With reference to the construction of the Weld County Recreation Building
at Island Grove Park, please be advised that we have completed the design
of all sewer, water and irrigation modifications necessary to clear the
area for the proposed building. The plans have been reviewed and approved
by the various officials of the City of Greeley.
Enclosed are two cost estimates for the necessary work including the current
sewer, water and drainage fees normally assessed by the City of Greeley
upon the issuance of a building permit. The first estimate reflects costs
that can be anticipated if the work is bid and awarded to a non-union con-
tractor. The second estimate reflects the cost if the work is added to
the Penner Construction Company's contract and performed by union labor.
You will note that both estimates include the following fees payable
directly to the City of Greeley:
1 . Sewer Tap $ 990.00
2. 1 1-2" Water Tap 895.00
3. 1 1-2" Water Meter 181 .00
4. Drainage Fee 3,000.00 +
Total $5,066.00
OFFICES IN GREELEY,GRAND JUNCTION,AND DENVER,COLORADO 730859
Weld County Commissioners
Page 2
July 27, 1973
We hope that this information will assist you in your deliberations with
the City of Greeley with regard to the proper allocation of these con-
struction costs and city charges. If, however, there is need for additional
information, please do not hesitate to call on us.
Very truly yours,
NELSON, HALEY, PATTERSON and QUIRK, INC.
John L. Haley, P.E.
President
JLH: llr
Enclosures 2
cc: Jack Huffman, Greeley City Manager
fro-` • 00-\
/
• ,
/
LOCAL NON-UNION CONTRACTOR
WELD COUNTY RECREATION BUILDING
ESTIMATED COST - SITE UTILITIES
Item Description Quantity Unit Unit Cost Total Cost
Sanitary Sewer
1. 8" VCP 626 L.F. . $ 5.00 $3,130
2. 6" VCP 155 L.F. 3.00 465
3. Manholes 3 Each 450.00 1,350
4. Cleanouts 1 Each 100.00 100 '
5. Asphalt Cut and Patch 36 S.Y. 20.00 720
6. Concrete Cut and Replace 11 S.Y. 20.00 220
7. Sewer Tap 1 Each 990.00 990
$6,975 $ 6,975
Water -
8. 1 1/2" Copper Service 90 L.F. 5.00 450
9. 1 1/2" Meter (Purchase
from City of Greeley) 1 Each 181.00 181
10. 1 1/2" Street Tap 1 Each 895.00 895
$1,616 $ 1,616
Irrigation System
11. 8" Concrete Pipe 132 L.F. 5.50 309 $ 726
Drainage Fee
"Estimated" at $2,926.50 by City Say 3,000 $ 3,000
Park Fee
None Required
TOTAL COST $12,017
r ,.�
. �.
PENNER UNION SUBCONTRACTOR
WELD COUNTY RECREATION BUILDING
ESTIMATED COST - SITE UTILITIES
Item Description Quantity Unit Unit Cost Total Cost
Sanitary Sewer
1. 8" VCP 626 L.F. $ 6.00 $3,756
2. 6" VCP 155 L.F. 4.00 620
3. Manholes 3 Each 550.00 1,650
4. Cleanout 1 Each 150.00 150
5. Asphalt Cut and Patch 36 S.Y. 20.00 720
6. Concrete Cut and Replace 11 S.Y. 25.00 275
7. Sewer Tap 1 Each 990.00 990
$8,011 $ 8,011
Water
8. 1 1/2" Copper Service 90 L.F. 6.00 540
9. 1 1/2" Meter (Purchase
from City of Greeley) 1 Each 181.00 181
10. 1 1/2" Street Tap 1 Each 895.00 895
$1,616 $ 1,616
Irrigation System
11. 8" Concrete Pipe 132 L.F. 6.00 792 $ 792
Drainage Fee
"Estimated at $2,926.50 by City Say 3,000 $ 3,000
Park Fee
None Required
TOTAL COST $13,419