Potential Impacts Associated with P roposal ( C ) ( 2 ) ( c ) ( i ) 24 3 . 2 . c . 2 Potential Adverse Effects Upon Plant and Animal Life ( C ) ( 2 ) ( c ) ( ii ) 25 3 . 2 . d Significant Environmentally Sensitive Factors ( C ) ( 2 ) ( d ) 25 3 . 2 . d . 1 Map of and Description of Impacts on Sensitive Features P resent in the Proposed Development or Activity and Its Vicinity ( C ) ( 2 ) ( d ) ( i ) 25 3 . 2 . e Visual Aesthetics and Nuisance Factors ( C ) ( 2 ) ( e ) ) 26 3 . 2 . e . 1 Key Facility Viewing Locations , Facility Simulations , and P ollution or Obnoxious Odors ( C ) ( 2 ) ( e ) ( i ) ) 26 3 . 2 . e . 2 Map or Describe Area within View of Project ( C ) ( 2 ) ( e ) ( ii ) 26 3 . 2 . e . 3 Describe Mitigation Strategies ( C ) ( 2 ) ( e ) ( iii ) 26 3 . 2 . f Transportation Impacts ( C ) ( 2 ) ( f ) 26 3 . 2 . f . 1 Impacts upon Transportation Patterns ( C ) ( 2 ) ( f ) ( i ) 26 3 . 2 . f . 2 Impacts on County Roads ( C ) ( 2 ) ( f ) ( ii ) 27 3 . 2 . f . 3 Required Improvements to County Roads ( C ) ( 2 ) ( f ) ( iii ) 27 3 . 2 . g Less Damaging Alternatives ( C ) ( 2 ) ( g ) 27 3 . 2 . g . 1 Potential for Significant Environmental Damage ( C ) ( 2 ) ( g ) ( i ) 27 3 . 2 . g . 2 Information on the Environmental Impacts and Cost - Effectiveness of the Alternatives ( C ) ( 2 ) ( g ) ( ii ) 27 3 . 3 Additional Requirements for Site Selection and Construction of Transmission Lines or Substations ( 21 - 3 - 330 ( C ) ( 3 ) ) 28 COLORADO ' S POWER PATHWAY xx 3 . 3 . a Electromagnetic Field Measurements ( 21 - 3 - 330 ( C ) ( 3 ) ( a ) ) 28 3 . 3 . b Colorado Public Utilities Commission ' s Rule 18 ( I ) ( 21 - 3 - 330 ( C ) ( 3 ) ( b ) ) 28 4 Waiver of Submittal Requirements ( 21 - 3 - 330 ( D ) ) 28 5 Approval Requirements 28 6 1041 USR Procedural Guide Planning Requirements Checklist 36 6 . 1 Pre - Application Meeting Minutes 36 6 . 2 Application Form 36 6 . 3 Authorization Form 36 6 . 4 Articles of Organization or Incorporation 36 6 . 5 1041 Questionnaire 36 6 . 6 Certified List of the Names , Addresses , and Parcel Numbers of the Surrounding Property Owners 36 6 . 7 Names and Addresses of Any Owner , Operator of Any Irrigation Ditch , Lateral , or Pipeline on the Property 37 6 . 8 Surface Use Agreement with Mineral Owners 37 6 . 9 Deed 37 6 . 10 Certificate of Conveyances 37 6 . 11 Statement of Taxes 37 6 . 12 Evidence of Adequate Water Supply 38 6 . 13 Evidence of Adequate Sewage Disposal 38 6 . 14 Notice of Inquiry Form 38 6 . 15 Drainage Narrative 38 6 . 16 Traffic Narrative 38 6 . 17 Sign Plan 39 6 . 18 Nuisance Abatement Plan 39 6 . 19 Landscape and Screening Plan 39 6 . 20 Decommissioning Plan 39 6 . 21 Emergency Incident Action Plan 39 6 . 22 Noise Study 40 6 . 23 Soil Report 40 6 . 24 Community Meeting Sign - In Sheet , Minutes , and Summary 40 6 . 25 Application Fee 40 6 . 26 Investigation Fee 40 6 . 27 Planned Access and Access Agreements 41 6 . 28 Names and Addresses of Persons or Entities with an Interest in any Real Property Proposed to be Physically Disturbed or Crossed 41 6 . 29 Names and Addresses of Mineral Interest Holders with an Interest in any Real Property Proposed to be Physically Disturbed or Crossed 41 COLORADO ' S POWER PATHWAY xxi 6 . 30 1041 USR Map 41 6 . 31 Map Showing Existing Transmission Lines 41 6 . 32 Map Showing Each Major Facility of a Public Utility within the County of the Type Proposed 42 6 . 33 Map of Features Present in the Vicinity and Potential Impact of the Proposal 42 7 Compliance with Review Criteria 23 - 2 - 220 . A and 23 - 2 - 230 . B 42 8 Compliance with Design Standards 23 - 2 - 240 . A 43 9 Compliance with Operation Standards 23 - 2 - 250 46 10 References 47 TABLES Table 1 : Colorado ' s Power Pathway by County 3 Table 2 : Estimated Individual Segment and Substation Construction and In - Service Dates 5 Table 3 : Typical 345 - kV Double Circuit Transmission Line Characteristics 11 FIGURES Figure 1 : Colorado ' s Power Pathway 2 Figure 2 : Estimated Pathway Schedule 6 Figure 3 : Pathway Routing and Siting Study Process 9 Figure 4 : Typical Transmission Pole Configuration ( Illustrative ) 12 COLORADO ' S POWER PATHWAY xxii ATTACHMENTS A : Vicinity Map B : Routing and Siting Study for Segment 1 C : Planning Questionnaire D : 1041 USR Map E : Cervi Laydown Yard Drainage Report and Site Plan F : Map of Existing Transmission Lines G : Certified List of Adjacent Property Owners H : Legal Description I : Application Form J : Decommissioning Plan K : Pathway Consistency with the Weld County Comprehensive Plan L : Water Resources Map M : Significant Environmentally Sensitive Factors Map N : Visual Simulations O : Noise and EMF Study P : Agricultural Lands Map Q : Pre -Application Meeting Minutes R : Articles of Incorporation S : Names and Addresses of Owner/ Operator of Irrigation Ditch , Lateral , or Pipeline on the Parcels Crossed by the Proposed Transmission Route T : Statement of Taxes U : Emergency Response Procedures V : Soil Report W : Public Open House Meeting Materials X : Noxious Weed Control Measures COLORADO ' S POWER PATHWAY xxiii LIST OF ACRONYMS AND ABBREVIATIONS 1041 Areas and Activities of State Interest Permit APEN Air Pollutant Emissions Notice Application 1041 Permit Application BMP Best Management Practice CCR Code of Colorado Regulations CDPHE Colorado Department of Public Health and Environment CPCN Certificate of Public Convenience and Necessity CPUC Colorado Public Utilities Commission CRS Colorado Revised Statutes dBA A - Weighted Decibel EMF Electric and Magnetic Fields FAA Federal Aviation Administration HIFLD Homeland Infrastructure Foundation - Level Data IEEE Institute of Electrical and Electronics Engineers kV Kilovolt P athway Colorado ' s Power Pathway P TC Federal Production Tax Credit ROW Right - of- Way S WMP Stormwater Management Plan TCA Temporary Construction Area Tetra Tech Tetra Tech , Inc . U SR Use by Special Review Xcel Energy Public Service Company of Colorado , a Colorado corporation conducting business as Xcel Energy COLORADO ' S POWER PATHWAY 1 1 INTRODUCTION P ublic Service Company of Colorado , a Colorado corporation conducting business as Xcel Energy ( Xcel Energy ) , proposes to construct , maintain , and operate Colorado ' s P ower Pathway ( Pathway ) in eastern Colorado . Xcel Energy is submitting this 1041 P ermit Application ( Application ) for a permit to locate and construct Major Facilities of a P ublic Utility or Public Agency ( 1041 permit ) , pursuant to the Weld County , Colorado , Chapter 21 , Article III , Division 3 , Permit Program for Site Selection and Construction of a Major Facility of a Public Utility ( Weld County 2023a ) . The Application addresses each section in the Weld County § 1041 Requirements as noted in the headings and tables throughout this Application . Like information is grouped throughout the Application . As a result , this Application does not follow the exact subsection order in the Weld County 1041 Regulations . P athway is a $ 1 . 7 to $ 2 billion investment proposed by Xcel Energy to improve the state ' s electric grid and enable future renewable energy development around the state . P athway will ensure safe , reliable , and economical electric service to the public , boost the regional economy , and create jobs during its construction . Pathway includes : • Installation of approximately 550 to 610 miles of new 345 - kilovolt ( kV ) double - circuit transmission line in 12 to 14 counties ; • Construction of up to four new electric substations ( Canal Crossing , Goose Creek , May Valley , and Longhorn ) ; and • Expansion , equipment additions , or equipment upgrades at four existing electric substations ( Fort St . Vrain , Pawnee , Harvest Mile , and Tundra ) . P athway will be constructed in five segments , with an optional sixth segment ( Figure 1 ) , with each new or expanded electric substation serving as endpoints for the transmission line segments : • Fort St . Vrain — Canal Crossing ( Segment 1 ) • Canal Crossing — Goose Creek ( Segment 2 ) • Goose Creek — May Valley ( Segment 3 ) • May Valley — Tundra ( Segment 4 ) • Tundra — Harvest Mile ( Segment 5 ) • May Valley — Longhorn ( Extension ) A fifth new substation ( Sandstone Substation ) may be constructed near the western end of Segment 4 and southern end of Segment 5 if an additional substation is determined COLORADO ' S POWER PATHWAY 2 to be necessary in this area to provide a location for future generation interconnections . A decision regarding the need for this substation will likely be made in 2023 . The estimated length of each transmission line segment and location of each substation is outlined in Table 1 . I ! t . ' IIILLIPs I • Fort St . Vrain Canal Crossing Pawnee 11 1 rn L '' c I L• : 1 ; r rp Fort Morgan 0 I . r rJ • - 1 •Segment ' urrd • • ort St . Vrain Canal Crossing vog _ • Segment 2 : men Denver Kral= al - CjE Canal Crossing Harvest Mile Goose Creek I - LLULII I Castle Rock• 70 - _ - - - - Burlington Limon Mor � urnenl , Segment 5 : undra arvest M " fie Goose Creek ( - : _ III r • I . _ Colorado Springs • Segment : a Goose Creep � - May Val le - ° = � , Eads • May valley Tundra Segment 4 : Pueblo . May Halley - Tundra Lamar . Las Animas • xtens on : May Valley Longhorn ( optional ) Longhorn r t Existing Substation ■ New Substation Springfield . ` ; Substation Siting Area Figure 1 : Colorado ' s Power Pathway COLORADO ' S POWER PATHWAY 3 Table 1 : Colorado ' s Power Pathway by County Segment ( Estimated Miles of Transmission ) County 1 2 3 4 Ext . Total Substation _Baca - - - - - 2 2 New Longhorn Cheyenne - 9 35 - - - 44 New Goose Creek Crowley - - - 41 - - 41 Kiowa - - 22 64 - 6 92 New May Valley Kit Carson - 62 - - - - 62 - Lincoln - - - - 4 - 4 Morgan 27 21 - - - - 48 New Canal Crossing , Existing Pawnee Equipment Additions Prowers - - - - - 51 51 - Washington - 53 - - - - 53 - Weld 47 - - - - - 47 Fort St . Vrain Equipment Additions El Paso - - - - 42 - 42 - Elbert - - - - 50 - 50 - Arapahoe - - - - 18 - 18 Harvest Mile Equipment Additions Pueblo - - - 23 28 - 51 Tundra Expansion Total 74 145 57 128 142 59 605 Pathway will be constructed in segments , with portions of Segment 1 proposed to be located in Weld County . The Vicinity Map ( Attachment A ) shows all Pathway facilities proposed in unincorporated Weld County that are subject to the 1041 , Use by Special Review , and Site Plan Review application processes . Pathway facilities subject to this 1041 Application include 38 miles of new 345 - kV double - circuit electric transmission line in new right - of - way ( ROW ) and a 67 . 6 - acre laydown area ( referred to as the Cervi Yard ) . Pathway facilities subject to the Use by Special Review application include 9 . 1 miles of new 345 - 1cV double - circuit transmission line within the ROW permitted under Use By Special Review ( USR ) - 1236 ; the relocation of 4 . 5 miles of existing 230 - kV electric transmission line into new ROW and the relocation of 4 . 5 miles of existing 230 - kV electric transmission line within the USR - 1236 ROW to accommodate engineering requirements for Pathway crossing of the existing transmission lines within the USR - 1236 ROW ; and a 59 . 4 - acre laydown area ( referred to as the Sarchet Yard ) . Pathway facilities subject to the Site Plan Review application include equipment additions to Xcel Energy ' s existing Fort St . Vrain Substation owned by PSCo . COLORADO ' S POWER PATHWAY 4 Note that Pathway is an addition to Colorado ' s backbone transmission system and does not provide distribution electric service ; as such , this Application does not address project - specific details that apply for developments or direct utility service projects . The Eastern Plains region of Colorado is one of the nation ' s best areas for wind and solar energy generation , but it does not currently have a network transmission system that can integrate these new generation resources into the state ' s interconnected grid system , which is needed to meet Colorado ' s clean energy goals . Pathway will support Xcel Energy ' s Clean Energy Plan ( Xcel Energy 2021 ) that is estimated to deliver as much as an 85 percent reduction in carbon dioxide emissions by 2030 and add approximately 5 , 000 megawatts of new wind , solar , and other resources . Pathway will help to meet the state ' s growing electricity needs , improve safety , reliability , and affordability , and enable the transition to clean energy . Pathway will allow developers of energy generation projects to interconnect energy resources located in the areas of the state that are underserved by backbone transmission lines and allow Xcel Energy to deliver energy to electric customers . In March 2021 , Xcel Energy filed a Certificate of Public Convenience and Necessity ( CPCN ) application with the Colorado Public Utilities Commission ( CPUC ) describing the purpose , need , and public benefits of constructing Pathway . In February 2022 , the CPUC provided verbal approval , and in June 2022 , CPUC provided written approval of the CPCN for Segments 1 - 5 , and conditional approval for the Extension , based on a determination that Pathway is in the public interest . While the CPUC determines a public need for Pathway , it does not approve the location of specific project facilities . The location and land use approvals will be through easement negotiations with landowners and the land use approval process in the applicable jurisdictions where the Pathway facilities will be located . 1 . 1 ESTIMATED PATHWAY SCHEDULL The estimated approval , construction , and in - service schedule for Pathway facilities is shown in Figure 2 . Many variables factor into the schedule for projects of this magnitude . The construction schedule is contingent on acquiring all necessary land rights and permits . Pathway will be constructed and brought in - service in phases . The estimated construction timeline for each segment and related substation , and anticipated in - service dates are shown in Table 2 and Figure 2 . Transmission line Segment 1 will be completed in 2026 assuming the required approvals are obtained . COLORADO ' S POWER PATHWAY 5 Table 2 : Estimated Individual Segment and Substation Construction and In - Service Dates Segment & Substation Construction In - Service Year S egment 1 & Fort St . Vrain Substation Spring 2024 — Spring 2026 Spring 2026 equipment additions S egment 2 & New Canal Crossing & Spring 2023 — Spring 2025 Spring 2025 Goose Creek Substations S egment 3 & New May Valley Substation Spring 2023 — Spring 2025 Spring 2025 S egment 4 & Tundra Substation Spring 2025 — Spring 2027 Spring 2027 Expansion S egment 5 & Harvest Mile Substation Spring 2025 — Spring 2027 Spring 2027 equipment additions Extension & New Longhorn Substation To be determined To be determined COLORADO ' S POWER PATHWAY 6 9 M March March Information mailed CPCN application filets with CPUC to jurisdictions within study areas CPCN application June publicly available Virtual project introduction meetings hosted by Xcel Energy Septemberire Virtual routing & siting Fall update meetings hosted by Xcel Energy Routing & siting open houses to receive feedback on possible locations for transmission lines and substations Preferred Route & Substation Locations Submit Permit Applications * Public meetings to present 9 •. File land use permit applications . to local jurisdictions the preferred route - for selected routes and sites and substation locations B 0 • Public Meetingssa. Public Hearings Host additional neighborhood or community • Jurisdictional public hearings associated meetings as required by land use permits .t •': ans with land use permit applications ' w • 0b 1.49. • • Target in - service date for Segment , 3 and Extension * Schedule is subject to permit approvals Target in - service date for Segment 1 •'• Schedule is subject to permit approvals :• N • Target in - service date for Segment 4 and 5 * The Extension permit applicaiton submission and in - service date Schedule is subject to will be determined after the Request for Proposal process . permit approvals Figure 2 : Estimated Pathway Schedule COLORADO ' S POWER PATHWAY 7 1 . 2 PA HWAY ACTIVITIES PRIOR TO SUBMITTAL OF APPLICATION 1 . 2 . a Pub is Outreach Public outreach efforts were conducted to receive public and stakeholder feedback and input on transmission line route and substation site selection ( see Transmission Line Routing & Substation Siting Studies section ) . • In June 2021 , three virtual introductory meetings were held for the public to discuss Pathways benefits to communities and the process to be used to identify the locations of the proposed transmission lines and new substations . These meetings were held virtually due to restrictions on large gatherings due to COVID - 19 . • In June through September 2021 , Pathway representatives met with jurisdictions within Pathways Study Areas to discuss Pathway and receive feedback . Pathway representatives met with Weld County representatives on June 17 , 2021 . • In September 2021 , two virtual routing and siting meetings were held for the public to learn about the progress made on Pathway , including the development of focus areas for identification of transmission line links and substation sites . These meetings were held virtually due to restrictions on large gatherings due to COVID - 19 . • In October and November 2021 , 15 in - person public open houses were held to gather public feedback on the preliminary transmission links . A public open house was held in Platteville on November 1 , 2021 . • In January through March 2022 , 15 in - person open houses were held to present the preferred route for Segments 1 , 2 , 3 , 4 , and the Extension and to present additional preliminary transmission links for Segment 5 . A public open house was held in Platteville on January 24 , 2022 . • In May 2022 , four in - person open houses were held to gather additional public feedback on the preliminary transmission links and partial preferred route for Segment 5 . • In August 2022 , two in - person open houses were held in the Eastern Review Area , an area further east from the Segment 5 preliminary transmission links and partial preferred route , to gather feedback from landowners in that area about potential additional route options . COLORADO ' S POWER PATHWAY 8 1 . 2 . b ransm - ss ' on L ' ne Routing & Substation Siting Studies Routing a new transmission line and siting a substation require a comprehensive review and analysis of factors and criteria including , but not limited to , electric system planning , engineering , environmental and cultural resources , land use , regulatory requirements , land rights , stakeholder input , and public and worker safety . As shown in Figure 3 , the five - step routing and siting process assesses constraints and opportunities between segment endpoints to ultimately identify the preferred route location for the transmission line and the preferred locations for new substation sites . The process is described in detail in the routing and siting studies for each segment of Pathway . The Routing and Siting Study for Segment 1 is attached to this Application as Attachment B . The other routing and siting studies are not provided because they do not involve transmission lines or substations within Weld County . COLORADO ' S POWER PATHWAY 9 7:0-41., STUDY AREAS • • s SUITABILITY ANALYSIS T' � �� Substation A Substation B tilliMit ` • _ . ' to "�� • " "It k . • �c 20 - miles - wide , developed based on segment end points ) Substation A and Substation B ) 1 - . • / n •J y . PRELIVINARY LINKS� a * *mini, - nalre Substation — . 1f I i - •-- mt - - as Substation { :r 1 *NSt Collect data on resources within and adjacent to study areas , . � ao _ • categorize based on compatibility with development of transmission line or substation 1 Substation A Substation B co a Based on suitability analysis , identify links that provide routing options between segment end points that FOCUS AR AS 4 , minimize crossing of constrained areas and maximize use of more compatible locations 1 i i L L 0 F • IS It al 0 Ca Smaller area within each segment study area where links have been identified , 9 eip If 0 within which the preferred route is anticipated to be located IRI , 5 REVISE LII IKS 81 IDENTIFY PREF BRED RC U Areas with constraints or that are less suitable for transmission line development Q I 1 are removed from further consideration it • , • a Substation A Substation B Preliminary links are revised ( removed , added , modified ) based on public and stakeholder review and input Comparative analysis to identify links to be removed from further consideration , evaluate end - to - end routes Select preferred route Figure 3 : Pathway Routing and Siting Study Process COLORADO ' S POWER PATHWAY 10 1 . 3 REGULATORY FRAM WORK Federal , state , and local permits and approvals may be required prior to Pathway construction . Outreach was conducted with each jurisdiction crossed by Pathway to solicit feedback and discuss potential permits that may be required . Multiple Colorado statutory provisions and local government land use plans and controls apply to Pathway , including approval of a CPCN from the CPUC ; notice , consultation , and permit approvals from counties and municipalities , and notice to owners of a mineral estate associated with the substation sites . All necessary land use , environmental , and construction permits , approvals and authorizations will be obtained prior to the start of and during construction as required and may include but are not limited to major land use permits , ROW permits , road use agreements , access permits , oversize / overweight permits , grading permits , and stormwater permits . Xcel Energy anticipates avoiding impacts to jurisdictional waters of the U . S . ( WOTUS ) in Weld County and therefore does not anticipate that Pathway facilities in the County will require a Nationwide Permit 57 or other U . S . Army Corps of Engineers permitting under the Federal Clean Water Act , Section 404 . The regulatory requirements identified by Xcel Energy are described in the response to Supplemental Question 15 . b . i of the 1041 Questionnaire ( Attachment C ) . 1 . 4 DESCR PT ON OF FAC L Y This Application addresses only the portion of the Pathway transmission line and other related facilities subject to the Application located within Weld County ( see Attachment A , Vicinity Map ) . Pathway land use permitting is occurring concurrently with El Paso , Elbert , Arapahoe , Lincoln , and Pueblo counties and the City of Aurora for the portions of Segments 4 and 5 that occur in those jurisdictions . Coordination is ongoing with additional jurisdictions for other Segments . This Application package was prepared per the requirements of the Weld County 1041 Regulations . The Application also was prepared based on direction provided by Weld County representatives during the Pre - Application Conference held on October 5 , 2022 . Pathway facilities proposed in Weld County subject to this Application include 34 . 3 miles of 345 - kV double - circuit transmission line in Segment 1 ( Attachment A ) . The proposed transmission line route in Weld County is generally located in the area between Platteville and Wiggins , oriented in a west to east direction . The proposed route crosses Interstate Highway 76 east of Roggen as shown on Attachment A . The COLORADO ' S POWER PATHWAY 11 following sections describe the Pathway transmission line facilities within Weld County jurisdiction subject to this Application . 1 . 4 . a Transmission L ' ne The new 345 - kV double circuit transmission line will be constructed using steel poles . A single pole will be used for most transmission pole locations ; however , two transmission poles will be required for certain high - loading transmission pole locations such as at angle locations where the line changes direction . Each transmission pole will be placed on a concrete foundation . Voltage , conductor sag , pole type , terrain , length of span between transmission poles , and minimum clearances of existing buildings influence the necessary height of transmission pole . The transmission poles will be weathering steel and a brown or rust color . The anticipated physical characteristics of a double - circuit pole are summarized in Table 3 , and a representative transmission pole with line is shown in Figure 4 . Table 3 : Typical 345 - kV Double Circuit Transmission Line Characteristics Characteristic Anticipated Design Typical height 105 - 140 feet ( transmission poles will not exceed 199 - foot maximum height ) Right - of - way 150 feet in total width , 75 feet on either side of the centerline Span length Typically 950 feet between transmission poles Material / color Weathering steel , brown or rust color Clearance Maintain all clearances as required by National Electric Safety Code COLORADO ' S POWER PATHWAY 12 ' `4, 0 , \, SHIELD WIRE ` , \ \ k. , • :- r INSULATOR 1-""••,, ,..\ 1 CONDUCTOR \\ \ , \ ,.�� , 1 �j • -.� • , ` CT/ II 1 , it ' II� TRANSMISSION frl POLE 4 411 _ p - • ROW 050 feet ) Figure 4 : Typical Transmission Pole Configuration ( Illustrative ) COLORADO ' S POWER PATHWAY 13 1 . 4 . b ransm - ss ' on Line Access Construction access roads will allow construction crews and vehicles to access transmission pole locations and temporary construction areas ( TCAs ; described below ) . Traffic controls may be required near TCAs during construction to ensure the safety of crews and the travelling public . Where practicable , existing public roads and private roads will be utilized during Pathway construction , maintenance , and operation . Some private roads may require improvements and some new access roads will need to be constructed to accommodate construction equipment and long - term maintenance of the transmission line . Where road improvements are needed , Xcel Energy will acquire any necessary grading , stormwater , and erosion control permits and comply with permit requirements . Xcel Energy will acquire access easements where necessary access routes traverse private property . Some access routes may remain post - construction to maintain access to transmission lines for operation and maintenance activities . 1 . 4 . c Temporary Construct ' on Areas TCAs will be used during construction to stage construction equipment and materials including construction trailers , cranes , and transmission poles . Some TCAs may require grading to level out the area for equipment placement and materials storage . TCAs are also necessary when stringing the conductor wire . The proposed TCAs needed for Pathway are represented in the 1041 USR Map ( Attachment D ) . Permits will be obtained for TCAs as required . At the end of each construction phase , all equipment will be removed from the TCAs for that construction phase . No proposed improvements at the TCAs will be permanent , and TCAs will be restored in a manner generally similar to preconstruction conditions . TCA locations are shown in Attachment D . Additional details about TCAs are discussed in the following sections . 1 . 4 . c . 1 Staging/Laydown Areas The Cervi Yard is 67 . 6 acres and is located in Parcel Number 121933000011 in the A ( Agricultural ) Zone District . The Cervi Yard is located south of the 1 - 76 Frontage Road and northeast of WCR 75 . 5 ( see Attachment A , Vicinity Map ) . The Cervi Yard will have two entrances along the 1 - 76 Frontage Road . The Cervi Yard will consist of a sub - base gravel surface pad that supports three 40 - foot - by - 20 - foot Conex containers , three 30 - yard - by - 10 - yard dumpsters , one 12 - foot - by - 56 - foot construction trailer , one water tank , and parking for construction worker vehicles COLORADO ' S POWER PATHWAY 14 and equipment . A temporary 4 - foot - high barbed wire security fence will be placed around the gravel surfaced pad . An infiltration pond will be placed west of the Cervi Yard gravel site pad to collect runoff from the site and prevent any flooding in the pad . Stormwater best management practices will be used to control stormwater runoff and reduce the spread of pollutants . Following construction , all equipment will be removed and the Cervi Yard will be restored . The perimeter fence and infiltration pond also will be removed following construction . The Cervi Yard Drainage Report and Site Plan is provided as Attachment E . 1 . 4 . c . 2 Conductor Stringing Areas TCAs will be used for stringing the conductor wire . The locations and use of TCAs for this function are required at specific angles to ensure the conductor wire is pulled in line with the transmission poles , thereby limiting the strain on the poles . In addition , TCAs may be used adjacent to public roadways for temporary guarding / protecting of the roadway during stringing of the new transmission line . Typically , these temporary guard sites will be restored following construction , as described above . 1 . 4 . d Areas for Other Construction Activities Construction contractors may utilize temporary concrete batch plants during construction to produce concrete needed for transmission pole foundations . A concrete batch plant consists of the various equipment and materials needed to make concrete . Concrete batch plant equipment typically includes mixers , batchers , conveyors , stackers , bins , heaters , chillers , silos , controls , and dust collectors . Concrete batch plants can be either stationary or mobile . The numbers , locations , and types of concrete batch plants will be determined by the construction contractor and will be a permitted accessory use pursuant to this Application that will be reviewed and approved administratively by County staff as described above and subject to local operational requirements prior to construction . The construction contractor will obtain and meet the requirements related to a Concrete Batch Plant Air Pollutant Emissions Notice ( APEN ) with the Colorado Department of Public Health and Environment ( CDPHE ) if necessary . Construction contractors also will use TCAs to store water trucks , traffic control items , and best management practice ( BMP ) materials . Water will be used in concrete production , dust suppression , and compaction activities . Traffic control will be implemented where required for the safety of the crews and the traveling public . BMPs will be installed to meet stormwater , grading , and erosion control requirements . COLORADO ' S POWER PATHWAY 15 Construction contractors will work with the appropriate jurisdictions to obtain and follow all related construction permits . TCAs are shown in Attachment D . 1 . 4 . e Construction Process 1 . 4 . e . 1 Construction Phases Construction of the transmission line is expected to occur in phases that generally include the following : construction access and vegetation clearing , installation of BMPs , equipment mobilization and material delivery , foundation construction , transmission pole placement and installation , conductor wire stringing and electrical equipment installation , and land restoration . Construction access road improvements , grading , and setup of TCAs , along with vegetation work , will be conducted prior to construction of the transmission line . Proposed access roads will allow construction crews and vehicles to access transmission pole locations and TCAs . Vegetation management within the ROW will be required prior to , or in conjunction with , construction . Trees and tall vegetation growing within or near the Pathway ROW can cause downed lines , power outages , and wildfire . Vegetation management crews will work to prevent these situations from occurring . Vegetation management involves the use of various types of treatment including removing , pruning , and mowing vegetation and the treatment of vegetation with herbicides to ensure safe operations . The extent of this work will vary along the transmission line depending on level of vegetation encroachment and additional ROW needs . 1 . 4 . e . 2 Transmission Line Construction Once the pre - construction preparation work has been completed , work on the transmission lines will begin . The new transmission pole foundations will consist of concrete reinforced with steel that can range in diameter and depth based upon the subsurface conditions . Construction crews will begin drilling for transmission pole foundations . Reinforced concrete drilled pier foundations typically range from 6 to 9 feet in diameter and are drilled 20 to 40 feet deep . Once construction crews have drilled the hole for the new transmission pole , the foundation is installed , and the hole is backfilled . Transmission poles will be placed using cranes . Crane installation will involve first hauling the transmission pole pieces to the location and then assembling the transmission poles at the installation locations and setting them with the crane . Once assembled , transmission poles will be transported by truck to installation locations and cranes will lift the transmission poles into place . COLORADO ' S POWER PATHWAY 16 Once all the transmission poles are in place , the conductor wire and optical ground wire are strung using a temporary pulley system attached to the insulators . Conductor is pulled from one transmission pole to the next through a pulley system temporarily placed on the transmission pole . After a section of conductor is pulled through a series of transmission poles , the conductor is attached to insulators , which are attached to the transmission pole and the pulleys are removed . Trucks , heavy equipment , and helicopters are used in this process . Federal Aviation Administration ( FAA ) safety requirements may require residences near the transmission line to evacuate during helicopter use . Xcel Energy and the construction contractor will coordinate with the FAA during helicopter operations and obtain all required permits . Xcel Energy and the construction contractor will provide residents with prior notice if evacuation is required . Other equipment including bird diverters , spacers , and anti - galloping devices are also installed as needed . TCAs will be located at specific angles to ensure the conductor wire is pulled in line with the transmission poles , remaining in alignment . 1ate . 3 Construction Staffing , Vehicles , and Equipment The first workers , vehicles , and equipment to mobilize for Pathway will conduct investigative fieldwork and prepare work areas for construction . Prior to construction and during the Pathway planning and design stages , soil borings are taken to understand the sub - surface conditions where Pathway facilities will be built . Geotechnical borings are taken using bore drill rigs . Vegetation clearing may be conducted to meet requirements for conductor clearances , minimize potential ignition sources , and to provide access within the ROW . Tree clearing and other vegetation removal is completed with both manual and mechanized equipment and will take place on the identified access route and the area within the easement . Matting is utilized as needed in wet or soft areas to prevent compaction , minimize soil disturbance , and improve site safety . It is anticipated that one 12 - hour shift per day ( Monday through Saturday ) will be worked during transmission line construction , but additional hours may be required . This will be during daylight hours , early morning to early evening . If additional hours are anticipated for shift work , a 24 - hour work permit will be obtained from Weld County . The maximum number of construction workers on site at any one time at any work area will be approximately 60 to 80 for the new transmission line when all phases are active . Transmission line construction is expected to be completed in phases over the duration of the construction schedule for each Pathway segment . The transmission line will not have any permanent on - site employees . Upon completion , Pathway will be operated and monitored remotely 24 hours a day , 7 days a week , 365 days a year to provide safe and reliable electric service . The transmission line will be inspected regularly ( at least annually ) to look for the following : COLORADO ' S POWER PATHWAY 17 • Non - compatible vegetation and hazards within the ROW . • Equipment needing repair or replacement . • ROW encroachments , which can be hazardous to safety and reliable operations . • Anything that might jeopardize safe , reliable operation of the power line . • Operations and maintenance staff must visit the ROW for these inspections , but visits typically are minimal , and landowners will be contacted prior to on - site inspections or maintenance . However , in cases of emergency , advanced contact may not be possible . It is anticipated that an average of 20 to 30 trucks per day will be utilized during the construction of the transmission line for crews , spotting materials , framing poles , and erecting poles . Concrete truck deliveries will be made daily when the foundations and piers are being constructed . Multiple deliveries of cement ( up to 20 to 30 per day ) will be required daily at certain stages of construction . Materials will be delivered to the Cervi Yard at the onset of construction . An additional 10 to 15 trucks will be needed to deliver steel poles , conductor , anchor bolts , and foundation materials daily to work areas . The impact to local public roads will vary day - by - day as the construction moves along the route . A crane , drill rig , concrete truck , boom trucks , trailers , transmission poles , steel casing , and rebar cages are equipment and materials that will be moved into the site for construction . The transmission poles are delivered by truck and assembled at the foundation site and set in place with the use of cranes and other heavy equipment . Trucks , heavy equipment and sometimes helicopters are used to install conductor wire after all transmission poles are erected in an area . To mitigate any potential impacts to Weld County roads , Traffic Control Plans will be prepared and followed during construction . XCEL ENERGY 18 2 APPLICATION SUBMITTAL REQUIREMENTS ( 21 - 3 330 ) ( B ) 2 . 1 SECTION 1041 PERMIT MAP ( 21 - 3 330 ( 6 ) ( 3 ) AND 21 - 3 - 330 ( B ) ( 4 ) ) The 1041 Permit Map is provided as Attachment D . 2 . 2 PROJEC N ORMAT ON ( 21 3 - 330 ( B ) ( 5 ) ) 2 . 2 . a Present Use and Zoning ( 21 - 3 - 330 ( B ) ( 5 ) ( a ) ) The portion of the Pathway transmission line subject to this Application is located in unincorporated Weld County in the A ( Agricultural ) Zone District ( Weld County 2023b ) . The present use of the 150 -foot transmission line ROW corridor subject to this Application is agricultural , including grassland , cultivated crop , and pasture . The route crosses several existing roads , railroads , and irrigation ditches . 2 . 2 . b Map of )( sting ransmission ' nes ( 21 - 3 - 330 ( B ) ( 5 ) ( b ) ) A map showing existing transmission lines 115 - kV or greater within Weld County is provided as Attachment F . 2 . 2 . c Sketch Map of AI Exist ' ng ransmission Lines and Pipelines Within One Mi e on Either Side of the Proposed Alignment ( 21 3 330 ( B ) ( 5 ) ( c ) ) Weld County Code Section 21 - 2 - 330 ( B ) ( 5 ) ( c ) only applies to upgrades of existing transmission lines . The portion of the Pathway transmission line subject to this Application does not involve any upgrades to existing transmission lines . 2 . 2 . d Sketch Map of Uti ity Fac ' ' ties within ' ve M ' es of Proposed Faci ' ty ( 21 - 3 - 330 ( B ) ( 5 ) ( d ) ) Weld County Code Section 21 - 2 - 330 ( B ) ( 5 ) ( d ) only applies if another major facility is proposed . The portion of the Pathway transmission line subject to this Application does not propose other major facilities of a public utility . 2 . 2 . e Type of Facility ( 21 - 3 330 ( B ) ( 5 ) ( e ) ) See the response to Supplemental Question 1 in the 1041 Questionnaire ( Attachment C ) . 2 . 2 . f Projected Development Schedule ( 21 3 - 3313 ( B ) ( 5 ) ( f ) ) See the response to Supplemental Question 2 in the 1041 Questionnaire ( Attachment C ) . XCEL ENERGY 19 2 . 2 . g Hazards and mergency Procedures ( 21 3 330 ( B ) ( 5 ) ( g ) ) S ee the response to Supplemental Question 3 in the 1041 Questionnaire ( Attachment C ) . 2 . 2 . h Name , Address , and Telephone Number of the Applicant ( 21 - 3 - 330 ( B ) ( 5 ) ( h ) ) The following information shows the applicant ' s contact information to address Section 21 - 3 - 330 ( B ) ( 5 ) ( h ) . Applicant : Jennifer Chester Xcel Energy Manager , Siting and Land Rights 1800 Larimer Street Denver , CO 80202 303 - 285 - 6533 2 . 2 . i Name and Address of the Fee Owners of the Property ( 21 - 3 - 330 ( B ) ( 5 ) ( ' ) ) S ee Section 6 . 7 of this Application in addition to Attachment G . 2 . 2 . j Legal Descript ' on of the Property Under Consideration ( 21 - 3 - 330 ( B ) ( 5 ) (D ) A list of the townships , ranges , and sections of the Pathway facilities subject to this Application is provided as Attachment H . 2 . 2 . k otal Acreage of the Parcel , Right - of - Way or Corridor Under Consideration ( 21 3 330 ( B ) ( 5 ) ( k ) ) The total acreage of the 150 - foot transmission line ROW corridor subject to this Application is 624 . 2 acres . 2 . 2 . 1 Existing Land Use of the Parcel , Right - of -Way or Corridor Under Consideration ( 21 3 330 ( B ) ( 5 ) ( ) ) The existing land use of the Pathway facilities subject to this Application is agricultural . S ee the response to Section 2 . 2 . a of this Application . XCEL ENERGY 20 2 . 2 . m Existing Land Uses of All Properties Adjacent to Said Parce , Right of - Way or Corridor ( 21 3 330 ( B ) ( 5 ) ( m ) ) Existing land uses present near Pathway facilities include industrial facilities , oil and gas wells , natural gas compressor station facilities , communication facilities , oil and gas pipelines , a photovoltaic solar facility , a landfill , a tire recycling facility , and several existing high voltage transmission lines and electric distribution lines . Few residences are present near Pathway facilities . Agricultural facilities located near Pathway facilities include cultivated crops , cattle feed yards , a confined animal feeding operation , and a meat processing facility . Other linear infrastructure , including railroads , Interstate Highways , U . S . Highways , and local roads exist in proximity to Pathway . 2 . 2 . n Present Zone and Overlay Zones ( 21 - 3 - 330 ( B ) ( 5 ) ( n ) ) The portion of the Pathway transmission line subject to this Application is located in unincorporated Weld County in the A ( Agricultural ) Zone District . Pathway is not in any designated Overlay Zones according to the Weld County Zoning Map ( Weld County 2023b ) . 2 . 2 . o Signatures of the Applicant and Fee Owners or heir Authorized Lega Agent ( 21 3 330 ( B ) ( 5 ) ( o ) ) Signatures of the applicant and fee owners or their authorized legal agent are provided in the completed Application Form , Attachment I . 2 . 3 SUMMARIZATION OF MAJOR NATURAL AND SOCIOECONOMIC ENV RONMEN AL CONSTRA NTS ( 21 - 3 330 ( 6 ) ( 6 ) ) A discussion of major natural and socioeconomic environmental constraints as they affect the site selection and construction of Pathway is provided in the responses to Supplemental Questions 4 and 15 of the 1041 Questionnaire ( Attachment C ) . 2 . 4 SUMMARIZATION OF T E F CT UPON T NATURAL AND SOCIOECONOMIC ENV RONM NT O TH IMPACT AREA ( 21 3 - 330 ( B ) ( 7 ) ) A discussion of effects of Pathway on the natural and socioeconomic environment of the impact area and methods to minimize and mitigate these impacts is provided in the responses to Supplemental Questions 4 and 15 of the 1041 Questionnaire ( Attachment C ) . XCEL ENERGY 21 2 . 5 ANALYSIS OF THE LONG - TERM EFFECTS OF THE PROPOS D S ITE SELECTION AND CONSTRUCTION UPON HE PHYSICAL AND SOC OECONOM C D VELOPMEN O MPACT AREA ( 21 - 3 - 330 ( B ) ( 8 ) ) A discussion of the long - term effects of Pathway upon the physical and socioeconomic development of the impact area is provided in the response to Supplemental Question 6 of the 1041 Questionnaire ( Attachment C ) . 2 . 6 DESCRIPTION OF A PROGRAM TO MINIMIZE AND MITIGATE ADVERB IMPACTS AND O MAXIMIZE POS VE IMPACTS ( 21 - 3 - 330 ( 6 ) ( 9 ) ) P athway will mitigate and minimize adverse impacts as described in the responses to S upplemental Question 15 of the 1041 Questionnaire ( Attachment C ) . 2 . 7 ANALYSIS OF NONS RUC ORAL ALTERNATIVES TO TH P ROJECT ( 21 3 330 ( B ) ( 10 ) ) An analysis of nonstructural alternatives to Pathway is provided in the response to S upplemental Question 8 of the 1041 Questionnaire ( Attachment C ) . 2 . 8 ANALYSIS OF REASONABLE STRUCTURAL . ALT RNAT VES TO PROJECT ( 21 3 - 330 ( B ) ( 11 ) ) An analysis of reasonable structural alternatives to Pathway is provided in the response to Supplemental Question 9 of the 1041 Questionnaire ( Attachment C ) and the S egment 1 : Fort St . Vrain — Canal Crossing Routing and Siting Study ( Attachment B ) . 2 . 9 ANALYSIS OF AIR AND WA ER POLLUTION IMPACTS AND CONTROL ALTERNATIVES ( 21 3 - 330 ( 6 ) ( 12 ) ) An analysis of air and water pollution impacts and control alternatives is provided in the responses to Supplemental Questions 10 , 15 . c . i , and 15 . d . i of the 1041 Questionnaire ( Attachment C ) . 2 . 10 ANALYSIS O DESIGN ALTERNATIVES CONCERNING ACCESS , ANDSCAP NG , ARCH CTURAL CON ROLS ( 21 - 3 - 330 ( 6 ) ( 13 ) ) An analysis of design alternatives is provided in the response to Supplemental Question 11 of the 1041 Questionnaire ( Attachment C ) . XCEL ENERGY 22 2 . 11 PROPOSED FORM O DEVELOPMENT AGREEMENT ( 21 - 3 - 330 ( B ) ( 14 ) ) No new or upgraded public services or facilities are anticipated to be needed to serve Pathway in Weld County . To the extent that new facilities are required , Xcel Energy will work with Weld County to enter into a mutually agreeable Development Agreement for Pathway as required by Section 21 - 3 - 330 ( B ) ( 14 ) of the Weld County , Colorado , Charter and County Code . 2 . 12 ANALYSIS O HYDROLOGIC , ATMOSP ER C , GEOLOGIC , PEDOLOG C , BIOTIC , VISUAL AND NOISE MPAC S ( 21 3 330 ( 6 ) ( 15 ) ) An analysis of hydrologic , atmospheric , geologic , pedologic , biotic , visual , and noise impacts is provided in the responses to Supplemental Questions 10 and 15 of the 1041 Questionnaire ( Attachment C ) . 2 . 13 SURFAC AND SUBSUR ACE DRAINAGE ANALYSIS ( 21 3 - 330 ( B ) ( 16 ) ) Xcel Energy will comply with permit application requirements , County Standards , and construction protocol to ensure that Pathway does not violate water quality standards . Xcel Energy is requesting an exception to the Drainage Report requirement as the subject of this Application is a transmission line . A drainage narrative is provided in the responses to Engineering Question 3 in the 1041 Questionnaire ( Attachment C ) . 2 . 14 DECOMM SS ON NG PLAN ( 21 3 330 ( B ) ( 17 ) ) A Decommissioning Plan is provided as Attachment J . 2 . 15 ADDITIONAL INFORMATION ( 21 3 330 ( B ) ( 18 ) ) No additional information has been requested to date . 3 SPECIFIC SUBMITTAL REQUIREMENTS ( 21 - 3 - 330 ) ( C ) ) 3 . 1 NE D FOR THE PROPOSED DEVELOPMEN OR ACTIVITY ( 21 3 330 ( C ) ( 1 ) ) 3 . 1 . a Present Popu ation and Tota Population to Be Served ( C ) ( 1 ) ( a ) A description of the population to be served is provided in the response to Supplemental Question 15 . a . i of the 1041 Questionnaire ( Attachment C ) . XCEL ENERGY 23 3 . 1 . b Predominant ype of Users or Communities to Be Served ( C ) ( 1 ) ( b ) Pathway is a transmission system that will serve communities throughout eastern and southern Colorado . See the response to Supplemental Question 15 . a . ii of the 1041 Questionnaire ( Attachment C ) . 3 . 1 . c Percentage of the Design Capacity of Current System ( C ) ( 1 ) ( c ) The current electric transmission facilities in the Eastern Plains region of Colorado do not have adequate capacity to meet the forecasted demand of 3 , 000 to 3 , 500 megawatts . See the response to Supplemental Questions 15 . a . iv and 15 . a . v of the 1041 Questionnaire ( Attachment C ) . 3 . 1 . d Relationship of the Proposal to the Applicant ' s Long Range Planning and Capital Improvements Programs ( C ) ( 1 ) ( d ) Pathway will support Xcel Energy ' s Clean Energy Plan ( Xcel Energy 2021 ) . See the response to Supplemental Question 15 . a . iv of the 1041 Questionnaire ( Attachment C ) . 3 . 1 . e Pub ' c Convenience and Necessity for Proposed Project ( C ) ( 1 ) ( e ) In March 2021 , Xcel Energy filed a CPCN application with the CPUC describing the purpose , need , and public benefits of constructing Pathway . In February 2022 , the CPUC provided verbal approval , and in June 2022 , CPUC provided written approval of the CPCN for Segments 1 - 5 , and conditional approval for the Extension , based on a determination that Pathway is in the public interest . See the response to Supplemental Question 15 . a . v of the 1041 Questionnaire ( Attachment C ) . 3 . 1 . f User Needs and User Patterns to Be u filled ( C ) ( 1 ) ( f ) A description of user needs and user patterns to be fulfilled by Pathway are described in the response to Supplemental Question 15 . a . v of the 1041 Questionnaire ( Attachment C ) . 3 . 1 . g Relationship to Other xisting and Planned Utility or Energy Generation and Transmission Facilities , Local Government Capital Improvement Programs , or Spec - al D ' strict Expansion Program ( C ) ( 1 ) ( g ) A description of the relationship of Pathway to other existing and planned energy generation and transmission facilities is provided in the response to Supplemental Question 15 . a . vii of the 1041 Questionnaire ( Attachment C ) . Pathway is not related to local government capital improvement programs or special district expansion programs . XCEL ENERGY 24 3 . 2 ENVIRONMENTAL IMPACT ANALYSIS ( 21 - 3 - 330 ( C ) ( 2 ) ) 3 . 2 . a Land Use ( C ) ( 2 ) ( a ) ) 3 . 2 . a . 1 Relationship of Project to Local Land Use , Policies , and Comprehensive Plans ( C) (2) (a) (1) A description of federal , state , and local permits and approvals that may be required prior to Pathway construction is provided in the 1041 Questionnaire response to S upplemental Question 15 . b . i ( Attachment C ) . An analysis of Pathway consistency with the Weld County Comprehensive Plan is provided as Attachment K . 3 . 2 . a . 2 Agricultural Productivity Capability of the Land Affected by the Proposal ( C) (2) (a) (11) P athway will not diminish agricultural productivity as explained in the 1041 Questionnaire response to Supplemental Question 15 . b . ii ( Attachment C ) . 3 . 2 . a . 3 Use of Existing Easements or Rights - of- Way for Associated Distribution or Collector Networks (C) (2) (a) (iii) A map showing existing transmission lines ( 115 - kV or greater ) within Weld County is provided as Attachment F . The transmission line ROW is located in existing easements or ROWs as much as possible . The Pathway transmission alignment within PSCo fee - owned ROW is subject to a separate Use by Special Review permit application submitted to Weld County concurrently with this Application . Information Regarding Other Utility Facilities ( C ) ( 2 ) ( b ) 3 . 2 . b . 1 Map each Existing Major Facility of a Public Utility of the Type Proposed for Development (5) (C) (2) (b) (i) A map showing existing transmission lines greater than 115 - kV within Weld County is provided as Attachment F . 3 . 2 . c Water Resources ( C ) ( 2 ) ( c ) ) 3 . 2 . c . 1 Map of Floodplains and Potential Impacts Associated with Proposal (C) (2) (c) (i) A map showing floodplains within the vicinity of Pathway is provided as Attachment L . P athway will avoid regulated floodplains to the extent practicable as described in the 1041 Questionnaire response to Supplemental Question 15 . c . i ( Attachment C ) . XCEL ENERGY 25 3 . 2 . c . 2 Potential Adverse Effects Upon Plant and Animal Life ( C) (2) (c) (ii) P athway will avoid or minimize impacts to plant and animal life generally as practicable . An analysis of potential adverse effects to plant and animal life is provided in the 1041 Questionnaire response to Supplemental Question 15 . c . ii ( Attachment C ) . 3 . 2 . d Significant Environmentally Sensitive Factors ( C ) ( 2 ) ( d ) 3 . 24 . 1 Map of and Description of Impacts on Sensitive Features Present in the Proposed Development or Activity and Its Vicinity ( C) (2) (d) (1) A map of Significant Environmentally Sensitive Factors is provided as Attachment M . A description of potential impacts on sensitive features is provided in the subsections below and in the 1041 Questionnaire response to Supplemental Questions 15 . d . i through 15 . d . v . ii ( Attachment C ) . Marshlands and Wetlands (C) (2) (d) (i) (a) P athway will avoid impacts to wetlands and other waters of the U . S . features to the extent practicable . An analysis of potential impacts to marshlands and wetlands is provided in the 1041 Questionnaire response to Supplemental Question 15 . d . i ( Attachment C ) . Groundwater Recharge Areas ( C) (2) (d) (1) (b) No impacts to groundwater recharge areas are anticipated . An analysis of potential impacts to groundwater recharge areas is provided in the 1041 Questionnaire response to Supplemental Question 15 . d . ii ( Attachment C ) . Potential Natural Hazards ( C) (2) (d) (I) (c) No significant natural hazards have been identified in the areas planned for Pathway development in Weld County . An analysis of potential impacts to potential natural hazards and risks from potential natural hazards is provided in the 1041 Questionnaire response to Supplemental Question 15 . d . iii ( Attachment C ) . Forests and Woodlands (C) (2) (d) (i) (d) P athway will avoid or minimize impacts to forests and woodlands generally as practicable . An analysis of potential impacts to forests and woodlands is provided in the 1041 Questionnaire response to Supplemental Question 15 . d . iv ( Attachment C ) . XCEL ENERGY 26 Critical Wildlife Habitat ( C) (2) (d) (1) (e) An analysis of potential impacts to wildlife species is provided in the 1041 Questionnaire response to Supplemental Question 15 . d . v ( Attachment C ) . Public Outdoor Recreation Areas ( C) (2) (d) (1) (t) No impacts to recreation areas are anticipated ; see the 1041 Questionnaire response to Supplemental Question 15 . d . vi ( Attachment C ) . Unique Areas of Geologic, Historic or Archeological Importance ( C) (2) (d) (i) (g) An analysis of areas of geologic , historic , or archaeological importance is provided in the 1041 Questionnaire response to Supplemental Question 15 . d . vii ( Attachment C ) . 3 . 2 . e Visual Aesthetics and Nuisance Factors ( C ) ( 2 ) ( e ) ) 3 . 2 . e . 1 Key Facility Viewing Locations , Facility Simulations , and Pollution or Obnoxious Odors ( C) (2) (e) (0) An analysis of potential visual impacts and noise and nuisance factors is provided in the 1041 Questionnaire response to Supplemental Question 15 . e . i ( Attachment C ) . Visual simulations from key locations where Pathway can be viewed are provided in Attachment N . 3 . 2 . e . 2 Map or Describe Area within View of Project ( C) (2) (e) (10 Visual simulations from key locations where Pathway can be viewed are provided in Attachment N . An analysis of the area within view of Pathway is provided in the 1041 Questionnaire response to Supplemental Question 15 . e . ii ( Attachment C ) . 3 . 2 . e . 3 Describe Mitigation Strategies ( C) (2) (e) (iii) Proposed mitigation strategies to minimize visual impacts , noise , and nuisance factors is provided in the 1041 Questionnaire response to Supplemental Question 15 . e . iii ( Attachment C ) . 3 . 2 . f ransportation Impacts ( C ) ( 2 ) CC 3 . 21. 1 Impacts upon Transportation Patterns ( C) (2) ( 00) Construction of Pathway is not expected to cause significant effects to Weld County transportation and any impacts will be temporary in nature ; see the 1041 Questionnaire response to Supplemental Question 15 . f . i ( Attachment C ) . XCEL ENERGY 27 3 . 212 Impacts on County Roads ( C) (2) (t) (ii) Temporary impacts to Weld County roads are described in the 1041 Questionnaire response to Supplemental Question 15 . f . ii ( Attachment C ) . Necessary road use and ROW permits will be obtained from Weld County as needed prior to construction . 3 . 2 . f. 3 Required Improvements to County Roads ( C) (2) (0010 Where practicable , existing public roads and private roads will be utilized during Pathway construction , maintenance , and operation . Some private roads may require improvements , and some new access roads will need to be constructed to accommodate construction equipment and long - term maintenance of the transmission line . Where road improvements are needed , Xcel Energy will acquire any necessary grading , stormwater , and erosion control permits and comply with permit requirements . Xcel Energy will acquire access easements where necessary access routes traverse private property . Some access routes may remain post - construction to maintain access to transmission lines for operation and maintenance activities . 3 . 2 . g Less Damaging Alternatives ( C ) ( 2 ) ( g ) 3 . 2 . g . 1 Potential for Significant Environmental Damage ( C) (2) (g) (1) An analysis of alternatives considered is summarized in the response to Supplemental Question 9 of the 1041 Questionnaire ( Attachment C ) . The Segment 1 : Fort St . Vrain — Canal Crossing Routing and Siting Study is included in Attachment B and provides an alternatives analysis to address this requirement . 3 . 2 . g . 2 Information on the Environmental Impacts and Cost- Effectiveness of the Alternatives (C) (2) (g) (ii) An analysis of alternatives considered is summarized in the response to Supplemental Question 9 of the 1041 Questionnaire ( Attachment C ) . The Segment 1 : Fort St . Vrain — Canal Crossing Routing and Siting Study is included in Attachment B and provides an alternatives analysis to address this requirement . XCEL ENERGY 28 3 . 3 ADDITIONAL REQUIREMENTS FOR SITE SELECTION AND CONSTRUC ON OF TRANSMISSION NES OR SUBS A IONS ( 21 - 3 - 330 ( C ) ( 3 ) ) 3 . 3 . a lectromagnetic Feld Measurements ( 21 3 330 ( C ) ( 3 ) ( a ) ) Noise and electric and magnetic fields ( EMF ) studies were conducted for Pathway and submitted as part of Pathways CPCN application ( Attachment O ) and is summarized in the 1041 Questionnaire response to Supplemental Question 14 . a ( Attachment C ) . 3 . 3 . b Colorado Public Utilities Commission ' s Rule 18 ( I ) ( 21 - 3 - 330 ( C ) ( 3 ) ( b ) ) A description of steps taken to comply with the CPUC ' s Rule 18 ( I ) is provided in the 1041 Questionnaire response to Supplemental Question 14 . b ( Attachment C ) . 4 WAIVER OF SUBMITTAL REQUIREMENTS ( 21 3 330 ( D ) ) Xcel Energy has conferred with County staff to ensure that this application gathers and presents everything that may be relevant to the County ' s decision , not unreasonably burdensome to produce , and that is not otherwise addressed by another agency or department with proper jurisdiction . It requests a waiver under Section 21 - 2 - 230 to the extent there are any code provisions requiring additional materials for submission . 5 APPROVAL REQUIREMENTS In accordance with Section 21 - 3 - 340 ( A ) of the Weld County , Colorado , Charter and County Code ( Weld County 2023a ) , this section describes how Pathway routing and site selection , construction , maintenance , and operation comply with the approval criteria for the Board of County Commissioners approval of the portion of the transmission line subject to this Application . Each criterion from Section 21 - 3 - 340 ( A ) is listed , followed by a description of how Pathway will comply . ( 1 ) The health , welfare and safety of the citizens of this County will be protected and served . P athway is a necessary capital improvement to expand the existing electric transmission grid system in Colorado . The location , construction , and operation of P athway will comply with applicable federal , state , and local regulations . P athway facilities will be designed , constructed , operated , and maintained to meet applicable standards of design and performance set forth in the National Electric Safety Code . XCEL ENERGY 29 P athway will be designed to minimize the risks from natural hazards , such as high winds and floods . Additional information on design and hazard avoidance and mitigation is provided in the 1041 Questionnaire response to Supplemental Question 3 ( Attachment C ) . (2) The natural and socio - economic environment of this County will be protected and enhanced . P athway facilities are sited to minimize impacts to natural resources as described in the responses to Supplemental Questions 4 and 15 of the 1041 Questionnaire ( Attachment C ) . Pathway will enhance the socio - economic environment in Weld County during the construction period via increased revenue to local businesses and social services . Project construction will require contract labor , and provide local jurisdictions and host communities with additional tax revenues and potential employment opportunities . Once in operation , Pathway may facilitate ongoing job opportunities and tax revenue in clean energy ( wind , solar , etc . ) that ultimately interconnect to Pathway . Additionally , generation developers will have the opportunity to build projects that otherwise were infeasible due to lack of transmission access to market and / or transmission constraints . These generation projects may provide other additional economic development through increased jobs associated with construction and local tax - based revenue associated with land usage , and payments to existing landowners . (3) All reasonable alternatives to the proposed action , including use of existing rights - of- way and joint use of rights - of- way wherever uses are compatible , have been adequately assessed and the proposed action is compatible with and represents the best interests of the people of the County and represents a fair and reasonable utilization of resources in the impact area . The design and need of Pathway have been approved by the CPUC and represents the use and application of best technology and industry standards for transmission and transformation of electric energy . Routing and siting studies were prepared to review and consider reasonable routing and siting alternatives for the new major electrical facilities ( pursuant to Colorado Revised Statute [ CRS ] 29 - 20 - 108 ( 4 ) ( a ) and ( b ) ) ( Attachment B ) . The Segment 1 : Fort St . Vrain — Canal Crossing Routing and Siting S tudy is included as Attachment B . Public open house meetings were conducted virtually in June 2021 and September 2021 and in Weld County in November 2021 and January 2022 to inform the public and key stakeholders about Pathway , gather feedback , and address questions and concerns . The analyses of alternatives evaluated in the routing and siting studies and feedback from public and key stakeholders were used to determine the proposed preferred locations for Pathway facilities in Weld County . The portions of Pathway in Weld County as described in this Application XCEL ENERGY 30 represent the best interests of the people in the County and the best utilization of resources in the impact area . ( 4) A satisfactory program to mitigate and minimize adverse impacts has been presented . P athway will mitigate and minimize adverse impacts as described in the responses to P upplemental Question 15 of the 1041 Questionnaire ( Attachment C ) . ( 5) The nature and location or expansion of the facility complies with all applicable provisions of the master plan of this County, and other applicable regional, metropolitan , state , and national plans . P athway is not inconsistent with any adopted county , regional , metropolitan , or state master plans or comprehensive plans . An analysis of Pathway consistency with the Weld County Comprehensive Plan ( Weld County , Colorado , Charter and County Code Chapter 22 , Comprehensive Plan ; Weld County 2023a ) is provided as Attachment K . P athway is sited within " Agriculture " zone districts within Weld County and is compatible with agricultural use . The transmission line alignment spans existing irrigation ditches and pivot irrigation in fields to minimize impact to existing agricultural operations ( Attachment P ) . Aside from the transmission pole foundation footprint , areas under and around Pathway facilities can continue to be used for agricultural operations after construction has been completed . Regarding transportation , Pathway will mitigate impacts to Weld County roads through use of BMPs and traffic control during construction , and post - construction restoration . ( 6) The nature and location or expansion of the facility does not unduly or unreasonably impact existing community services . P athway will not negatively affect the existing emergency health care facilities , social services , or law enforcement services as described in the response to Supplemental Question 4 of the 1041 Questionnaire ( Attachment C ) . P athway will not cause a significant change in land use in the immediate area . Current uses adjacent to Pathway facilities will be able to continue mainly unchanged after construction of Pathway thereby preserving desirable community and rural patterns which exist . Following construction , agricultural activities along the transmission line route can continue outside of the area occupied by the transmission poles . ( 7) The nature and location or expansion of the facility will not create an expansion of the demand for government services beyond the reasonable capacity of the community or region to provide such services , as determined by the Board of County Commissioners . XCEL ENERGY 31 P athway will not require additional local government services beyond those currently provided in the area . Pathway creates no additional demand for transportation infrastructure , educational facilities , housing , water ( other than water for construction ) , wastewater treatment , or public transportation . As described in the response to Supplemental Question 10 of the 1041 Questionnaire ( Attachment C ) , it is anticipated that an average of 20 to 30 trucks per day will be utilized during the construction of the transmission line for crews , spotting materials , framing poles , and erecting poles . Concrete truck deliveries will be made daily when the foundations and piers are being constructed . Multiple deliveries of cement ( up to 20 to 30 per day ) will be required daily at certain stages of construction . Materials will be delivered to the Cervi Yard at the onset of construction . An additional 10 to 15 trucks will be needed to deliver steel poles , conductor , anchor bolts , and foundation materials daily to work areas . The impact to local roads will vary day - by - day as construction moves along the route . To mitigate any potential impacts to Weld County roads , Traffic Control P lans will be prepared and followed during construction . ( 8) The facility site or expansion area is not in an area with general meteorological and climatological conditions which would unreasonably interfere with or obstruct normal operations and maintenance . P athway is not located in an area with meteorological or climatological conditions that would unreasonably interfere with normal operations and maintenance . Pathway is designed to minimize the risks from natural hazards such as high winds and floods . ( 9) The nature and location of the facility or expansion will not adversely affect the water rights of any upstream , downstream , or agricultural users , adjacent communities or other water users . P athway will not require water rights for construction or operation and will not affect existing water rights . ( 10) Adequate water supplies are available for facility needs . Water to be used during construction will be obtained from a local , permitted source . P athway will not require water use during operation . 01 ) The nature and location of the facility or expansion will not unduly interfere with any existing easements for or rights - of-- way, for other utilities , canals , mineral claims , or roads . As part of the land rights acquisition process , Xcel Energy will identify any existing easements or ROWs for other utilities , canals , mineral claims , or roads and will not XCEL ENERGY 32 cause any undue interference with existing easements or ROWs during construction and operation of Pathway . ( 12) Adequate electric , gas , telephone , water, sewage , and other utilities exist or shall be developed to service the site . P athway facilities will not require gas , telephone , water , sewage , or other utility service in Weld County . ( 13) The nature and location for expansion of the facility will not interfere with any significant wildlife habitat or adversely affect any endangered wildlife species , unique natural resource or historic landmark within the impact area . S ensitive natural resources and wildlife interests were considered in identifying the preferred location for the transmission line to minimize potential interference from P athway facilities . In addition , Xcel Energy has communicated with Colorado Parks and Wildlife and U . S . Fish and Wildlife representatives regarding Pathway and will continue to coordinate with them throughout design and construction of Pathway including compliance with applicable regulatory requirements . Pathway will not affect unique natural resources or historic landmarks in Weld County . ( 14) The nature and location or expansion of the facility, including expected growth and development related to the operation and provision of service , will not significantly deteriorate water or air quality in the impact area . Construction activities will be performed by methods that prevent entrance or accidental spillage of solid matter , contaminants , debris , or other pollutants and wastes into flowing streams or dry watercourses , lakes , and underground water sources . Activities will follow BMPs for the management of wastes to avoid and minimize effects from potential spills or other releases to the environment . Construction of the transmission line will not create runoff in excess of previous site levels and will not change existing topography or adversely affect drainage . No alteration in the pattern or intensity of surface drainage will occur as a result of construction or operation of the transmission line . Xcel Energy will comply with permit application requirements , Weld County standards , and construction protocols to ensure that Pathway does not affect water quality . Prior to construction , a Storm Water Permit for Construction Activities will be obtained from CDPHE , and a site - specific Stormwater Management Plan ( SWMP ) will be developed . S hort - term effects to air quality are anticipated from a temporary increase in construction vehicles , which may increase fumes and fugitive dust , construction equipment exhaust ( fumes ) , and clearing and preparing areas for construction ( dust ) . XCEL ENERGY 33 The short - term effects are not expected to cause a public nuisance . If a nuisance arises during construction , the nuisance will be mitigated in coordination with Weld County . Xcel Energy will apply for a CDPHE APEN for land development prior to construction and follow state standards to control the release of fugitive dust related to construction , if necessary . The APEN will be required for a disturbance greater than 25 contiguous acres and land development activities longer than 6 months . ( 15) The geological and topographic features of the site are adequate for all construction , clearing , grading, drainage , vegetation , and other needs of the facility construction or expansion . Xcel Energy will conduct geotechnical investigations to identify potential geologic hazards along the transmission line alignment . Xcel Energy also has institutional knowledge of the area because Xcel Energy owns the existing Fort St . Vrain Substation facilities immediately adjacent to the existing area that will be utilized . Based upon investigations to date and knowledge of the area , Xcel Energy does not believe there are significant risks from geological hazards associated with Pathway . The landscape along the Pathway facilities in Weld County is flat with little variation in topography . Pathway will not significantly change the existing topography . The transmission line is designed to conform with existing topography . ( 16) The existing water quality of affected state waters will not be degraded below state and federal standards or established baseline levels . Construction activities will be performed by methods that prevent entrance or accidental spillage of solid matter , contaminants , debris , and other pollutants and wastes into flowing streams or dry watercourses , lakes , and underground water sources . Activities will follow BMPs for the management of wastes to avoid and minimize effects from potential spills or other releases to the environment . Water quality will be maintained during construction through BMPs and the site - specific SWMP . Pathway will not impact the quantity or quality of water flowing off of the site . Where feasible , the transmission line will span streams and waterways that cross the corridor and impacts to state wafters will be avoided to the extent practicable . ( 17) The proposed project will not have a significantly adverse net effect on the capacities or functioning of streams , lakes and reservoirs in the impact area , nor on the permeability, volume , recharge capability, and depth of aquifers in the impact area . XCEL ENERGY 34 The transmission line will span or avoid any wetlands , streams , lakes , and reservoirs as feasible . Water quality will be maintained during construction through BMPs and the site - specific SWMP . Pathway will not impact aquifers . ( 18) The benefits of the proposed developments outweigh the losses of any natural resources or reduction of productivity of agricultural lands as a result of the proposed development . Construction and operation of Pathway will result in minimal permanent impacts to natural resources or agricultural lands . Aside from the transmission pole foundation footprint , areas under and around Pathway facilities can continue to be used for agricultural operations after construction has been completed . The development of Pathway in Weld County is anticipated to provide local economic benefits during construction and potential long - term economic benefits should new generation resources be developed in the area . Pathway will also improve the state ' s electric reliability , thereby benefiting all consumers in Colorado . ( 19) The applicant has obtained or will obtain all property rights , permits and approvals necessary for the proposed project, including surface , mineral and water rights and easements for drainage , disposal, utilities , access , etc . If the applicant has not obtained all necessary property rights , permits and approvals , the Board may, at its discretion , grant the permit conditioned upon completion of the acquisition of such rights prior to issuance of a zoning or building permit by the County . Xcel Energy will acquire all applicable permits and approvals necessary for Pathway ahead of conducting any work subject to such permits and approvals . Xcel Energy will also acquire possession of all necessary property interests in a parcel before initiating construction or other work associated with such interests . ( 20) The proposed project (nonlinear facilities) will not present an unreasonable risk of exposure to or release of toxic or hazardous substances within the impact area . The determination of effects of the project shall include the following considerations : (a) The means by which outdoor storage facilities for fuel, raw materials , equipment and related items are adequately enclosed by a fence or wall . No hazardous materials will be used , stored , or generated on site of Pathway facilities . Chemicals that may be used during construction and operation are those found in diesel fuel , gasoline , coolant ( ethylene glycol ) , and lubricants in machinery , and such chemicals , if any , will be kept within the TCAs pursuant to appropriate storage protocols and applicable regulatory controls . XCEL ENERGY 35 (b) The likelihood of hazardous materials or wastes being moved off the site by natural causes or forces . No hazardous materials will be permanently used , stored , or generated on site of Pathways facilities . Hazardous materials used during construction and operation will be used and disposed of in compliance with applicable federal , state , and local regulations . Enclosed containment will be provided for trash disposal . Construction waste , including trash and litter , garbage , other solid waste , petroleum products , and other potentially hazardous materials , will be removed and taken to a disposal facility authorized to accept such materials . Construction , operation , and maintenance activities will comply with applicable federal , state , and local laws and regulations regarding the use of hazardous substances . Construction activities will be performed using methods that prevent entrance or accidental spillage of solid matter , contaminants , debris , or other pollutants and wastes into flowing streams or dry watercourses , lakes , and underground water sources . Activities will follow BMPs for the management of wastes to avoid and minimize effects from potential spills or other releases to the environment . (c) Containment of inflammable or explosive liquids , solids or gases . Chemicals that may be used during construction and operation would be stored within TCAs , as set forth in Criterion ( 20 ) ( a ) above . Measures to contain or control any spill that may occur and to contact appropriate emergency offices and personnel will be formulated and designed in accordance with applicable federal , state , and local requirements . ( 21 ) The scope and nature of the proposed project will not unnecessarily duplicate existing services within the County. The scope of Pathway does not duplicate any existing services within Weld County . Pathway fills a need for a network transmission line facility to connect demand centers with areas of the state best situated for wind and solar generation projects . ( 22) If the purpose and need for the proposed project are to meet the needs of an increasing population within the County, area and community development and population trends demonstrate clearly a need for such development . The purpose and need for Pathway are not to meet the needs of an increasing population within Weld County but are primarily to meet the state ' s growing electricity needs ; improve electric safety , reliability and affordability ; and enable the transition to clean energy . XCEL ENERGY 36 6 1041 USR PROCEDURAL GUIDE PLANNING REQUIREMENTS CHECKLIST 6 . 1 PRE - APPLICATION MEETING MINUTES Xcel Energy participated in apre - application meeting with Weld County representatives on October 5 , 2022 . A copy of the pre - application meeting minutes provided by Planning Services is provided as Attachment Q . 6 . 2 APPL CA ION FORM The completed application form is provided as Attachment I . 6 . 3 AUTHOR ZA ION FORM Xcel Energy is currently negotiating with the potentially affected landowners for necessary land rights along the proposed transmission line route . These negotiations include securing an option for a permanent non - exclusive easement for the 150 - foot - wide ROW of the transmission line as well as permanent and temporary easements required for access and TCAs during and after construction . Once land surveying , final engineering design , and permitting have been completed , Xcel Energy will exercise the options and record the final easements . Easements required for Pathway construction will be secured and recorded prior to the start of construction on each individual parcel . ART CL S OF ORGANIZATION OR INCORPORATION The articles of incorporation of Xcel Energy are provided as Attachment R . 6 . 5 1041 QU ST ONNA R The completed 1041 Questionnaire , which addresses Supplemental questions for 1041 major facilities of public utilities , Planning questions , Environmental Health questions , Engineering questions , and Building questions , is provided as Attachment C . 6 . 6 CERT ED LIST O THE NAMES , ADDR SS S , AND PARC L NUMBERS OF T SURROUNDING PROPER Y OWNERS Attachment G contains a certified list of names , addresses , and the corresponding Parcel Identification Numbers assigned by the County Assessor of the owners of property within 1 , 250 feet on either side of the Pathway centerline . XCEL ENERGY 37 6 . 7 NAMES AND ADDRESSES OF ANY OWNER , OPERATOR OF ANY IRRIGATION DITCH , LA RAL , OR P PEL NE ON E PROP R Y The names and addresses of the owner/ operator of any irrigation ditch , lateral , or pipeline on the parcels crossed by the proposed transmission route is included as Attachment S . SURFACE USE AGR MENT W MINERAL OWNERS The " Surface Development Notification Act " ( Colorado Revised Statutes [ CRS ] 24 - 65 . 5 - 101 et seq . ) was passed specifically to facilitate mineral owner agreements like those contemplated by 21 - 3 - 330 ( B ) ( 2 ) ( d ) for many types of developments . That Act specifically excludes applications associated with electric lines , CRS 24 - 65 . 5 - 101 and 24 - 65 . 5 - 102 ( 2 ) ( a ) . That is because , generally speaking , transmission lines do not impact mineral interests . To the extent there are any active oil and gas activities or facilities within Xcel Energy ' s final proposed easement areas , Xcel Energy works with the owners / operators of such facilities to ensure it addresses and mitigates their concerns . 6 . 9 DE D Xcel Energy is currently negotiating with the potentially affected landowners for necessary land rights along the proposed transmission line route . These negotiations include securing an option for a permanent non - exclusive easement for the 150 - foot - wide ROW of the transmission line as well as permanent and temporary easements required for access and TCAs during and after construction . Once land surveying , final engineering design , and permitting have been completed , Xcel Energy will exercise the options and record the final easements . Easements required for Pathway construction will be secured and recorded prior to the start of construction on each individual parcel . 6 . 10 CER F CATE OF CONVEYANCES Conveyances are not required for Pathway . 6 . 11 STATEMENT OF TAXES Xcel Energy is currently negotiating with the potentially affected landowners for necessary land rights along the proposed transmission line route . These negotiations include securing an option for a permanent non - exclusive easement for the 150 - foot - wide ROW of the transmission line as well as permanent and temporary easements required for access and TCAs during and after construction . Once land surveying , final engineering design , and permitting have been completed , Xcel Energy will exercise the XCEL ENERGY 38 options and record the final easements . Easements required for Pathway construction will be secured and recorded prior to the start of construction on each individual parcel . Xcel Energy has no delinquent taxes for the parcels owned by Xcel Energy in Weld County , as demonstrated in Attachment T . 6 . 12 EV DENCE OF ADEQUA E WA ER SUPP Y Water to be used during construction will be obtained from a local , permitted source . P athway will not require water use during operation . 6 . 13 V D NCE OF AD QUATE SEWAG DISPOSAL P athway will not create any wastewater nor have any facilities requiring wastewater treatment . Portable temporary bathrooms that will be serviced on a regular basis will be on site during the construction period . 6 . 14 NO ICE OF NQU RY FORM Xcel Energy understands that Weld County will initiate this form if required for Pathway . DRAINAGE NARRAT A Drainage Narrative is provided in the responses to Engineering Question 3 in the 1041 Questionnaire ( Attachment C ) . 6 . 16 RAF IC NARRATIV 1 . Describe how many roundtrips / day are expected for each vehicle type : Passenger Cars / Pickups , Tandem Trucks , Semi - Truck / Trailer/ RV ( Roundtrip = One ( 1 ) trip in and One ( 1 ) trip out of site ) . S ee the response to Engineering Question 1 . b in the 1041 Questionnaire ( Attachment C ) . 2 . Describe the expected travel routes or haul routes for site traffic . S ee the response to Engineering Question 1 . c in the 1041 Questionnaire ( Attachment C ) . 3 . Describe the travel distribution along the routes ( e . g . 50 % of traffic will come from the north , 20 % from the south , 30 % from the east , etc . ) . S ee the response to Engineering Question 1 . d in the 1041 Questionnaire ( Attachment C ) . 4 . Describe the time of day that you expect the highest traffic volumes . XCEL ENERGY 39 See the response to Engineering Question 1 . e in the 1041 Questionnaire ( Attachment C ) . 6 . 17 SIGN PLAN No signage is proposed . 6 . 18 NUISANCE ABATEMENT PLAN Short - term effects to air quality are anticipated from a temporary increase in construction vehicles , which may increase fumes and fugitive dust , construction equipment exhaust ( fumes ) , and clearing and preparing areas for construction ( dust ) . The short - term effects are not expected to cause a public nuisance . If a nuisance arises during construction , the nuisance will be mitigated in coordination with Weld County . 6 . 19 LANDSCAPE AND SCR N NG PLAN A landscaping plan is not proposed as a part of Pathway . Visual simulations from key locations where Pathway can be viewed are provided in Attachment N . The anticipated impact to visual aesthetics is provided in the response to Planning Question 1 . m in the 1041 Questionnaire ( Attachment C ) . The transmission poles will be weathering steel that oxidizes to resemble a natural brown look . 6 . 20 DECOMMISSIONING PLAN The Decommissioning Plan is provided as Attachment J . 6 . 21 EMERGENCY INCIDENT ACTION PLAN Xcel Energy ' s substations and powerlines are monitored and controlled remotely from an operations center where event response is coordinated . In the rare event of an emergency , Xcel Energy will likely be aware of an issue before the general public or emergency responders . Nevertheless , the public is encouraged to contact Xcel Energy ' s emergency number : 800 - 895 - 1999 to report an emergency . Unauthorized personnel , including emergency responders , should not approach the facilities and should not touch the electric lines or anyone or anything in contact with them . In the event of an outage or transformer failure , the affected substation equipment is immediately de - energized by the breaker equipment and Xcel Energy personnel are dispatched to the site . Xcel Energy personnel receive safety training for emergency situations relating to high - voltage electrical equipment . Xcel Energy also coordinates closely with local fire departments and first responders and consults with them to discuss any concerns within their response area . Xcel Energy offers free online safety training to fire departments and first responders that is based on national standards XCEL ENERGY 40 through the Responding to Utility Emergencies Program . The Weld County 1041 USR P rocedural Guide Major Facility of a Public Utility includes a requirement for a draft emergency incident action plan if applicable . Xcel Energy ' s Emergency Response P rocedures are provided as Attachment U . 6 . 22 NO SE STUDY Noise and EMF studies were conducted for Pathway and submitted as part of P athways CPCN application and is included as Attachment O . The study concluded that the maximum projected noise level measured at 25 feet from the edge of the ROW is 49 . 8 A - weighted decibels ( dBA ) . Per CPUC Rule 3206 ( f ) , noise levels below 50 dBA are not subject to further review regardless of the use of land , and noise levels below 75 dBA are deemed reasonable for land within an Industrial Zoning at 25 feet from the property line ( Section 4 Colorado Code of Regulations [ OCR ] 723 - 3 ) . The projected noise levels from the Pathway transmission line were deemed reasonable by the CPUC and not subject to further review . 6 . 23 SOIL REPORT ' A Soil Report of the site prepared by the Natural Resource Conservation Service is provided as Attachment V . 6 . 24 COMMON TY ME NG SIGN - N S T MIND S , AND SUMMARY P ublic open houses were held regarding Pathway in Platteville on November 1 , 2021 , and January 24 , 2022 ( see Section 1 . 2 . a for additional information ) . Copies of the public open house sign in sheets and public information boards from these meetings in P latteville is provided as Attachment W . A summary of the public open houses is provided in Section 3 . 4 , Step 4 : Focus Areas , of the Routing and Siting Study for P egment 1 ( Attachment B ) . 6 . 25 APPL CA ION E The application fee will be submitted once this Application has been deemed complete by Weld County . 6 . 26 NVEST GAT ON P athway is not under investigation for any violations . XCEL ENERGY 41 6 . 27 PLANN D ACCESS AND ACC SS AGREEM NTS Construction and maintenance access for the proposed transmission line are shown on Attachment D . Only a small portion of the transmission line ROW will be disturbed for structure installation and vehicle access . Much of the transmission line ROW can be accessed from existing Weld County roads . Once vehicles have entered the transmission line ROW , access will follow the ROW where possible . In areas where construction access is required outside of the transmission line ROW , temporary construction easements will be secured to support construction . No easements or other forms of access agreements have been executed by Xcel Energy by the date of this Application , nor will such access be acquired prior to County approval of the Project . All associated driveway access permits will be obtained from Weld County prior to the commencement of construction . The proposed transmission line road right - of- way crossings are described in the response to Engineering Question 2 of the 1041 Questionnaire ( Attachment C ) . 6 . 28 NAMES AND ADDRESSES OF PERSONS OR ENTITIES WITH AN N RES IN ANY REAL PROPER Y PROPOS D TO BE PHYS CA LY DISTURBED OR CROSSED Attachment G contains a certified list of names , addresses , and the corresponding Parcel Identification Numbers assigned by the County Assessor of persons or entities with an interest in any real property proposed to be crossed by the 150 - foot - wide ROW of the transmission line that is the subject of this Application . 6 . 29 NAMES AND ADDRESSES OF M NERAL IN ERES HOLDERS WIT AN NT R ST IN ANY REAL PROP RTY PROPOSED TO BE PHYSICALLY DISTURBED OR CROSS D See response to Section 6 . 8 , Surface Use Agreement with Mineral Owners , of this Application . 6 . 30 1041 USR MAP The 1041 USR Map is provided as Attachment D . 6 . 31 MAP SHOWING EX S NG TRANSM SS ON LINES A map showing existing transmission lines ( 1154V or greater ) within Weld County is provided as Attachment F . XCEL ENERGY 42 6 . 32 MAP SHOWING EACH MAJOR FACILITY OF A PUBLIC UTILITY W N HE COUNTY OF HE TYPE PROPOSED A map showing existing transmission lines ( 1154V or greater ) within Weld County is provided as Attachment F . 6 . 33 MAP OF EATURES PRESENT IN HE VCN Y AND POT NT A IMPACT OF THE PROPOSAL The Significant Environmentally Sensitive Factors Map ( Attachment M ) includes the following features in the vicinity of the proposed transmission line subject to this Application : • Marshlands and wetlands • Groundwater recharge areas if applicable . • Potential natural hazards • Forests and woodlands • Critical wildlife habitat • Public outdoor recreation areas • Unique areas of geologic , historic or archeological importance 7 COMPLIANCE WITH REVIEW CRITERIA 23 - 2 - 220 . A AND 23 - 2 - 230 . 6 1 . That the proposal is consistent with in Chapter 22 (the Weld County Comprehensive Plan) and any other applicable code provisions or ordinances in effect . An analysis of Pathway consistency with the Weld County Comprehensive Plan is provided as Attachment K . 2 . That the proposal is consistent with the intent of the district in which the use is located . Pathway is sited in the Agricultural zone district and is consistent with the intent of this district as described in the response to Planning Question 3 of the 1041 Questionnaire ( Attachment C ) . XCEL ENERGY 43 3 . That the uses which would be permitted will be compatible with the existing surrounding land uses . P athway is sited in the Agricultural zone district and is compatible with existing agricultural land use as described in the response to Planning Question 1 . b of the 1041 Questionnaire ( Attachment C ) . 4 . That the uses which would be permitted will be compatible with the future development of the surrounding area as permitted by the existing zone and with future development as projected by Chapter 22 of this Code and any other applicable code provisions or ordinances in effect, or the adopted master plans of affected municipalities . P athway is compatible with future development as described in the response to P lanning Question 4 of the 1041 Questionnaire ( Attachment C ) . 5 . That the application complies with Articles V and XI of this Chapter if the proposal is located within an overlay zoning district or a special flood hazard area identified by maps officially adopted by the county. P athway is not located within an overlay zoning district or special flood hazard area . 6 . That if the use is proposed to be located in the A (Agricultural) Zone District, the applicant has demonstrated a diligent effort has been made to conserve prime farmland in the locational decision for the proposed use . P athway facilities have been sited to conserve prime farmland as described in the response to Planning Question 6 of the 1041 Questionnaire ( Attachment C ) . 7 . That there is adequate provision for the protection of the health , safety and welfare of the inhabitants of the neighborhood and the county. P athway will not interfere with the protection of the health , safety , and welfare of the inhabitants of the neighborhood and the County as described in the response to P lanning Question 7 of the 1041 Questionnaire ( Attachment C ) . 8 COMPLIANCE WITH DESIGN STANDARDS 23 - 2 - 240 . A 1 . Adequate water service in terms of quality, quantity and dependability is available to the site to serve the uses permitted . Water to be used during construction will be obtained from a local , permitted source . P athway will not require water use during operation . 2 . Adequate sewer service is available to the site to serve the uses permitted . XCEL ENERGY 44 Pathway will not create any wastewater nor have any facilities requiring wastewater treatment . Portable temporary bathrooms that will be serviced on a regular basis will be on site during the construction period . 3 . If soil conditions on the site are such that they present moderate or severe limitations to the construction of structures or facilities proposed for the site , the applicant has demonstrated how such limitations can and will be mitigated . No significant natural hazards have been identified in the areas planned for Pathway development in Weld County . See the response to Supplemental Question 15 . d . iii of the 1041 Questionnaire ( Attachment C ) and the Soil Report ( Attachment V ) . 4 . Adequate fire protection measures are available on the site for the structures and facilities permitted . Xcel Energy ' s facilities are designed , constructed , operated , and maintained to meet or exceed all applicable requirements of the Institute of Electrical and Electronics Engineers ( IEEE ) standards and accepted industry standards and practices including IEEE 979 , Guide for Substation Fire Protection . Applicable fire laws and regulations , as outlined in CRS 31 - 15 - 601 , will be observed during construction and normal operation of the transmission line . See the response to Planning Question la - o of the 1041 Questionnaire ( Attachment C ) . 5 . Uses shall comply with the stormwater drainage criteria requirements set forth in this Code . A Drainage Narrative is provided in the response to Engineering Question 3 in the 1041 Questionnaire ( Attachment C ) . 6 . All parking and vehicle storage shall be provided on the site . Parking and loading areas shall be designed and constructed in accordance with Division 1 of Article IV of this Chapter. No public parking spaces are needed for Pathway and access drives from nearby roads for construction and maintenance are shown in Attachment D . 7 . The use shall comply with all the Bulk Standards requirements of the zone district . Section 23 - 3 - 70 of the Weld County , Colorado , Charter and County Code includes the bulk standards requirements of the Agricultural zone district . The Pathway facilities subject to this Application do not require lots , occupied buildings , or structures . Pathway is not requesting approval of animal units . Pathway facilities subject to this Application do not include sources of light . Therefore , the bulk standards requirements of Section 23 - 3 - 70 do not apply . XCEL ENERGY 45 8 . The access shall be located and designed to be safe ; ingress and egress shall not present a safety hazard to the traveling public or to the vehicle accessing the property. For uses generating high traffic volumes and large number of large , slow- accelerating vehicles , acceleration and deceleration lanes may be required to mitigate a potential traffic hazard . Access to the transmission poles will be off nearby roads to the transmission line ROW . All necessary access permits will be obtained prior to construction . See the response to Engineering Question 2 in the 1041 Questionnaire ( Attachment C ) . 9 . New accesses to public rights - of- way shall be constructed in accordance with this Code . Any new accesses to public ROW will be constructed in accordance with Weld County Code . See the response to Engineering Question 2 in the 1041 Questionnaire ( Attachment C ) . 10 . Buffering or screening of the proposed use from adjacent properties may be required in order to make the determination that the proposed use is compatible with the surrounding uses . buffering or screening may be accomplished through a combination of berming , landscaping and fencing . No screening is proposed . See the response to Planning Question 1 . m in the 1041 Questionnaire ( Attachment C ) . 11 . Uses by Special Review in the A (Agricultural) Zone District shall be located on the least prime soils on the property in question unless the applicant can demonstrate why such a location would be impractical or infeasible . Aside from the transmission pole foundation footprint , areas under and around Pathway facilities can continue to be used for agricultural operations after construction has been completed . Pathway facilities have been sited to conserve prime farmland as described in the response to Planning Question 6 of the 1041 Questionnaire ( Attachment C ) . 12 . The placement of signs on the site shall comply with the requirements of Article IV, Division of this Chapter. No signs are proposed . 13 . Trash collection areas or facilities shall be screened from public rights - of- way and adjacent properties . These areas shall be designed and used in a manner that will prevent wind - or animal - scattered trash . Construction waste , including trash and litter , garbage , other solid waste , petroleum products , and other potentially hazardous materials , will be removed and taken to a XCEL ENERGY 46 disposal facility authorized to accept such materials . Enclosed containment will be provided for trash disposal . 9 COMPLIANCE WITH OPERATION STANDARDS 23 - 2 - 250 A . The operation of the USES shall comply with the noise standards enumerated in Section 25 - 12 - 101 , et seq . , C . R . S . The CPUC provides reasonableness determinations associated with noise and requires CPCN applicants to evaluate the expected level of noise of the proposed transmission facilities . Xcel Energy is required to meet state standards as outlined in the Code of Colorado Regulations ( Section 4 CCR 723 - 3 ) . See the response to Supplemental Question 15 . e . i of the 1041 Questionnaire ( Attachment C ) and the noise and EMF studies ( Attachment O ) . B . The operation of the USES shall comply with the air quality regulations promulgated by the Colorado Air Quality Control Commission . During operation of Pathway , exhaust and dust are not expected . See the response to Supplemental Question 10 of the 1041 Questionnaire ( Attachment C ) . C . The operation of the USES shall comply with the water quality regulations promulgated by the Colorado Water Quality Control Commission . Pathway will comply with applicable federal and state regulations . Xcel Energy will comply with permit application requirements , County Standards , and construction protocols to ensure that Pathway does not violate water quality standards . Prior to construction , a Storm Water Permit for Construction Activities will be obtained from CDPHE . An analysis of water resources impacts and control measures is provided in the response to Supplemental Question 15 . d . i of the 1041 Questionnaire ( Attachment C ) . D . The USES shall comply with the following lighting standards : 1 . Sources of light, including light from high - temperature processes such as combustion or welding , shall be shielded so that light rays will not shine directly onto ADJACENT properties where such would cause a nuisance or interfere with the USE on the ADJACENT properties ; and No lighting is proposed . 2 . Neither direct nor reflected light from any light source may create a traffic hazard to operators of motor vehicles on PUBLIC or private XCEL ENERGY 47 STREETS/ROADS and no colored lights maybe used which maybe confused with or construed as traffic control devices . No lighting is proposed . E. The USES shall not emit heat so as to raise the temperature of the air more than five degrees ( 5 °) Fahrenheit at or beyond the LOT line . The transmission line will not emit heat . F. Property shall be maintained in such a manner that grasses and weeds are not permitted to grow taller than twelve ( 12) inches . In no event shall the property owner allow the growth of NOXIOUS WEEDS . Measures will be implemented to minimize the spread of noxious weeds in the ROW . S ee the response to Supplemental Question 15 . d . iv of the 1041 Questionnaire ( Attachment C ) and the Noxious Weed Control Measures provided in Attachment X . G . Any off- site and on - site Improvements Agreement shall be made in conformance with the County policy on collateral for improvements . Xcel Energy will negotiate an Improvements Agreement with Weld County prior to construction , if required . 10 REFERENCES APLIC ( Avian Power Line Interaction Committee ) . 2006 . Suggested practices for raptor protection on power Lines ; the State of the Art in 2006 . Edison Electric Institute , APLIC and the California Energy Commission Washington , D . 0 and Sacramento , CA . CNHP ( Colorado Natural Heritage Program ) . 2022 . Statewide Elements by 7 . 5 - minute U SGS Quadrangle ( shapefile ) . Available online at : https : // cnhp . colostate . edu / maps / cnhp - spatial - layers / # element . Accessed January 2023 . CPW ( Colorado Parks and Wildlife ) . 2020 . Recommended Buffer Zones and Seasonal Restrictions for Colorado Raptors ( 2020 ) . Available online at : https : // cpw . state . co . us / Documents / WildlifeSpecies / LivingWithWildlife / Raptor - Buffer - Guidelines . pdf . Accessed January 2023 . CPW . 2021 . Recommended Survey Protocol and Actions to Protect Nesting Burrowing Owls . Available online at : https : // cpw . state . co . us / Documents / WildlifeSpecies / LivingWithWildlife / Recommended - S urvey - Protocol - Burrowing - Owls . pdf . Accessed January 2023 . XCEL ENERGY 48 CPW . 2022a . All Species Activity Mapping Data . Updated January 6 , 2022 . Available online at : https : / / hub . arcgis . com / content / 190573c5aba643a0bc058e6f7f0510b7 / about . Accessed January 2023 . CPW . 2022b . Threatened and Endangered Species List . Available online at CPW All S pecies Activity Mapping Data - Overview ( arcgisscom ) Available online at : http : / / cpw . state . co . us / learn / Pages / SOC - ThreatenedEndangeredList . aspx . Accessed January 2023 . CPW . 2022c . CPW Species Profiles . Available online at : https : / / cpw . state . co . us / learn / Pages / SpeciesProfiles . aspx . Accessed April 2022 . EPA ( U . S . Environmental Protection Agency ) . 2022 . Current Nonattainment Counties for All Criteria Pollutants . Available online at : https : / / www3 . epa . gov / airquality / greenbook / ancl . html . Accessed December 2022 . FRED ( Federal Reserve Economic Data ) . 2022a . Unemployment Rate in Weld County , Colorado . Available online at : https : / / fred . stlouisfed . org / series / COWELD3URN . Accessed December 2022 . FRED . 2022b . Unemployment Rate in Colorado . Available online at : https : / / fred . stlouisfed . org / series / LOUR . Accessed December 2022 . Google . 2022 . Google Earth Pro Aerial Imagery . Accessed online at : https : / / earth . google . com / web / . Accessed January 2023 . HIFLD ( Homeland Infrastructure Foundation - Level Data ) . 2022 . Electric Power Transmission Lines . Available online at : https : / / hifld - geoplatform . opendata . arcgis . cam / datasets / geoplatform : : electric - power - transmission - lines / explore ? location = 38 . 995337 % 2C - 87 . 352132 % 2C11 . 99 . Accessed December 2022 . NLCD ( National Land Cover Database ) . 2019 . National Land Cover Database . Available online at : https : / / www . mrlc . gov / data ? f % 5B0 % SD = category % 3ALand % 20Cover & f % 5B1 % SD = year % 3A2019 . Accessed May 2023 . P LJV ( Playa Lakes Joint Venture ) . 2022 . Playa Lakes Joint Venture Probable Playa Dataset . Available online at : https : / / pljv . org / playas / playa - tools / . Accessed January 2023 . U . S . Census Bureau . 2022 . QuickFacts : Weld County , Colorado . Available online at : https : / / www . census . gov / quickfacts / weldcountycolorado . Accessed December 2022 . U SFWS . 2022a . ECOS Threatened and Endangered Species Active Critical Habitat Report , Available online at : http : / / ecos . fws . gov / crithab / . Accessed January 2023 . XCEL ENERGY 49 U SFWS ( U . S . Fish and Wildlife Service ) . 2022a . USFWS Information for Planning and Conservation ( IPaC ) . Available online at : https : // ecos . fws . gov / ipac / . Accessed January 2023 . U SFWS . 2022b . Threatened & Endangered Species Active Critical Habitat Report . Available online at : https : // ecos . fws . gov / ecp / report / table / critical - habitat . html . Accessed January 2023 . U SFWS 2022c . National Wetland Inventory Mapper . Available online at : https : //fwsprimary . wim . usgs . gov/ wetlands / apps / wetlands - mapper / . Accessed January 2023 . U SFWS . 2022d . USFWS Threatened and Endangered Species Active Critical Habitat Report . Available online at : https : // ecos . fws . gov/ ecp / report / table / critical - habitat . html . Accessed January 2023 . U SGS ( U . S . Geological Survey ) . 2019 . Land Cover Database . Multi - Resolution Land Characteristics ( MRLC ) Consortium . Available online at : https : / / www . mrlc . gov /viewer/ . Accessed January 2023 . U SGS . 2022a . National Hydrography Dataset . https : // www . usgs . gov/ national - hydrography / national - hydrography - dataset . Accessed April 2022 . U SGS . 2022b . USGS Historical Topographic Map Explorer . Available online at : https : / / ngmdb . usgs . gov / topoview / viewer/ # 15 / 30 . 1212 / - 81 . 5196 . Accessed December 2022 . Weld County . 2023a . Weld County , Colorado , Charter and County Code . Version June 8 , 2023 . Available online at : https : // library . municode . com / co / weld county / codes / charter and _ county_code . . Accessed June 2023 . Weld County . 2023b . Weld County Property Portal : Zoning . Available online at : https : // www . co . weld . co . us / maps / zoning / . Accessed March 2023 . Xcel Energy . 2021 . Our Energy Future : Destination 2030 , 2021 Electric Resource Plan and Clean Energy Plan . March 31 , 2021 . Available online at : https : / / www . xcelenergy . com / cornpany / rates and regulations / resource plans / clean _ene rgy plan . Accessed March 2022 . COLORADO ' S POWER PATHWAY ATTACHMENT A : VICINITY MAP SEE TYLER NUMBER 2024 - 0555 Weld County Site Selection and Construction of Major Facilities of a Public Utility Application COLORADO S POWER PATHWAY ATTACHMENT B : ROUTING AND SITING STUDY FOR SEGMENT 1 SEE TYLER NUMBER 2024 0552 Weld County Site Selection and Construction of Major Facilities of a Public Utility Application COLORADO ' S POWER PATHWAY ATTACHMENT C : PLANNING QUESTIONNAIRE Weld County Site Selection and Construction of Major Facilities of a Public Utility Application COLORADO ' S POWER PATHWAY i LIST OF ACRONYMS AND ABBREVIATIONS 1041 Location and Extent Areas and Activities of State Interest ( 1041 ) 24 / 7 / 365 24 Hours a Day , 7 Days a Week , 365 Days a Year APEN Air Pollutant Emissions Notice BMP Best Management Practice CCR Code of Colorado Regulations CDPHE Colorado Department of Public Health and Environment CFR Code of Federal Regulations Compass Colorado Cultural Resource Online Database CPCN Certificate of Public Convenience and Necessity CPUC Colorado Public Utilities Commission CPW Colorado Parks and Wildlife CRS Colorado Revised Statutes dBA A - Weighted Decibels EMF Electric and Magnetic Fields FAA Federal Aviation Administration HIFLD Homeland Infrastructure Foundation - Level Data - 76 Interstate 76 IEEE Institute of Electrical and Electronics Engineers IPaC Information for Planning and Consultation KOP Key Observation Point kV Kilovolt mG Milligauss NAAQS National Ambient Air Quality Standards NESC National Electrical Safety Code NHD National Hydrography Dataset NWI National Wetland Inventory Pathway Colorado ' s Power Pathway ROW Right - of- Way COLORADO ' S POWER PATHWAY ii S C Species of Concern S WMP Solid Waste Management Plan TCA Temporary Construction Area U S - U . S . Highway U SFWS U . S . Fish and Wildlife Service U SR Use by Special Review WOTUS Waters of the U . S . Xcel Energy Public Service Company of Colorado , a Colorado corporation doing business as Xcel Energy TABLES Table 1 : Employees and Shifts per Phase 4 Table 2 : Anticipated Segment 1 In - Service Dates 5 Table 3 : Land Use Permit Requirements and Applicability to Pathway 16 Table 4 : Land Use and Land Cover Present within 1 Mile of Proposed Pathway Facilities in Weld County — New Transmission Line ROW 23 Table 5 : Land Use and Land Cover Present within Proposed Pathway Facilities in Weld County — Within Cervi Yard and Parcels Adjacent to Cervi Yard 24 Table 6 : NWI Length Crossed by the Transmission Line in Weld County — New Transmission Line ROW 26 Table 7 : Special - Status Species Potentially Occurring within 1 Mile of Proposed P athway Facilities in Weld County 29 Table 8 . Summary of Views from Selected Key Observation Points ( KOPs ) 36 Table 9 . Daily Vehicle Trips during Transmission Line Construction in Weld County 51 COLORADO ' S POWER PATHWAY 1 U SE BY SPECIAL REVIEW QUESTIONNAIRE S UPPLEM NTAL QUESTIONS FOR 1041 MAJOR FAC L T S OF P UBLICU IL I . S The sections that follow address potential impacts from construction , maintenance , and operation of the portion of Colorado ' s Power Pathway ( Pathway ) in Weld County subject to the Location and Extent Areas of Activities of State Interest ( 1041 ) Application , as well as proposed mitigations where appropriate . Pathway is being proposed by Public Service Company of Colorado , a Colorado corporation conducting business as Xcel Energy ( Xcel Energy ) . 1 . Describe the type of facility . Specify where applicable : a . The voltages and lengths of transmission lines . The voltage of the double - circuit transmission line will be 345 - kilovolt ( kV ) . The length of transmission line in Weld County that is subject to the 1041 Application is 34 . 3 miles . Additional transmission lines will be permitted through Weld County as a Use by Special Review ( submitted concurrently with this 1041 Application ) . b . Power source and generating capacity . No generation is proposed . c . The functions and sizes of substations . Additions to the Fort St . Vrain Substation are not subject to this 1041 Application ; they are subject to a Site Plan Review separate from this 1041 Application . d . The capacities of storage tanks and types of petroleum derivative to be stored . No petroleum derivative will be stored , and no storage tanks will be needed . e . Corridor locations . The proposed transmission line corridor subject to 1041 Application is shown on Vicinity Map in Attachment A . The corridor subject to this 1041 Application starts approximately 0 . 9 mile east of Weld County Road 33 , travels to the north for approximately 0 . 5 mile to Weld County Road 28 , then east along Weld County Road 28 for approximately 2 miles to Weld County Road 39 . The corridor continues south along Weld County Road 39 for approximately 0 . 5 mile to Weld County Road 26 , then east along Weld County Road 26 for approximately 8 miles . The corridor continues southeast for approximately 5 . 5 miles COLORADO ' S POWER PATHWAY 2 to the Interstate 76 ( I - 76 ) / US - 6 ( US - 6 ) right - of - way ( ROW ) and continues east for approximately 6 miles where the transmission line corridor crosses the I - 76 / US - 6 ROW . The corridor then generally parallels the Burlington Northern Santa Fe Railroad ROW for approximately 9 . 5 miles to the corridor endpoint . f. Service area . P athway is an addition to Colorado ' s backbone transmission system and does not provide distribution electric service ; as such , this 1041 Application does not address project - specific details that apply for developments or direct utility service projects . g . Resource area (e . g . , source of power being generated or transmitted) . P athway does not connect to a specific power source . Facilities in Weld County are part of the larger Pathway that creates a transmission " loop " to provide additional transmission capacity . Pathway is being routed through some of the best wind and solar resource zones in Colorado . New renewable energy generation is anticipated to be developed in these zones . The location of these new generation resources is currently unknown until Xcel Energy ' s Electric Resource Plan process has been completed . Generally , new generation resources are expected to interconnect at substations located at segment endpoints . h . Applicable support facilities (e . g . , pollution control, parking areas , landscaping , etc . ) to be provided . As described in the response to review criteria 21 - 3 - 340 ( A ) ( 14 ) in Section 5 of this 1041 Application , best management practices ( BMPs ) will be used during construction to control sediment and runoff from work areas . Compliance with applicable federal , state and county construction and waste management procedures will prevent accidental spills or runoff of sediment or contaminants to waterbodies or groundwater . P athway is not anticipated to generate pollution during operations and maintenance and will not require permanent pollution control equipment . A Stormwater Management Plan ( SWMP ) will be created , and stormwater management features incorporated into the design as necessary . No public parking spaces are needed for Pathway , and access drives from nearby roads for construction and maintenance have been incorporated into the transmission line design . Access to the transmission poles will be off nearby roads to the transmission line ROW . Once construction has been completed , areas not needed for operations and maintenance will be reclaimed in a manner generally similar to their condition prior to COLORADO ' S POWER PATHWAY 3 construction or as may be provided for in private agreements ( including by re - seeding in accordance with Xcel Energy ' s vegetation management standards and SWMP ) . 2 . Describe the projected development schedule . Specify where applicable : a . Estimated maximum number of employees , number of shifts and employees per shift during the construction , operation and maintenance phases of the project . It is anticipated that one 12 - hour shift per day ( Monday through Saturday ) will be worked during transmission line construction , but additional hours may be required . This will be during daylight hours , early morning to early evening . If additional hours are anticipated for shift work , a 24 - hour work permit will be obtained from Weld County . The maximum number of construction workers on site at any one time at any work area will be approximately 60 to 80 for the new transmission line when all phases are active . Transmission line construction is expected to be completed in phases over the duration of the construction schedule for each Pathway segment . Construction of the Pathway transmission line is expected to occur in phases that generally include the following : construction access and vegetation clearing , installation of BMPs , equipment mobilization and material delivery , foundation construction , transmission pole placement , and installation , conductor wire stringing and electrical equipment installation , and land restoration . Construction access road improvements , grading , and setup of temporary construction areas ( TCAs ) , along with vegetation work , will be conducted before construction of the transmission line . Proposed access roads will allow construction crews and vehicles to access transmission pole locations and TCAs as needed . Segment 1 construction , including the Pathway facilities in Weld County , is expected to last up to 24 months , with construction beginning in spring / summer 2024 and a target in - service date in spring / summer 2026 . See Section 1 . 1 of this 1041 Application for additional information regarding the Pathway schedule . The transmission line will not have any permanent on - site employees . Upon completion , Pathway will be operated and monitored remotely 24 hours a day , 7 days a week , 365 ( 24 / 7 / 365 ) days a year to provide safe and reliable electric service . The transmission line will be inspected regularly ( at least annually ) to look for the following : • Non - compatible vegetation and hazards within the ROW . • Equipment needing repair or replacement . COLORADO ' S POWER PATHWAY 4 • ROW encroachments , which can be hazardous to safety and reliable operations . • Anything that might jeopardize safe , reliable operation of the power line . Operations and maintenance staff must visit the ROW for these inspections , but visits typically are few , and landowners will be contacted prior to on - site inspections or maintenance . However , in cases of emergency , advanced contact may not be possible . Table 1 shows the estimated maximum number of employees , number of shifts , and employees per shift during the construction and operation and maintenance phases of P athway . Table 1 : Employees and Shifts per Phase Construction Phase Em • to ees Shifts Em • to ees • er Shift Construction 60 to 80 employees for One 12 - hour shift Up to 80 employees transmission line ( Monday to Saturday ) Operations None — the facilities are Remotely monitored None unstaffed with the 24 / 7 / 365 exception of remote monitoring Maintenance 2 - 6 employees 1 to 2 times a month , 2 to 6 employees as needed b . Any future phases or extensions of the facility and relationship of the facility (if currently foreseen) to larger programs and plans . The proposed facilities in Weld County are part of Pathway . Pathway will add a network transmission system that can integrate wind and solar generation sources in the Eastern Plains region of Colorado where they are most efficient to where the energy demand is the highest . By linking the best areas for generating wind and solar energy with where demand is , Pathway will improve the state ' s electric grid and enable future renewable energy development in the Eastern Plains region of Colorado . Pathway will increase electric service safety and reliability , boost the regional economy , and create jobs during construction . This 1041 Application describes a portion of Pathway in Weld County ; the overall system includes approximately 550 to 610 miles of transmission line and new and expanded substations . P athway facilities proposed in Weld County subject to this 1041 Application include 34 . 3 miles of 345 - kV double - circuit transmission line . Other Pathway facilities in Weld County include 11 . 2 miles of 345 - kV double - circuit electric transmission line in existing P SCo fee - owned property and the relocation of 4 . 5 miles of existing 230 - 1( V electric transmission line into new ROW ( subject to a Use by Special Review [ USR ] Permit ) and COLORADO ' S POWER PATHWAY 5 Fort St . Vrain Substation equipment additions ( subject to a Site Plan Review Permit ; see the Vicinity Map in Attachment A ) . c . Timetable for planning (e . g . , federal permits , other state permits , local zoning , etc . ) . A timetable for obtaining required federal , state , and local permits is described in response to Supplemental Question 15 . b . i of this 1041 Questionnaire . d . Estimated beginning and completion of construction and beginning of operation of facility . The estimated schedule for Pathway construction in Weld County is shown in Table 2 . Many variables factor into the schedule for projects of this magnitude . The construction schedule is contingent on acquiring all necessary land rights , permits , labor , and materials . Pathway will be constructed and placed in - service in phases . Table 2 : Anticipated Segment 1 In - Service Dates In - Service Se ! went & Substation Construction Year Segment 1 , including Fort St . Vrain Substation Spring / Summer 2024 — Spring 2026 equipment additions Spring / Summer 2026 3 . Describe hazards and emergency procedures . Specify where applicable : a . Hazards , if any, of fire , explosion and other dangers to the health , safety and welfare of employees and the general public . Transmission lines are built and maintained to meet or exceed safety standards , such as those specified by the National Electrical Safety Code ( NESC ) and the North American Electric Reliability Corporation . Every effort is made to ensure safety in construction , operation , and maintenance of transmission lines . Transmission lines are designed to withstand extreme weather conditions and protective devices at line terminals stop the electricity flow under abnormal operating circumstances . The transmission poles will be equipped with shield wires above the energized line ; this equipment adds to the pole height but also provides protection against lightning strikes . Xcel Energy ' s transmission lines are monitored 24 / 7 / 365 for line contact , the term describing when an object comes in contact with the transmission line conductors . If there is an unanticipated event in the line , the line is isolated from the system to protect the public and the line from operating under unsafe conditions . Xcel Energy ' s transmission lines are inspected annually to check for line connections and damage . COLORADO ' S POWER PATHWAY 6 For the safety of the general public , unauthorized personnel are not permitted to come in contact with the transmission line conductor wire . b . Hazards , if any, of environmental damage and contamination due to materials used at or activities taking place at the proposed facility . Chemicals that may be used during construction and operation are those found in diesel fuel , gasoline , coolant ( ethylene glycol ) , and lubricants in machinery . Hazardous materials will not be drained onto the ground or into streams or drainage areas . Enclosed containment will be provided for trash disposal . Construction waste , including trash and litter , garbage , other solid waste , petroleum products , and other potentially hazardous materials , will be removed and taken to a disposal facility authorized to accept such materials . No hazardous materials will be used , stored , or generated on site of Pathway facilities . Pathway will not require transportation of hazardous materials . Construction , operation , and maintenance activities will comply with applicable federal , state , and local laws and regulations regarding the use of hazardous substances . Construction activities will be performed using methods that prevent entrance or accidental spillage of solid matter , contaminants , debris , and other pollutants and wastes into flowing streams or dry watercourses , lakes , and underground water sources . Activities will follow BMPs for the management of wastes to avoid and minimize effects from potential spills or other releases to the environment . Short - term , temporary increases in fugitive dust and construction equipment exhaust ( fumes ) are anticipated during construction activities . These are not expected to cause a public nuisance . Transmission line operations will not require on - site staff and will be monitored remotely . Visits from personnel will be limited to emergencies or maintenance and inspection activities . As a result , increased dust or exhaust are not expected during operations . Xcel Energy will apply for a Colorado Department of Public Health and Environment ( CDPHE ) Air Pollutant Emissions Notice ( APEN ) for land development prior to construction and follow state standards to control the release of fugitive dust related to construction , if necessary . The APEN will be required for a disturbance greater than 25 contiguous acres and land development activities longer than 6 months . Pathway will not cause hazardous conditions , potential air or water pollutants , or other noxious influences . COLORADO ' S POWER PATHWAY 7 C . Emergency procedures to be used in the event of fire , explosion or other event which may endanger the public health , safety and welfare . Xcel Energy ' s facilities are designed , constructed , operated , and maintained to meet or exceed all applicable requirements of the Institute of Electrical and Electronics Engineers ( IEEE ) standards and accepted industry standards and practices including IEEE 979 , Guide for Substation Fire Protection . Applicable fire laws and regulations , as outlined in Colorado Revised Statutes ( CRS ) 31 - 15 - 601 , will be observed during construction and normal operation of the transmission line and substation . Fires along transmission lines are very rare . Xcel Energy ' s powerlines are monitored and controlled remotely from an operations center where event response is coordinated . In the rare event of an emergency , Xcel Energy will likely be aware of an issue before the general public or emergency responders . Nevertheless , the public is encouraged to contact Xcel Energy ' s emergency number : 800 - 895 - 1999 to report an emergency . Unauthorized personnel , including emergency responders , should not approach the facilities and should not touch the electric lines or anyone or anything in contact with them . Xcel Energy also coordinates closely with local fire departments and first responders and consults with them to discuss any concerns within their response area . Xcel Energy offers free online safety training to fire departments and first responders that is based on national standards through the Responding to Utility Emergencies Program . d . Any prevalent natural hazards that will affect or be affected by development, and describe mitigating measures to be taken to reduce danger due to such natural hazards . Xcel Energy electric facilities , including transmission poles , are specifically designed for the locations where they are placed . Geotechnical studies are conducted for transmission poles to identify subsurface conditions and determine foundation specifications . Transmission lines are structurally designed according to the NESC , which incorporates standards from the American Society of Civil Engineers on structural loading . The NESC requires poles over 60 feet tall to be able to resist the loading from various ice and wind scenarios . The base design wind speed for eastern Colorado is 95 miles per hour . This wind speed is part of an equation that also considers terrain , span length between transmission poles , and transmission pole height to produce an overall wind pressure applied to the wires and the transmission pole . In addition , the design scenario considers how the structural capacity of a transmission pole is affected by the icing conditions on the wire . The weight of the ice increases the tension in the wires and therefore the loading on the COLORADO ' S POWER PATHWAY 8 transmission pole . The result of this design scenario is that transmission lines typically have additional structural capacity for much higher wind speeds than the NESC requires after accounting conservatively for icing conditions . 4 . Summarize major natural and socioeconomic environmental constra ' nts as they affect the site se ection and construction of the facility as proposed . A discussion of environmental constraints is described in the response to Supplemental Question 15 of this 1041 Questionnaire . According to the U . S . Census Bureau ( U . S . Census Bureau 2022 ) , Weld County had a total estimated population of 340 , 036 in 2021 . This is an increase of approximately 3 percent since the 2010 Census . U . S . Census demographics from 2021 for Weld County show a 51 percent male and 49 percent female distribution of the predominantly 91 percent white population . Per capita income in Weld County is $ 35 , 7075 approximately 10 percent lower than the statewide estimate of $ 395545 ( U . S . Census Bureau 2022 ) . In October 2022 , unemployment in Weld County was 3 . 7 percent according to the U . S . Department of Labor : Bureau of Labor Statistics ( FRED 2022a ) . The October 2022 statewide average for unemployment was 3 . 0 percent ( FRED 2022b ) . Pathway will deliver economic benefits to rural communities across eastern and southern Colorado , including Weld County , over the short and long - term . More immediately , Pathway construction will provide local jurisdictions and host communities with potential additional tax revenue and employment opportunities . Revenue may increase for local businesses such as restaurants , gas stations , grocery stores , hotels , and other local businesses . Existing businesses and social services are adequate to support Pathway given the size of the construction crew and temporary nature of the construction activities . No impacts to emergency health care facilities or law enforcement services are therefore anticipated . Once Pathway has been constructed , it will facilitate ongoing job opportunities and tax revenue in the clean energy projects ( wind , solar , etc . ) that ultimately interconnect to Pathway . Additionally , generation developers will have the opportunity to build projects that otherwise were infeasible because of a lack of transmission access to market and / or transmission constraints . These generation projects may provide other additional economic development through increased jobs associated with construction and local tax - based revenue associated with land usage , and payments to existing landowners . COLORADO ' S POWER PATHWAY 9 Xcel Energy anticipates that a maximum number of 60 to 80 construction workers will be needed for construction of Pathway transmission lines in Weld County . Construction crews may reside in the area during construction . 5 . Summarize the effects of the proposed s ' te se ection and construction upon the natural and socioeconomic environment of the impact area as applicable to submission requirements . Included should be an analysis of impacts upon agricultural productivity and agricultural resources and upon vested water rights . An analysis of the effects of the proposed site selection and construction upon the socioeconomic environment of the impact area is provided in the response to S upplemental Question 4 of this 1041 Questionnaire . An analysis of impacts upon agricultural productivity and agricultural resources is provided in the response to S upplemental Question 15 . b . ii and the response to Planning Question 6 of this 1041 Questionnaire . Pathway will not require water rights for construction , maintenance , or operation and will not affect existing water rights . 6 . Inc ude analysis of the long -term effects of the proposed site selection and construction upon the physica and socioeconomic development of the impact area . The development of Pathway in Weld County is anticipated to provide local economic benefits during construction and potential long - term economic benefits should new generation resources be developed in the area . Pathway will also improve the state ' s electric reliability , thereby benefiting all consumers in Colorado . See also the response to Supplemental Question 4 of this 1041 Questionnaire . 7 . Inc ude a description of a program to minimize and m ' tigate adverse impacts and to maximize the positive impacts of the proposed site selection and construction . P athway will mitigate and minimize adverse impacts as described in the responses to S upplemental Question 15 of this 1041 Questionnaire . 8 . Inc ude analysis of nonstructural a ternatives to the project such as conservation of energy use , no development or management ( different schedu ing , conservation programs , facility design , and trades , etc . ) , if applicab e . The purpose of Pathway is to create a network transmission system that can integrate new generation resources needed to meet Colorado ' s clean energy goals . The existing COLORADO ' S POWER PATHWAY 10 infrastructure is not adequate for this purpose . Therefore , no non - structural alternatives are viable . 9 . nc ude analysis of reasonable structura alternatives to the project such as alternate ocations and routes , alternalve types of facilities , use of existing rights - of - way , joint use of rights - of - way with other uti ities , and upgrading of existing facilities . P athway routing and siting efforts were divided by segment and documented in a series of six Routing and Siting studies . Each Routing and Siting Study is interrelated due to the overlap in segment Study Areas and shared substation endpoints . Each Routing and Siting Study documents the process utilized to review and consider reasonable siting and routing alternatives for the new major electrical facilities ( pursuant to CRS 29 - 20 - 108 ( 4 ) ( a ) and ( b ) ) . The Segment 1 : Fort St . Vrain — Canal Crossing Routing and S iting Study is included in Attachment B and provides an alternatives analysis to address this requirement . 10 . Inc ude analysis of air and water pollution impacts and control a ternatives . Air Quality Weld County is in attainment with National Ambient Air Quality Standards ( NAAQS ) for the following criteria pollutants : particulate matter , carbon monoxide , nitrogen oxides , sulfur dioxide , and lead ( EPA 2022 ) . The Denver Metropolitan Area is designated nonattainment for the 8 - hour ozone NAAQS 2015 Standard — Moderate Classification of 0 . 081 up to but not including 0 . 093 parts per million . The Denver Metropolitan Area consists of Adams , Arapahoe , Boulder , Broomfield , Denver , Douglas , Jefferson , and parts of Larimer and Weld counties . S hort - term effects are anticipated from a temporary increase in construction vehicles , which may increase fumes and fugitive dust , construction equipment exhaust ( fumes ) , and clearing and preparing areas for construction ( dust ) . The short - term effects are not expected to cause a public nuisance . If a nuisance arises during construction , the nuisance will be mitigated in coordination with Weld County . It is anticipated that an average of 20 to 30 trucks per day will be utilized during construction of the transmission line for crews , spotting materials , framing poles , and erecting poles . Concrete truck deliveries will be made daily when the foundations and piers are being constructed . Multiple deliveries of cement ( up to 20 to 30 per day ) will be required daily at certain stages of construction . Materials will be delivered to the Cervi Yard at the onset of construction . An additional 10 to 15 trucks will be needed to deliver COLORADO ' S POWER PATHWAY 11 steel poles , conductor , anchor bolts , and foundation materials daily to work areas . The impact to local roads will vary day by day as the construction moves along the route . Water trucks will be utilized during construction activities around roadway access points to suppress dust from vehicles and equipment as necessary within the ROW and county roads as per coordination with Weld County . Xcel Energy will apply for a CDPHE APEN for land development prior to construction and follow state standards to control the release of fugitive dust related to construction , if necessary . The APEN will be required for a disturbance greater than 25 contiguous acres and land development activities longer than 6 months . During operation , Pathway will not generate trips in excess of those currently experienced as the transmission line facilities represent a passive use and will not be staffed . Transmission line operations will not require on - site staff and will be monitored remotely . Visits from personnel will be limited to emergencies or maintenance and inspection activities and increased fumes , exhaust , and dust during operations are not expected . Water Resources An analysis of water resources impacts and control measures is provided in the responses to Supplemental Questions 15 . c . i and 15 . d . i of this 1041 Questionnaire . 11 . Inc ude analysis of design alternatives concerning access , landscaping , archlectural contro s , and so forth . The transmission poles will be weathering steel that oxidizes to resemble a natural brown look . Access to the transmission poles from nearby Interstate , U . S . Highways , and local roads is shown in the 1041 Permit Map , Attachment D . 12 . nc ude analysis of hydrolog ' c , atmospheric , geologic , pedolog ' c , biotic , v . sual and noise impacts . An analysis of atmospheric impacts is provided in the response to Supplemental Question 10 of this 1041 Questionnaire . An analysis of hydrologic , geologic , pedologic , biotic , visual , and noise impacts is provided in the responses to Supplemental Question 15 of this 1041 Questionnaire . 13 . Include surface and subsurface drainage analysis . Xcel Energy will comply with permit application requirements , County Standards , and construction protocols to ensure that Pathway does not violate water quality standards . COLORADO ' S POWER PATHWAY 12 A Drainage Narrative is provided in the response to Engineering Question 3 of this 1041 Questionnaire . 14e App ' cants seek ' ng a permit for the site selection and construction of transmission Ines or substations shall submit the fol owing additional documents and information : a . Computer modeled electromagnetic field measurements within the proposed transmission line easement for that portion of transmission line between substations or transition sites ; and Pathway facilities will be designed , constructed , operated , and maintained to meet or exceed applicable standards of design and performance set forth in the NESC . Electric and magnetic fields ( EMF ) exist wherever electricity is produced or used , including around any electric appliance or wire that conducts electricity . Electric fields are created by voltage — the higher the voltage , the stronger the field . Any time an electric appliance is plugged in , even if it is not on , an electric field is created in its vicinity . Electric fields are easily blocked by walls , trees , clothes , and skin . The farther the distance from the source of the electric field , the weaker it becomes . EMF extend outward from the conductor wire and decrease rapidly with distance from the conductor . There is no federal standard for transmission line EMF . Additional information is available online at Transmission - EMF - Fact - Sheet . pdf ( coloradospowerpathway . com ) . Noise and EMF studies were conducted for Pathway and submitted as part of Pathway ' s Certificate of Public Convenience and Necessity ( CPCN ) application , and is included as Attachment O . The study concluded that magnetic field levels at the edge of the Pathway transmission line ROW are projected to be 54 . 7 milligauss ( mG ) . These levels are below 150 mG and were deemed reasonable by the Colorado Public Utilities Commission ( CPUC ) . b . Measures taken to comply with the concept of prudent avoidance with respect to planning , siting , construction and operation of transmission lines , which may be those steps taken to comply with the Colorado Public Utilities Commission 's Rule 18 ( 1) , or similar authority, for projects where other similar authority is applicable . The routing and siting study process used to locate Pathway facilities in Weld County is provided in Attachment B of this 1041 Application . In February 2022 , the CPUC provided verbal approval for the CPCN for Pathway Segments 1 through 5 and conditional approval for the Extension , determining Pathway is in the public interest and COLORADO ' S POWER PATHWAY 13 in compliance with relevant CPUC rules and regulations . The CPUC provided written approval of the Pathway CPCN application on June 2 , 2022 . 15 . Specrc submitta requirements . he fo lowing informat ' on may also be required : a . Detailed description of the need for the proposed development or activity, including► but not limited to : i The present population of the area to be served and the total population to be served when the project is operating at full capacity, The purpose of Pathway is to create a network transmission system that can integrate new generation resources needed to meet Colorado ' s clean energy goals . Pathway is a backbone transmission system that will connect generation sources in eastern Colorado to demand throughout Colorado . The current electric transmission facilities in the Eastern Plains do not have adequate capacity to meet the forecasted demand . Facilities in Weld County are part of the larger Pathway that creates a transmission " loop " to provide additional transmission capacity . Pathway will be able to integrate approximately 3 , 000 to 3 , 500 megawatts of electric power output from new generation . ii The predominant type of users or communities to be served by the proposal . P athway is an addition to Colorado ' s backbone transmission system and does not provide distribution electric service ; as such , this Application does not address project - specific details that apply for developments or direct utility service projects . iii The percentage of the design capacity at which the current system is now operating . The current electric transmission facilities in the Eastern Plains region of Colorado do not have adequate capacity to meet the forecasted demand of 3 , 000 to 3 , 500 megawatts . See the response to Supplemental Questions 15 . a . iv and 15 . a . v of this 1041 Questionnaire . iv The relationship of the proposal to the applicant 's long - range planning► and capital improvements programs . P athway will support Xcel Energy ' s Clean Energy Plan ( Xcel Energy 2021 ) that is estimated to deliver as much as an 85 percent reduction in carbon dioxide emissions by 2030 and add approximately 5 , 000 megawatts of new wind , solar , and other resources . P athway is a $ 1 . 7 to $ 2 billion investment proposed by Xcel Energy to improve the state ' s electric grid and enable future renewable energy development around the state . COLORADO ' S POWER PATHWAY 14 v A description of why public convenience and necessity require a facility of the size and nature proposed . The Eastern Plains region of Colorado is one of the nation ' s best areas for wind and solar energy generation , but it does not currently have a network transmission system that can integrate these new generation resources into the state ' s interconnected grid system , which is needed to meet Colorado ' s clean energy goals . Pathway will help to meet the state ' s growing electricity needs , improve safety , reliability , and affordability , and enable the transition to clean energy . Pathway will allow developers of energy generation projects to interconnect energy resources located in the areas of the state that are underserved by backbone transmission lines and allow Xcel Energy to deliver energy to electric customers . In March 2021 , Xcel Energy filed a CPCN to the CPUC describing the purpose , need , and public benefits of constructing Pathway . In February 2022 , the CPUC provided verbal approval , and in June 2022 , CPUC provided written approval of the CPCN for S egments 1 to 5 and conditional approval for the Extension , based on a determination that Pathway is in the public interest . vi A description of the user needs and user patterns to be fulfilled by the proposed project . S ee the response to Supplemental Question 15 . a . v of this 1041 Questionnaire . vii A description of the relationship of the project to other existing and planned utility facilities of a similar nature , other communication or energy generation and transmission facilities , local government capital improvement programs and special district expansion programs . P athway is a backbone transmission system that will support Xcel Energy ' s Clean Energy Plan ( Xcel Energy 2021 ) that is estimated to deliver as much as an 85 percent reduction in carbon dioxide emissions by 2030 and add approximately 5 , 000 megawatts of new wind , solar , and other resources . Pathway will help to meet the state ' s growing electricity needs , improve safety , reliability , and affordability , and enable the transition to clean energy . Pathway will allow developers of energy generation projects to interconnect energy resources located in the areas of the state that are underserved by backbone transmission lines and allow Xcel Energy to deliver energy to electric customers . See additional discussion in Section 1 of this 1041 Application . P athway is not related to local government capital improvement programs or special district expansion programs . COLORADO ' S POWER PATHWAY 15 b . Environmental impact analysis — land use . i Describe the relationship of the project to local land use , policies and comprehensive plans and to policies and plans adopted or under preparation by federal, state , regional or other affected local governmental agencies . An analysis of Pathway consistency with the Weld County Comprehensive Plan ( Weld County , Colorado , Charter and County Code Chapter 22 , Comprehensive Plan ; Weld County 2022a ) is provided as Attachment K . Federal , state , and local permits and approvals may be required prior to Pathway construction . Outreach was conducted with each jurisdiction crossed by Pathway to solicit feedback and discuss potential permits that may be required . Multiple Colorado statutory provisions and local government land use plans and controls apply to Pathway , including approval of a CPCN from the CPUC ; notice , consultation , and permit approvals from counties and municipalities , and notice to owners of a mineral estate associated with the substation sites . All necessary land use , environmental , and construction permits , approvals and authorizations will be obtained prior to the start of and during construction as required and may include but are not limited to major land use permits , ROW permits , road use agreements , access permits , oversize / overweight permits , grading permits , and stormwater permits . Xcel Energy anticipates avoiding impacts to jurisdictional waters of the U . S . ( WOTUS ) in Weld County and therefore does not anticipate that Pathway facilities in the County will require a Nationwide Permit 57 or other U . S . Army Corps of Engineers permitting under Section 404 of the Federal Clean Water Act . The regulatory requirements identified by Xcel Energy are described in Table 3 . Table 3 is intended as an illustrative list of the permits and approvals that may be required for Pathway , but other permits or approvals may be required . COLORADO ' S POWER PATHWAY 16 Table 1 : Land Use Permit Requirements and Applicability to Pathway Pathway Jurisdiction Com • onents Title Tr ! • er Statutory Reference Status Federal Aviation Structures occurring in FAA Form Objects affecting Title 14 Code of Federal To be submitted following Administration Navigable Airspace 7460 - 1 , Notice navigable airspace Regulations ( CFR ) Part 77 final design . ( FAA ) of Proposed Construction or Alteration CPUC All CPCN Need for new Colorado Revised Statutes Proceeding No . 21 A - electrical facility in ( CRS ) 40 - 5 - 101 , CRS et 0096E , Approved June 2 , Colorado seq . , and Rule 1303 2022 . 4 Code of Colorado Regulations ( CCR ) 723 - 1 and Rules 3002 , 3102 , and 3206 , 4 CCR 723 - 3 All Notification of Filing permit CRS 29 - 20 - 108 In addition to other Intention to application for notifications , Xcel Energy Submit Permit location , met with Weld County on Application for construction , or June 17 , 2021 , and Major Electrical improvement of October 5 , 2022 , about Facilities major electrical or Pathway . natural gas facilities All Government Public hearing by a CRS 24 - 65 . 5 - 103 In accordance with the and State local government statute CRS 24 - 65 . 5 - 103 , Notice on an application the applicant will provide Requirements , for development notice to the mineral Mineral Owners owners associated with Fort St Vrain Substation prior to the Weld County hearing . Mineral owners may choose to waive their right to receive the notice not less than 30 days before the hearing and may also waive their right to a separate hearing regarding notification . COLORADO ' S POWER PATHWAY 17 Pathway Jurisdiction Components Title Tr ' • • er Statutory Reference Status CDPHE All Construction Construction sites 5 CCR 1002 - 61 To be obtained prior to General that disturb one construction . Stormwater acre or greater Permit and SWMP _ All Land Construction 5 CCR 1001 - 14 To be obtained prior to Development disturbance construction , if necessary . APEN greater than 5 acres or duration longer than 6 months _ Colorado Components crossing Access and Crossings of state 2 CCR 601 - 1 To be obtained prior to Department of state and federal Crossing roadway construction . Transportation roadways Permits Colorado State To be determined Determination Potential impacts CRS 24 - 80 - 401 - 411 , CRS Pathway will coordinate Historic following final design of Compliance to historic , 24 - 80 - 1301 - 13055 with the State Historic Preservation and pre - construction with Historical , prehistoric , and / or 8 CCR 1504 - 7 Preservation Office on any Office surveys Prehistorical , archaeological applicable requirements for and resource cultural resources review . Archaeological _ Resources Burlington Components crossing Access and Crossings of 49 CFR 200 . 1 et . Seq . , To be obtained prior to Northern Santa railroads Crossing railroad CRS 32 - 12 - 123 , CRS 37 - construction . Fe Railroad Permits 95 - 108 COLORADO ' S POWER PATHWAY 18 Pathway Jurisdiction Com • onents Title Trigger Statutory Reference Status _ Concurrent County Land Use Permits Weld County Segment 1 1041 Permit Proposed Weld County Charter and Anticipated submittal Fort St . Vrain ( this document ) , development of an County Code Chapter 21 Spring — Summer 2023 S ubstation equipment Use by Special activity of state Areas and Activities of additions Review , and interest ( major State Interest ; Weld Site Plan facility of a public County , Colorado , Charter Review utility ) and change and County Code Chapter to an existing 23 Article 2 , Division 5 approved Use by Special Review Permits for Special Review Major Facilities of a Public permit in Weld Utility or Public Agency ; County Weld County , Colorado , Charter and County Code Chapter 23 Article 2 , Division 3 Site Plan Review Weld County Segment 1 Floodplain Crossing of Weld County Charter and Anticipated submittal 2023 Fort St . Vrain Development floodplains County Code Division 3 , S ubstation equipment Permits associated with the Article XI and Floodplain additions South Platte River , Development Permit Box Elder / No ( FHDP ) Name Creek , and Procedural Guide Checklist Lost Creek in Weld _ County Weld County Segment 1 Right - of- Way Crossing of Weld Weld County Charter and Prior to construction Fort St . Vrain Permits County Roads County Code Chapter 8 , S ubstation equipment Article XII additions Weld County Segment 1 Access Permits Temporary and Weld County Charter and Prior to construction Fort St . Vrain permanent access County Code Article XIV S ubstation equipment from Weld County additions roads COLORADO ' S POWER PATHWAY 19 Pathway Jurisdiction Com • onents Title Tr ' • • er Statutory Reference Status Arapahoe County Segment 5 1041 Permit Proposed Regulations Governing Anticipated submittal Harvest Mile and Location development of an Areas and Activities of Summer 2023 Substation Expansion and Extent activity of state State Interest in Arapahoe Permit ( to be interest ( major County confirmed at facility of a public Arapahoe utility ) in Arapahoe County Pre - County application Meeting ) Crowley County Segment 4 Use by Special Development of Crowley County Planning Use by Special Review Review public utility and and Zoning Manual , Permit approved in public service Section 2 Resolution Number 2023 - structures , 8591 on April 24 , 2023 . including transmission lines in Crowley County El Paso County Segment 5 1041 Permit Proposed El Paso County Land Anticipated submittal development of an Development Code ; Summer 2023 activity of state Attachment B : Guidelines interest ( major and Regulations for Areas facility of a public and Activities of State u tility ) in El Paso Interest County Elbert County Segment 5 1041 Permit Proposed Guidelines and Anticipated submittal development of an Regulations for Areas and Summer — Fall 2023 activity of state Activities of State Interest interest ( major Elbert County facility of a public u tility ) in Elbert County Pueblo County Segment 4 , 5 , 1041 Permit Proposed Pueblo County Code , Title Anticipated submittal Tundra Substation development of an 17 , Division 2 : Areas and Summer — Fall 2023 activity of state Activities of State and interest ( major Local Interest facility of a public u tility ) in Pueblo County COLORADO ' S POWER PATHWAY 20 Pathway Jurisdiction Com • onents Title Tr ' • • er Statutory Reference Status City of Aurora Segment 5 Conditional Use Proposed Aurora Unified Anticipated submittal Permit development of a Development Ordinance , Spring — Summer 2023 conditional use in Article 146 Zoning and City of Aurora Subdivision Procedures , Section 5 Specific Procedures County and City Land Use Permits Filed in Summer 2022 Morgan County Segment 1 , 2 1041 Permit Proposed Guidelines and 1041 Permit issued on Canal Creek development of an Regulations for Areas and November 16 , 2022 . S ubstation , equipment activity of state Activities of State Interest additions at Pawnee interest ( major S ubstation facility of a public utility ) in Morgan County Kit Carson Segment 2 Land Use Any proposed Kit Carson County Code , Land Use Change Permit County Change Permit change in land use Article 2 issued on September 21 , in unincorporated 2022 Kit Carson County Washington Segment 2 Use by Special Proposed - Application for Use by Use by Special Review County Review and development of Special Review , Permit was issued on 1041 Permit transmission line in Washington County November 21 , 2022 ;• 1041 Washington Permit was issued on _ County December 13 , 2022 Cheyenne County Segment 2 , 3 Conditional Use Proposed Cheyenne County Conditional Use Permit Goose Creek Permit and development of a Comprehensive Plan and was issued on September S ubstation 1041 Permit conditional use in Zoning Ordinance 30 , 2022 . 1041 Permit was Cheyenne County issued on September 30 , 2022 . Kiowa County Segments 3 , 4 , and 1041 Permit Proposed Guidelines and 1041 Permit was issued on S ew May Valley development of an Regulations for Areas and November 22 , 2022 S ubstation activity of state Activities of State Interest interest ( major County of Kiowa facility of a public utility ) in Kiowa County COLORADO ' S POWER PATHWAY 21 Pathway Jurisdiction Components Title Trigger Statutory Reference Status _ Other County and City Land Use Permits Considered Baca County Extension Not applicable Not applicable Per letter dated February Not applicable . New Longhorn 28 , 2019 , Baca County Substation Board of Commissioners confirm Baca County does not require land use permits ( Baca County 2022 ) own of Segment 1 Not applicable Town confirmed Platteville Municipal Code , Not applicable . Platteville only Colorado Chapters 15 - 18 Department of Transportation permit required COLORADO ' S POWER PATHWAY 22 ii Detail the agricultural productivity capability of the land affected by the proposal ( SCS classification) . A map of Pathway facilities and agricultural lands is provided as Attachment P . Aside from the transmission pole foundation footprint , areas under and around Pathway facilities can continue to be used for existing purposes , such as agriculture . Xcel Energy will coordinate with landowners regarding the placement of Pathway facilities on properties enrolled in the Conservation Reserve Program . Areas disturbed during construction of Pathway will be restored in a manner generally similar to pre - construction condition in coordination with the landowners and their current land use . Pathway will result in minimal permanent impacts to agricultural lands . Current uses adjacent to the Pathway facilities will be able to continue mainly unchanged after construction , thereby preserving desirable community and rural patterns that exist . Following construction , agricultural activities along the transmission line route can continue outside of the area occupied by the transmission poles . iii Specify how the proposed development will utilize existing easements or rights - of- way for any associated distribution or collector networks . A map showing existing transmission lines ( 115 - kV or greater ) within Weld County is provided as Attachment F . The transmission line ROW is located in existing easements or ROWS as much as possible . The Pathway transmission alignment within PSCo fee - owned ROW is subject to a separate USR Permit Application submitted to Weld County concurrently with this Application . c . Environmental impact analysis — water resources . i Documentation of the historical flooding activity should be included . Detail potential , adverse impacts related to the associated floodplain . A map showing floodplains within the vicinity of Pathway is provided as Attachment L . The transmission line subject to this 1041 Application will cross floodplains associated with Box Elder/ No Name Creek and Lost Creek in Weld County . Pathway will avoid regulated floodplains to the extent practicable . The transmission line will span floodplain areas with overhead conductors where feasible . Pathway will obtain a Floodplain Development Permit for each floodplain crossing from Weld County . COLORADO ' S POWER PATHWAY 23 II Describe the potential adverse effects of the proposal upon plant and animal life dependent upon the water resources In question . Land Cover The Land Cover Resource Map in the Routing and Siting Study for Segment 1 ( Attachment B ) illustrates land cover for Pathway in Weld County . Land cover is dominated by grassland / herbaceous cover ( approximately 73 percent ) and cultivated crops ( approximately 18 percent ) . The total acreage and percent of land cover types within 1 mile of proposed Pathway facilities is presented in Table 4 . The total acreage and percent of land cover types within the 67 . 5 - acre Cervi Yard and within the parcels adjacent to the Cervi Yard are presented in Table 5 . A description of the Cervi Yard is provided in Section 1 . 4 . c . 1 of the 1041 Application . Table 4 : Land Use and Land Cover Present within 1 Mile of Proposed Pathway Facilities in Weld County — New Transmission Line ROW Land Use/ Land Cover Description Acres Percent Grassland / Herbaceous 35 , 605 71 . 1 Cultivated Crops 10 , 192 20 . 4 Scrub / Shrub 2 , 820 5 . 6 Developed , Open Space 742 1 . 5 Developed , Low Intensity 269 0 . 5 _ Pasture / Hay 222 0 . 4 Developed , Medium Intensity 115 0 . 2 Developed , High Intensity 32 < 0 . 1 Emergent Herbaceous Wetlands 36 < 0 . 1 Open Water 11 < 0 . 1 Woody Wetlands 1 < 0 . 1 _ Deciduous Forest 7 < 0 . 1 Mixed Forest < 1 < 0 . 1 Barren Land ( Rock / Sand / Clay ) 4 < 0 . 1 Total 50 , 058 100 Source : NLCD 2019 COLORADO ' S POWER PATHWAY 24 Table 5 : Land Use and Land Cover Present within Proposed Pathway Facilities in Weld County — Within Cervi Yard and Parcels Adjacent to Cervi Yard Within Cervi Yard Land Use/ Land Cover Descri • fon Acres Percent Developed , Open Space 2 . 3 3 . 4 Developed , Low Intensity 0 . 3 0 . 4 Developed , Medium Intensity 0 . 3 0 . 4 Grassland / Herbaceous 64 . 6 95 . 7 Total 67 . 5 100 . 0 Parcels Ad ' acent to Cervi Yard Developed , Open Space 14 . 9 1 . 1 Developed , Low Intensity 38 . 1 2 . 8 Developed , Medium Intensity 25 . 8 1 . 9 Developed , High Intensity 0 . 2 < 0 . 1 Shrub / Scrub 132 . 7 9 . 7 Grassland / Herbaceous 1006 . 9 73 . 2 Pasture / Hay 1 . 4 < 0 . 1 Cultivated Crops 154 . 9 11 . 3 Total 1 , 374 . 9 100 Source : NLCD 2019 Management Areas and Priority Habitat Federal , state , and local agencies designate areas to help conserve habitats critical to migratory birds and other sensitive species ( e . g . , National Wildlife Refuges , National Grasslands , state parks , and state wildlife areas ) . The Jurisdiction Resource Maps in the Routing and Siting Study for Segment 1 ( Attachment B ) illustrate land jurisdiction for Pathway in Weld County . No federally or state - managed conservation areas are within 1 mile of proposed Pathway facilities in Weld County . In addition , no Critical Habitat designated by the U . S . Fish and Wildlife Service ( USFWS ) is mapped in the same area ( USFWS 2022d ) . Beyond these priority habitats , Pathway will avoid or minimize impacts to habitat generally as practicable . Impacts to most vegetation will be temporary and limited to the 150 - foot - wide ROW and TCAs . The ROW will be cleared of tall vegetation for ongoing maintenance . Measures will be implemented to minimize the spread of noxious weeds in the ROW as provided in Attachment X . To avoid or minimize impacts to aquatic habitat within the ROW , surface waters , riparian areas , and wetlands in areas at a crossing will be spanned as practicable . Pathway will adhere to BMPs and erosion control measures outlined in the SWMP . Special Status Wildlife A desktop analysis of the portion of Pathway transmission lines within Weld County was completed to characterize the environmental setting of Pathway and evaluate the potential for occurrence of special - status species based on available habitat . The COLORADO ' S POWER PATHWAY 25 analysis included the transmission line route plus a 1 - mile buffer . The buffer was used to evaluate biological resources that could be influenced by Pathway construction , maintenance , or operation ( e . g . , raptor nests ) . To assess the potential for occurrence of special - status species within the County , the following publicly available information was reviewed : • Google Earth Aerial Imagery ( Google 2022 ) • National Land Cover Database ( USGS 2019 ) • USFWS Information for Planning and Consultation ( IpaC ) online tool ( USFWS 2022a ) • USFWS Critical Habitat Portal ( USFWS 2022b ) • Colorado Natural Heritage Program Species Elements Database ( CNHP 2022 ) • Colorado Parks and Wildlife ( CPW ) Species Activity Mapping Data ( CPW 2022a ) • CPW State Species List ( CPW 2022b ) • Online species profiles and distribution information ( CPW 2022c ) In addition to publicly available information , a windshield survey of the proposed Pathway facility locations was completed in September 2021 to identify any potential areas of concern for biological resources . Ground - based raptor nest surveys and aerial raptor nest surveys were conducted in April and May 2022 to identify potentially active eagle and other raptor nests within 0 . 5 mile of the proposed transmission line route in Weld County . The Pathway team has been conducting ongoing coordination with CPW and USFWS regarding potential biological resources that may be impacted by Pathway . The Pathway team had a project introduction meeting with CPW on December 12 , 2021 , followed by a routing workshop on January 10 , 2022 , and afollow - up routing discussion on April 22 , 2022 . On May 9 , 2022 , the Pathway team had a project introduction meeting with USFWS . The feedback received from CPW and USFWS during these meetings has been used to inform the siting and routing of Pathway . The Pathway team will continue to coordinate with CPW and USFWS through permitting , construction , maintenance , and operation of Pathway as needed to ensure compliance with applicable federal and state regulations . COLORADO ' S POWER PATHWAY 26 d . Environmental impact analysis — significant environmentally sensitive factors . Detail the potential impact of the proposal upon each feature : A map of Significant Environmentally Sensitive Factors is provided as Attachment M . f Marshlands and wetlands . A desktop analysis of the portion of Pathway within Weld County was completed to identify potentially jurisdictional wetlands and other WOTUS that may be subject to regulation under Section 404 of the Clean Water Act . The following digital information was evaluated for the 150 - foot ROW and an additional 50 - foot buffer on either side of the ROW : • USFWS National Wetland Inventory ( NWI ) dataset ( USFWS 2022c ) • USGS National Hydrography Dataset ( NHD ; USGS 2022a ) • Playa Lakes Joint Venture Probable Playa Dataset ( PLJV 2022 ) The Water Resources Map in the Routing and Siting Study for Segment 1 ( Attachment B ) illustrates the mapped NWI , NHD , and PLJV locations within the Study Area for Weld County . The major NHD - mapped drainages associated with wetlands and other WOTUS features near proposed Pathway facilities in Weld County include the South Platte River , Box Elder Creek , and associated unnamed tributaries ( USGS 2022a ) . NWI - mapped features associated with these drainages include riverine wetlands and freshwater emergent wetlands ( USFWS 2022c ) . As outlined in Table 6 , the transmission line ROW intersects 23 of these mapped wetland features , of which the longest crossing of which is approximately 557 feet . The nearest PLJV - mapped playa is located approximately 0 . 4 mile south of the Pathway facilities and no impacts are anticipated ( PLJV 2022 ) . The Cervi Yard does not intersect mapped NWI , NHD , or PLJV locations . Table 6 : NW Length Crossed by the Transmission Line in Weld County — New Transmission Line ROW NWI Wetland T • e A • • roximate Len • th Feet Freshwater Emergent Wetland 557 . 1 Freshwater Emergent Wetland 238 . 3 Freshwater Emergent Wetland 233 . 8 _ Freshwater Emergent Wetland 195 . 4 Freshwater Emergent Wetland 187 . 8 _ Freshwater Emergent Wetland 148 . 0 Freshwater Emergent Wetland ` 78 . 0 Riveri ne 343 . 4 Riveri ne 74 . 1 Riveri ne 66 . 9 COLORADO ' S POWER PATHWAY 27 NW Wetland T • e A • • roximate Len • th Feet _ Riveri ne 34 . 7 Riveri ne 21 . 0 Riveri ne 19 . 9 Riveri ne 0 . 3 Riveri ne 0 . 3 Riveri ne 0 . 2 Riveri ne 0 . 1 Riveri ne 0 . 1 Riveri ne < 0 . 1 _ Riveri ne < 0 . 1 Riveri ne < 0 . 1 Riveri ne < 0 . 1 P athway will avoid impacts to wetlands and WOTUS features to the extent practicable . The potential wetlands and WOTUS identified through desktop analysis of NWI data that may be impacted by construction of Pathway have been field - verified and will be marked in the field prior to construction so construction workers avoid impacts . The transmission poles can be located to span wetlands and other WOTUS features , thereby avoiding permanent impacts . Based on the lengths provided in Table 6 , P athway pole siting is not anticipated to result in permanent impacts to wetlands or other WOTUS features in Weld County . Associated access roads , laydown yards , and other features of Pathway will be sited to avoid permanent impacts to wetlands and WOTUS features . Pathway is therefore not anticipated to result in permanent impacts to wetlands or other WOTUS features in Weld County . Temporary impacts to wetlands and WOTUS during construction of Pathway will be avoided to the extent practicable . If wetlands cannot be avoided , matting and other protective temporary measures will be used . Depending on the condition of the wetland soil and hydrology , matting may be used to protect wetlands from rutting . Prior to construction , a Storm Water Management Plan ( SWMP ) will be prepared according to the Colorado Department of Public Health and Environment ( CDPHE ) requirements . To avoid potential indirect impacts from construction - related erosion and sediment movement during construction , Pathway will adhere to BMPs outlined in the SWMP , which will include erosion control and revegetation measures . P athway will not generate pollutant loads . Construction of the transmission line will not create runoff in excess of preconstruction levels and will not change existing topography or adversely affect drainage . There will be no alteration in the pattern or intensity of surface drainage as a result of construction or operation of the transmission line . COLORADO ' S POWER PATHWAY 28 Xcel Energy will comply with permit Application requirements , County Standards , and construction protocols to ensure that Pathway does not violate water quality standards . ii Groundwater recharge areas , if applicable . No groundwater discharge areas are located near Pathway ( see Attachment M , S ignificant Environmentally Sensitive Factors Map ) . No impacts to groundwater recharge areas are anticipated . BMPs will be used during construction to control sediment and runoff from work areas . Compliance with applicable federal , state and county construction and waste management procedures will prevent accidental spills or runoff of sediment or contaminants to waterbodies or groundwater . iii Potential natural hazards . No areas of geologic hazards or geologic areas of importance are located near P athway . No significant natural hazards have been identified in the areas planned for P athway development in Weld County . Professional engineers who will guide construction do not foresee any unusual risks . Xcel Energy electric facilities , including transmission poles , are specifically designed for the locations where they are placed . Geotechnical studies are conducted for transmission poles to identify subsurface conditions and determine foundation specifications . Transmission lines are structurally designed according to the NESC , which incorporates standards from the American S ociety of Civil Engineers on structural loading . The NESC requires poles over 60 feet tall to be able to resist the loading from various ice and wind scenarios . The base design wind speed for eastern Colorado is 95 miles per hour . This wind speed is part of an equation that also considers terrain , span length between transmission poles , and transmission pole height to produce an overall wind pressure applied to the wires and the transmission pole . In addition , the design scenario considers how the structural capacity of a transmission pole is affected by the icing conditions on the wire . The weight of the ice increases the tension in the wires and therefore the loading on the transmission pole . The result of this design scenario is that transmission lines typically have additional structural capacity for much higher wind speeds than the NESC requires after accounting conservatively for icing conditions . iv Forests and woodlands . The Land Cover Resource Maps in the Routing and Siting Study for Segment 1 ( Attachment B ) illustrate land cover for Pathway in Weld County . Forested areas in the vicinity of the transmission line route are shown in the Significant Environmentally S ensitive Factors Map ( Attachment M ) . As shown in Tables 4 and 5 ( see response to Question 15 . c . ii ) , the total area of forested and woodland land cover within 1 mile of proposed Pathway facilities is less than 0 . 1 percent ; there are no forested or woodland COLORADO ' S POWER PATHWAY 29 areas within or adjacent to the Cervi Yard . Pathway transmission lines will avoid or minimize impacts to forests and woodlands generally as practicable . Impacts to most vegetation will be temporary and limited to the 150 - foot - wide ROW and TCAs . The ROW will be cleared of tall vegetation for ongoing maintenance . Measures will be implemented to minimize the spread of noxious weeds in the ROW as described in Attachment X , including minimizing ground disturbance and utilizing weed - free seed mixes . v Critical wildlife habitat . The USFWS iPaC online tool and CPW online databases were used to identify federally and state - protected species that may occur near Pathway facilities in Weld County , including species listed or proposed for listing under the Endangered Species Act , bald and golden eagles protected under the Bald and Golden Eagle Protection Act , and state - listed threatened or endangered species ( CPW 2022a , CPW 2022b , CNHP 2022 , U SFWS 2022a , USFWS 2022b ) . In addition to the federally and state - listed species that receive regulatory protection , state Species of Concern ( SC ) were also evaluated . Although SC species do not receive any regulatory protection , they have been identified by the state as having management interest either due to declining populations or habitat loss . The Wildlife Species Habitat and Avian Habitat Resource Maps in the Routing and S iting Study for Segment 1 ( Attachment B ) illustrate mapped special - status wildlife and avian habitat for Pathway in Weld County . A total of 19 special - status wildlife species were identified as potentially occurring within 1 mile of proposed Pathway facilities in Weld County . Table 7 outlines the likelihood of occurrence of each species based upon review of known species ranges , habitat requirements , land cover data , and aerial imagery . Table 7 : Special - Status Species Potentially Occurring within 1 Mile of Proposed P athway Facilities in Weld County Federal ! Common Scientific State Likelihood of Name Name Status ' Habitat Associations / Ran • e Occurrence2 Mammals Black - tailed Cynomys - I SC Occurs in the eastern third of High prairie dog ludovicianus Colorado , in shortgrass prairie habitat below 6 , 000 feet elevation . The species lives in colonies and they construct burrows where they live and raise their young . One - mile buffer of proposed Pathway facilities is within the overall species range , medium and high potential colony occurrence area . COLORADO ' S POWER PATHWAY 30 Federal / Common Scientific State Likelihood of Name Name Status ' Habitat Associations / Ran • e Occurrence2 Gray wolf Canis lupus FE / - Requires large areas of contiguous Unlikely habitat , including forests and mountain terrain , with an abundance of prey and cover . The species has been considered extirpated from Colorado until very recently . Preble ' s Zapus FT / ST Riparian vegetation with adjacent , Low meadow hudsonius preferably undisturbed grassland and jumping preblei nearby water sources . One - mile buffer mouse of proposed Pathway facilities is within mapped overall range ; however , the n earest mapped occupied habitat occurs approximately 5 . 6 miles north near Milliken , Colorado . Swift fox Vulpes velox - / SC Occurs in shortgrass prairie habitat Unlikely with flat or rolling terrain and high visibility over long distances , up to 7 , 000 feet elevation . One - mile buffer of proposed Pathway facilities outside range for the species . Birds Bald eagle Haliaeetus BG EPA / Large rivers , lakes , and reservoirs with High leucocephalus SC an abundance of fish . Nesting is typically in large trees close to water . One - mile buffer of proposed Pathway facilities within overall species range . Nest site mapped approximately 1 . 1 miles south of the 1 - mile buffer of proposed Pathway facilities ; roost site is mapped within the 1 - mile buffer of proposed Pathway facilities . Additional n ests and roosts are located along the South Platte River and Milton Reservoir approximately 2 . 2 miles to n ortheast of the 1 - mile buffer of _proposed Pathway facilities . Ferruginous Bute ° regalis - / SC Occurs in arid and open habitats High hawk including grasslands , sagebrush or saltbush plains , and deserts . Nests in lone trees , cliffs , rock outcrops , or on the ground in a high area like a knoll . One - mile buffer of proposed Pathway facilities within species breeding range . Golden eagle Aquila BGEPA / Open native habitats with an 1 Moderate chrysaetos - abundance of prey . Nesting occurs on cliffs , knolls , and raised areas . One - mile buffer of proposed Pathway facilities within overall species range . COLORADO ' S POWER PATHWAY 31 Federal / Common Scientific State Likelihood of Name Name Status ' Habitat Associations / Ran • e Occurrence2 Long - billed Numenius - / SC Occurs in grasslands in close Low curlew americanus proximity to ponds , reservoirs , playas , and wet meadows . One - mile buffer of proposed Pathway facilities within species breeding range . Mountain Charadrius - / SC Occurs in shortgrass prairie habitat , Moderate plover montanus nesting in sparsely vegetated areas or areas with barren open ground , and often found near prairie dog colonies . One - mile buffer of proposed Pathway facilities is within species breeding range . P iping plover3 Charadrius FT / ST Reservoirs , lakes , and rivers with sand Unlikely — No melodus and gravel areas and sparse downstream vegetation . One - mile buffer of impacts proposed Pathway facilities outside anticipated . range for the species . Western Athene - / ST Open habitats with low or sparse Moderate burrowing owl cunicularia vegetation on gently sloping terrain . hypugaea Nesting typically occurs in small mammal burrows . Often found nesting in the perimeters of prairie dog colonies . One - mile buffer of proposed Pathway facilities occurs in species breeding range , medium and high potential prairie dog colony occurrence area . Whooping Grus FE / SE Freshwater marshes , wet prairies , Unlikely — No crane3 americana shallow lakes , and lagoons . One - mile downstream buffer of proposed Pathway facilities impacts outside range for the species . anticipated . Fish P allid Scaphirhynchu F / - Large river systems with firm sandy Unlikely — No sturgeon3 s albus bottoms ( i . e . , Missouri River ) . One - downstream mile buffer of proposed Pathway impacts facilities outside range for the species . anticipated . Reptiles Common Thamnophis - / SC Occurs in grasslands , prairies , Moderate gartersnake sirtalis streams , wetlands , and is often found near water . One - mile buffer of proposed Pathway facilities within overall species range . Amphibians N orthern Rana pipiens - / SC Riparian areas , wet meadows , and Low leopard frog ponds , with nearby upland habitat . I nsects Monarch Danaus FC / - Found in a wide variety of habitats and Moderate butterfly plexippus are known to occur in grasslands and prairie habitats in Colorado . The species requires milkweed ( Asclepius spp . ) host plants to lay their eggs . COLORADO ' S POWER PATHWAY 32 Federal / Common Scientific State Likelihood of Name Name Status ' Habitat Associations / Range occurrence2 Plants Ute ladies ' - Spiranthes FT / - Moist meadows associated with Low tresses orchid diluvialis perennial stream terraces , floodplains , and oxbows at elevations below 6 , 500 feet . Western Platanthera FT / - Unplowed calcareous prairies and Unlikely - No prairie fringed praeclara sedge meadows . One - mile buffer of downstream orchid3 proposed Pathway facilities outside impacts range for the species . anticipated . Invertebrates Cyllindrical I Scaphirhynchu - / SC Headwater lakes or low - gradient Low papershell s albus streams with muddy and sandy bottoms ; requires warm water fish for hosts . 1 FC = Federal Candidate , FE = Federally Endangered , FT = Federally Threatened , ST = State Threatened , SE = State Endangered , SC = Species of Concern , BGEPA = Bald and Golden Eagle Protection Act 2 Likelihood of Occurrence : Unlikely — unsuitable habitat in project and vicinity ; Low — marginally suitable habitat in project and vicinity ; Moderate — suitable habitat present in project , or species known to occur in habitat similar to project , High — highly suitable habitat present in project , or known populations exist in project vicinity . 3 Platte River Species = Water - related activities or uses in the Platte River Basins may affect these species in downstream reaches . Of these 19 species , three federally protected or candidate species ( golden eagle , bald eagle , and monarch butterfly ) and one state - protected species ( burrowing owl ) were determined to have a moderate or high likelihood of occurrence within the 1 - mile buffer of proposed Pathway facilities in Weld County . In addition to listed species , CPW tracks and maps data for big game species habitat throughout the state ( CPW 2022a ) . The Wildlife Species Habitat Resource Maps in the Routing and Siting Study for Segment 1 ( Attachment B ) illustrate mapped big game habitat for Pathway in Weld County . Three mule deer ( Odocoileus hemionus ) winter concentration areas , three areas identified as winter range , two areas identified as winter concentration area and two areas identified as severe winter range occur within the 1 - mile buffer of proposed Pathway facilities . The following occur within the 1 - mile buffer of proposed the Pathway facilities in Weld County : • one pronghorn antelope ( Antilocapra americana ) concentration area , one area identified as winter range , one area identified as winter concentration , and one area identified as severe winter range • one white - tailed deer ( Odocoileus virginianus ) concentration area and two areas identified as winter range No other big game species habitat is mapped in the same area . COLORADO ' S POWER PATHWAY 33 Potential impacts to wildlife species would primarily be associated with temporary disturbance from construction activities within the ROW , namely the removal and management of vegetation . In addition , increased noise and equipment movement during construction may temporarily displace mobile wildlife species from the immediate workspace area . These impacts are considered short - term in duration and normal wildlife movements would be expected to resume after construction has been completed and disturbed areas have been restored in a manner generally similar to preconstruction conditions . To avoid or minimize impacts to wildlife , Pathway will implement measures such as requiring proper trash and food debris disposal and compliance with posted speed limits . CPW recommendations ( CPW 2021 ) will be incorporated where practicable . To avoid or minimize potential project impacts to eagles and other migratory birds and raptors , tree / vegetation clearing will be conducted during the nonbreeding season for birds ( September 1 — April 15 ) if feasible . If vegetation clearing cannot occur during the nonbreeding season , vegetation clearance surveys , raptor nest surveys , and burrowing owl surveys may be conducted per USFWS and CPW guidance to identify avian nesting activity and determine appropriate avoidance buffers ( CPW 2020 , CPW 2021 ) or monitor actives nest sites until determined to be inactive . In addition , electrical components of the transmission lines will be separated to minimize the risk of avian contact and will follow Avian Power Line Interaction Committee ( APLIC ) guidelines ( APLIC 2006 ) . Bird flight or swan diverters or other marking devices may be used as determined necessary for specific locations . Xcel Energy will continue to coordinate with USFWS and CPW to address concerns regarding wildlife impacts throughout planning , design , and construction of Pathway , and will comply with all regulatory requirements . vi Public outdoor recreation areas . No local public outdoor recreation areas are present in the vicinity of Pathway facilities in Weld County ( USGS 20224 No impacts to recreation areas are anticipated . vii Unique areas of geologic , historic or archeological importance . Pathway facilities will be located in areas mapped as alluvium , eolian deposits , residuum weathered from shale , and mixed deposit outwash ( NRCS 2019 ; see Attachment V , Soil Report ) . A geotechnical study , based on soil borings along the length of the transmission line will be conducted for Pathway . Engineers will use this study to determine the size and type of foundations needed to support transmission poles as well as soil resistivity . No significant natural hazards have been identified in the COLORADO ' S POWER PATHWAY 34 areas planned for Pathway development in Weld County . Professional engineers will guide construction and do not foresee any unusual risks . Both a desktop cultural resources study and a field reconnaissance survey ( from May 5 to 6 , 2022 ) were completed where proposed Pathway facility locations and potential historic or archeological resources in Weld County were visible from public roads . Cultural resource records were reviewed using archaeological site files and the Colorado Cultural Resource Online Database ( Compass ) maintained by the Colorado Historic Society Office of Archaeology & Historic Preservation . Included in the Compass database are records of properties listed in the National Register of Historic Places . The cultural resources site file search was conducted for the 150 - foot transmission line ROW . Within the 150 - foot buffer , 22 previous cultural resource surveys have been conducted . These surveys cover over 8 miles of Pathway ROW . Six previously recorded cultural resources are located within the ROW . The resources include four historic ditch segments , one railroad segment , one transmission line , one Centennial Farm , and two isolated lithics . Three sites within the 150 - foot transmission line ROW have been determined Eligible for listing in the National Register of Historic Places . These sites include a segment of the Union Pacific Railroad ( 5WL . 1969 . 34 ) , a segment of the Farmers Independent Ditch ( 5WL . 2589 . 2 ) , and the Kiowa Creek to Weld Transmission Line ( 5WL . 3155 ) . Pathway will span these resources . One site , 5WL . 2083 , is a Centennial Farm and is Unevaluated . The boundaries of Centennial Farms encompass all areas of the farm , including areas that have no cultural features . The transmission line will avoid any areas with cultural features . The remaining sites include two that have been determined Not Eligible and two sites that are recommended Not Eligible . The sites that are recommended Not Eligible are isolated finds that can only be eligible under very rare circumstances , and neither of these resources fulfill these requirements . Therefore , Pathway will not have an adverse effect on any cultural resource . COLORADO ' S POWER PATHWAY 35 e . Environmental impact analysis - visual aesthetics and nuisance factors . i Identify key locations where the facility can be viewed from and its proximity to residences , simulate the appearance of the facility_, and identify noise pollution or obnoxious odors which may stem from the proposal . Visual / Aesthetic Resources Visual simulations from selected representative locations where Pathway can be viewed are provided in Attachment N . High - use roads and highways and residential land uses were prioritized in selecting the locations of the key viewpoints . A visual resource inventory based on available data found no designated federal , state , or local scenic resources within 2 miles of the Pathway transmission line route in Weld County . Several parcels adjacent to the eastern portion of the Pathway transmission line route in Weld County are owned and managed by Colorado State Land Board ; however , these areas are not accessible to the public or improved for any recreational , scenic , or other use . The Pathway transmission line route through Weld County , selected key observation points ( KOPs ) and identified public lands in the vicinity are shown in Attachment N on the KOP Resource Inventory map . The existing visual landscape in the area around the proposed Pathway transmission line route consists of mainly agricultural land uses including pivot irrigated crops and pastureland . Trees are sparse and shrub / scrub and herbaceous land cover dominate the area . Industrial facilities present near Pathway include oil and gas wells , natural gas compressor station facilities , communication facilities , oil and gas pipelines , a photovoltaic solar facility , a landfill , and a tire recycling facility . Agricultural facilities located near Pathway include cultivated crops , cattle feed yards , a confined animal feeding operation , and a meat processing facility . Electric distribution lines are visible throughout the area and are generally located along roads to serve residential and commercial areas . Several existing high voltage transmission lines and electrical substations are located in Weld County ( HIFLD 2022 ) . Other linear infrastructure , including railroads , Interstate Highways , U . S . Highways , and local roads exist in proximity to Pathway . Three residences are located within 300 feet of the Pathway transmission line centerline through Weld County . Visual impacts of Pathway will vary based on proximity . With increased distance , the scale of the transmission line poles will be minimized . As demonstrated by the visual simulations ( Attachment N ) , Pathway will be visible and , in some cases , dominant from roadways and a small number of residences , particularly where it occurs near viewers , up to approximately 0 . 5 mile . Viewers would primarily include motorists / travelers on COLORADO ' S POWER PATHWAY 36 roads ( who would view Pathway dynamically and briefly as they pass in a vehicle at highway speeds ) and residents located in the vicinity of Pathway whose views would be static and of longer duration . Roadways that intersect with or would have foreground views of Pathway include several Weld County Roads and Interstate 76 . Table 8 lists the views selected for photo simulations and a description of the simulation results . Where Pathway would be visible in the immediate foreground , it would introduce tall , vertical elements that are in some cases larger in scale than existing distribution lines located in the area and would appear as a dominant feature . Viewers located farther away are likely to experience less visual impact because screening from existing features ( topography , vegetation , buildings ) and distance from the facilities will decrease potential views and visual dominance . Table 8 . Summary of Views from Selected Key Observation Points ( KOPs ) Distance to Nearest Simulation / Facility Representative Representative View Component Viewer Viewpoint No . ' Viewpoint Direction ( Approx . ) Group View Comments KOP 1 County Road 49 North 300 feet Motorist / Transmission line crosses Weld Traveler County Road 49 . A transmission pole at this location will require additional height to pass over an existing distribution route that runs parallel to Weld County Road 49 . Existing large distribution lines are visible from this location . KOP 2 1 - 76 at Exit Northeast 1 , 200 feet Residential Transmission line passes 48 / Frontage Rd . / Motorist parallel with 1 - 76 for approximately 7 miles , including within foreground views of two to three residences . Existing distribution lines and industrial storage facilities to the south are visible from this location . KOP 3 I - 76 West - 3 , 200 feet Motorist / Representative view for 1 - 76 southwest Traveler westbound travelers . Multiple Pathway transmission poles will be seen paralleling the highway until the route crosses over the highway to continue east away from 1 - 76 . Existing large format industrial storage facilities are present in the background from this view . KOP 4 Weld County North 1 mile Residential Transmission line is visible Road 59 / Motorist along the horizon but is not dominant at this distance . An existing distribution line is present in the view , parallel with Weld County Road 59 . 1 - A total of 10 locations in proximity to the Pathway transmission line route through Weld County were visited in the field in January 2023 to document existing conditions and collect field photos for the simulations . Of those 10 locations , 4 representative locations were selected for simulations . COLORADO ' S POWER PATHWAY 37 Noise and Nuisance Factors The CPUC provides reasonableness determinations associated with noise and requires CPCN applicants to evaluate the expected level of noise of the proposed transmission facilities . Xcel Energy is required to meet state standards as outlined in 4 CCR 723 - 3 . Construction - related noise will result in temporary short - term increases in noise in areas where construction and staging are taking place . Short - term noise will result during foundation construction and assembly and erection of the transmission line poles and is anticipated from construction equipment such as auguring machines , cranes , heavy machinery , and trucks . Indirect effects from post - construction activities , which include the noise from transmission line inspections and maintenance activities are anticipated to be negligible because of their short duration and infrequency . All high - voltage transmission lines experience significant corona during wet weather , when water droplets form on the line . In normal , fair - weather conditions , corona and its corresponding audible noise are usually at low levels ( approximately 25 decibels less than wet weather noise ) . Corona also increases approximately 1 decibel for every 1 , 000 feet in elevation gain . Based on the noise study conducted for Pathway ( Attachment O ) , the maximum projected noise level measured at 25 feet from the edge of the ROW is 49 . 8 A - weighted decibels ( dBA ) . Per CPUC Rule 3206 ( f ) , noise levels below 50 dBA are not subject to further review regardless of the use of land , and noise levels below 75 dBA are deemed reasonable for land within an Industrial Zoning at 25 feet from the property line ( Section 4 CCR 723 - 3 ) . The projected noise levels from the Pathway transmission line were deemed reasonable by the CPUC and not subject to further review . it Where significant, reap or describe areas Within view of project . Visual simulations from key locations where Pathway can be viewed are provided in Attachment N . Describe proposed mitigation strategy . Where feasible , the Pathway route through Weld County is collocated along existing infrastructure to minimize impacts to the surrounding area . The type of steel used will be weathering steel that oxidizes to resemble a natural brown look and is not shiny . The visual landscape along the route features existing transmission lines , roadways , and industrial elements , and Pathway will result in an incremental increase in infrastructure in the viewshed . COLORADO ' S POWER PATHWAY 38 Existing undisturbed trees , shrubs , and native vegetation will be preserved to the extent possible to maintain visual contrast in the landscape . Following construction , the ROW will be restored in a manner generally similar to pre - construction conditions consistent with previous representations . Construction vehicles and equipment will be maintained in proper operating condition and equipped with manufacturer ' s standard noise control devices ( e . g . , mufflers or engine enclosures ) . f Environmental impact analysis — Transportation impacts . i Describe what impacts the proposal will have upon transportation patterns in the area intended to be served or affected by the proposal . Construction of Pathway is not expected to cause significant effects to Weld County transportation , and any impacts will be temporary in nature . Work crews will mobilize each day from the laydown yard to the work areas . Traffic to local work areas will be limited to supervisory vehicles transporting work crews , required construction equipment , and equipment delivery vehicles . Construction equipment or labor transportation are not anticipated to have a significant impact on traffic volumes or flow on local roadways or state / county highways . Any increases in traffic will be short term and limited to the construction time period near individual transmission poles . P athway will cross the existing Burlington Northern Santa Fe Railroad in Weld County near Weld County Road 95 % and Weld County Road 26 % approximately 5 miles southwest of Wiggins . Xcel Energy will obtain all appropriate permits from the Burlington Northern Santa Fe Railroad . No impacts to the existing railroad are anticipated . P athway will cross I - 76 / US - 6 approximately 2 . 5 miles east of the Weld County Road 73 interchange at Roggen . Xcel Energy will obtain required permits from CDOT . No impacts to transportation on I - 76 / US - 6 are anticipated . P athway is not located within the approach or departure zone of any airports in Weld County . The closest airport to the Pathway route within Weld County is approximately 1 . 75 miles away . Therefore , no impacts to airports are anticipated . Xcel Energy will file with FAA as necessary for certain poles or areas of the line . ii Describe the potential impact on roads within the County . The portion of the Pathway transmission line subject to this 1041 Application will cross I - 76 , US - 6 , the 1 - 76 Frontage Road , and the following Weld County Roads : 28 , 31 , 33 , 386 ( Phanter Road ) , 39 , 41 , 43 ( Cavanaugh Road ) , 49 , and 59 . Traffic will be delayed temporarily for the time it takes to string conductor across the road . Traffic Control Plans will be developed in areas where travel on roadways could be impacted during COLORADO ' S POWER PATHWAY 39 construction . Construction updates and schedules will be discussed with local government officials as needed as details are determined . Necessary road use and ROW permits will be obtained from Weld County as needed prior to construction . Identify improvements required to any roads within the County in order to serve the project adequately . Where practicable , existing public roads and private roads will be utilized during Pathway construction , maintenance , and operation . Some private roads may require improvements and some new access roads will need to be constructed to accommodate construction equipment and long - term maintenance of the transmission line . Where road improvements are needed , Xcel Energy will acquire any necessary grading , stormwater , and erosion control permits and comply with permit requirements . Xcel Energy will acquire access easements where necessary access routes traverse private property . Some access routes may remain post - construction to maintain access to transmission lines for operation and maintenance activities . g . Environmental impact analysis — less damaging alternatives . f the Planning Department determines that the nature or extent of the proposal involves the potential for significant environmental damage or warrants examination of specific , less environmentally damaging alternatives , the Planning Department may request that the Board require the applicant evaluate and present information on such alternatives as part of the application . Required information on alternatives may include , but shall not necessarily be limited to , information on the environmental impacts and cost- effectiveness of the alternatives in relationship to the proposal presented . The process utilized to review and consider reasonable siting and routing alternatives is described in the Segment 1 : Fort St . Vrain — Canal Crossing Routing and Siting Study ( Attachment B ) and the response to Supplemental Question 9 of this 1041 Questionnaire . COLORADO ' S POWER PATHWAY 40 PLANNING QUESTIONS 1 . Exp a ' n , in detai the proposed use of the property . Include , at a minimum , the fo lowing : a . Current or previous use of the land, if any . Of the 45 miles of proposed Pathway 345 - kV double - circuit transmission line transmission line routing planned for construction in unincorporated Weld County , 34 . 3 miles of the route will be located in newly acquired transmission line easements and ROWs that will require permitting subject to this 1041 Application . Approximately 3 miles of the Pathway route subject to this 1041 Application will be located adjacent to an existing electric transmission corridor west of I - 76 , 6 . 5 miles will be adjacent to or near 1 - 76 , and 2 miles of the transmission line will be adjacent to an existing railroad . The transmission line will be located across A ( Agricultural ) Zone District lands within Weld County . The transmission line will traverse lands currently u sed for agriculture ( crop and animal production ) , oil and gas development , and grassland / grazing areas ( see Attachment P , Agricultural Lands Map ) . To mitigate against any negative impacts this transmission line route might have on the active farmlands surrounding it , Xcel Energy has worked directly with the individual surface u se owners to strategically locate the alignment proposed along the quarter section lines and along property lines to avoid as feasible impacts on farming and other types of agricultural operations in the area . b . Describe the uses surrounding the site and explain how the proposed use is compatible with them . Existing land uses present near Pathway facilities include industrial facilities , oil and gas wells , natural gas compressor station facilities , communication facilities , oil and gas pipelines , a photovoltaic solar facility , a landfill , a tire recycling facility , and several existing high voltage transmission lines and electric distribution lines . Agricultural facilities located near Pathway facilities include cultivated crops , cattle feed yards , a confined animal feeding operation , and a meat processing facility . Other linear infrastructure , including railroads , Interstate Highways , U . S . Highways , and local roads exist in proximity to Pathway . Pathway is compatible with these uses because it has been sited specifically to minimize surface - use impacts to the surrounding community and preserve land for agriculture , rangelands , wetlands , and critical habitat areas . Because Pathway will be u nstaffed and monitored remotely 24 / 7 / 365 , with only annual site visits to inspect the overall infrastructure , no impacts will be felt from long - term additions of traffic or COLORADO ' S POWER PATHWAY 41 services needed on the region . Once Pathway has been completed , it may result in job opportunities and employment in the energy projects that ultimately interconnect to P athway and align with the intent of the zone district as further energy development will be possible with Pathway ' s development . c . Describe the proximity of the proposed use to residential structures . Avoidance of residential subdivisions and planned development were major factors in identifying the preferred and alternative routes ( see Attachment B , Routing and Siting S tudy for Segment 1 ) . Residential areas are concentrated near the municipalities of Gilcrest , Platteville , Fort Lupton , Hudson , Keenesburg , Roggen , Wiggins , Fort Morgan , and Log Lane Village . Residences are few and widespread within the more rural parts of unincorporated Weld County where Pathway is sited . Existing residences are shown on Attachment A , Vicinity Map . d . Describe the hours and days of operation (e . g . Monday thru Friday 8 : 00 a . m . to 5 : 00 p . m . ) . The utility line , once in operation , will be in operation 24 / 7 / 365 . See the response to S upplemental Question 2 of this 1041 Questionnaire . e . List the types , number, and uses of the proposed structures to be erected . A description of the Pathway transmission line and other related facilities subject to this 1041 Application is provided in Section 1 . 4 of this 1041 Application . f. Describe the size of stockpile , storage or waste areas to be utilized, if any . Once Pathway is operational , no permanent stockpile or storage areas will be required . TCAs will be used during construction to stage construction equipment and materials including construction trailers , portable toilets , cranes , and transmission poles . At the end of each construction phase , equipment will be removed from the TCAs for that construction phase . No proposed improvements at the TCAs will be permanent , and TCAs will be restored in a manner generally similar to pre - construction conditions . See S ection 1 . 4 . c of this Application for additional information regarding TCAs , including the Cervi Yard . All required Grading and Access Permits will be obtained prior to construction of P athway in Weld County . COLORADO ' S POWER PATHWAY 42 g . Describe the method and time schedule of removal or disposal of debris , junk and other wastes associated with the proposed use . P athway is not anticipated to generate pollution during operations and maintenance and will not require permanent pollution control equipment once in operation . Required federal , state and county construction and waste management procedures will be followed to prevent accidental spills or runoff of sediment or contaminants to waterbodies or groundwater . Once construction has been completed , construction equipment and materials will be removed from the site and waste products from the construction process will be properly disposed of as needed . Areas that will not be needed for operations and maintenance will be reclaimed in a manner generally similar to their condition before construction or as may be provided for in private agreements ( including re - seeding per Xcel Energy ' s vegetation management standards and S WMP ) . h . Include a time table showing the periods of time required for the construction of the operation . S ee the response to Supplemental Question 2 of this 1041 Questionnaire . i . Describe the type of lot surface proposed and the square footage of each type (e . g . asphalt, gravel, landscaping , dirt, grass , buildings) . The proposed Pathway facilities subject to this Application are 34 . 3 miles long by 150 feet wide and is located across A ( Agricultural ) Zone District active farmland and rangeland . The transmission line alignment spans existing irrigation ditches and pivot irrigation in fields and follows section lines , road ROWs , and property boundaries to minimize impact to existing uses and agricultural operations ( see Attachment P , Agricultural Lands Map ) . Permanent Pathway facilities will be limited to the footprint of the individual transmission poles and transmission access roads ( see Section 1 . 4 . c of the Application ) . With the exception of these areas , remaining areas disturbed during construction will be reclaimed in a manner generally similar to their condition prior to construction or as may be provided for in private agreements ( including by re - seeding in accordance with Xcel Energy ' s vegetation management standards and SWMP ) . j . How many parking spaces are proposed ? How many handicapped (ADA ) parking spaces are proposed ? No permanent public parking spaces are proposed or required for Pathway because the transmission line will be unstaffed and monitored remotely 24 / 7 / 365 once in operation . During construction , access drives from nearby roads for construction and maintenance will be incorporated into the transmission line design and temporary parking of COLORADO ' S POWER PATHWAY 43 construction vehicles will be located within the designated TCAs . Once construction has been completed , areas not needed for operations and maintenance will be reclaimed in a manner generally similar to their condition prior to construction or as may be provided for in private agreements ( including by re - seeding in accordance with Xcel Energy ' s vegetation management standards and SWMP ) . k . Describe the proposed screening for all parking and outdoor storage areas . No fencing or screening is proposed because no permanent parking or outdoor storage areas are proposed . I . Describe the existing and proposed landscaping for the site . Given the small area occupied by the transmission poles , and the minimal anticipated visual impact , landscaping is not proposed as part of Pathway . Existing undisturbed trees , shrubs , and native vegetation will be preserved to the extent practicable to maintain visual contrast in the landscape . Once construction has been completed , areas not needed for operations and maintenance will be reclaimed in a manner generally similar to their condition prior to construction or as may be provided for in private agreements ( including re - seeding in accordance with Xcel Energy ' s vegetation management standards and SWMP ) . m . Describe the type of fence or other screening proposed for the site . There is no proposed or existing screening . A temporary 4 - foot - high barbed wire chain link security fence will be installed around the Cervi Yard during construction . The perimeter fence will be removed following construction . The Pathway route through Weld County is collocated along existing transmission infrastructure and county roads to reduce visual impacts . The type of steel used will be weathering steel that oxidizes to resemble a natural brown look and is not shiny . Visual impacts of the transmission line will vary based on proximity and with distance , the scale of the transmission poles will be minimized . The visual landscape along the route features existing transmission lines , roadways , and industrial elements , and Pathway will result in an incremental increase in infrastructure in the viewshed . n . Describe reclamation procedures to be employed as stages of the operation are phased out or upon cessation of the activity . Once construction has been completed for each Pathway segment , temporary work areas and the transmission line ROW will be restored in a manner generally similar to their condition prior to construction and as may be provided for in private agreements . This work may include drain the and fence repair , rut removal , decompaction , tilling , COLORADO ' S POWER PATHWAY 44 seeding and stabilization measures . Areas not needed for ongoing operations and maintenance and not being used for crop production will be reclaimed and / or reseeded as soon as practicable and in coordination with the landowner following construction in a given area . If any loss or damage occurred to crops or other non - restorable property during construction , Xcel Energy will compensate the landowner for such loss or damages . ROW agents will meet with landowners to learn about site - specific circumstances , which may need to be addressed . o . Describe the proposed fire protection measures . Transmission lines are built and maintained to meet or exceed safety standards , such as those specified by the National Electrical Safety Code and the North American Electric Reliability Corporation . Every effort is made to ensure safety in construction , operation , and maintenance of transmission lines . Transmission lines are designed to withstand extreme weather conditions , and protective devices at line terminals stop the electricity flow under abnormal operating circumstances . The transmission poles will be equipped with shield wires above the energized line ; this equipment adds to the pole height but also provides protection against lightning strikes . Xcel Energy ' s facilities are designed , constructed , operated , and maintained to meet or exceed all applicable requirements of the IEEE standards and accepted industry standards and practices including IEEE 979 , Guide for Substation Fire Protection . Applicable fire laws and regulations as outlined in CRS 31 - 15 - 601 will be observed during construction and normal operation of the transmission line . Fires along transmission lines are very rare . Xcel Energy ' s facilities are monitored and controlled remotely from an operations center where event response is coordinated . In the rare event of an emergency , Xcel Energy will likely be aware of an issue before the general public or emergency responders . Nevertheless , the public is encouraged to contact Xcel Energy ' s emergency number : 800 - 895 - 1999 to report an emergency . Unauthorized personnel , including emergency responders , should not approach the facilities and should not touch the electric lines or anyone or anything in contact with them . In the event of an outage or transformer failure , the affected equipment is immediately de - energized by the breaker equipment and Xcel Energy personnel are dispatched to the site . Xcel Energy personnel receive safety training for emergencies relating to high - voltage electrical equipment . Xcel Energy also coordinates closely with local fire departments and first responders and consults with them to discuss any concerns within their response area . Xcel Energy offers free online safety training to fire departments and first responders that is based on national standards through the Responding to Utility Emergencies Program . COLORADO ' S POWER PATHWAY 45 2 . Explain how this proposal is consistent with the Weld County Comprehensive Plan . P athway is compatible with the future development of the surrounding area and directly aligns with many of the County Comprehensive Plan goals provided in Chapter 22 of the Weld County Code . P athway will not directly cause significant changes in land use intensity or development in the immediate area . Aside from the transmission pole foundation footprint , areas under and around Pathway facilities can continue to be used for agricultural operations after construction has been completed ( see Attachment P , Agricultural Lands Map ) . After construction , current uses adjacent to Pathway will be able to continue and preserve desirable community and rural patterns meeting goal 22 - 2 - 30 ( A ) ( 2 ) of the Weld County Comprehensive Plan . P athway facilities have been sited to minimize surface - use impacts on the surrounding community and preserve land for agriculture , rangelands , wetlands , and critical habitat areas . As such , Pathway is in alignment with goal 22 - 2 - 30 ( C ) ( 2 ) of the Weld County Comprehensive Plan . Xcel Energy acknowledges that there are local economic benefits when multiple businesses collocate and combine operations and technology . Pathway encourages agglomeration economies of synergistic businesses directly related to goal 22 - 2 - 40 ( A ) ( 5 ) of the Weld County Comprehensive Plan . Encouraging the development of new technologies in Weld County is essential to ensuring its economic prosperity . The Eastern Plains region of Colorado is one of the nation ' s best areas for wind and solar energy generation , but it does not currently have a network transmission system that can integrate these new generation resources into the state ' s interconnected grid system , which is needed to meet Colorado ' s clean energy goals . Pathway will support Xcel Energy ' s Clean Energy Plan ( Xcel Energy 2021 ) which is estimated to deliver as much as an 85 percent reduction in carbon dioxide emissions by 2030 and add approximately 5 , 000 megawatts of new wind , solar , and other resources . Pathway will help to meet the state ' s growing electricity needs , improve safety , reliability , and affordability , and enable the transition to clean energy . P athway will allow developers of energy generation projects to interconnect energy resources located in the areas of the state that are underserved by backbone transmission lines and allow Xcel Energy to deliver energy to electric customers . P ee Attachment K for more details as to how Pathway aligns with each specific Weld County Comprehensive Plan goal . COLORADO ' S POWER PATHWAY 46 3 . Explain how this proposal is consistent with the intent of the zone district ' n which 1 is located . ( Intent statements can be found at the beginning of each zone district section in Article III of Chapter 23 . ) The Pathway facilities subject to this Application are located in unincorporated Weld County within the A ( Agricultural ) Zone District . Pathway has been sited to minimize surface - use impacts to the surrounding community and preserve land for agriculture , rangelands , wetlands , and critical habitat areas . By working with individual landowners , collocating the transmission line route , or strategically locating the route adjacent to other existing public infrastructure improvements or property lines , the Pathway alignment has minimized the impacts to adjacent agricultural uses ( see Attachment P , Agricultural Lands Map ) . Once in operation , Pathway will not create adverse impacts to the existing agricultural u ses resulting from uncontrolled and undirected business , industrial , or residential land u ses . The transmission line will be unstaffed and monitored remotely 24 / 7 / 365 . Xcel Energy ' s transmission lines are normally inspected annually to check for line connections and damage . During construction , minimal permanent impacts to natural resources or agricultural lands will occur . After construction , lands can continue in agricultural use , with the exception of the footprint of the individual transmission poles . As part of the land rights process , Xcel Energy will identify easements or ROW for other u tilities , canals , or roads . Pathway will not cause any undue interference with existing mineral extraction , easements , or ROW during construction and operation . Pathway will enhance the socioeconomic environment in Weld County during the construction period via increased revenue to local businesses and social services . Construction will require contract labor , and provide local jurisdictions and host communities with additional tax revenues and potential employment opportunities . Once in operation , Pathway may facilitate ongoing job opportunities and tax revenue in energy that ultimately interconnects to Pathway . Additionally , generation developers will have the opportunity to build projects that otherwise were infeasible due to lack of transmission access to market and / or transmission constraints . These generation projects may provide other additional economic development through increased jobs associated with construction and local tax - based revenue associated with land usage , and payments to existing landowners . COLORADO ' S POWER PATHWAY 47 4 . Explain how this proposal will be compatible with future development of the surrounding area or adopted master plans of affected munic ' palities . P athway will be compatible with future development of the surrounding area because it has been sited to minimize surface - use impacts to the surrounding community and preserve land for agriculture , rangelands , wetlands , and critical habitat areas . P athway will allow developers of energy generation projects to interconnect energy resources located in the areas of the state that are underserved by backbone transmission lines and allow Xcel Energy to deliver energy to electric customers . Encouraging the development of new technologies in Weld County is essential to ensuring its economic prosperity . Pathway will support Xcel Energy ' s Clean Energy P lan ( Xcel Energy 2021 ) which is estimated to deliver as much as an 85 percent reduction in carbon dioxide emissions by 2030 and add approximately 5 , 000 megawatts of new wind , solar , and other resources . Pathway , while not located within any municipal jurisdiction within Weld County , will help to meet the state ' s overall growing electricity needs , improve safety , reliability , and affordability , and enable the transition to clean energy . See also the response to Planning Question 3 . 5 . xplain how this proposal complies with Article V and Article XI of Chapter 23 if the proposal is located within any Overlay Zoning District ( Airport , Geologic Hazard , or Historic Townsites Overlay Districts ) or a Special Flood Hazard Area identified by maps officially adopted by the County . P athway is not located in any airport , geologic hazard , or historic townsites overlay districts . The Pathway alignment subject to this Application will cross two Federal Emergency Management Agency - designated 100 - year floodplains within unincorporated Weld County associated with the Box Elder / No Name Creek and Lost Creek ( see Attachment L ) . Prior to construction , Xcel Energy will obtain Floodplain Development P ermits from Weld County for crossing these floodplains . 6 . If the proposed use is to be located in the A ( Agr ' cu tural ) Zone District , expla ' n your efforts to conserve pr ' me agricultural and in the locationa decision for the proposed use . Construction and operation of Pathway will not inhibit agricultural production or operations . Pathway will result in minimal permanent impacts to agricultural lands ( see Attachment P , Agricultural Lands Map ) . Through private agreements with individual landowners , the proposed alignment spans existing irrigation ditches and pivot irrigation COLORADO ' S POWER PATHWAY 48 in fields . It is sited to run adjacent to and parallel with section lines , parcel boundaries , and public ROW to limit impacts from the development on overall agricultural operation and production in the area . During construction , temporary impacts to agricultural activities are expected to be minor . Xcel Energy will avoid the removal of ground cover where possible . Disturbed areas will be revegetated following construction . Disturbed areas will be returned to pre - construction conditions or reseeded according to landowner requests and Weld County requirements . Agricultural use can continue for these lands except the footprint of each transmission pole . Permanent Pathway facilities will be limited to the footprint of the individual transmission poles and transmission access roads ( see Section 1 . 4 of this Application ) . 7 . Explain whether this proposal interferes with the protection of the health , safety and welfare of the inhabitants of the neighborhood and the County . By working with individual landowners , obtaining , and meeting applicable federal state and county permits , collocating the transmission line route , or strategically running the route adjacent to other existing public infrastructure improvements , the Pathway alignment mitigates and minimizes to the furthest extent possible the impacts to the health , safety , and welfare of the adjacent agricultural inhabitants . Pathway will not affect wetlands or critical habitats in Weld County . Sensitive natural resource areas , including wetlands and critical habitats for wildlife , were specifically considered as part of the routing and siting analysis when the preferred location for the transmission line was identified to minimize potential interference from Pathway facilities ( see Attachment B , Routing and Siting Study for Segment 1 ) . Xcel Energy has communicated with CPW and USFWS representatives regarding Pathway and will continue to coordinate with them throughout design and construction of Pathway and comply with applicable regulatory requirements . COLORADO ' S POWER PATHWAY 49 ENV RONMEN A HEALTH QUESTIONS 1 . What is the dr ' nking water source on the property ? If ut ' I ' zing a dr ' nk ' ng water we I inc ude ether the well perm ' t or we permit application that was submitted to the State Division of Water Resources . If utilizing a pub is water tap include a letter from the Water D ' strict , a tap or meter number , or a copy of the water bil . Water to be used during construction will be obtained from a local , permitted source . Pathway will not require water use during operation . 2 . What type of sewage disposal system is on the property ? If uti izing an existing septic system provide the septic permit number . If there is no septic permit due to the age of the exist " ng septic system , apply for a septic permit through the Department of Public ealth and nvironment pr or to submitting th ' s application . If a new septic system will be ' nstalled please state " a new septic system is proposed . " Only propose portable toilets if the use is consistent with the Department of Public Health and nvironment ' s portable toilet pol ' cy . Pathway will not create any wastewater nor have any facilities requiring wastewater treatment . Portable temporary bathrooms that will be serviced on a regular basis will be on site during the construction period . 3 . If storage or warehousing is proposed , what type of items wi be stored ? No permanent storage is proposed . TCAs will be used during construction to stage construction equipment and for materials storage ( steel poles , conductor wiring , etc . ) . At the end of each construction phase , all equipment will be removed from the TCAs for that construction phase . 4 . Describe where and how storage and / or stockpile of wastes , chemicals , and / or petro eum wi occur on this s ' te . No hazardous materials will be used , stored , or generated on site of Pathway facilities . Chemicals that may be used during construction and operation are those found in diesel fuel , gasoline , coolant ( ethylene glycol ) , and lubricants in machinery , and if any such chemicals are used , they will be stored within the TCAs pursuant to appropriate storage protocols and applicable regulatory controls . COLORADO ' S POWER PATHWAY 50 5 . If there w ' be fuel storage on site , indicate the gallons and the secondary containment . State the number of tanks and gallons per tank . No additional fuel storage will be used , stored , or generated on site of Pathway facilities with the exception of storage of diesel fuel , gasoline , coolant ( ethylene glycol ) , and lubricants in machinery within the TCAs , as described in the response to Environmental Health Question 4 . 6 . If there will be washing of vehic es or equipment on site , indicate how the wash water wil be contained . Washing will be performed once on each vehicle or piece of equipment dedicated to P athway to avoid spread of noxious weeds prior to commencement of construction operations . Washing will be performed offsite at commercial washing facilities . If there wi I be floor drains , indicate how the fluids will be conta ' ned . No floor drains are proposed . 8 . Indicate if there will be any air emissions ( e . g . painting , oil storage , etc . ) . S hort - term effects to air quality are anticipated from a temporary increase in construction vehicles , which may increase fumes and fugitive dust , construction equipment exhaust ( fumes ) , and clearing and preparing areas for construction ( dust ) . Exhaust and dust during operation is not expected . An analysis of air pollution impacts and control alternatives is provided in the response to Supplemental Question 10 of this 1041 Questionnaire . Provide a design and operations plan if applicable ( e . g . composting , landfills , etc . ) . P athway is not a composting or landfill facility . 10 . Provide a nuisance management p an if applicable ( e . g . dairies , feedlots , etc . ) . P athway is not a dairy or feedlot . 11 . Additional information may be requested depending on type of and use requested . Environmental Health has not requested any additional information . COLORADO ' S POWER PATHWAY 51 ENGINEERING QUESTIONS 1 . Inc . ude a traff ' c narrat ' ve w ' th the information below . A traffic impact study may be required . Improvements to adjacent streets / roads may be necessary to prov ' de adequate safe and effic ' ent transportat ' on to and from the site . An Improvements Agreement may be requ ' red . a . The projected number of vehicle trips (average per day, maximum per day, peak hour data) to and from the site and the type of vehicles (passenger, semi- truck, etc . ) . The approximate duration and estimated roundtrips per day per vehicle type for the construction of the transmission line subject to this Application are provided in Table 9 . Table 9 . Daily Vehicle Trips during Transmission Line Construction in Weld County Approximate Approximate Daily Approximate Daily . Approximate Major Construction Construction Passenger Car Truck trips by Total Daily Tasks Duration ( Weeks ) Trips Vehicle Ty se Roundtrips Foundation 13 weeks 15 Flatbed trucks 5 48 Installation Concrete trucks 28 (74 per day ) Steel Pole 16 weeks 10 Flatbed and 35 Installation ( 74 per Semi - trucks 25 day ) Conductor/ Optical 14 weeks 5 Semi - trucks 15 21 Ground Wire Crane 1 Aerial Lifts 2 b . Describe how many roundtrips/day are expected for each vehicle type : Passenger Cars/Pickups , Tandem Trucks , Semi- Truck/Trailer/RV (Roundtrip = 1 trip in and 1 trip out of site) See response to Item 1 a . c . Describe the expected travel routes for site traffic . Construction traffic will utilize two laydown yards for deliveries of construction materials and equipment : the Sarchet Yard and Cervi Yard . Construction activities in the eastern half of the proposed transmission corridor will utilize the Cervi Yard and construction activities in the western half of the proposed transmission corridor will utilize the Sarchet Yard . • Cervi Yard : East - west - bound Interstate Highway 76 ( 1 - 76 ) : Construction traffic will access the Cervi Yard from I - 76 via the I - 76 frontage road . COLORADO ' S POWER PATHWAY 52 • Sarchet Yard : North - south - bound Colorado Highway 85 : Construction traffic will access the Sarchet Yard via Weld County Road 32 . Daily construction crew traffic will likely access Weld County Road 32 from Highway 85 near Platteville . Once construction has commenced , traffic will originate from both the Cervi and Sarchet yards and will travel along the following Weld County Roads to access the transmission line ROW : 18 , 20 , 22 , 23 , 26 , 28 , 30 , 32 , 33 , 39 , 43 , and 49 . The portions of these roadways utilized will be those Weld County Road segments west and north of the 1 - 76 corridor and east of the U . S . Highway 85 corridor . During construction , the total traffic volumes accessing Weld County Roads are estimated at 50 percent from the Cervi Yard and 50 percent from the Sarchet Yard . However , when construction is concentrated in the western half of the transmission line corridor , traffic volumes are estimated at 75 percent from the Sarchet Yard and 25 percent from the Cervi Yard . When construction is concentrated in the eastern half of the transmission line corridor , traffic volumes are estimated at 75 percent from the Cervi Yard and 25 percent from the Sarchet Yard . During foundation installation , a portion of daily truck traffic will deliver concrete directly to the ROW , without an interim trip to a laydown yard . d . Describe the travel distribution along the routes (e . g . 50 % of traffic will come from the north , 20 % from the south , 30 % from the east, etc . ) See response to Item 1c . e . Describe the time of day that you expect the highest traffic volumes to and from the site . The highest traffic volumes will occur between 6 a . m . and 8 a . m . when personnel arrive at the laydown yard to begin work and to travel from laydown yards to the ROW . Deliveries will be mostly between 6 a . m . and 10 a . m . Traffic will primarily remain on the ROW when work is being done . Traffic associated with concrete trucks will be between 8 a . m . and 3 p . m . on days when concrete is being poured . At the end of each day , work traffic will head back to the laydown yard between 5 p . m . and 6 p . m . Deserte where the access to the site is plannedu The 1041 Map ( Attachment D ) illustrates the proposed transmission line road crossings . The 1041 Map lists each crossing location , road name , reception number , book and page number , and road ROW width . COLORADO ' S POWER PATHWAY 53 3 . Drainage Design : Design and construction of a detention pond as described ' n an approved Drainage Report is required unless the project falls under an exception to stormwater detention requ ' rements per code . ( See be ow . ) Does your site qually for an exception to stormwater detention ? If so , describe in a drainage narrative the following : a . which exception is being applied for ? Include supporting documentation . P athway qualifies for exception number 5 in Section 8 - 11 - 40 of the Weld County Code : " Pipelines or transmission lines , excluding laydown yards , metering sites , substations , and any other above ground appurtenances " as the subject of this 1041 Application is a transmission line . b . Does the water flow onto the property from an offsite source ? If so , from where ? Off - site water flow onto the property will range due to the length and linear nature of P athway . Off - site surface water flow onto the property will not change due to construction . c . Describe where the water flows to as it leaves the property . S urface flow from Pathway will range due to the length and linear nature of Pathway . S urface water flow from Pathway will not change due to the minor localized grading impacts and pole installation . If needed , culverts will be designed and installed for the continued free flow of water . Culvert design and required water quality controls ( i . e . , riprap and erosion control measures ) will be submitted to Weld County for approval . If installed , culverts will be inspected , maintained , and repaired regularly throughout the life of Pathway to minimize blockage and verify proper function . d . Describe the direction of flow across the property . S urface flow varies across the property due to the nature of a linear build . The direction of flow will not change due to construction , even in areas where minor localized grading is expected . COLORADO ' S POWER PATHWAY 54 e . Describe the location of any irrigation facilities adjacent to or near the property . The transmission line crosses a number of irrigation canals . Xcel Energy will execute agreements with the ditch companies , and no impacts to the ditch from construction or operation of the transmission line will occur . f Describe any previous drainage problems with the property . Xcel Energy is not aware of any previous drainage problems with the properties . If your site does not qualify for an exception , the fo lowing applies : a . A Drainage Report summarizing the detention pond design with construction drawings and maintenance plan shall be completed by a Colorado Licensed Professional Engineer and adhere to the drainage related sections of the Weld County Code . Xcel Energy is requesting an exception as the subject of this 1041 Application is a transmission line . b . The Drainage Report must include a certification of compliance , which can be found under the Development Review webpage on the Planning and Zoning website , stamped and signed by the PE . Xcel Energy is requesting an exception as the subject of this 1041 Application is a transmission line . c . See the attached Drainage Report Review Checklist . Xcel Energy is requesting an exception as the subject of this 1041 Application is a transmission line . COLORADO ' S POWER PATHWAY 55 BUILDING QUESTIONS 1 . List the type , size ( square footage ) , and number of existing and proposed structures . Show and label al exist ' ng and proposed structures on the USR drawing . Labe the use of the building and the square footage . S ection 1 . 4 . a of the 1041 Application describes the proposed transmission line poles . The anticipated physical characteristics of adouble - circuit transmission line are summarized in Table 4 , and a representative transmission pole with line is shown in Figure 4 of the 1041 Application . The new transmission line will be constructed on monopole steel structures within a 150 - foot - wide ROW . Assuming an average span length of approximately 950 feet between structures , the transmission line would require approximately 191 poles . 2 . Explain how the exist ' ng structures wil be used for this USR . P athway will not use any existing structures . 3 . List the proposed use ( s ) of each structure . P athway is a 345 - kV double circuit electric transmission line . COLORADO ' S POWER PATHWAY ATTACHMENT D : 1041 USR MAP SEE TYLER NUMBER 2024 0555 Weld County Site Selection and Construction of Major Facilities of a Public Utility Application COLORADO ' S POWER PATHWAY ATTACHMENT E : CERV LAYDOWN YARD DRAINAGE REPORT AND SITE PLAN Weld County Site Selection and Construction of Major Facilities of a Public Utility Application Drainage Design Memo Xcel Energy - PWAY Segment 1 Fort Saint Vrain - Cervi Yard Weld County , Colorado April 7 , 2023 By : Samuel Acosta , PE & Maria Chavez Weld County PWAY Segment 1 — Fort Saint Vrain — Cervi Yard 1r T -) , Drainage Design Memo Certification Statement This memo for the drainage design of PWAY Segment 1 Fort Saint Vrain - Cervi Yard was prepared in accordance with the provisions of Weld County Engineering and Construction Criteria ( WCECC ) and the design meets drainage requirements set forth in the county criteria . The variance request information is included in the at the bottom of the Certificate of Compliance in Appendix A . Design Criteria References Drainage design for the PWAY Segment I Fort Saint Vrain - Cervi Yard follows the WCECC manual and references the most current Mile High Flood District ( MHFD ) for specific design guidance . Specific notable criteria utilized in the project design can be found in table 1 . AB E 1 - W LD COUNTY D SIGN CRI ERIA Design Frequency for Storm Sewers Minor 10 - year & flowing at 80 % of full pipe capacity Major 100 - year Velocity The maximum velocity in all storm sewers shall be 18 ft / sec . he minimum velocity shall be 3 ft / sec . EGL & HGL The final EGL shall be at or below the proposed ground surface . The HGL shall not exceed the crown of the pipe for the minor storm . In cases where the conduit is designed to convey up to the full 100 - year flow , the allowable HGL must be 1 foot below inlet elevations , or 1 foot below ground where no inlets are present . Pipe Size - Storm Sewers Type Minimum Equivalent Pipe Diameter Storm Sewer in public ROW 15 - inch Culverts in public ROW 15 - inch Outlet Pipe for Detention Facilities 12 - inch Pipe Slopes Minimum slope of 0 . 5 % , but 1 . 0 % is recommended General Information Cervi Yard is located on the northwest 1 / 4 of Section 4 , Township 2N , Range 62W , 5 ' P . M and on the southwest 1 / 4 of Section 33 , Township 2N , Range 62W , 5 ' P . M . Cervi Yard ' s longitude and latitude coordinates are N40 ° 10 ' 27 " and W104 ° 19 ' 47 " . Cervi Yard is south of Frontage Rd and 176 and northeast of County Road 75 . 5 . The Lost Creek is roughly about 4 . 5 miles North of the Cervi Yard . The owner of the project sites is Public Service CO of Colorado , Xcel Energy . The project scope includes constructing a sub - base gravel surface pad that supports conex containers , dumpsters , trailers , personal vehicle and equipment . Security fence will be placed around the gravel surfaced pad . The gravel pad and yard will be restored upon the completion of the project . The Project will have two entrances to the site along 1 - 7 6Frontage Rd . An hdrinc . com 1670 Broadway Suite 3400 Denver , CO 80202 Weld County PWAY Segment 1 — Fort Saint Vrain — Cervi Yard 1 r T I , Drainage Design Memo infiltration pond will be placed west of the Cervi Yard gravel site pad to collect runoff from the site and prevent any flooding in the pad . Stormwater best management practices will be used to control stormwater runoff and reduce the spread of pollutants . Go gle Maps . iip e"., km - it a: . 4 - . ; . 1 i ‘ e lb a mlLiT‘P ri u. 4 " la • s .PS • N V . a : I i 4 ilokeL i - . A4 il :ga; a I " latii4a alit% - -,4 _ : 9 . j . t t‘.; , I t4 10 ti 4 386 , P1 1ECT SITE ( CER' I YARD ) nt 1(4 " 1 .44 * A 1 ) n 0 1 i 4 - , , , , _ 114p4-14tist. IP ' 44; f 9 . _ + - ..s • nothA) • had Lai C u • 4 A I , eiti IIIK Vile. ii.: a ‘ 1 : 1 9/k � j,p� + 4 • t • a R'S 9Rw � ti ' I • ems � 1 .r • C W . : ' • 4 :Irk- 4 e 73 A .• itti: 9 , . 1 ash.,,,,ta„4„ : / 4 = vv. . 7 'V : - i Fe :I t _is sir * i t tr - -im /ilk Asi MA tett 411‘3% , _ , ; _ • t: .13‘t t , lit , - . , 14 M 6 ... . 1 I 4 it lir i % illei -4.4%11111111111.11 i ode Imagery 2023 al ES / Airbus ,us , Landsat 1 Copernicus , Maxar Technologies , LISP . Geological Survey, L DA/ FPAC /GFp, Map data 1 mi Figure 1 : Vicinity Map Hydrology Hydrology was developed for the project area using the M H FD U D - Rational Method Workbook version 2 . 00 . The workbook was modified to utilize the Weld County ' s runoff coefficient equations from WCECC table 5 - 3 , for the 5 - year , 10 - year , and 100 - year storms . The workbook was also modified to utilize WCECC impervious values . Weld County ' s rational method is accepted in the WCECC for urban basins less than 160 acres in size . Per Weld County criteria , the minimum time of concentration for non - urban areas shall be limited to 10 minutes . The hydrologic criteria is summarized below in Table 2 . TABL 2 — HYDROLOGIC CRITERIA SUMMARY TABL Hydrology Weld County Engineering & Construction Criteria Acceptable Methods Rational Method for Basin < 160 acres in size Runoff Coefficients Table RO - 5 , ( USDCM 2007 Runoff Coefficients ) , ( WCECC ) Imperviousness Values Table 5 - 2 , Percentage Impervious Values for Weld County , ( WCECC ) hdrinc . com 1670 Broadway Suite 3400 Denver , CO 80202 Weld County PWAY Segment 1 — Fort Saint Vrain — Cervi Yard 1r T -) , Drainage Design Memo P reeplaton Rainfall intensity - duration frequency table values for this project were determined using values from NOAA Atlas 14 Point Precipitation Frequency Estimates at the centroid of the Project . See Appendix E for full table on point precipitation estimates . TABLE 31- NOAA ATLAS - POINT PRECIPITATION FREQUENCY ESTIMATES ( INCHES ) FOR CERVI YARD Average Recurrence Interval ( years ) Duration 2 5 10 25 50 100 500 60 m i ns 0 . 887 1 . 17 1 . 44 1 . 87 2 . 25 2 . 67 3 . 80 24 h rs 1 . 82 2 . 32 2 . 77 3 . 45 4 . 01 6 . 62 6 . 22 SO . S S oil information was obtained from Natural Resources Conservation Service ( NRCS ) Websoil S urvey . Cervi Yard project area consists of Hydraulic Soil Groups Type A , Valent Sands with 0 to 3 percent slopes . Infiltration rates for the site were obtained from NRCS . This soil could infiltrate at a high rate of 29 . 97 inch per hour . See Appendix C for NCSS soil maps . Existing Conditions In existing conditions , Basin E2 and E2 . 1 consists of native vegetation . Runoff flows southeast to northwest . The project is south of 1 - 76 Frontage RD . A roadside ditch is just south of 1 - 76 Frontage Rd , but the ditch is very flat . A gravel road runs just west of the project site from north to south from 1 - 76 Frontage Rd to the Burlington Northern Railroad . P roposed Conditions In proposed conditions , drainage patterns will remain the same . For Basin P2 , there will be two entrances to the site along 1 - 76 Frontage Rd . Both will entrances will be via aggregated surfaced . Proposed imperviousness will increase by 3 acres of gravel using the WCECC impervious value of 40 % . An onsite stormwater filled swale will be placed along the north side of the project to collect site runoff . An infiltration pond is proposed on the west side of the project site and will collect all site runoff . A berm will be placed on the along the north side of the site to prevent flows from the roadside ditch to enter or overflow into the site . Design Discussion Infiltration Pond & Spillway Design The proposed infiltration pond was located such that the entire gravel pad is approximately 2 . 0 ' above the 100 - year , 24 - hour duration water surface elevation . This will prevent flooding in the site during a rainfall event . The second method in the WCEC was used for calculating the infiltration pond volume . The infiltration pond was sized 2 . 0 times the developed site runoff of the 100 - year . 24 - hour storm event plus 1 additional foot of freeboard . Due to grading constraints , the volume of the pond will be sized 0 . 5 times larger than the WCEC requirement and will not have an outlet structure or spillway . The bottom of the pond was sized large enough to infiltrate 29 . 97 in / hour or higher and will release 97 % of all runoff from a rainfall event that is less than or equal to the 5 - year storm of 0 . 34 acre - feet within 72 hours after the end of the hdrinc . com 1670 Broadway Suite 3400 Denver , CO 80202 Weld County PWAY Segment 1 — Fort Saint Vrain — Cervi Yard 1r T , Drainage Design Memo event . The 100 - year , 24 - hour duration volume of 2 . 26 acre - ft is 4 feet deep . Infiltration pond calculations have been included in Appendix F . F oodp a ' n Analysis The project extents are within FEMA FIRM Panel 08123C2025E for Weld County , Colorado . The project is located in a Zone X floodplain in an area of minimal flood hazard . Zone X is not regulated and will not require a floodplain permit . See Appendix C for map . rosion Control Erosion and sediment control plans will be developed based on the WCECC , in conjunction with other recommended resources in the Mile High Flood District ' s Urban Storm Drainage Criteria Manual , Volume 3 , Chapter 7 , Construction BMPs . Erosion and sediment control will be provided for construction activity throughout the entirety of the project . Water Qua ly The project sites are not within the Weld County ' s state permitted Municipal Sperate Storm Sewer System and will not require water quality . See Appendix H for MS4 map . Conc us ' on The infiltration pond , storm system , hydrologic and hydraulic design were designed to meet Xcel Energy Criteria , WCECC and the Mile High Flood District ' s Urban Storm Drainage manual to provide a functional drainage system for the project site . The design will adequately protect public health , safety , and general welfare and have no adverse impacts on public rights - of- way or offsite properties . References • Weld County Engineering and Construction Criteria , January 2021 . • Urban Storm Drainage Criteria Manual : Volume I , January 2016 . • Urban Storm Drainage Criteria Manual : Volume III , November 2010 . • National Food Insurance Program , Flood Insurance Rate Map , Weld County , Colorado , 08123C2025E ( January 20 , 2016 ) • National Oceanic and Atmospheric Association ( NOAA ) Atlas 14 . https : / / hdsc . nws . noaa . gov / hdsc/ pfds / pfdsmapcont . html hdrinc . com 1670 Broadway Suite 3400 Denver , CO 80202 5 Weld County PWAY Segment 1 — Fort Saint Vrain — Cervi Yard I . T Drainage Design Memo Appendix A . Certificate of Compliance B . Basin Maps C . FEMA FIRM Map D . Soil Maps E . Precipitation Information F . Rational Method Calcs G . Pond Calcs H . Drainage Checklist & MS4 Map hdrinc . com 1670 Broadway Suite 3400 Denver , CO 80202 6 Weld County PWAY Segment 1 — Fort Saint Vrain — Cervi Yard 1 T Drainage Design Memo Appendix A - Certificate of Compliance hdrinc . com 1670 Broadway Suite 3400 Denver , CO 80202 7 ‘ ntlit Weld CountyDrinage Code - _ _ ' ' - _ _ CertIcate of Compliance :. ,.Ro : . rLeP r 1 44, "Weld County Case Number : ~ Parcel Number : 130104000012 , 121933000011 5825 - A PT SE4 & E2SW4 33 3 62 LYING S OF HWY # 76 Legal Description , Section / Township / Range : 5565 N2 4 2 62 EXC NW4NW4 ALSO EXC BEG N872 ' FROM E4 COR OF SEC THENCE N1320 ' S87DW 869 ' S03DE 1320 ' TON SIDE OF BURLINGTON - NORTHERN RR R / W N87DE 800 ' TO BE Date : 03 / 21 / 2023 0 s ) I Sam Acosta Consultant Engineer for Xcel Energy ( Applicant ) , understand and acknowledge that the applicant is seeking land use approval of the case and parcel in the description above . I have designed or reviewed the design for the proposed land use set for in the application . I hereby certify , on behalf of the applicant , that the design ea xtv11 applicable drainage requirements of the Weld County Code with the exception of the variances described • i ':�� '�' ac )1 - tibits . This certification is not a guarantee or warrant either expressed or implied . ( ) , . . P�j� �ej � g Y p p Stam : O *r: " en a Engineer ' s �� - qp v Co \ , (S ) 52470 / - o ' , 03 / 21 / 2023 , ' < c , , , Engineer of Record Signature F N s/ � k oNAL ts, ���— Akvv ariance Request If Applicable ) 1 . Describe the hardship • Y7ls c the variance is being requested . 2 . List the design criteria of the Weld County Code of which a variance is being requested . 3 . Describe the proposed alternative with engineering rationale which supports the intent of the Weld County Code . Demonstrate that granting of the variance will still adequately protect public health , safety , and general welfare and that there are no adverse impacts from stormwater runoff to the public rights - of - way and / or offsite properties as a result of the project . 1 ) This project proposes installing a laydown yard in Weld County , Colorado . The proposed laydown yard will consist of 3 acres of gravel installed approximately 2 - foot above 100 - year , 24 - hour storm water surface and requires a stormwater detention pond to meet discharge criteria . The existing site topography is flat and does not have an outfall fora stormwater pond nor does the site have an adjacent irrigation canal that the pond can tie into . 2 ) The project proposes to install a stormwater infiltration pond instead of a stormwater detention pond . This variance is for Weld County Engineering and Construction Criteria Manual Section 5 . 10 . 1 Retention . 3 ) The proposed alternative is to install a stormwater infiltration pond . This pond will follow Weld County Criteria and will be sized 2 . 0x the developed site runoff for the 100 - year , 24 - hour storm . This variance request will still adequately protect public health , safety and general welfare . There are no adverse impacts from stormwater runoff to the public rights - of- way or properties as a result of this project or this variance . Public Works Director/ Designee Review ( If Applicable ) Public Works Director / Designee Name Signature Date of Signature f 1 Approved ❑ Denied Comments : Department of Public Works Development Review 1111 H Street , Greeley , CO 80631 I Ph : 970 - 304 - 6496 1 www . weldgov . com / departments / public_ works / development _ review 08 / 02 / 2019 Weld County PWAY Segment 1 — Fort Saint Vrain — Cervi Yard 1rm 1=) , Drainage Design Memo Appendix B - Basin Maps hdrinc . com 1670 Broadway Suite 3400 Denver , CO 80202 8 � J / 1 44 / 47 (2 N - -\-- 111•jr - '1$IItIttw. ��� ( 1 /� /�� x.16 /'' V. •1- �_..� / .- - o0 • a / ' '' / -'/ - q69 / -/ ♦♦ \ /moo/ tt ♦ E2 { \ \w 0.02 -' \ t,t I "S _ \ / I /// I NI -- ` 4p, J 1 c� ` \ -- \J t� 45.3 0.2 J as" 1►, 1 / \\ t / �o 'S.- / L. N. ''v - S I i `� / / L \1 ( 1 -- REV DATE WBS 4 REVISION DESCRIPTION REV DATE WBS 4 ♦ 4\ \ \ y \ \ \ / _----c 0 /4 � ''. %. �,/\ STAGING AREA BOUNDARY �00000 t f' � I S ` / ti BURLINGTON NORTHERN RAILROAD REVISION DESCRIPTION REV DATE WBS 4 0.1 1 2023/03/30 1 A.0001671.003.001.002 1 IFP - PATHWAY SEG 1 SHEET NOTES: 1. CONTOURS REPRESENT TOP OF SURFACES, UNLESS INDICATED OTHERWISE. UNCHANGED SURFACES ARE SHOWN AS DASHED (EXISTING). ALTERED CONTOURS ARE SHOWN AS SOILD (PROPOSED). 2. TOPOGRAPHY DERIVED FROM UNITED STATES GEOLOGICAL SURVEY (USGS). ROGGEN Us KEY MAP SCALE: 1" = 5700' LEGEND A A BASIN NAME B BASIN SIZE (ac) B C10 C 5YR COEFFICIENT C 100YR COEFFICIENT FLOW ARROW EXISTING BASIN FLOW PATH -- PROPERTY LINE EXISTING MAJOR CONTOUR • EXISTING MINOR CONTOUR 600 SCALE: 1" = 150' CL=54 ft / /_ ISSUED BY ENGINEERING DEPT FOR: PERMITTING, NOT FOR CONSTRUCTION THIS MAP/DOCUMENT IS A TOOL TO ASSIST EMPLOYEES IN THE PERFORMANCE OF THEIR JOBS.YOUR PERSONAL SAFETY IS PROVIDED FOR BY USING SAFETY PRACTICES, PROCEDURES AND EQUIPMENT AS DESCRIBED IN THE SAFETY TRAINING PROGRAMS, MANUALS AND SPARS. _ / PATHWAY SEGEMENT 1 - EXISTING DRAINAGE MAP (-J CERVI YARD REVISION DESCRIPTION SCALE REV 7 XcelEnergy® SHEET 1 OF 2 1"=150' O.1 1 (D O cv) Wz 0 0 z I- 0 )� / N o �\ . '2 \ J 1 / rte/ / I rl ) / / I C� (I 1 \ STORMWATER BERM I SITE c ACCESS VIA .AGGREGATE' �/.. nFia5 SURFACE I // / // "�6g5if ��111 C®\\\� •tAl�l • \11e / LIJ 1 1 I —II 1 I —II 1 1-1.1 •a' LL' 1 VV1 1 1 p 'F�ON�•...''\\ �� EXISTING DRAINAGE SWALE ❑N SITE STORMWATER SWALE TEXAS CROSSING GRAVEL SURFACED V' / \ I `L f oy , r / I / i PROPOSED FENCE / it PROPOSED STORMWATER �` � j �, / \ TREATMENT BASIN--,c� S / / z 1 (INFILTRATION) L � I / \ _ BASIN MAINTENANCE ACCESS �,f\ 4700 ( / DRAINAGE SWALE TO BASIN \ 1,\ \ c � / \ / ) I /7 ( i4690_2 690,/ / / V Jam/ tl -i rl / /r \ / I \ 1 n/ -I I C 1 \J r 1 \ / J I 1. N. REV I DATE I WBS4 I REVISION DESCRIPTION REV I DATE WBS 4 ) C S \ ( - \ 1 1 \ � -�• \ N47,0 / 1 STAGING AREA BOUNDARY I / \ \\ f i \ � 1 , o /J \ / / \ % ( -7 \ \ t I - - / - - - / ) < r ( > -C r - _J- `� L _ BURLINGTON NORTHERN RAILROAD ! - REVISION DESCRIPTION I REV I DATE I WBS 4 I REVISION DESCRIPTION SHEET NOTES: 1. CONTOURS REPRESENT TOP OF SURFACES, UNLESS INDICATED OTHERWISE. UNCHANGED SURFACES ARE SHOWN AS DASHED (EXISTING). ALTERED CONTOURS ARE SHOWN AS SOILD (PROPOSED). 2. TOPOGRAPHY DERIVED FROM UNITED STATES GEOLOGICAL SURVEY (USGS). ROGGEN Us KEY MAP SCALE: 1" = 5700' LEGEND A A BASIN NAME BC5 B BASIN SIZE (ac) c10 C 5YR COEFFICIENT C 100YR COEFFICIENT FLOW ARROW PROPOSED BASIN FLOW PATH (SURFACE) PROPERTY LINE 100 EXISTING MAJOR CONTOUR - -99- EXISTING MINOR CONTOUR 100 PROPOSED MAJOR CONTOUR 99 PROPOSED MINOR CONTOUR INFILTRATION POND STAGE STORAGE STAGE (FT) AREA (FT^2) AREA (ACRE) V❑LUME (FT^3) V❑LUME CAC -FT) 4681 23,083 0153 - - 4682 25,757 01591 24,413 0156 4683 28,537 01655 51,550 11183 4684 31,449 01722 81,534 11872 4685 34,490 01792 114,493 21628 4686 37,660 01865 150,557 31456 POND VOLUMES 100-YR AC -FT 5-YR INFILTRATION POND VOLUME 0134 AC -FT 0 150 300 600 SCALE: 1" = 150 i Ni ISSUED BY ENGINEERING DEPT FOR: PERMITTING, NOT FOR CONSTRUCTION THIS MAP/DOCUMENT IS A TOOL TO ASSIST EMPLOYEES IN THE PERFORMANCE OF THEIR JOBS.YOUR PERSONAL SAFETY IS PROVIDED FOR BY USING SAFETY PRACTICES, PROCEDURES AND EQUIPMENT AS DESCRIBED IN THE SAFETY TRAINING PROGRAMS, MANUALS AND SPARS. PATHWAY SEGEMENT 1 CERVIYARD PROPOSED BASIN MAP SCALE XcelEnergy® SHEET 2 OF 2 1150' 0.1 1"=150' N O O cC a) M CD O N LU 0.1 I 2023/04/07 I A.0001671.003.001.002 I IFP - PATHWAY SEG 1 pm - W 1=n PATHWAY SEGMENT 1 LAYDOWN YARDS - CERVI YARD A PORTION OF THE NORTHWEST QUARTER OF SECTION 4, TOWNSHIP 2 NORTH, RANGE 62 WEST, 6TH P.M. A PORTION OF THE SOUTHWEST QUARTER OF SECTION 33, TOWNSHIP 2 NORTH, RANGE 62 WEST, 6TH P.M. WELD COUNTY, STATE OF COLORADO ENGINEER HDR ENGINEERING, INC. 1670 BROADWAY, SUITE 3400 DENVER, CO 80202 CONTACT: BRIAN BROWN (970) 215-4616 0 LOCATION MAP 1320 2640 SCALE: 1" = 1320' XCEL ENERGY 5280 PUBLIC SERVICE COMPANY OF COLORADO 1800 LARIMER STREET DENVER, CO 80202 CONTACT: SASCHA ARCHIE (718) 869-4118 INDEX OF DRAWINGS 1 OF 5 COVER SHEET 2 OF 5 EXISTING CONDITIONS 3 OF 5 PROPOSED CONDITIONS 4 OF 5 SITE PLAN 5 OF 5 DETAILS PROPERTY OWNER'S CERTIFICATION I, the undersigned, certify that the uses, buildings and structures located on this Site Plan Review are designed and will be constructed and operated in accordance with the development standards heron and the district requirements for the Zone District as stated in Chapter 23 of the Weld County Code. I understand failure to comply with the development standards, applicable provisions of County Code, and/or any conditions of approval could result in the County initiating a compliance action against me or my successors. Signature of Property Owner The foregoing instrument was subscribed and sworn to me before me this day of ,20 ___ by WITNESS my hand and official seal. My commission expires: Notary Public DEPARTMENT OF PLANNING SERVICES' ADMINISTRATIVE REVIEW CERTIFICATION This map is accepted and approved for filing. Director of Planning Services The foregoing certificate was acknowledged before me this WITNESS my hand and official seal. My commission expires: Notary Public day of 20 _, by ISSUED BY ENGINEERING DEPT FOR: PERMITTING, NOT FOR CONSTRUCTION THIS MAP/DOCUMENT IS A TOOL TO ASSIST EMPLOYEES IN THE PERFORMANCE OF THEIR JOBS.YOUR PERSONAL SAFETY IS PROVIDED FOR BY USING SAFETY PRACTICES, PROCEDURES AND EQUIPMENT AS DESCRIBED IN THE SAFETY TRAINING PROGRAMS, MANUALS AND SPARS. PATHWAY SEGEMENT 1 COVER SHEET CERVI YARD Xcel Energy® 0 M O O 0 M N- 0 7 REV I DATE WBS 4 REVISION DESCRIPTION REV I DATE WBS 4 REVISION DESCRIPTION REV DATE 0.1 2023/04/07 WBS 4 A.0001671.003.001.002 IFP - PATHWAY SEG 1 REVISION DESCRIPTION SHEET 1 OF 5 SCALE REV S SHOWN 0.1 N O N N N I /' / l J �' //iii/� /i//�i l! / / \ ( — } \ ) \ \`\%% / / / —�\ / / /1 ( } \\\ 1 \ �. /• . - ) ) / f l / / ( \ ii/'/ /iii/ / i \) / ^ 1 I ri 1 \ \ \\ / —\� cl Th / Ir ,\ \-/ - _17 0�"/i / ) I./ ( ) / lr I \ \\ ( \ r \'N \ I /� ^ r [ /iii/ /'/ ( ) \ ! l ? \\ \\\ �- ee\ •\ \)\� ` ` 1 % V1 /- //�� _ -�- / / ^ /I / \ ► �'- ✓� / ` ) ! (✓ y / / A �� / /I ( -N / / ( \ \ \ \ \\ \ \ �\ ,/ /mil r_) // 0- / ( / / �/� /- \( �/ / \\ I '% \C //_-\ II /. /�// �// ��� } I N. \\� /� _ / • r- \ ? \ 1 1 1\ ) \ _ _} / i -\ '1 \ \�•\ /1\—/��.._ ,r;.� ��� ` /,s// } I / �•// . /-.//�i /� ji//// .i\I \�f�';��\./�J'-`�"`—I /J I �— `--I \/ l ` \ 1 \ \\ \l 1 > \ ( r\ 111 \\ / / //�/ i%� / /s' i'/ / ( 1\ \ C / \ \ 9 1 \ \\ / \ 1 /i// /s // //i \) \ , / \ l /i// /i/i / \\) ! — -' 7< �/ ) I / / [� o/•_ 1 1 \ 1 \ / \ C o I I \ 1 1 \ ( ) \ ' \ ,/, �6 //'- ` ., /' \% \ ) r \\ \ /- ^J -\// /I-)' 1 / \ ` \ } I - \\ \ \ \ 1 J ` �) \ 1 "..`\ / / \ \ /i"/i - �' '1 ) ` \ \/ \'\\\\\( \ \ 1 _ -' ) / //� 1 ` ) ( ' \ \ .-- - r .� -. / / \ ` ( r ✓ O ( L ( I /` J L . \ \ \\ \ \ \ \ / ( \ \ \ \ \\ e \ ) `� \ , J! ` ( /%� � r ` ��/%. I ✓ \ \ \ \ �...� /`_ ter\ . � / / / J j i \ \ ` / L. i/� I / / \ / / _ ,\ / _ L / _ ¼ ¼ l /' - (/ / �.-2i; / / / l rte ) ( /� \ \ \ \ \ \ \ •" i \ \ \ \ I / ^� \ / /\ /yam/ / /ii% �'% / - / c I \ \ \ \ \ ) I \ \ ( \ \ }- -\ \� // // / /// / i' /i/ ` �\ 7/c ) \ \ 1 , \ •, vex 1 / L / / / / —1 �/ '////// // �/ ` / / 1 -mil 1 ) I \ \ \\ -.\. ( .\ C* ( `/ / J //j/j/ ///!i/// ///.k �'�- �- ( ( �\ \ \/�. -- \� \ / I f / // / ! / S ,` / / / / �� / /��/ // \ / I / / 'I �// / J/ \ 1 \ I \ \ �1 i' I I \ � \ \ / / ) 7r'(( (� / / e // \ 1 \ \ � � \. \ \\ / / �• , / 1 J \ 1 ) } 1 / ( � j /— i \ \ 1 \ \ s \ r—`� 1 ' / �\ / / ................................. ,ii/� /� % �/ L / - / I I� \ / 1\\ I /\ \\ <' / /J I / _ / - _-_/ \ , 1\ \. \ \\ r -f ) ) I J `_\ \\\_\^ / c / I J \) / \ 1 I \ \ N. / \ ✓ -" i o-' _• / / / r / / ` \ / / C `� \ \ l S -- \ \ ''/� / / '• ` /� - // r/ / - �-t/—� _ �1) / i /� / \I \� ✓ • %i FFLON� l\.) (`` / ,/ \\ �/ (l // r ///—_--/`�—.-�-r.\ - 1\� `I) (I \\ \ <\.\\N� /\ ^-` f\\` / / // // - r J I I \ \/ \/ S J \ 1 ( / () /ii ii/ ' � //ie%�/ -f �l \ 1 �/ ( / I \ / 1- \ r- \� ) !//�,\\ / / / / I 1 • `� \ /' \\1\ /5 / //// /`j / \ f / / 1 _ _ , 1 \ I / / ✓I I I \, \�/ / O ) \ ` } / / / / —/ (L) ) o` ) _ \\ /\ ) J I `\ ( \ / / /i /'% /� %/\�. `-_ —_ / / ( I -� 1 / 1 / j� 1 \ \ 1 c� \\ \ \\\ \ / / / \ \ 1 \ \\ \ \ \ \ \\ / 1 I / r \ /% \ / f \/ / / / / / / �_v►' ) \\ �y-,p _.) \ 1 \\\ �`� \ \) j\ ) \\ �\ j / / \ NJ 1 \/ / /% �i / // / ) r I \\�_/ / / \ \\ __/\\ ` / (1 11 \ ) � _ —/ \\ v \ ) / II (( / / f �� / �� y/ // \ \\ \ / / \\ \J 1 r \) .—�\/ (\ // /�\) \ I\ �/ !/� \ `( j'— /—\ \\ \ \`J r— //`\ \ \ \ ) ) ) / // —/ \. ( \\\\ \_�/J \ ~�I \ _\ - .. I V I _ Jr` \ ` \\ ( 1 ) ) a� / / /--\�- '— I \\I i _ \\ \\ ✓ /- //\ 1`i / ) 1 I / I _ _/-��\�\''I \\\\ \\ /% I \ r \ / / \ I \ \ / \ \i \ ) \ \l \ ) \ \ \ /\ yv. ' Q/- v - \\vv A v v v ( J \ S /C \ \ \ �� / / \\ 1 / l 1 \ ( � r ( I \ \ \ \ \ \ \� 1 \ \ <'�- \ \\\ 111 \ 1, . \ �\ \\\\\\ �/1 / ! 1/ ,\ \ ) i� 1 �. /" ` / / �1.. - 1 " \\\ \ I I! / .- \" l "•-'"�/ \\V11 \ \\�\ L k \\ \\ \\\ / ) /rte \ \ 1 _•, STAGING AREA BOUNDARY / STAGING AREA BOUNDARY --, -' / \\\\ - / t \ 11 ! �. / ( \\;��\ r \ / ) / / ) `Y J / \ 1 \ ,^ \ I\ ) - \ I (, , \ \ \ \1 ` \ l y �\ / / \ \ \ 1 � . = \ \ L \ / / ,-} \\ ` - - \ \ \ \ \ \ �r I -l-_ \ 1 / -" 1 l «( ,\ \ ' 1 I ✓ \\\1 r / \\ \%, \ -- 1 `_✓/ r } `\ --\ \\ , -- l \\J ) \ •\ \ j ( i l ! \I 1\ / 1 r %^� \ _{{'t l\\\\\\\ \� l \ ' (} l \\ j /\� \ / r3 ) (7 J- 1 \ \\ \ \� ) / 1 ( \ ) `1 /) ) 1 \ _ / \\ / 1 \ • ) I ) r'\ %\ \ I ) I \ ) \ \ \ 1 0 r ( l \/ / I �'\ ) , - '1 I \ \ I �ti \ / \\ ) l _// / r ---- i /- \ -'./ / • 1 ( L'�1 ( / / iiz( �_ \ \ _ i' I 1 \ r \ \ ( / / ! i //l \ \ \ ( \ -� �\ 1 \ \� lam\ •\ _ , ) O/�/ / 1t \ ,, II ( \ I tr / J \ ( i t �\, \ r ;' ) ( ! I 1 ( \ _ \ ) ),I `� \� \ I\1 �✓ I -- ' V ) I \• ) V `� (/ f \1 (/� C\1\mil \ /r// /i /^I( /�-- J� J\ \ \ / 1 \ / r 1 i `.,% \\ , / f ) ) I I i ` \ l r• - _ - _-_- �� \ - _ r . (I / _ �/ !/ \t \ I ( l / \ \ _=_�__ } , 'I I \ / i \ / / I ( _ ) \ 1 > ( ( /' _ l - �� \ I ) / I / ) I'L�t '(/!�� _-_-- \�O\y\ ` = = \ / / / \ l / { - / J \ L\ 7 ( \ 1 11 I I/�///,/ / \ \\\\ \ )/ie_ \. \ .\.\ `. \ ,\ 1 // ! 1 I \\ / \ C \ \ f / I 1 I II II 1 / I/� \, r / \ ` ( J / 11 III 1 \ \�1 Ii� \ �� / �� __ /_/ } \ I / / r 1 / / ltl III 1 111 I \ ` \ I = �r / - 1 / / 1 . j / I l .Ij111 I I } II1 / \ \ 1 \ �/ / (� \1 \\ 1 1\} 1� \ / �� ( I C `S/ / ) \\ 1 / \ i I _— k I �\ I jl 1jlI 'Il \I L� ) / III ) , am\ I \ I \\ ( (/ ) \\ \ I (1 (~— J a} \\��`\1 I I \\ / �, 1 ' /) ! I\ �L1 ) / \ 1 r ( / ( \ \ \ ��1 I I / // I \• I I l 7 1 _' �> l ( ��• 1 \ �-- /�- \ ( )1 r\/\ \ \\•I` I '\II \ / 11 1I 1 \ ) ) , I r I I ( / / I ( ( I / / / \ \ ( \ \ '/ _ J,. o \ I I % \`, r / \ ( \\ `tik lI ' 11 \ ' `\ 11 r \, \ — 1 I \ �i ( < / \ r - i \/ ) / ) l _. J1�` ( \ ) L / / \}„ 1�\\ -� 1\iI1I� ` r_ . 1 / / / I r �� ) , \ - 1 \ / r �/ (\ _ �� -\ \ r \ `- `v-- -i \ �- ' / / (/ \ / (` ` �L / ) // \j; t L Tr�~// / % ,' \\J� 1�/ 1 � 1� J > ` vj \� .... `r - � / � _-r_ ._ �- -- _I 1 - -/ %. / ` ^ — C( \ __ - - -. - - ---C. / ` r ( _I / v .� / — — I _ / \ �- ..— i. �, /' ^ / S \ / I • —� �— ..�'� .� � _. l •/- /� J -� f ( - - -- r .� 1 A /• a _� \`�1 -^ _� -� - 1 `--� ..../ - / /I �\ / J -_ r + t `��f•3'- 1 \-.-. / '\ .. / l '\ e ` ` r — v , 9 V 1 \ --� �% " / _ — 1 / _� �__ —i- =tee_ _� G� — ---�• _ _- -_ .-. — --7 _ 7 \ % l 1 (• _. l (\/ _ v / ti _ -- - _ _ — _! - -'(\\\, I — -_ / -• I I �� `J -/ ��\ �/ r / ) / - �\ -�f r ' .� _—� ) �\/ I l_ -�\ \ _�• f rl` -� _�\ - \ I a -_-_� - / I ) ` �- r / C\_� / -a ` \ ` > J-- \ s i '• — ya 6 _S �_-- --1 N i \ \ 1 ( — l / , 3 c =—_ =f \ �C �. �` \ ` — o. ( \( //) L )� s,(� \ �I / /! �1 )-'� f / J %J / '� / / ( I/ \ f I I'� I \) / 1 ) \\\\ 1 /((,/// l / / \ \ l i \\\ \ \� -- �"� /� r 1 �)1) / ( \ \\ ( ) ` \ _ / / /r rJ i ,� ( !l )) v`J�L C`� / \ \\\ �+ \ \1\ I i ._r\\ \ \ L'_ /-- /-_ \\ t 1 \ ) ) ) ` // l / y\, �� �\ \� -\ l- 1 — f/ �/ o``' // ,r/ / \\ Q / / I I � \_ 1 �' \ ///// I ( \ ` \ U( ` r �u \ _ ��L , / Jam_- ///� / I \ \\, ( \ \ � / / /) r // ! I / 1 \ I P ! / _ \ ( \" ( r I • \ /� / /( / 1 \ \ I / ) I I I \ I \\\11\1 } \ l l \) \ I ( \ ) I / \ / I \\ \ c�C. . —f --- ( / i 1 _\ ) \ I / \ \� ) /— 1 1 /7 1 ( 1 \' /) / `—L �' / —/ O / ( l \i'2\ >` \ I 11 \�^\ \ > / / �� / I e ! '/ // J —"r `^ ) rl I ) ` ( I r<//�`\ \ (� \�} \ l ( ( ) I C h \ \\ e --'I — r _ `__—'' ^/ y / / ( \ \ 11 ) J / ) \ \ l 1 \ 1 I �/ /— 1 r. -`)/ / . ( �� 1l1\ \\ t'f� \\/��- k\( l \ \ \ t r _-. C�1.-• "-- - - / - -• / / / \\ ( / / �- n( I I , r \ \\ r- �_ \ \ / r / / /) / / r I \ — \ \ \ ( ) \ / / \\ \ ) 1 \\ \^71 / / I 1\ 1 \\\\ \ ` \` \\ \\ \ /� �,i ( v/; r^� /� �( , f r I 1 1(` / I 1 \ I \ I \\ C3 \\ —J / \ I \\ \— ) \ \\ \_ r 1 I ,c ) r / \ 1 \\•\`�^ \ \\\�)%l \ \ \/ 5 (/ c( / r / / / ) \ \ \ \ \ ! ( V \ \ r ` r — - / I \ \ \ \-_% , \\ \ I ) , v I} \ \ _ , / 4710 ) / a t / / ) \ \\ . \ e \ \ I \ \ \ — (/ / ! I ! \ \\ \ �-/ \ r ri\\ I ) / ^r— / / / -� �i �� / / ) J • ) \ \�� — \\1 \\�\) \ \ \I i �- / ! \ L / ) 4� .1 I / - \ \� / / / \ \.\) I " ( / r \ \ \ \ / / > ( / ! \ \ \ ��'\ , N I 1 r ) t _ % / \ \ ' \ { / I / �/ ) �-- _ _ .......... /\ I \ \ � l / r / / / / / / / r -- > r) r) ` \\ �` /) !/ �� I\„ ( \- �� /, �� - l -/ fv r r // //\ - �- .. ) / REV I DATE WBS4 REVISION DESCRIPTION REV I DATE WBS 4 REVISION DESCRIPTION REV I DATE 0.1 I 2023/04/07 WBS 4 A.0001671 .003.001.002 IFP - PATHWAY SEG 1 REVISION DESCRIPTION GENERAL NOTES: 1. HORIZONTAL DATUM: NAD 83, CO STATE PLANE, NORTH ZONE, US FOOT, GROUND 2. VERTICAL DATUM: NAVD 88 - GEOID 09 3. CONTOURS REPRESENT EXISTING SURFACE ELEVATIONS AT 1 FOOT INTERVALS. 4. TOPOGRAPHY DERIVED FROM UNITED STATES GEOLOGICAL SURVEY (USGS). LEGEND: EX DRAINAGE SWALE EX MAJOR CONTOUR (5') EX MINOR CONTOUR (1') SITE BOUNDARY R0GGEN 76 / CERVI YARD J KEY MAP SCALE: 1" = 5700' N TRACT IN SW 1/4 OF THE NW 1/4 OF SECTION 4 TOWNSHIP 2N RANGE 62W 6TH P.M. 74.25 ACRES WELD COUNTY COLORADO OWNER: PUBLIC SERVICE CO OF COLORADO (XCEL ENERGY) RID: 130104000012 ADDRESS: XXXX 1-76, WELD 0 200 400 800 SCALE: 1" = 200' i N ISSUED BY ENGINEERING DEPT FOR: PERMITTING, NOT FOR CONSTRUCTION THIS MAP/DOCUMENT IS A TOOL TO ASSIST EMPLOYEES IN THE PERFORMANCE OF THEIR JOBS.YOUR PERSONAL SAFETY IS PROVIDED FOR BY USING SAFETY PRACTICES, PROCEDURES AND EQUIPMENT AS DESCRIBED IN THE SAFETY TRAINING PROGRAMS, MANUALS AND SPARS. PATHWAY SEGEMENT 1 EXISTING CONDITIONS CERVI YARD Xcel Energy® SHEET 2 OF 5 SCALE S SHOWN REV 0.1 7 N N O O O w U. U, N 0) M 0 N N 1 7 fJ mil\ Jam✓ / i / ✓/ /i Ste) c -c' (.1. 6� ROCKED ENTRANCES CA I / / / % H� .•...... \\\ eo c / j / / / / / / PROPOSED STORMWATER 4r / / TREATMENT BASIN - / j (INFILTRATION) / - - GRAVEL LAYDOWN YARD % / �� �~� i• `_. / N 1 / H Q ^\ U1 \ l \ \\ter ,\ (\ r N r� S, \ l - YARD OUTSIDE OF FENCE AND DRAINAGE r N \ 7 IMPROVEMENTS WILL NOT BE GRADED. `S \ \ 1 AREA WILL BE DRIVE AND CRUSH OVER \ f\ � / / / r� , EXISTING SOIL/VEGETATION. ( ` % \ 1 \ \ ) - I \ ) \ `(A) 2 ' / c \ cTh I 12 1 ,"/'' \ Rio f ( \ I I \ ( , N 4 1 \(( _ \ U Ut / r H 2 O _ J ✓ ) - - - - . - -_ '- - -- -� - a y _ _ \ / ./ _ Jam. c _ - -- _ _ _ _ - ThPy r - N � / r ) [ l r, C 1 `mil I / s 1 J ✓f \ N J 7 / / (/ REV I DATE I WBS 4 I REVISION DESCRIPTION I REV I DATE I WBS 4 I REVISION DESCRIPTION I REV I DATE I WBS 4 I REVISION DESCRIPTION 0.1 1 2023/04/07 I A.0001671.003.001.002 1 IFP - PATHWAY SEG 1 SHEET NOTES: 1. CONVEYANCE SWALE AND POND AREAS TO BE SEEDED AND MULCHED FOR FINAL STABILIZATION WHILE YARD IS IN USE. STAGING YARD AREA WITHIN SECURITY FENCE TO BE AGGREGATE SURFACED. 2. UPON DECOMMISSIONING OF SITE, POND GRADES ARE TO BE RE -STORED TO PRE -CONSTRUCTION GRADES, YARD AGGREGATE TO BE REMOVED, AND STOCK PILED TOPSOIL TO BE PLACED ACROSS DECOMMISSIONED POND AND AGGREGATE SURFACED AREA. AREA WILL BE RESTORED PER EROSION CONTROL REQUIREMENTS. 3. ALL SIDE SLOPES SHALL BE 4H:1V OR FLATTER, UNLESS NOTED. 4. ACCESS FROM STABILIZED YARD TO REMAINDER OF SITE TO BE THROUGH GATES. GATE LOCATIONS TO BE DETERMINED AND INSTALLED BY CONTRACTOR. LEGEND: EX DRAINAGE SWALE EX MAJOR CONTOUR (5') EX MINOR CONTOUR (1') - - -4895- - - PROP MAJOR CONTOUR (5') -------------- PROP MINOR CONTOUR (1') --------- SITE BOUNDARY YARD CONEX/TRAILER YARD SECURITY FENCE 1-76 ROGGEN KEY MAP SCALE: 1" = 5700' N 0 200 400 CERVI YARD 800 SCALE: 1" = 200' ISSUED BY ENGINEERING DEPT FOR: PERMITTING, NOT FOR CONSTRUCTION THIS MAP/DOCUMENT IS A TOOL TO ASSIST EMPLOYEES IN THE PERFORMANCE OF THEIR JOBS.YOUR PERSONAL SAFETY IS PROVIDED FOR BY USING SAFETY PRACTICES, PROCEDURES AND EQUIPMENT AS DESCRIBED IN THE SAFETY TRAINING PROGRAMS, MANUALS AND SPARS. PATHWAY SEGEMENT 1 PROPOSED CONDITIONS CERVIYARD SCALE REV Xcel Energy® SHEET 3 OF 5 AS SHOWN 0.1 pm - V in N 0 0 M N- 0 LI- U, N GD N U, //' /' / // /' // ' ' --/ / // / �--/ // ////////' / /-----5- // /' //' // //' ' / \ \ /' /'/''/' / // // // // // //' -/ i// / /- / /- /- ,/ , /- -a--- 6 a- ////// , // / i // // /// //' SITE P SURFi / CROS -1--- / / / / / / / / / -// /''/''/ /'' /'' OFF SITE STORM WATER SWALE / / / / / / / / / / / / / / / / / / / / / / / / / / / , / / /' _/ ' �/ /// //'/%// / /%// //%// // // //'//' / /' /// // // // / / 1 1 / / 46 / / \ /'/' / /// / I I / / / ' ' -' /' / /' /' �' ' / / � / / '' ' '' '' '' /' / ' ' '' '' '' '' ' / / /' ' /' /' /' /' j /' /' /' / /' / /' / 9 / / /' /' /' /' /' /' /' / / /' /' ESS VIA AGGREGATE -/''/ j //' //'/'' -/' -/'' /'' :, SEE DRAINAGE /'///////' ' -/'' •' /--' G DETAIL ' / •' ,. _, ► \ /- / / /' /� /' // /' /' �/ ' l� / / / / / / / // / // /� / / /' /' / -1 --/- �\ / \ / \/ � I / / ' - \ -/ // / // 1-�.� // - / SITE ACCESS VIA AGGREGATE // /'' / //' ' \ \/ \ / SURFACE SEE DRAINAGE 000 / �\ .a. ' // / / -/ // // ' /' /' //' // /' -' /' / \ ( / / CROSSING DETAIL / ('j�G pS ° / /-/ - -/ - / / , 'C P . / X0O / - - 0 \ / / / ON O o 00 00// - 60opo op ,- / , 1 / - / /�////// / �/- / \ 1 1 / - - ,/ ,/ // / // , -/ , // -/ ,/ 000 000 00 00 000 \ 0000oo00OOoo0oo0 \ , _,/' /' / /' //' /0 oQO OoQO OoQO OuUQO, OuUO OoQO Oo \ ____/ \ / '' / - /'' /' / - / / / /' /' 2�6 00OOUOOO�QUOOO�JOUo0O 0U000C�0U000�0U000�J0U000� / i a \ // 5- 4- -' / /' / // // //// / / -/ a-/ �./ O 00 O 00 O 00 O 00 0 00 0 00 0 \ / / 000 0000 0000 000 000 0000 0000 000 000 ---- / / r / /' /'/'/' __a-__.___ /' -/''/ O Qc70 \ O°VO\ O°IJOUO°VO\J°lJo\ O°VO\ O°lJo\J°VO\J D \ \\ \ I \\ /'/ / \ '' /' '' '/ 0 X0O X0O X0O X0O X0O X0O X0O X0O X0O > / o o OoQ ooQ ooQ ooQ OoQ ooQ ooQ ooQ OoQ / \ ' l // / / '' ///�� ;/- // : / OO O 0O O0 O0 O0 O0 O0 O0 O0 O0 / / /� //� /a- �/ / O O OoQ O�Q 0�(�_n0�(1_nOQ(�_n0on UL) uuu UU Mu 06Q O13 000a-- - o�O0oo�O�o ON SITE STORMWATER SWALE ?No_ O�o�9\W- K(\v)No o�O�� _ I / ------------------------------------ 5- / // O Q O Q p ( Q p Q p Q O Q p Q p Q p/ 00 0 000 000 000 TEXAS CROSSING )0 000 000 000 000 000 00> - /� /// //' 030,E o O� OOOOOOOOOOOOOOO( 00000000000000000000000000 O�Q O�Q UD( O�Q 10 WIDE 6 DEPTH ) O�Q O�Q OoQ O�Q O�Q OQ / �'� / / /'' ' /' `\ _ _ ' -/ 50 O O O O O GRAVEL SURFACED O O O O O O \ / O�OOO�OOO�OOO�OOO�OOO�uU0UuU0UuU0Uu00�000�000�000�000�000�000� I ''''/ ' Qoo Qoo QOo Qoo Qoo Qoo Qoo Qoo Qoo 0o Qoo Qoo Qoo Qoo Qoo O O OO O O O O O O O O O O O O O O O I I \ /'-/;/' / '- r ooQO ooQ ooQ ooh ooQ ooQ ooQ 0 Q ooQ ooQ ooQ ooh ooQ ooQ 0oQ ooh o0 /' ' / ' - / O O O O O O O O O O O O O O O 0 O O OU gO jOO��OO�Oo'�OO��OO��OO��OOd�OOdgOOQ/00dg00dg00dq006q00d/00dq00��00 / o0 000 000 000 000 000 000 000 000 000 000 000 000 000 000 000 000 000 000 \ I j /i/ / /' /' / /' - - - \ //.''•'' / 0600 Op�O OQDo Op�O Orgy Op�O Oo00 Op�O OI,0O Op�O Oo00 Op�O OI,oO Op�O Oo00 Op�O OI,oO Op�O Ooh 1 , -- %�- \\ 00°°OO(1°°�0(1°°O00°OX00°°O9( NN(°°O9 )ON(vtS 1°°�0(°°OO(°°X00°°OO(1°°�0(�°°O00°°�9\T 1°°0 / / �o �o Qo �O �o �o �O �O �o \ 0OQ 0OQ 0OQ 0O0OQ 0OQ 0OQ 0OQ 0OQ 0OQ 0OQ 0OQ 0OQ 0OQ 0OQ 0OQ 0OQ� I \ - �'�5- - 00 o Oo 0 00 0 00 &'Q o O 00 O Oo o Oo O Oo O 00 o Oo o Oo O O 00 o Oo o Oo O Oo 0 O �•/ /'/' \ppaO Oo OpuO 0p�0 Op�OO6UO 0p�0 LIn l nnonnnnO�n oo OD00 0�Q0 OoQo Op�O OpuO uu�u p I I \ \ Ft 1 / $� j \\ ��\\ �o�9T go oEO�ogOtQEO�o�9( OE96 9\ GRAVEL LAYDOWN YARD o�O�o�O P�\,� ODoogO�o�O�o�O�oo�O I ''� ,/'%'� y W�Q�0pOQ�0pOQ0pOQ�0oOQ0OQ0O, ooOQ�00Q�?OOQ�?OOQ�?OOQOucQOOpOQOOpOQO0pOQ00 ' REV I DATE WBS 4 / /, /, / 00000 00000 0000000 00000 0000 0000 00000 00000 0000 0000 00000 0000 �2 0000 00000 00000 0000 0000 00000 I / a O a O o O I 1 I 000�00�0000�0000�0000�0000�0000�000 / 1\ / I I RIPRAP RUNDOWN , / 000 000 000 000 000 000 000 000 000 0 n o_ / \\ 00 0 00 0 00 0 00 0 0 O f O 0 0 00 0 00 0 00 0 00 0 00 0 -5- - \ \ \ \ O�QO OoQO OoQO OoQO O 000 00 OoQO OoQO O�QO 0000 Oo oO oO O oO oO oO oO oO� S\T_'Op090°ONo_ NNE9a, 9o_ �O or,OgO��r,O°00M0°0�0�0°0�0�0°O, = Ci'S.. y y\ •\ . OQ o00Q0o00Q0o00Q0o00Q0o00Q0o00Q00 0 O O OQOo WATER TANK )'0 000 000 Oo O Oo Oo O0o O 0 Oo o �o �p 0000 00000 O \ \ \\\\ \`✓� J J y �L J J J\ QO°o\ (�OO� O° Off\ �QO° O° �� �o� 0Q� \ \ \ U IJOU IJOU IJO a OVUOO°VOUO°IJOUO°VOUO° � / / / o PROPOSED STORMWATER a\ \\" \ �000�000�000�000�U O O 000�000�000�000"J000�000� / �\ \ 00000000000 0 0 00000000000000000,E r `\00 O OoQO OuQO MukD 06()0 OoQO 0 , / \ \"��\\\\ W W (INFILTRATION) W \\� \\\�\�O°C�o�o°C�o�o° / / i i \\ \�y\�\"\\ y o y y \� \�\\ \ OOQQ�OOOOQ� 0O o �OOOOQ�OOQ�OOQ�OOQ�OOQ� / — ' / ' - \� \ o \a\ \\00�0j/�^�) 0 0 N. o �lO�Q01oo/Q`.0 �l0Q0QoO /' , \\ \\\ \k\ y o. Y �Y 4, y �Y �Y �L \\ `y U r / / `\\a\\W\\� a a w a \\ \\\ \`\ O0pOQ pO O OpOQOOpOQUOp \ ,i' /' / , / 0000 p6 OO OO o0On OO O RIPRAP RUNDOWN \ \\\ \\ \ •-- /, ` ' \\ A \\\ ✓ W W \ O p 00 O O OO0O� 0 / / /// \ \ \ i o00�Q o 00Q0 \\\\\\ \ y w w 1 O�pO O r / / // \\\\\\t .r 4, w �OOO OOOO l / I \ (! I \>\\ \ v v w-v5/�/y/ �j /go°00 � l / /r \ I 1 1 l / I \\\\ \\ it y -S.-/-���/��j/'�v5-/' �r1OQOO // // 1 ff f \ \ / I / / \�\ Iw YARD OUTSIDE OF FENCE AND DRAINAGE �' \ \ / -' ��--'// - IMPROVEMENTS WILL NOT BE GRADED. _ /' I ---/ �-- AREA WILL BE DRIVE AND CRUSH OVER I I EXISTING SOIL/VEGETATION. / l 1 / Ic / II // BASIN MAINTENANCE ACCESS ( /,/ DRAINAGE SWALE TO BASIN i I \ / / I / / / / I / / / I / \ / / - \ \ -I- I / \ / ' 1 / / \ / REVISION DESCRIPTION I REV I DATE I WBS 4 I REVISION DESCRIPTION I REV I DATE I WBS 4 I REVISION DESCRIPTION 0.1 I 2023/04/07 I A.0001671.003.001.002 I IFP - PATHWAY SEG 1 SHEET NOTES: 1. CONVEYANCE SWALE AND POND AREAS TO BE SEEDED AND MULCHED FOR FINAL STABILIZATION WHILE YARD IS IN USE. STAGING YARD AREA WITHIN SECURITY FENCE TO BE AGGREGATE SURFACED. 2. UPON DECOMMISSIONING OF SITE, POND GRADES ARE TO BE RE -STORED TO PRE -CONSTRUCTION GRADES, YARD AGGREGATE TO BE REMOVED, AND STOCK PILED TOPSOIL TO BE PLACED ACROSS DECOMMISSIONED POND AND AGGREGATE SURFACED AREA. AREA WILL BE RESTORED PER EROSION CONTROL REQUIREMENTS. 3. ALL SIDE SLOPES SHALL BE 4H:1 V OR FLATTER, UNLESS NOTED. 4. ACCESS FROM STABILIZED YARD TO REMAINDER OF SITE TO BE THROUGH GATES. GATE LOCATIONS TO BE DETERMINED AND INSTALLED BY CONTRACTOR. LEGEND: EX DRAINAGE SWALE - e e EX MAJOR CONTOUR (5') EX MINOR CONTOUR (1') - - -4895- - - PROP MAJOR CONTOUR (5') -------------- PROP MINOR CONTOUR (1') ---------- SITE BOUNDARY YARD CONEX/TRAILER YARD SECURITY FENCE 1-76 ROGGEN KEY MAP SCALE: 1" = 5700' N 0 50 100 CERVI YARD 200 SCALE: 1" = 50' I NI A ISSUED BY ENGINEERING DEPT FOR: PERMITTING, NOT FOR CONSTRUCTION THIS MAP/DOCUMENT IS A TOOL TO ASSIST EMPLOYEES IN THE PERFORMANCE OF THEIR JOBS.YOUR PERSONAL SAFETY IS PROVIDED FOR BY USING SAFETY PRACTICES, PROCEDURES AND EQUIPMENT AS DESCRIBED IN THE SAFETY TRAINING PROGRAMS, MANUALS AND SPARS. PATHWAY SEGEMENT 1 SITE PLAN CERVIYARD SCALE REV Xcel Energy® SHEET 4 OF 5 AS SHOWN 0.1 O r O N O O Co 0 . xcelEMey ru 'i;: AGGREGATE DRAINAGE CROSSING A TEMPORARY ACCESS CONTROL MEASURE (CM) TO CREATE A STABILIZED SURFACE ACCROSS A DRAINAGE SWALE. AGGREGATE SWALE CROSSING FLOW LINE TO MATCH UP -GRADIENT AND DOWN -GRADIENT SWALE ELEVATIONS AND NOT IMPEDE ROADSIDE SWALE FLOW. DESIGN AND INSTALLATION 1. STRIP 9" OF TOPSOIUSUBGRADE FROM SWALE AND STOCKPILE WITH DOWNGRADIENT CMs. SEGREGATE TOPSOIL FROM SUBGRADE. 2. INSTALL SEPARATION FABRIC ON EXPOSED SUBGRADE (BELOW AGGREGATE). 3. INSTALL 9" THICK ROCK AGGREGRATE (D50 = 6") IN A FIXED POSITION TO MATCH EXISTING SWALE GRADE. GENERALLY, AGGREGATE DRAINAGE CROSSING IS SELF -MAINTAINED. IF EXCESS SEDIMENT BUILDS UP, REMOVE FROM AGGREGATE AND DISPOSE OF PROPERLY. REMOVE AGGREGATE AND FABRIC FROM SWALE AND RESTORE SWALE TO PRE-EXISTING GRADE BY BACKFILLING WITH 4" OF STOCKPILED TOPSOIL FROM INTIAL EXCAVATION OF CROSSING. REV I DATE WBS 4 REVISION DESCRIPTION REV I DATE WBS 4 ROADWAY VL RIPRAP (6" D50), 9" THICK SEPARATI (I.E. MIRAFI 140N) REVISION DESCRIPTION 0 O PLAN VIEW NOT TO SCALE MAINTAIN SWAT F CROSS SECTION A -A' NOT TO SCALE REV I DATE 0.1 1 2023/04/07 WBS 4 A.0001671.003.001.002 IFP - PATHWAY SEG 1 AGGREGATE YARD SURFACING EXTENDS BEYOND LIMITS SHOWN 1nu.1li °!DE SLOPES AGGREGATE YARD SURFACING REVISION DESCRIPTION ISSUED BY ENGINEERING DEPT FOR: PERMITTING, NOT FOR CONSTRUCTION THIS MAP/DOCUMENT IS A TOOL TO ASSIST EMPLOYEES IN THE PERFORMANCE OF THEIR JOBS.YOUR PERSONAL SAFETY IS PROVIDED FOR BY USING SAFETY PRACTICES, PROCEDURES AND EQUIPMENT AS DESCRIBED IN THE SAFETY TRAINING PROGRAMS, MANUALS AND SPARS. PATHWAY SEGEMENT 1 DETAILS CERVIYARD Xcel Energy® SHEET 5 OF 5 SCALE S SHOWN REV 0.1 �a� Y a "Jf" I` u I ."' t :I�J /i A 1, _. - - -- ' . - ___ S L . p 1 _��. - �- COUNTY ROAD"I38, .:, " M1 • I. ' 4 _ _ •'!I♦. ♦ 1 f \r . I,n.. H I � � 1 _ �• 1 Z O lilt : - -3a_ O I ❑� 1 a r. QI ''' C®UNTY ROAD 36 wl 4 ♦ ryv � Y, .# 1 / []. IIII r _ Hr _ _ COUNTY ROAD_34 4 . CL RADO'S POWER PATHWAY I _ -. Legend ®Proposed Transmission Line Route Subject to 1041 Permit Application COUNTYROAD o /rT_ y hP Cervi Yard P :1 — ... . - - _______________ I -. y - - '- Boundary ` ! III - - _ - I . . -.E•r Vd (CDOT 2021, DOLA 2021, Weld County 2022) - -._'i'! r. - - I aS - a I - - ___ IW*_ I - Municipal-- . I - . . - — .______________ - 4 - I _:_a . - — — — — — — — -. .:- . . .T . It :Count- . . . - y . :1 . Transportation (CDOT 2021, BTS 2020) - . . . .. - .:---F -: - .. - - %` . Interstate __________________________________________________________________________________________________ -. .._ ._*..-# ._..I • .. . U.S. Highway LL -: l State Highway M M M ❑ ❑ Q/ Local Road 0 O LL �--� Railroad - . oI Existing Electric Infrastructure o ., `� ° O (HIFLD 2021) w a 69kV Transmission Line •�S• Y COUNTYIROAD 34 1. ..: - 115kV Transmission Line 85 p 230kV Transmission Line �. ti a Co ❑ 4 kV Transmission z �E 3 5Line O nificant Environmental/ Sensitive Factors ❑ 'I w rER �; ,-. � I,.,'yam if / -- / - id it I1II1111I^^I1I111 w - j❑ d =r. , �` l.-LJ• c� r- e J - ~STS PIaf elle ❑ II J Il E ❑1 li I;� _ q II,�, J i . I,,,.. . !!=- . • �f .A ' il 1, Je. i , 1 �\ .t_ I a i s N apltt/' J:1%t ❑ s.- z 1 `^5 � � `t ❑ E_ I I � K 4 COAUNI s 4 ,r� 9 IN Meadows Event Center � I.J —4 Pr as. `'.. COUNTY ROAD 30 ,f lll\ ,I \1 4 1 Lr� NTY ROAD 28 ` -.'%° (NWI 2020, NHD 2020, NLCD 2019, CSU 2020) - -` ;. t.l �. IIII I 1 ,1♦�A, , =� • 0 U _Ii i- _ Y, +J " Fort Vazquez NRHP Site IIII COUNTY ROAD 32 Conservation Easement °: 1 III - iir . . . F t dA - . ._.1I - }_ .. •• �IIJJY. J4 \1 a _ - 4!! . ::.. TT.. y T T ri is COUNTY ROAD 26 .I- 1� y , � e Vry s p m. ores a rea NWI Wetland Swamp/Marsh *No groundwater discharge areas, geologic hazards, or geologic areas of importance near proposed transmission line subject to 1041 permit application PRELIMINARY, SUBJECT TO CHANGE The information contained herein is believed to be accurate and suitable for limited internal uses only. Xcel Energy/Public Service Company of Colorado makes no warranty as to the .S TV accuracy or suitability of any information contained herein ' for use by third parties. The accuracy of this map and the information depicted should be verified prior to use. The user ___ -. - ___________ shall assume all risk and responsibility for any and all '- - damages, including consequential damages, which may arise from the user's reliance on this information. 0 0.5 1 Miles Greeley • • Existing Fort 34 L. . i5 V,r-ain S bstation 2 3 4 us 85 76 'Brigl�t� - ADAMS COUNTY DENVER COUNTY Revised: 6/22/2023 I NOT FOR CONSTRUCTION Path: \\cess706gisfsl\CES\Projects\DEN\1163_0039_C0_Pathway_Permits\GIS\Layouts\Permitting\Weld_Co11041\1041 _Pmt_Fig S' Significant Environmentally Sensitive Factors - Sheet: 1 Legend ® Proposed Transmission Line Route Subject to 1041 Permit Application Cervi Yard Boundary (CDOT 2021, DOLA 2021, Weld County 2022) Municipal County Transportation (CDOT 2021, BTS 2020) Interstate U.S. Highway State Highway Local Road I Railroad Existing Electric Infrastructure (HIFLD 2021) 69kV Transmission Line 115kV Transmission Line 230kV Transmission Line 345kV Transmission Line Significant Environmentally Sensitive Factors* (NWI 2020, NHD 2020, NLCD 2019, CSU 2020) Fort Vazquez NRHP Site Conservation Easement Forested Area COUNTY I NWI Wetland Swamp/Marsh *No groundwater discharge areas, geologic hazards, or geologic areas of importance near proposed transmission line subject to 1041 permit application PRELIMINARY, SUBJECT TO CHANGE The information contained herein is believed to be accurate and suitable for limited internal uses only. Xcel Energy/Public Service Company of Colorado makes no warranty as to the accuracy or suitability of any information contained herein for use by third parties. The accuracy of this map and the information depicted should be verified prior to use. The user shall assume all risk and responsibility for any and all damages, including consequential damages, which may arise from the user's reliance on this information. 0 0.5 1 Miles Greeley Existing Fort 34 1 us 85 �i�bstation Revised: 6/22/2023 1 NOT FOR CONSTRUCTION Path: \\cess706gisfsl\CES\Projects\DEN\1163_0039_CO_Pathway_Permits\GIS\Layouts\Permitting\Weld_Co11041\1041 _Pmt_Fig S' Significant Environmentally Sensitive Factors - Sheet: 2 Legend Proposed Transmission Line Route Subject to 1041 Permit Application r - \\ '\\ - - - - - - - - •� - r _ O - Y• - 11 Hi I r - %---------------- _i, -:- . ---- La T r -:r..3 --- --: , I -, ±_ - - • •//\ / - - I , I { I _ 1 [ .. . -. - III .1 . ___ E:.s .--! ! : •i - INFERS . _. -_.- - - - 76 I. r Ii j j A II .:t I r ya-ll- I' Ih, II I q I . t I � � sa Y - ll1 j,. / • // I �� oA , x r t, F , - _ i Y/ G.f Saar -,,�. I : I S... . � _ _ l � III � � ���{ F� ' -1 _ � ,,,. III I _ - I ,• , _ IiI _ c - 1-- : 4- 'H. -- - ....-. I' - H. Cervi Yard Boundary (CDOT 2021, DOLA 2021, Weld County 2022) Municipal County - - - - - - , Transportation (CDOT 2021, BTS 2020) Interstate U.S. Highway State Highway Local Road I Railroad Existing Electric Infrastructure (HIFLD 2021) 69kV Transmission Line 115kV Transmission Line 230kV Transmission Line 345kV Transmission Line Significant Environmentally Sensitive Factors* (NWI 2020, NHD 2020, NLCD 2019, CSU 2020) Fort Vazquez NRHP Site Conservation Easement Forested Area NWI Wetland Swamp/Marsh *No groundwater discharge areas, geologic hazards, or geologic areas of importance near proposed transmission line subject to 1041 permit application PRELIMINARY, SUBJECT TO CHANGE The information contained herein is believed to be accurate and suitable for limited internal uses only. Xcel Energy/Public Service Company of Colorado makes no warranty as to the accuracy or suitability of any information contained herein for use by third parties. The accuracy of this map and the information depicted should be verified prior to use. The user shall assume all risk and responsibility for any and all damages, including consequential damages, which may arise from the user's reliance on this information. 0 0.5 1 Miles Greeley G 1, Existing Fort 34 Revised: 6/22/2023 1 NOT FOR CONSTRUCTION Path: \\cess706gisfsl\CES\Projects\DEN\1163_0039_CO_Pathway_Permits\G[S\Layouts\Permitting\Weld_Co\1041\1041 _Pmt_Fig S' Significant Environmentally Sensitive Factors - Sheet: 3 nI Legend ® Proposed Transmission Line Route Subject to 1041 Permit Application Cervi Yard Boundary (CDOT 2021, DOLA 2021, Weld County 2022) Municipal County Transportation (CDOT 2021, BTS 2020) Interstate U.S. Highway State Highway Local Road �--�� Railroad Existing Electric Infrastructure (HIFLD 2021) 69kV Transmission Line 115kV Transmission Line 230kV Transmission Line 345kV Transmission Line Significant Environmentally Sensitive Factors* (NWI 2020, NHD 2020, NLCD 2019, CSU 2020) Fort Vazquez NRHP Site Conservation Easement 1W Forested Area I NWI Wetland Swamp/Marsh *No groundwater discharge areas, geologic hazards, or geologic areas of importance near proposed transmission line subject to 1041 permit application PRELIMINARY, SUBJECT TO CHANGE The information contained herein is believed to be accurate and suitable for limited internal uses only. Xcel Energy/Public Service Company of Colorado makes no warranty as to the accuracy or suitability of any information contained herein for use by third parties. The accuracy of this map and the information depicted should be verified prior to use. The user shall assume all risk and responsibility for any and all damages, including consequential damages, which may arise from the user's reliance on this information. 0 0.5 1 Miles Greeley Existing Fort rai�bstation 1 us 85 Brighton / WELD C 1' ADAMS COUNTY DENVER COUNTY Revised: 6/22/2023 1 NOT FOR CONSTRUCTION Path: \\cess706gisfsl\CES\Projects\DE N\1163_0039_CO_Pathway_Permits\G[S\Layouts\Permitting\Weld_Co\1041\1041 _Pmt_Fig s Significant Environmentally Sensitive Factors - Sheet: 4 Garden City Roggen k Legend Proposed Transmission Line Route Subject to 1041 Permit Application Cervi Yard Project Area (2mi Radius) Historic Site 6 KOP (Simulation) Jurisdiction (COMap 2019) CO State Land Board Boundary (CDOT 2021, DOLA 2021, Weld County 2022) Municipal County Transportation (CDOT 2021, BTS 2020) Interstate U.S. Highway State Highway Local Road Railroad Hydrology (NHD 2020, FEMA 2020) Stream/River Lake/Pond NAIP Imagery 2021 PRELIMINARY, SUBJECT TO CHANGE The information contained herein is believed to be accurate and suitable for limited internal uses only. Xcel Energy/Public Service Company of Colorado makes no warranty as to the accuracy or suitability of any information contained herein for use by third parties. The accuracy of this map and the information depicted should be verified prior to use. The user shall assume all risk and responsibility for any and all damages, including consequential damages, which may arise from the user's reliance on this information. Go 1.5 3 Miles Revised: 5/15/2023 1 NOT FOR CONSTRUCTION Path: \\cess706gisfsl\CES\Projects\DEN\1163_0039_CO_Pathway_Permits\GIS\Layouts\Permitting\Weld_Co\1041\WeldCo_1041_I KOP Resource Inventory SliVAl (S Sill _ IS 11181111:2re,1011wife]111:iNr111rllillY.i1[I111i1 p Illf:l[a[CICllll[IE.'i[N:A10L' r.1iDt1i1IIVA1II41Ut41iIi 111H11111W1.&YISIF (• N111 ttH.Ii1t141(.&Yt1II.1IllP: 1111 N11111.IN iIYAYflhi IiI51IIIiIi r.uoit: iIut11ut•1iI•1' Hilillilil Xcel Energy Greeley o;u I I —_ -I P H I S L -Is P — .Greeley q COUNTY LARIMER l ou ODUNTY WELD COUN Y- Fort Morgan ( ___ 1 85 I Akron • 34 ,r SEGMENT 1: I MORGAN COUNTY I •Wray.:. o I FORT ST VRAIN - CANAU CROSSING I WASHINGTON I NEBRASKA I 1 COaDNTY ---- ---- _ _a --J------- -._ KANSAS is ■■■ T YUMA COUNTY BrightonADAMSCOUNTY 0 ora o s ower a wa aproposed i i o n investment Existing Substation Broomfield ®`E-N`-VER-COUNTY SEGMENT 2. -� M I I CANAL CROSSING - GOO E CREEK I improvethe state's electric rid re Iona econom create obs 2 ' ' Denver New Substation Ito ARAPAHOE I I — ■ ■ ■ �y% COUNTY I I °s Littleton — _ I during construction and connect new energy resources in eastern olorado. • -I__ _________ � I I I ,JEFFERSON Substation Siting Area COUNTY(. I I KIT CARSON COUNTY Study Focus Castle I KIOWa LBERT COUNTY I Burlington / area area �� DON LAS Rock I SEGMENT 5: I 70 3s TUNDRA — Segment 1: { HARVEST MILE Hugo 4 Fort StVrain - Canal Crossing COUNTY I Ti -.i I ��' I I u s I • • - - Includes r xtelyit m nTELLER 24 o ,st se a isICOUNTY I . - Study Focus \ I ■ in-service eLIfour new an mi I COUNTY a--___ Cheye I Cripple Colorado• I 40 our *, � Segment 2: I Creek S fin S I SEGMENT 3: ex an e - w ou-circil] wit of erse ments Canal Crossing Goose Creek 1GOOSE CREEK _ j______aVALLEY 1rH t t� n345111111ll,,V tcompletei nStud Focussu saoso y 25 I KIOWA COUNTY area area fi - � E: FREMONT � �l I •Fads b■b■b■ n m I I n n 7 i COUNTY g I CROWL Y I MAYVALLEY—TUNDRA Goose Creek- May Valley I •LINTY �--- Study Focus CUSTER , Pueblo I y I I z area area COUNTY / Lamar' 50 Segment 4: I 78 PUEBLO COUNTY •LasAnimas La Junta May Valle - Tundra r t ) I PROWERS Y I I I COUNTY � BENT COUNTY I Study Focus �--- I I I MAY VALLEY — area area I j LONGHORN �„ �.� I �OTERO COUNTY I I I I EXTENSION Se ment5: �' I us g HUERFANO :_-�- 87c-- �j Tundra - Harvest MileVValsenbur l I Study Focus � j • area area I BACA COUNTY • , , LAS COUNTY ANIMAS I Springfield • COSTILLA �� r _�� I �6 �� TMa Valle - Lon horn 1 fr� Y Y g �✓ Extension I I l u 'ic ou rear o or uni ies March JuneSeptemberSubmit Permit Public Hearings Target in-service w'111continuethroug g ■ Applications date for Segment I CPCN Virtual project Vlrtual Jurisdictional public ener iza ion o a se men s i File land i application introduction routin & hearings associated Schedule Is subject to g filed with meetings siting update use permit with land use permit permit approvals ■ p andare shown as redcircles P applications to CPUC hosted by meetings applications g ■ • Xcel Energy local jurisdictions hosted by alo nthetimel'ine.for selected Xcel Energy routes and sites o........... o........... Se men s andare ' March ! � .......... ............. Fall anticipate tobe inissionservice Information .. Preferred Routing & siting Route & Target in- 9fl91 to g ■ open houses to Substation Public Meetings service date for Segment is anticipated j u r i s d i ct i o n s .. Target in-service receive feedback Locations Host additional w i t h i n stud - Segment 2, 3 and date for Segment 4 ■ y = on ossible nei hborhood or I S I 7A p I � _ •1 • A!1 1A -- I A - p Public meetings g Extension and 5 o e i n- s e ry i c e a n areas I cations f r = communit meetin s 0 0 to present the Y g . Schedule is sub ect to i - CPCN application transmission lines : referred route and as required by land use J Schedule is subject to p . ublicl available and substations ermits permit approvals permit approvals e men s an i n substation locations p p y [:j.j all IITU Iii i4J 1:] 11:) J 1 [:1.1.1 d Es iTJ:4:1 ii 1:1 11:1J k New transmission lines encourage and Turbines support thdevelopment of renewable Plant ... energy tbring more ow -cos electricity Short- erm and tohelmeet needs of our rowin ioji £ roj o0{4 6. jfoj£ aj6ojro�{.b. $ d� o. d o r>�< ". o' .. ro Generator state POSITIVE positivet Step Uplong-term o b ��oo }{o%{p'��ry ox { i is{..oxx.'o � c - Substation economic impact Bulk } } `£ Transmission a o onon Colorado's PowerBulk Substation Pathway supports od•ro 40�� Transmission £o£ EnergysCleanEnergythatW'11iadd / .o'xjo$w,£o jw$jo gf f f }ro f£ f{{f Fi jo {}o£}o£}o£}o£} }zoo approximate 5,000megawatts of new INCREASED TAJCf ewtemporaryanRE�E��Ewind solar and other resources rough Distribution permanenjo s 2030 o ena e e s a es ransi ion to Load Serving Substation ease revenue an Transmission Transmission {{. clean ener 0 6 bo {mom'{ u x x £ x gy zw5, o � �� • a12o jo. t. increasetax revenue tot. }%.oYo . o tro bo j.jro jo j U Existing transmission on the eastern plains primarily serves local needs and is Increase rel'iability � nearly "full" and additional transmission of the electric grid capacit is ded to inte rate more Distribution y neegfor all users and Lines renewable generation availability for new renewable energy projects Colorado's Power Pathway provides high voltage "backbone" transmission How 11 '.rn more aPathway Approval Process.? March 2021: Application filed with Colorado Public Utilities Commission (CPUC) � � - - � � � - � � � • If approved, the CPUC will issue a Certificate of Public Convenience and Necessity, certifying the need for the proposed facilities. View Xcel Energy's application at PUC.Colorado.Gov, navigate to EIIIIIIIIiFilings and enter the Proceeding No. in the Search field. C] LU R O D trFWY I FALL 2021 I xcelenergy.com � O0 20 COU.NTY-------_---- PH'I L -L" IP Greele Gill I L O G AYN-C . y. Greeley I f" COUNT Y LARIMER BOULDER What aretransm fission substations?COUNTYI WELD GoUNTY Fort I ■■� 76 Morga I I I 85 I Akron• 34 SEGMENT 1:i MORGAN COUNTY I Wray I FORT ST VRAIN - CANAL CROSSING I NEBRASKA ------_----------_----------- - --� C YUMA COUNTY KANSAS �` 'Brighton I ADAMS COUNTY a 'Broomfield F7vETR-COUNTY SEGMENT 2: I CANAL CROSSING - GOO E CREEK Step�upor step =Denver Jnc u e e ec rlca r 41 1 ■ ■ COUNTY I I 1! down volta e s approximately e ul men JEFFERSON r COUNTYt.r between theto acres Kiowa IKICOUNT ONenc oseI Burhngtan Casf/e I ALBERT rOUNTY I IN SERVICE 2025 • Rock I �� DOUGLAS I SEGMENT 5: I �- COUNTY I transmissionlinessecurityI TUNDRA- I j I r HARVESTMILE I LE • Hugo PARK :OUNTY I I I -�� PawneeExpansion TELLER I 24 COUNTY I I I I•TiI6 II - N ■ I ! I LINCOLN C NNE EL PASO COUNTY UNTY Canal New COUNTY Cheyenne Wells. � Cripple Colorado I 4o SEGMENT 3: e exls In su s a Ions wl e ex an e o accommo a e e new Creek Springs I � I I GOOSE CREED oose ree New 1 I MAY VA transmission l'ines and associated equipment needed operate I ------ K I O W A C O U N T ■ FREMONT - ay New r COUNTY I I SEGMENT 4: the nes . ' C• LEY MAYVALLEY-TUNDRA COUNTY I Longhorn New CUSTER Pue o I Ordway • I COUNTY I 'L - I I LaI I I I i i mar• 50 I N SE RV I CE 2026 7$ PUEBLO COUNTY I •LasAnimasI C I La JD it I I PS P I ■ ■ I I BENT COUNTY COUNTY I Fort rain Expansion --- MAY VALLEY - I LONGHORN I OTERO COUNTY EXTENSION j TRANSMISSION i HUERFANO I I s I N S E RV I C E 2027 ■ ■ _L.- $--��'�j---- SUBSTATION X35-----------J--------�-� --- � Walsenburg �I I Connectionpointsfortwo or . TRANSMISSION BACACOUNTY • ' • TundraExpansion LINES �OSTILLA LAS ACOUNTY ANIMAS .Springfield more ransmission Ines COUNTYy� �r ■ •' e Expansion Harvest Study Focus Study Focus area area area area 0 Existing Substation Segment 1: Fort StVrain - Canal Crossing Segment 4: May Valley - Tundra ® New Substation Segment 2: Canal Crossing - Goose Creek — Segment 5: Tundra - Harvest Mile TRANSMISSION , Substation Siting Area Segment 3: Goose Creek — May Valley May Valley - Longhorn Extension LINES *0 * 0 0 0 A 1 - r I / - - - -. - .. - 0 0 0 a I 1 I � x •r � � / I I .I � I _LLLj. _ 1___ __ . - __ = _________ I I -' p • "nP� - /� , 11l1 # } ■L�� I ' r - •• ♦ } t / 4. J L Ot phil! M r��_�.� 1 l � � � I� I w _ • 11 �1_Il ZYI_ y • v ' n n V - . I 1 . .�fi '�I���••-lii �11j1 1 I� _ _ 4 a �r _ YIJ. :•ate .- � �� ®i . . . • � Jib. T --�---T rT _ �„ � 'T u . FALL 2021 xcelenergy■com 0 2021 Xcel Energy Inc■ Xcel Energy Is a registered trademark of Xcel Energy Inc■ iii [.] Di::i [ I I 1O11 10 roiiiil [ mu tiii it ill.]iKlfli KBI [0] iI311U[NO I i Wi i :1 i I iI1 ftl 011] rn 11ff013:3IIIINu11 I I.1 Ii ii1rnuauuiu i ii II1 11010] FWi I I I �i 'iii I I01 iitciei 0111 iiimi UI IV4 01 i'ia I 0101 fticl 1 i10 E IIJ*. A ,4 oiii 0IlAT' I 10111 iIi A Gill ri LOIOFYiVi r [I 1 I!] ll-'i!Ol RYAY I Kill iti iii; LV4 01 III1 lffll*111 K]iIII I 10] !Jfll I iiiI 0I1IViVLIil1 111 iBifil KBI [Oil I3ftl[IlU I 1I • Weathering steel or galvanized grey color Ii11F:T1111F:f1[.]1 liii:: :1ld![.kQIi:I: II a� a� M . . Y Voltage Terrain 4 —+ STRUCTURE Sag of the conductor Length of span between transmission structures 000.00000 00000000 0`0`0000 / Structure type Minimum clearance prescribed ROW (150 feet) by the National Electric Safety Code C] V"HAX"tl "POT H W Y I FALL 2021 I xcelenergy.com O0 20 A YAT I A :prj1d:}: lii: IiL(:]d:1:4 Sill, .I!I:t(.iiii:]E: iii.: si.jlIilI[!lg1Ll[:]-: YAYL: j]'&Y1 p 1i Ii: :]u4YAI.]I1ij:]Il. ]ulihvl: ilt!I1 i • • • • • • • • • :1!I4l[.]: • •Iii:i: • 1111111111 14: • • (:111F;] 22161W • nrt� R JM1J 'y i �',.� ��r MaF• a. �i � P♦ 1. T'w l _ l r- `*ti r;- - s aiY i 1i y. vi •7fµ1:It�1 1 1s ._p - f t i'. t ,� tn! L �i 4���� �' a '14 ? �,�, tr�.. r� • r+ ,!ter , ., e ' 11 � ✓ + 1•R �y ' .Y. + F. _ r a�w ^, -�• - it 1. 1/- r\ 1 r 1 a .- -. Jr �.. 1 •ra J V ti } _ i y �r4 ?a C +�Z 1 A u .J. •' ���• a `''1 �.� . �f la k Ij�e �.._a�`1i �`,R •*h, fY1. ��4^.I ` t \ �. ' r •ir 1 _ a 1� '.`\ \i 1 IA1 ', 1 .� , 'r `.. I^ a �r� 9 M I `'E nil•- n i.•t a n - • .J' 1 - I fl r'� ,. 1,�'- . J ' 1!'�'r � �" I lE \'4'H� l {+x.�i�. . `� l''� r�` I � � � I`'• /�/�, i I � `I� •'�1/ ,,Llr.�• ;..._ • ' • - '.. f` •. ' • V r f r )1 VII \Q�b�• 1• /J l , r o- t _�• v.r .,: 'r �_ ..� ?'./ •. .. ,`+.. �a.- - A„- -F '.r !ii ]1 �f !I r �. 1 �� Y • !. 1 �( f te r. „_ a ,k T �i�• "ti 1: , _' rJ �:�E � i n -�'. a� Wi -.� � " i t _EX. as i3 f.-,.�#a �\\ � •♦ �. I;�It t• 1 "�a�u r � n n enc oor ins 'ion n Wetl a sa Birsn U . a e r rce ea or om Iance a e esous 1• 0!! • 1 11 i.V0000'''' '1 0.0' 1 111- •1 • • •11.1 • 1 11 11 •''*yy 11 •1• V 1 • 00* * 1 0.0 • 1 • 1 1'1 11 1 '1 • • ' 0.00 1 111 '1 1 1 1 000 1 ••*• .00 0.0 1 . 1 '. . 1 . 1 1• 1 1 . '1 .0 •1 • '• 00 • 1 • 1 • 1 •'• 0*.00*00 0.0 • • 1 1 1 0.0 11 1 0..O • 1 1 00* 1' *00 1 00*00 t ` ' 000*0 1 1 0*0.0 1' 11 1 •• 1• 1 • 1 •1 1• 1 1 1 •` 1 1' 0 0 *. .0 • 0 0 0 0 0 0* 0 * •* * .0 • 0 * 1• 1 • 1 '• 0*o00*00 • 1• 1 1'1 1 00.00 '1 1 1 I. 1 ',•*•• 1 1 . X1.1 *A.** 1 1 1 1 • 11 000 1 • 1 1' . . . 1 1. 1 *000 11 1 • 1 11 1 • 1 • 1 I • 0 0* *0. • *0 0 * * 1• • 1 • i 1 1 1 1• 1• C 0 L.. 0 R A D 0 , S P 0 W E R PATHWAY I FALL 2021 I xcelenergy.com I OO 2021 Xcel Energy Inc. I Xcel Energy is a registered trademark of Xcel Energy Inc. 4(1111 1_ '0- -- ■ us I J Weldona 6 Snyde 1 04 Eads � Log ane - - 0 e e - _ _ Brando1 Sheridan Lake 11 e a - Haswell I � 0 oc KIT CARSON • Chivington 76 �- Fort Morgan I J m ___ � Akron 0W C Platner Otis 34 I Yuma Eckley I � Lair lb I • • �■ ■ ■■■■ P1■■i■■ I Wray KIOWA US ... �...■ 287 55h1uu1 ��� •� ; _ MORGANLIETiF.Ft% - ■I!■1 ■1 YUMA Arapahoe I �1eY I ■�■■■■11■ e - Bristol Hartman Fu1!JIIii1 11 ■■ U s Wild Horse U S /S® McClave Hastyark Granada Holly La t ChanceLindon ■■■ Idalia Kit Carson 1Iu11I 1 I � ■ ■ 36 ii ■■�■ Joes Hale U S N I 287 tl9 � o z ■111 11..■ ■■■■�■• Kirk P R O W E R S WASHINGT ■ ■ o --_-- ---- CHEYENNE o z __- n ■�■■� ■■I KIT A R N o �1■�• C S O o � �!1� o z ] 1 Agate l� K I O W A I `4 P 385 ■� � Toonerville Peconic Towner e na Stratton BurlingEads e Arriba Flagler =70Sheridan Lake Genoa —� ■ �� Chivington L�m I 1■ ■ � — Lycan s I I. ___ . 11.. ■ � � 24 I ■i BACA 11._.1 ■ III ■■ -Deora Two Theson I Hugo ■ _Milo 11I - I UI• • • - - 1■1 ■ ■ - • 287 Existing Substation us 40 [r �� U5 — I ® New Substation • _ Boyero 385 Springfield Segment 2 Focus Area C H E Y E N IN E Segment 3 Focus Area Extension Focus Area • us 160 _ Walsh L__., Substation Siting Area CheyenneSt ' Substation Siting Area Substation Siting Area Vilas _ r F4ro ya Wild Horse Wells, Arapahoe r P R O W E R S - [c1v4I [CThAI TAv 'V YJA cl.I.}:] I I 1 11 I 1 1 I 1 11 11 '' 1 I 1 11 1 11 1iiiIi i miii!] liI *t ta i.i i iii 00 0 00 0 •.i 000 0 OS .0 0 0 00 S 0 am 5 • Ia *, Am S * 1aa • • * 0 S I 0 0 0 5 • 0. 0 0*0 a 5 * I mm 0 0 a A a • • 1 • I '• 1 i 1• 'I 0 1 •,a 1 I' 05 0000 I 1 t' it .5 050 1 •1 a a 1. ••a 0 50 • 05 • a, 5 * 5 ala O •a a, a �� � � � �' S P D W E R PDT H WDV I FALL 2021 I xcelenergy.com � OO 2021 Xcel Energy Inc. � Xcel Energy is a registered trademark o' I.-. • 0- Ac4jIJI ellin on Nunn` I •KiVon Keota Elizabeth Peconic Bennett owa a Stratton Sfrasburc Burl►ng ton s Watkins s Last Genoa Arriba Flagler Seibert Chance 70 • 40 a Byer Peoria Pierce - b Limon I Elbert , I Briggsdale Buckingham Raymer A R A P A H O Matheson e Ault Stoneham I Hugo I -=1 i Deer Trail _ L_ g s u s Foxfi'eld I _ I L►ttl t n Ramah r 285 �Centennia 11a I 385 f us 1 1 -- u s I Tim ath Severance Eaton Galeton — Calhan Peyton � 8 rJ Lone parker ICornish Castle Tree Lucerne I I WELD I M O R G A N Pines Agafe Windsor I Boyero � s Gill 40 Sedalia(( Falcon Arapahoe Frankto n Gree/e i Ellicott Yoder kRu shc Wild Horse Elizabeth it = E L B E R T I �I Cheyenne Wells � K►o Castle 70 Kersey us I Kit I Rock I - Karval Carson I I Genoa nstown • 34 I Goodrich Weldona E L PASO 25 • I - Snyder Limon Masters I Log Lane EMER:1 Larkspur Elbert / Village u s I LINCOLN I� Matheson I p DOUG AS Gilcrest • I - Simla Brush " L d Westcreek L _ Hugo ad Fort Morgan _ Wigwam Eads '" T ��� Wiggins • Brando ' Monument Sheridan I Haswell Chivin Lake I s Calhan I Peyton s Black Forest 24 I h 85 ( 25 L I Wodland Park • p Arlington u s '■■ 25 Firestone C R O L E Y I I 24 Divide if Falcon I i II Keenesburg Boone rII —' ^T i Ordway Dacono I Crowle y Sugar C Lupton Hudson Ilueblo y gMidland Manif Springs -- P Wattenberg _ Bristol Hartman �/ Ellicott Yoder � Hoyt us Lochbuie I Chera►nI CO�Orad Fowler I • 50 Granada E L PAS O Woodrow Lamar • PUEBLO Las Animas /ngS Caddoa Karval Roc Ford' Crlp�Ie Creek. � Securit Br► hton PROWERS y victor j 1 Goldfield Cedarwood ' a Junta Henderson L I Fountain r L L 25 - 14111 r Timpas 1 I Wigwam J L ` J 350 I Toonerville 28IS 7 • Existing Substation I r PU BLO Bennett Deora Stone City Watkins u s Ninaview � � �ycan - I I Denver us Strasburg ' T 40 ® New Substation 36 • Existing Substation Two Buttes Byers Segment 1 Focus Area Segment 4 Focus Area • Existing Substation 3 25 70 j1Ik"t U5 , Substation Siting 2Area Segment 5 Focus Area • 5 .� 8 I ulio . Littleton Springfield® Pueblo Boone i SEGMENT SEGMENW4 ■ ■ 1 w w •ILHTi:w'A•:, V. 'AII Endpoints: Fort St Vrain Substation, Endpoints: May Valley Substation, Endpoints: Tundra Substation, Canal Crossing Substation Tundra Substation Harvest Mile Substation In Service: 2026 In Service: 2027 In Service: 2027 Major routing and siting considerations: Major routing and siting considerations: Major routing and siting considerations: • End points are fixed at Fort St. Vrain and � End point fixed at Tundra substation End points are fixed at Tundra and Harvest Mile Pawnee/Canal Crossing • Formally designated and/or protected state • U.S. Army Pueblo Chemical Depot • Platte River to the north and federal land • Black Forest • Must cross I-76 • Queens State Wildlife Area • Buckley and Schriever Space Force bases • Dense development to west and oil & gas U.S. Army Pueblo Chemical Depot USAFA Bullseye Airfield & training areas throughout most of study area • Transportation Technology Center • Existing wind facilities • Existing electric and gas lines • Lesser prairie�chicken habitat • Existing & planned residential • Conservation easements • Stewardship Trust land • Stewardship Trust land C] LU R O D U"POT H W Y- I FALL 2021 I xcelenergy.com � OO 20 STUDY AREAS � Np . • SUITABILITY ANALYSIS r �' "! {• ......•... ". : - • �- �G 20 -miles -wide, developed based on segment end points (Substation A and Substation B) t. x • :.- •l.•:I 'I,. :- ' •J•...; PRELIMINARY LINKS : . *1 . I Collect data on resources within and adjacent to study areas, categorize based on compatibility with development of transmission line or substation N FOCUS AREAS �`"A Based on su'tability analysis, identify links that provide routing options between segment end points that � minimize crossing of constrained areas and maximize use of more compatible locations I L 0 A ___ _EEEEEEE. II Smaller area within each segment study area where links have been identified, � o � within which the preferred route is anticipated to be located I^I . ��n REVISE LINKS & IDENTIFY PREFERRED ROUTE Areas with constraints or that are less suitable for transmission line development are removed from further consideration • I. -.,F - - - _-.. __ __ __ Preliminary links are revised (removed, added, modified) based on public and stakeholder review and input Comparative analysis to identify links to be removed from further consideration, evaluate end -to -end routes Select preferred route MAGNET 1 C F 1 E L D S 7 Xcel Energyo AND NOISE MAGNETIC FIELDS Typical magnetic fields six inches from The chart below provides typical noise AUDIBLE NOISE common home appliances measured levels encountered in common settings in milliGauss (mG) are depicted in the Imeasured in decibels [dB(a)] Edge of ROW Edge of ROW chart below. z5' from Edge of 25'from ROW ROW Edge of ROW ROW 450 Magnetic i i BOO%C2p2CIIY � I I I Limi�I=50 dBA 40o Vacuum Audible Noise (Rain) i il�l� Pneumatic � � � (25'eet'r°m Cleaner E°97 �°`R°`", 350 � I � chipper 300 300 120-130 c� i I It PUC limit g m 250 i 'i-........ at edge ' ' ' d i Magnetic i 50%Ca acit iMof ROW Loudaudiblehorn � i i Audible Noise D Iii c i a v i ICfOWaVe � I (11 mile away►3°zoai i 150 Limit=150mG 770-720 ¢ i Magnetic i 20 i I I I 25% Capacity __ i __... _... i i i 100 -� � Machine Inside motorbus 10 r 80-90 °-1zs -7s -zs 0 25 75 ° -125 -75 -25 0 25 75 Distance from Centerline (feet) - - Distance from Centerline (feet) Garbage Disposal _a_ � � �... Average traffic PUC limit i i on street depending I on zoning %0-80 50-75 MAGNETIC FIELDS, measured in Hair Dryer I dB�a) Q Q Conversation CORONA is a phenomenon milliGauss (mG�, are produced by electric � .Z 60-'o associated with all transmission lines. current and only exist when an electric i Corona is a small electrical discharge, appliance is turned on the higher the current, Blender � Living room not unlike the static electrical charge the greater the magnetic field. As with � � 4o -so that a person may experience when electric fields, the strength of a magnetic field Fluorescent i touching a metal object when walking Library ambient dissipates rapidly as you move away from its L'Ight � noise on carpet. Corona is what creates the source. = 30-40 hissing or crackling sound that often Dishwasher Broadcasting emanates from transmission lines. The power line serving your neighborhood � 1�1 studio Corona increases substantially in wet produces EMF just like household appliances '0-2o weather, when water droplets form on such as your toaster, hair dryer, lamps and Computer ri Threshold of a transmission line which increase the washing machine. Business equipment, such as � hearing corona (and increase audible noise. computers, copiers and fluorescent lights, also o-�o produce EMF A V a a a a a a aa a a a a a a a a a a a Y A! a a ' ', 1 . 11 1.1 . 1 . 1 a, ' ' , 000. ' a,,' •* .0 ' 1 1 . 1' 000* 0 1 11' . 1 . 1 . . 1 . 1 1.1 . 1 1 1 u u u fl tit •i r 'L r •% Sr� • '� • za*'. ry.r {� 11 Y 11.♦'}�Y ,,y �.�f ..:i• yi '" �.pis rr_',-.f i •.♦XLea.-- l-y,G• r-!::7..LY- f,_ r�.J :. U-' ,.I1�a..•.r. .. J. 1 ..n �r.. .. � J J ..1 .. i.. L.. .. r sti v: ... .i r. .. ... ,.r.. 1.L.. '.n r • y.'.' .y . asi , ,� a , Jr :. n � 1 t ': rt / l �1. :h...f A � fr ':r f rl. � _. n.,a If •. Ti i. +:� `' i.J t 1' .!. {rl r ! .. ..- 4 i r..9� .` Y. '-e. ..: i' i rSti. • 1 e � ... ..- 1 ;..a � nti J) r r ': �. r ..� l_ A ;.'.. i.. r. ' 'r '.r v. •r { r r •�F ..r - r ,• z . il.f • t . I .. ?: '.'r " .. n r. i G ?. . a •y �I. a �. _l ♦ I'.. • r VAx.Id [.PIIQIi: Yf:io [1lI [•] I IA El I1IJ [:] j[:] ii :1!II[.IIj [:±711uI d! [.T1QIi:1 t 00 a . a aa 00 Ia... a a. t' . .. . t . t 0000 ••, '1 . t t •a, . . 1.. .0 t 00 t I 1 . '. t . 1 a1 t C '. t ,a,, t so .s Sa . ,a, . '. '. . . 1 t .00 . t 1 a a aa a . . is I ,a aa,a, a •a • 5, • I a .11 . X11 1' raa.rur. 'a aa yaa,y 0.'.' • . •,a, a, . . . , 5, a a 00 00 •a, a,, a a,a,a a ai I 00. 0500 . a a a 5 a • • I a,a so ,a •nn.l , a C O L O RA Q O, � � O W E R PATHWAY I FALL 202'�� I xcelenergy.com � O0 2021 Xcel Energy Inc. Xcel Energy is a registered trademark o Xcel Energy In� Keota " S Nunn Fi ellin on Weldona 6 Snyde I 04 Log Lane ' _ _ • • - - - Village Pierce I Q • - Briggsdale Buckingham Raymer I 76 • C oc Morga KIT CARSON Stoneham Fort J m Ault C W - , •Ak us _ - _- Plainer 34 Eckley Z 10 ; . �I Yuma I Otis■ 1 3� 1� Lair ■�� Tim ath Severance \Eat::Galeton — Cornish • • ■ ■■■■■ NNEi 4 I• Wray Windsor Lucerne WELD I M O R G A NHPiL� ■■�■ Il__ - - Gill us M O R a N .. ■■■ 385 Greeley I 1�IL■■i' iii YU MA N .......11. 11 Kersey u I 6 �■ � ai111U115 g Arapahoe Jo nstown 34 I I3 Goodrich Weldona 11 1 1' is Snyder ■ ■ u s Wild Horse 5 -• Masters � 385 40 Log Lane f us ■ ■ ` 41- U S Lind 1 ■1 111 1 ■ Idalia Kit Carso ■ Gilcrest La t Chance 36 Ant ■■ 1 ■e! Cl) • Brush i ad u s ��� Wiggins Fort Morgan , ■�.�u - Co 36 ■ Joes !IIiJJp. Kirk Hale 1 i us 1 7s 2 WASHI 85 --- HE ENNE 12 25 Fire one ■■� KIT ARSON Q Keenesburg �� '� � Dacono Agate I K I W A ■ . j1� Z Lupton Wattenberg I 385 Lochbuie Hoyt 1O Cl) — Woodrow O • Peconic Towner Brighton/ Stratton, Burlington Eads 13 9► Seibert Vona • Arriba lagler 70 Sheri Lake Genoa �i Henderson Chivington L I Limon I 9 g II.1Iik!!11' I I I I IIII o 70 I- J L —� • Existing Substation IIIii • • Existing Substation ' - us - .L0 Bennett New Substation Denvc' us Watkins Strasburg "S New Substation 40 • 40 36 Segment 3 Focus Area Segment 2 Focus Area `u us • - Byers Segment 1 Focus Area Boyero ICHEYE 38525 70 ,Substation Siting Area Substation Siting Area Sheet Map Extent 285 _ Sheet Map Extent Ch eyenne Che enne Sheet Map Extent Wells Arapahoe P R 0 W E R S Aroya Wild Horse ` . L a9�i 1 SEGMENT 1: 1 SEGMENT 2: 1 EGMENT 3: :1 yA;yA1I C[.I.I] I I Elizabeth Kio wa I Peconic -� Watkins Bennett s I Burlin ton , I S r Strasburg Flagler Seibert Vona Stratton g Last KIOWA 36 Chance Genoa Arriba 70 �u s e , J 40 Byer Peoria • Eads 13 Elbert 1Limon � � � I Brand Sheri n Lake 25 ARAPAH Matheson Hugo u s • Dee rail I Haswell Chivington I I ____ ____ j _ 285 L►ftlett 2 Simi la I 385 Centennia Fox Id r1 us 24 ._ -- -- — s I - - Pe ton Calhan I I - — y 85 Lone ker . _ Castle Tree o ero I BPines y 4� Sedalia K I O W A us 287 Falcon I Arapahoe � � - Frankto n Ellicott Yoder Rush Wild Horse Cheyenne Wells • I zabeth KIO ELBER f 22 Castle 20 70 us I Kit / Rock I I 385 Karval ' Carson I I Genoa E L PASO 25 ,�,;, Limon _ I LINCOLN - Larkspur us McClave u -- I ,� I � Matheson 50 Hasty � D O U G A S L ar Granada u s Holly W<gw .� L Wes tcreek L o ,h l I ug0 14 @ T 19 15 — Monument 23 cn �� Sh idan 16 �,r e.La I Peyto u s Calhan Black Forest I N W odland Park 24 I Z 25 I P OWERS r a CROWLEY Q Arlington u s t '■� 13Divide Falcon I 24 Boone - -� - i 18 ueblo Ordway �1 I I Crowley • Sugar Ci� I I I J Mamt Springs I JI Hartman Midland Ellicott Yoder Bristol Colorad i;c;r::i;;rn.P- _ Cheraw I_24 �amar• 50 Granada I I PUEBLO • Las Animas ` SP �ngs Rocky Ford Caddoa Cripple Creek. Security Karval I P ROWERSToonerville • I Victor Cedarwood La Junta I — 1 — Goldfield I 1 Fountain L- �• 25 _ r Lycan Timpas s I Wigwa A �. 25 u s Toonerville I Deora 350 I V 287 ....� • Existing Substation P U B 0 Ninaview _J_ __ Lycan Stone City 16 I I u s Segment 4 Focus Area — — = _- T'• Existing Substation Deora 287 _ Two Buttes Segment 5 Focus Area Extension Focus Area Substation Siting Area Substation Siting Area Sheet Map Extent I Sheet Map Extent • - I field Sheet Map Extent •Spsrin g Springfield • j5 ' Pueblo _ „ Boone 160 Pritchett Vlas Walsh SEGMENT 4 _ 1 SEGMENT 5: 1 MAY "hL.L VIA! 1Ujm];yA _______ C] LU R O D U" � P U W E R POT H W O Y I FALL 2021 I xcelenergy.com � D 20 SliVAl (S Sill _ IS 11011 II F hR _ ::oliiliilflul - 1(KIIiiUIt11I its] 11 11 rIl i I IY.1 I [Il11 ill p Illf:l[a[CICllll[IE.'i[N:A10L' r.1iDt1i1IIVA1II41Ut41iIi 111H11111W1.&YISIF (• N111 ttH.Ii1t141(.&Yt1II.1IllP: 1111 N11111.IN iIYAYflhi IiI51IIIiIi r.uoit: iIut11ut•1iI•1' Hilillilil ey vv e L D • AboutMap '�"`� �i ^ l �m FoMo,4a�, � r �r 0U DtRSegment 1: Wray. Colorado's Power Pathway is a proposed $1.7 to $2 billion investment #1's' #' Fort St.Vrain- Existing Substation .y' Canal Crossing to improve the state's electric grid, boost the regional economy, create .._N Segment 2: jobs during construction and connect new energy resources in eastern New SubstationARAFAHOE CanalCrossing- COlOfadO. :......, � Goose Creek Substation Siting Area ;w ii I I ca;ueA0 LBERT I IL. • Burlington Focus Area DOUGLAS \ Lima. � J i / Routing/links TELLER Monument t Segment 5: Includes Approx�rnately First segments o � Tundra Segment 1: Goose Cree Harvest M'Ile four new and 56050 mi in-servicby 2025 � Fort StUrain-Canal Crossing four expanded �w dou1circuit \ with other segments o ColoradojkXV Segment3 1111 substations ,'% 345�lrOVO1tcomplete inse9mentz:Goose CreekMay Valley Canal Crossing Goose Creek EL PASOrt smissines r 2026 and 2027 O• Segment 4: sn '"f / T Se ment3: k May Valley —Tundra CUSTER Segment 4: - ,ama,� May Valley - Tundra PUEBLO Las Animas I I ... . � OT"'`", Extension: Segment 5: May Valley - Longhorn Tundra - Harvest Mile (optional) waiseneu,g. Segment 5: Area Undergoing Evaluation LAS -�-- - Tio Springfield.Springfield.meline Extension: May Valley- Longhorn Public outreach opportunities w'111 continue through � March O Submit Permit Public Near�n s June � September � � - - y � Target in-service Applications date for Segment I ener ization of all se menu CPCN Jurisdictional public g g Virtual project Virtual File land � hearin s associated � Schedule is subect to and are shown as red circles application introduction routing & g � l filed with meetings siting update use permit with land use permit permit approvals along the t'imel'ine. CPUC hosted by meetings applications to applications Xcel Energy hosted by local jurisdictions Xcel Energy for selected routes and sites I,. � � - • • • • Segments 2, 3 and 6 are o.......•..o..•........ anticipated to be in-service by 2025, Segment 1 is March Fall ` 1 — Information Preferred anticipated to be in-service by mailed to Routing & siting Route & Target in - open houses to Substation Public Meetings service date for jurisdictions = Target in-service 2026 and Se m e n is 4 and 5 receive feedback : Locations Host additionalSegmentdate for Se ment 4 g within study 2, 3 and on possible Public meetings neighborhood or � Extension* g areas � g O O and 5 in 2027. locations for to present the � community meetings CPCN application transmission lines preferred route and as required by land use Schedule is subject to Schedule is subject to publicly available and substations �� substation locations � permits � permit approvals � permit approvals O O O * Extension timing will be finalized based on the outcome of the CPCN determination by the PUC. ALURODU"� FPUWER W Y I WINTER 2022 I xcelenergy.com�O020 E:.] F.] ;I [.: .ViY1:] r jj i1'iTtV Ii] IJ.] I j: �i1ID [1(I 1i(DL! [SI Es] I I • 1Y IMI TATAI1E']i iI !IIlftI[:}:: i:IL!IIi:Th 'I.]ii1]LT AAiIi. :f:i.i;iu [:;. ;I : 5] I t1 I:I iii [f] Es] I :IYJ:41:1 ii 'I1 d [:1: :1 [:Is [•] Y [ ] I' 1Y iii! I Iii I [: ! ii II I [: [I I1 11:41 I ! i(:Th (5 Ii.] �i:I: I ! 1:] I :ff:I: 1Y [sIsI] I.VAYL:] r •.] all ii Ii [:}: I• I I :1 [:fl L!kIIliIE:I: ;lmIs :][:1.ThuIdE.]hT !1I:]i: 1s1!Im1.. Iii: :4Tl(: •i:11i:iji li.]il liii: Turbines _____ / lectric System Benefits Plant a as"aa as da o aa'aa os oa p >b.a.A Qb' oa o , Generator New transmission lines encourage Existing transmission on the eastern °Uy0 O O a Step Up an su or e eve o men o ains rimar� serves oca nee s „ Substation Bulk renewable energy to bring more and is near "full" and additional Transmission oh S°k�SOF S4Y {c �S'$5TTf°}T°T. ry. c4r oST�� �rynw �� w o }T4.aQo( o} 06� >{oJo{o�J o ° Bulk Substation 000. 00�0��q ow -cos electricity helpmeettransmission ca aci is nee e Transmission needs of our growing state. tto integrate more renewable generation Distribution Colorado's Power Path s u p ports Colorado's Power Path Load Serving Substation Transmission XcelClean Energy Plan high voltage "backbone 0 gr'id supported }L o.f. pro {6} kxi•"j0.2 that w'111add approximately A me awa s o new win , soar a n ac one ra nsm fission is e er other resources through 2030 to positioned to Wiwithstand outa es. enable the state's transition to clean energy Distribution Lines •] ill iii! I 1 i5J 1] I1:I V 110] i iii- i.i• iii or. H e _ - ill 0Is 1V1 ii. oxi ioi •i a — iIi oiHi—.i - Ii - reislo is _ I5IOl1S1l11L5uIli10M51 iiisicx� ,Ii[�- isi ;iI -1l1�.;v1IM0]III 10]i rx = cwi iii r -ci irwii •i - i ci'- oioi txsi ALURODU"� PIPUWER W Y I WINTER 2022 I xcelenergy.com�OO20 VAI mu [.1 i .11.21. Di:j:i ! I • Steel double -circuit transmission structure SHIELD WIRE • Single pole for most structures, two poles for certain high -loading structures • Each pole will be on a concrete foundation \\\\\ • Typical poles range 105 to 140 feet above ground • 150 -foot -wide Right -of -Way N 'El flU ;y / INSULATOR • Typical span length of 950 feet between transmission structures n. '• • Weathering steel or galvanized grey color CONDUCTOR � ;. ., Transmission line structures vary in height \ ;:� .. ; dependin g on: / Voltage Terrain 1/ __ __ __ __ ___ __ ___ STRUCTURE Sag of the conductor Length of span between transmission structures 00.00000*0 .0.000.00000*00 0000000 :ii. 00000000000000000 .0000 0 000 Structure type Minimum clearance prescribed ROW (150 feet) by the National Electric Safety Code [IL F) R O D El" � PPU W E R POT H W O Y I WINTER 2022, I xcelenergy.com I O0 20 LOGAN PHILLIPS relex wEL4 - I�� �r� • • • -. . • F - I C WhPUMA re r misubstations?a a n a � s�1n O LARIM - . Fort Morgan Yu ma C 4 _ _ BOULDER ' • Seament 1. Wra f ,t+ Canal Crossing ADAMS ^ ._ � Segment 2: Step-up or Include electrical Require oe,� i '�� „„E o Cana�Crossiny step-down voltages equipment approximately ,. Goose Creek IN SERVICE 2025 between the enclosed by 30 to 60 acres L Pawnee Expansion transmission lines security fence Castle ooU, Limon. Canal Crossing New .... MonumeSegments: I_, Goose Creek New HarvestMile M8y Valley New The existing substations will be expanded to accommodate the °E° new "`"'" Segment 3: transmission lines and the associated e ui ment needed to �- Longhorn New q p Goose Creek - May Valley operate the lines. FREMONT ELPASO �L4ift Segm May Valley Tundra n= IN SERVICE 2026 Fort St. Vrain Expansion CUSTER PUEBLO Las Animas Lamar I N S E RV I C E 2027 Extension: Lios May Valley — Longhorn Tundra Expansion (optional) HUEFFANO TRANSMISSION Harvest Mile Expansion SUBSTATION Connectionpoints for two or Walsenburg. TRANSMISSION LINES LAS ANIMAS more transmission lines � Extension timing will be finalized Springfield, based on the outcome of the CPCN determination by the PUC. I, Existing Substation I I Segment 1: Fort St Vrain - Canal Crossing I •i Segment 5: Tundra - Harvest Mile • New Substation I I Segment 2: Canal Crossing - Goose Creek \\\� Segment 5: Area Undergoing Evaluation Substation Siting Area I I Segment 3: Goose Creek — May Valley I I May Valley - Longhorn Extension TRANSMISSION LINES D Focus Area I I Segment 4: May Valley - Tundra v - � - A_ 1 I � I rQ' ^ • f• J I - _ III � i __ 1 _ _ - I' l I ♦ I I --fir, �•�ps„ - _ it ra - 1 AA •- 7Y J •• Y 1 1 • a 1i f 1`- {a „� wF ~�_ ALI�.Y� Ir��Y111 i ��� �a I _ • 9 ! `!w • �� Y" _ +\fi rs� k I ` I .. � I i r! . i _ ' ....��---- 'F a• �� �y ®� • . W, ALURODU"� FPUWER MWOY I WINTER 2022 I xcelenergy.comIOO20 XcelEnergy KIOWA _ wa i.. • . Q N � • • Eads � 1 mi �K I T CARSON — — — Haswell — a„9 � I ,..,��,� Lake moree�� Akron i i1I I Platn e r - Otis Ii5t Yuma Eck le ' MORGANTa�.I I KIOWA t� PUMA ____—__ __ _-- 85 Wild Horse 8 I Wiley 40 1Bristol Hartman EcClavem" _____ ___ ___ cs ua Chance 3wean Anton j 1 p 1% HastyLdTdI\ Granada Holly 1I a.m w¢arsm a a oeeo. � i gp Cope Joes36 Hale �)) 0 Z I O H LwAH1 aNGi.. I Kirk� CHEYENNE °u IPR WERS O Nr KIT CARSOo I o fo z KIOWA I 0 gate Ij SeibertVona Burlington Peconic Ea Js lawn. 'rya�b� TDOOVH PnO� �ape� � JO - SMnWn Lakee NN Genoa Limon 1 • ze i7w Matheson I Hugo( i °iai aWuz. • Existing Sub station � � — — — �~ _ � _ _ r � ZBj �Y-� Segmenl3 Focus Area L J Extension Focus Area Segment Focus Area � e"�o � C H E Y E N N E �3as L � Substation Siting Area L � Substation Siting Area L Substation Siting Area Cheyenne I � WAaO Pritchett ,Springfield 1 — A A was xers� I Wells �•^^• Wiley P R O W E R S `-- 60 Vilas SEGrVIEN r 2: SEGMENT 3: ���AY VALLEY CANAL CROSSING GOOSE CREEK - LONGHORN GOOSE CREEK MAY VALLEY FXTENSION Endpoints: Canal Crossing Substation, Endpoints: Goose Creek Substation, Endpoints: May Valley Substation, Goose Creek Substation May Valley Substation Longhorn Substation Major routing and siting considerations: Major routing and siting considerations: Major routing and siting considerations: • End point fixed at Pawnee/Canal Crossing and new • End points are Goose Creek and May Valley • Arkansas River crossing Goose Creek substation location to be identified • Existing wind generation • Two Buttes Reservoir State Wildlife Area • Must cross I-70 • Sand Creek Massacre National Historic site • Santa Fe Trail Scenic and Historic Byway • Waterway crossings and associated resource • Queens State Wildlife Area • Conservation easements sensitivities • Conservation easements • Existing & planned wind farms • Existing wind generation • Lesser prairie -chicken habitat • Lesser prairie -chicken habitat • High density of oil and gas wells and multiple large gas pipelines • Big Sandy Creek and associated sensitive * Extension timing will be finalized based on the outcome of resources the CPCN determination by the PUC. • Several municipal airports • Brush Prairie Ponds State Wildlife Area • Longest segment 41[uIJIiLJ'1f Keota 3• Elizabeth Kiowa Ii - Peconic Bennett Burl►n ton Last Nunn I Wa t ins Chance elling�on ' Seibert Vona Stratton g �_-f- Strasbu 36 Genoa Arriba 7o Flagler 40 �,- Byer Peoria Pierce il_ I __Elbert Lim 1 O E Brggsdae Buckingham Raym er Stoneham Matheson I u/f Ramah Hugo r us Littlteh' Deer Trai► Mla r us 285 us 1 385 `x Centennial Foxfield _ Timr�ath 24 1 s I Severance Eaton Galeton — i — Calhan I Lone Peyton -- � $j Parker Comish I Castle Tree Windsor Lucerne WMO RGAN ELD I Boyero Pines Agate ` G�tl i 40 I Sedalia 1., I Falcon �+ Arapahoe Franktown Gr;ele} I -)) • Ellicott Yoder ! use Wild Horse Cheyenne Wells. Elizabeth E L B E R T Castle I 70 Kersey us I I I �'t Rock • - - • Carson t. I Genoa 34 Goodrich Weldona Karval I stown • I 25 0 EL PASO __ / h- Masters - I Larks ur Elbert Vi►/age S �� — Matheson I I D O U G A S Simla Gilcrest • Westcreek L • Brush d : Wigwam Hug Fort Mor an _ .. -I - Eads T Wiggins • Brando'•�' ' Sheridan Monument Lake Cal Chivin ton han Peyton us 1 � Black Forest 24 us. W odland Park 85 25 L I I ® � Arlington u s � Firestone Dmde 7�25 C R O 11/ LEY �I - — Falcon Keenesburg 1 Boone � � �' I 24 Dacono Fort/')Pueblo Ordway EL PASO Hudson I Crowley • Sugar City I J Manito Springs Lupton �I Midland Wattenberg Bristol Hoyt � � � � -`'� � Hartman - Ellicott - Yo ck ' us Colorad Lochbuie I+.IL .� _, J Chera►nI Gran L. Fowler Lamar 50 ada -- Woodrow PUEBLO • Las Animas ings L I N C 0 L N Bri hton Rocky Ford Caddoa I Crip�le Creek. Security Karval g • P R O W E R S Victor � - Goldfield Henderson Cedarwood I - La .Iun a I Fountain � I I � r .� I Timpas I • Existing Wigwam Substation 1 U S To onerville u S _ 70 h J L 350 ' 287 �, ® Existing Substation r • • • I Existing Substation Segment 5 Focus Area P U E O �-- Bennett , Ninaview _ _ I �yc� , _ Stone City � us Watkins us Substation Sitm Area V 40 �Sb= _ 36 L 9 Segment 4 Focus Area — T oeo a r Substation Siting Area Two Buttes Bye. Segment 1 Focus Area , Substation Siting Area Area Undergoing Evaluation - I � 70 L r I g g � r us I E • 285' Tyrone u s Springfield. 160 � a Pueblo Boone L •Littleton ®� - i 11s 1 • 1 Os •t 111 1 1 t 1 1 1 Os 1 1 Os 1 • 1 Major routing and siting considerations: Major routing and siting considerations: Major routing and siting considerations: • End points are fixed at Fort St. Vrain and • End point fixed at Tundra substation • End points are fixed at Tundra and Harvest Mile Pawnee/Canal Crossing • Formally designated and/or protected state • U.S. Army Pueblo Chemical Depot • Platte River to the north and federal land •Black Forest • Must cross 1111111111111176 • Queens State Wildlife Area • Buckley and Schriever Space Force bases • Dense development to west and oil & gas •U.S. Army Pueblo Chemical Depot •USAFA Bullseye Airfield & training areas throughout most of study area . Transportation TechnologyCenter Existing wind facilities • Existing electric and gas lines • Lesser prairie -chicken habitat • Existing & planned residential • Conservation easements •Stewardship Trust land • Stewardship Trust land [IL F) F)"� FPUWER W Y _ I WINTER 2022 I xcelenergy.comIOO20 V • • • • . �. . • • • • • . �. . • • • • • • • -S • • I.. . . . . • •S. ••� • . . . • •.• . • • •• . • . • . . • . •ii 11 • u u u - ' � '+ "i a'4• � n%' r #r' y `I'r '_I � ��ryRN�� ,. ��i - �"r iN '� ♦i:� I y fi 'TAO r.. 1::.. 1 r i}< T♦'K IT:Ir Y :'. ',, 1. y.. Irb -y.u. •ra ` �Y - . .. .. n .. v r R. i i ♦ ... r ... 1.. .. r 6JJ ..,.r. .. J. 1 ... n r 7 r .. .. d Tti .. r. . .{ .. ... f in n 41. ..I F 9' 'r - .. • r. n �f' . a '..1 J o:. J F' .' r .. ..r. e ♦ 1 o A. ...n 'rr i5 rl i .. 'a\ -. v: r .i'. 4 x ...f A �� r r..r. ... f:. n r :._.' 1i I'�:' rn � • a A \ . _. r i , 1 '.I ^l yy]1 (.':: r r .. i t J i ._ v : r. n r r v.. It. f 1a �ti .1 •o _. .- _ 4 _ .c. aP / ... �� L' n. �.. .+�1 i '[ i r r : 1 . f a � 1 i"Y .� r A ..:. p• � r I ." _ •T -. tY.'av-.l irn '. 1 • .>�".. _. - f:'r . . n r.1 1 • '.1� '� ^ _ VAx.Id E.PIIQIi: Yt:io [1lI ES] I IA F-i ;t: [:] j[:] jj i1!II[.II. F:11111 d! [.TkQIi:1 • • • • • • . •• . • . . . • • • • • .• . . . • . . • . • . . . • • • • • • . • • • • . . • • • • . . . • • • • • • . • •. • . • • • . . . • • • . . S.... • • .05 . • • • . . OS • S 0015 • SI. 'S , y,vSy. S not an adequate d'istance from power or that grow 55 . S SS Our goal is tprovide • S • • ►' possible c• one of your •. :• tatur,21 res _r C O L O R A Q O, � � O W E R PAT H �� I w� NTE R 2022 I xcelenergy.com � O0 2022 Xcel Energy Inc. Xcel Energy is a registered trademark o Xcel Energy Inc. MAGNET 1 C F 1 E L D S 7 Xcel Energyo AND NOISE MAGNETIC FIELDS Typical magnetic fields six inches The chart below provides typical AUDIBLE NOISE from common home appliances noise levels encountered in measured in milliGauss (mG) are common settings measured in depicted in the chart below. I decibels [dB(a)] 25Ef Edge of ROW Edge of ROW ROW ROW Edge of ROW Row's 450 Magnetic i i BOO%C2p2CIIY 60I I I Limi�I=50 dBA Cleaner40oiVacuum iiAudible Noise (Rain) iil�l� PneumaticE°9�°`R°�25'ee'°m `", 350� chipper 50 _ , 300 300 ,J120-130 i PUC limit g m 250 'i-........ at edge ' ' ' d i Magnetic i 50%Ca acit iMEof ROW LouaU I @horn � i i Audible Noise D Iii i a v i ICfOWaVe � (11 mile away) d 3° 200 150 Limit=150mG 770-720 ¢ I Magnetic i 20 i I I 100 25% Capacity I i i -� Copy 50 ', Machine Inside motorbus 10 r 80-90 °-1zs -7s -zs 0 25 75 ° -125 ae -25 0 25 75 Distance from Centerline (feet) - - Distance from Centerline (feet) Garbage Disposal _a_ � � � � Average traffic PUC limit I i on street depending I on zoning %0-80 50-75 MAGNETIC FIELDS, measured in Hair Dryer dB(a) Q Q Conversation CORONA is a phenomenon milliGauss (mG), are produced by TJ .Z 60-'o associated with all transmission electric current and only exist when i lines. Corona is a small an electric appliance is turned on — Blender � �� Living room electrical discharge, not unlike the higher the current, the greater -so the static electrical charge the magnetic field. As with electric that a person may experience Fluorescent fields, the strength of a magnetic field L'Ight Library ambient when touching a metal object dissipates rapidly as you move away � � noise when walking on carpet. from its source. = 30-40 Corona is what creates the Dishwasher Wilderness with no hissing or crackling sound The power line serving your � �5d oranimal activity that often emanates from neighborhood produces EMF just like transmission lines. Corona household appliances such as your Computer � � Threshold of increases substantially in wet toaster, hair dryer, lamps and washing �earuiOM10Weather, when water droplets machine. Business equipment, such form on a transmission line as computers, copiers and fluorescent which increase the corona (and lights, also produce EMF. increase audible noise). I U A __ I U _ _ __ _ 1 :] bT ! 1i •1 I:] A 'Is] 111 ] i:I ARI :j YK: ] .IsI:f . :Yf] L! [l: 1 AI I 1 A:I 111 [f1 Esi I E:1 lAVA u111:1ll P I] I to IuAf.] LVK:1 Ij:1ll i: L! I Fl1. '1.1111 iI F1 sJ: :X( i:il Il l 1 F1l1 l:Th F1 l ;111. [!IAl(: ;ljl. :4YJ:4(:]jni Criteria Acquisition of Land Rights Substation Engineering Transmission Engineering Electric System Planning Economics Environmental and Cultural Resources Public Involvement Renewable and Other Generation Resources Regulatory Compliance Consideration Existing easements and Vacant developable Topography/slope Adjacency to existing Overall route length Land use/land cover Landowner feedback Existing and planned Local land use fee -owned property land transmission lines utility -scale wind and permitting Proximity to buildings — reliability and Construction, Proximity to residences Stakeholder solar facilities requirements such as Jurisdiction and land Available for purchase (homes, businesses) redundancy operation, and and structures discussions zoning and setbacks ownership maintenance needs Renewable generation 60 -acre site Transportation Electric system such as access Designated scenic Comments received zones Coordination with Formally designated infrastructure interconnections areas during public open Colorado Parks & areas with restrictions Accessibility for Roads (substations) Structure types houses and through Future electric system Wildlife and U.S. Fish & that prohibit construction and Railroads required for straight Special status and Project website, email, interconnections Wildlife Service development of operation — located Airports Line length sections for turns/ protected species and hotline transmission lines adjacent to maintained angles habitat, critical habitat Federal Aviation public roads Proximity to homes Administration and Existing and planned Military and other Wetlands and Noise Department of Defense developments special use airspace waterways EMF and/or other military (residential, Oil & infrastructure Wildlife impacts Agricultural airspace requirements commercial, other) that gas Cultural and historic operations may not have enough such as wells and sites Traffic Army Corps of space for easements pipelines Visual impacts Engineers for wetlands/ Landowner interest waterways 9 0 Q9 0 Identifying the location for the new 9 transmission line segments is accomplished g p 0 through a process that includes engaging the 0 o public, landowners and other stakeholders. C 0 Cultural and historic resources, technical and 0 engineering requirements, environmentali I • constraints, existing and planned land use $ and other factors that people have told use $ are important to consider are evaluated and compared for transmission line route options. Q Q 0 The final route proposed in the local land use 0 permitting processes will balance all these factors. Alternative Routes Preferred Route ALURODU"� FaUWER PDTHWOY I WINTER 2022 I xcelenergy.comIOO20 STUDY AREAS � Np . • SUITABILITY ANALYSIS r �' "! {• ......•... ". : - • �- �G 20 -miles -wide, developed based on segment end points (Substation A and Substation B) t. x • :.- •l.•:I 'I,. :- ' •J•...; PRELIMINARY LINKS : . *1 . I Collect data on resources within and adjacent to study areas, •� categorize based on compatibility with development of transmission line or substation N FOCUS AREAS �`"A Based on su'tability analysis, identify links that provide routing options between segment end points that � minimize crossing of constrained areas and maximize use of more compatible locations I L 0 A ___ _EEEEEEE. UI Smaller area within each segment study area where links have been identified, � o � within which the preferred route is anticipated to be located I^I . ��n REVISE LINKS & IDENTIFY PREFERRED ROUTE Areas with constraints or that are less suitable for transmission line development are removed from further consideration • I. -.,F - - - _-.. __ __ __ ' Preliminary links are revised (removed, added, modified) based on public and stakeholder review and input Comparative analysis to identify links to be removed from further consideration, evaluate end -to -end routes Select preferred route 1)1 Keota u s I ellin on Nunn � I Weldona 6 Snyde I O Lo Lane g •• • Village W Pierce • • Q • _ Briggs Buckingham Ramer gg g y I 7s ., O oc KIT CARSON Stoneham Fort — Ault Morga 0 W —� Ak► u5 Z -_______ _ _ — �- I Plainer Otis 34 l Yuma Eckley 0 1 0 tl Tim th Severance Eaton Galeton - � � — 3� Lai iiiIEJ Cornish I ■ ■■ 4 Wray Windsor WELD I M O R G A NIiNP!.r� ri Gill I MO R us __ __�� �Q� � 385 Greeley I • I YUMA A � 11 Kersey u s I T 5 e Lstown Goodrich Weldona ' ' I l us Snyder ■■ ' Wild Horse I Masters 385 Log Lane ■� I__— us ■ 0 Gilcrest 6 La Chance us Lind �1 36 1 /dalia Kit Carso • Brush d W► ins Fort Morgan , ■■ ■� e s s a 36 �■■ �Hale 287 —��' i■.■�ME oes Kirk 76 2 I W SHI GT ■■ 85 _ CHE ENNE 1r2 Fire one i ■�■ ■1 0 _ — ■��� KIT ARSON —,-- 25 — Keenesburg I �,■�■■� r 1 I ■ !fir o z K I WA cono gate Lupton � 8 Wattenberg I P 385 Lochbuie Hoyt C �— — Woodrow Arriba Brighton • • la ler Seibert Vona Towner 7Burlington Peconic Eads 13 - Stratton g 70 / Sherid Lake Henderson • • I Limon `�� ������■ Chivington 24 �� I I I I r —� I I Hu o II J L •IIiJQ • • - . . I • Existing Substation S Existing Substation I Bennett Segment 2 Focus Area 40 I— '` , U5 Watkins _ - Segment 3 Focus Area 40 �e1 V strasb , Substation Siting Area 36 � Segment 1 Focus Area •, Substation Siting Area Bo ero us — 7 • - Be gy 38 5 25 ICHEYE Substation Siting Area y 70 Sheet Map Extent D Sheet Map Extent I Cheyenne Sheet Map Extent . 285 _ y IArapahoe PROWERS Aroya Wild Horse I! Wells Ara ahoe Littleton /�. SEGMENT 1: I SEGMENT 2: 1 SEGMENT 3: :1 yA;yA1I C[.I.I] I I Elizabeth KIOwa I , Peconic '�^ Bennett Burlin ton us Wat ' us Last KIOWA I Flagler Seibert Vona Stratton g s r+ Strasburg _ 36 Chance Genoa Arriba u s - 70 40 B er Peoria Ea ds 13 I Elbert Limon �` A R A A H O E Brando n Lake Matheson _ I � HugoDeer Trail Haswell g us Littlet n Chivington I I Sheri I Ramah . ` _ / J - Centenna u s Foxfeld 5 385 285 24 — — us 21 Peyton Calhan GI3 - 5 Lone parker • . - Tre I � 8Cast e Pin Boyero us Us 40 Sedalia I K I O W A 287 _ Falcon PI I Arapahoe anktown _ s y I R E R I �f r 23 Ellicott Yoder _ IIKUS� -- Wild Horse Cheyenne Wells . I I zabet 20 Castle 70 us I Kit Rock '� ' I I 385 Genoa Karval ' Carson E L PASO _ 25 Lim I Wil l I _ Larkspur McClave I LINCOLN us Matheson I 50 Hasty L ar• us •_ D O U G L A Simla Granada Holl Westcreek L _y� Hug Caddoa I 50 y Wi w 1 4 • Brando III 6 15 R i Sh 'dan Monument I 24 0 1Haswell Chivin ton La I u s Calhan I m 13 , Pe on Black Forest I W odland Park 24 I � Z 25� I P OWERS Arlington I u s Divide C RO L EY __ _ ____.___J__!___ I 24 Falcon Boone �— —' � Ordway E L PAS O _.-- ueblo a Crowley Sugar City I I Midland J Manito Springs �I I Ellicott Yoder I us Bristol Hartman I Colorad 7/ Chera 25 Fowler J � ` . 50 Granada � Lamar LINCOLN I PUEBLO Las Animas �ngs Rocky For Caddoa I Cripple Creek. Security , Karval PROW E R S Toonerville I — � Victor Goldfield • • • 17 Cedarwood a I I a Jun L Fountain Timpas • Existing Substation W wa B A A 26 350 ( Toonerville �I 287 ••• • Deora y �r • Existing Substation I Segment 5 Focus Area P U E B L O - rwo e Ninaview �` �.1y_ , Stone City 6 u5 Segment 4 Focus Area i _- — Substation Siting Area 287 Deora Two Buttes I Extension Focus Area ISubstation Siting Area Area Undergoing Evaluation3 — r • • � � Substation Siting Area Sheet Map ExtentI EJ Sheet Map Extent Springfield us Sheet Map Extent f l Springfield. 160 Pueblo Boone j L 160 Walsh Pritchett Vilas KiI'AIIiE [chv4l Ii'E __ •1 VIA! 1Ujm];yA C]LURO DU" � PUW E R POTH WOY I WINTER 2022 I xcelenergy.com��20 I U U A yly A :]j1i:}: .1 .1!I sPF:1(.]ii:]i: •I.]ii1iil!I�1I[:I: 'iYt: Il 1i ilt!I1 Ii :1!I4l[.]: Iii:i: Iini1II1Iini1I{: •Ic&(:]ilf1 Iii1.1IsThu[: . Y _ar. �S�s .I • 'la � < v �• . Mr }'��h�1•,. tl.j ���_--♦y -. : _ -�— - y � � • �v s �.,. r '�� I ' E . �. V Yom__ ♦ 5 Y y�ay� i 1 - ___ * - - - 7 _________ ______ ___ - I ♦ r:- �Y d l Suit r I 7 1 I 1 I '.rl 'fi-• y. i. l'n ♦• �' .. �- 'l' Y♦ - •' r. ��1 1 1 1. ` 1!c f l . - I-T;Ivw _ II Impacts to wetlands will be avoided or Locations of known habitat are mapped and Xcel Energy filed an application with the minimized by careful placement of the avoided where possible. Colorado Public Utilities Commission in March substations and transmission lines. 2021 (Proceeding Number: 21A�0096E). Conservation easements, national wildlife We attempt to site transmission structures in refuges and state wildlife areas will be avoided Xcel Energy will coordinate with wildlife locations that will avoid conflicts with irrigation to the extent possible. agency representatives regarding the proposed equipment and its operation to the extent project throughout planning, design and possible. Seasonal restrictions are implemented to avoid construction and will comply with all regulatory constructing near habitat during certain seasons requirements. Impacts to rivers and streams will be avoided or (such as nesting) as recommended by Colorado minimized by placing transmission structures Parks and Wildlife and U.S. Fish and Wildlife Local land use and construction permits will outside the waterway and spanning where Service guidance. be obtained in the jurisdictions crossed and possible. include: Electrical components of the transmission lines and substations will be separated to minimize • 1041, Use by Review, Land Use Change, the risk of avian contact. Bird diversion devices Special Use Review, Major Land Use will be installed where necessary. Permits • Right -of -Way Use, Road Use Agreements, Access, Transport, Grading, Stormwater [IL El El -� PIPUWER W Y I WINTER 2022 I xcelenergy.com�O020 Hello