HomeMy WebLinkAbout20252064.tiffResolution
Approve Community Development Block Grant Advisory Committee (CDBGAC)
Recommendation for Additional 2025 Funding Allocation Award for Phase II
Housing Rehabilitation Project Program — Town of Firestone
Whereas, the Board of County Commissioners of Weld County, Colorado, pursuant to
Colorado statute and the Weld County Home Rule Charter, is vested with the authority of
administering the affairs of Weld County, Colorado, and
Whereas, on May 7, 2025, the Board of County Commissioners of Weld County,
Colorado, approved Funding Allocations for Community Development Block Grant
(CDBG) Program 2025 Projects based on the Weld County Community Development
Block Grant Advisory Committee (CDBGAC) Recommendation, of which, one project
awarded and allocated is further identified below:
• #25-3 Town of Firestone Housing Rehabilitation Project Program (Phase II) —
$75,000.00
Whereas, the U.S. Department of Housing and Urban Development, Office of Community
Planning and Development, awarded Weld County with Community Development Block
Grant (CDBG) funds for Fiscal Year 2025, in the actual amount of $1,251,662.00, totaling
$40,352.00 more in grant funding than the estimated amount of $969,048.00, and
Whereas, the Board has been presented with the Community Development Block Grant
Advisory Committee (CDBGAC) Recommendation for Additional 2025 Grant Funding
Allocation Award, in the amount of $30,000.00, to the Town of Firestone for the Phase II
Housing Rehabilitation Project Program through the Community Development Block
Grant (CDBG) Program, and
Whereas, after review, the Board deems it advisable to approve sad recommended
additional project funding allocation.
Now, therefore, be it resolved by the Board of County Commissioners of Weld County,
Colorado, that the Community Development Block Grant Advisory Committee (CDBGAC)
Recommendation for Additional 2025 Funding Allocation Award, in the amount of
$30,000.00, to the Town of Firestone for the Phase II Housing Rehabilitation Project
Program through the Community Development Block Grant (CDBG) Program, for a total
award for said Project #25-3 amounting to $105,000.00, be, and hereby is, approved and
allocated.
L(,'. CothhCCP
'AC.,
o� \ aac as
2025-2064
FI0082
Community Development Block Grant Advisory Committee (CDBGAC) Recommendation
for Additional 2025 Funding Allocation Award for Phase II Housing Rehabilitation Project
Program — Town of Firestone
Page 2
The Board of County Commissioners of Weld County, Colorado, approved the above
and foregoing Resolution, on motion duly made and seconded, by the following vote on
the 21st day of July, A.D., 2025:
Perry L. Buck, Chair: Aye
Scott K. James, Pro-Tem: Aye
Jason S. Maxey: Aye
Lynette Peppier: Aye
Kevin D. Ross: Aye
Approved as to Form:
Bruce Barker, County Attorney
Attest:
Esther E. Gesick, Clerk to the Board
2025-2064
F 10082
BOARD OF COUNTY COMMISSIONERS
PASS -AROUND REVIEW
PASS -AROUND TITLE: Award of additional CDBG funding for the 2025 grant year
DEPARTMENT: Finance/CDBG DATE: July 9, 2025
PERSON REQUESTING: Cheryl Pattelli and Cynthia Martin
Brief description of the problem/issue:
Weld County has been awarded $1,251,662 in 2025 CDBG funding — an additional $40,352 more than last
year's allocation on which the earlier round of grant awards the BOCC approved was based. Of this additional
funding, 80% may be awarded in grant funding or $32,282 while reserving 20% for program administration.
The Weld County CDBG Advisory Committee voted 5 to 0 at their July 2, 2025 meeting to recommend the
Board of County Commissioners award $30,000 in additional funding to the Town of Firestone for their
Housing Rehabilitation Program II and set aside the remaining $2,280 for contingencies. The Firestone project
was funded in the earlier round however received less funding than they requested due to insufficient funding.
The $30,000 additional funding will allow Firestone to provide up to $15,000 in minor repairs to two additional
single-family homes owned and occupied by low- and moderate -income residents.
What options exist for the Board?
1. Approve the additional funding request as recommended by the CDBG Advisory Committee.
2. Schedule a work session to discuss.
Consequences:
Approving this request as presented will allow for the full usage of 2025 CDBG funding received.
Impacts:
If this CDBG funding is not allocated to 2025 projects, it would need to be held over for future use.
Costs (Current Fiscal Year / Ongoing or Subsequent Fiscal Years):
No cost to award this funding.
Recommendation:
It is recommended that the Board approve the additional award of $30,000 to Project #25-3 Firestone Housing
Rehab Program II and $2,280 set aside for contingencies as recommended.
Support Recommendation Schedule
Place on BOCC Agenda Work Session Other/Comments:
Perry L. Buck
Scott K. James
Jason S. Maxey
Lynette Peppier
Kevin D. Ross
2025-2064
7/Z\
0OS
2025 Grant Applications
WC CDBG Advisory Committe recommendations
Amount requested
2025 funding
$1,001,330
Surplus funding
$66,892
Total estimated funding
$1,068,222
#25-1 Pierce Senior Center Improvements II (min. $150,000)
$250,000
$242,440
Waitlist
#25-2 Lochbuie ADA Accessible Sidewalks
$167,305
$167,400
#25-3 Firestone Housing Rehbilitation Program II (min. $75,000)
$150,000
$75,000
Waitlist
#25-5 Nunn Community Center Renovation
$167,700
$167,700
#25-7 Eaton Non -Conforming ADA Ramp Replacement Phase III
$122,384
$122,400
#25-8 Platteville Park Restroom Facilities (min. $261,000)
$536,432
$261,000
Waitlist
Balance left
$32,282
Waitlisted Projects:
Funding gap
#25-1 Pierce Senior Center Improvements II
$7,560
#25-3 Firestone Housing Rehab II
$75,000
$30,000
#25-8 Platteville Park Restroom Facilities
$261,000
Balance left - Contingency
$2,282
Actual grant allocation $1,251,662 x 80% = $1,001,330