Change Order No. 1
Date Anguct 24. 1473
PROJECT Masters-Hardin Bridge PROJECT N0. 73-1-CCA-0228
OWNER Weld County. Colorado CONTRACTOR Loveland Fxcavating Company
DESCRIPTION OF CHANGE - That said Contract shall be changed in the following particulars:
Add to Office of Emergency Preparedness Item 5-21, a portion of the road known as the
K-4 Ranch Road (Co. Rd. 44 x Rd 87, 1.5 mile) and designate it as 5-21A. Repair flood
damage using quantities below.
and that after the said changes shall have been made with additions and/or deletions are
hereby directed to be a part of the original Contract, the agreement as shown by the
original Contract together with the above-named additions and/or deletions shall constitute
the agreement and Contract of the parties hereto
JUSTIFICATION:
Weld County Engineer
CHANGE IN CONTRACT COST:
Item Description Quantity Unit Unit Cost Total Cost
1 . Embankment 8680 C.Y. 1 .50 13,020.00
3 Gravel Surfacing 2544 Ton 2.50 —6,360.00
7 18" C.M.P. Relay 30 L.F. 10.00 300.00
8 Clam Bucket & Crain 4 Hr_ 40.00 160.00
Total Amount this change order $ 19,840.00
Net of Previous Change Orders (+) (-) $ -0-
Original Contract Amount $ 55.062.50
Revised Total Contract Amount $ 74.902.50
CONTRACT TIME:
Completion Date August 31 , 1973
Previous Days Allowed 68
Days Allowed This Change Order __
Revised Completion Date
Recommended: Approved: - k;t / -c-PL-- =re_
NELSON, HALEY, PATTERSON and QUIRK, INC.
Ow
BY: kb& mac rn.vi" Pkat(
Field Representative By: Invahnd Fxrav Ling Cnmpeny
AA-7
� � (Contrac r)
Date: A A% - 2¢ 07,3 /� �/
Approved: AlfAlfroject ManagerQ� Date:
Date: 8"24-73
730906