HomeMy WebLinkAbout740592.tiff RESOLUTION
WHEREAS, heretofore and on May 16, 1973, by Resolution, the
Board of County Commissioners, Weld County, Colorado, did authorize
the execution of a contract and agreement with Penner Construction
Company, Lakewood, Colorado, to construct the Weld County Recreation
Building at Island Grove Park and to pay therefor from Federal Sharing
Revenue Funds, all pursuant to proper advertisement for bids and in
accordance with statutes for said purpose, and
WHEREAS, it has now come to the attention of the Board that
said construction of the aforesaid building is subject to AIA Document
G701 concerning Change Order No. 5, with reference made to
Architect's Project No. 73-1-CCA-0117 concerning complete con-
struction work and with further reference made to contract date of
July 13, 1973, copies attached hereto for ready reference, and
WHEREAS, in order to be in compliance with the Federal Law,
the Board believes it to be in the best interest of the County to incor-
porate the aforesaid Change Order No. 5 within the contract and agree-
ment previously entered into with Penner Construction Company.
NOW, THEREFORE, BE IT RESOLVED, by the Board of County
Commissioners, Weld County, Colorado, that Change Order No. 5
hereinabove mentioned and made a part hereof by reference, be and
the same hereby is ordered to be made a part of the contract and agree-
ment heretofore mentioned and entered into between Weld County and
Penner Construction Company for the erection of the Weld County
Recreation Building at Island Grove Park.
The above and foregoing Resolution was, on motion duly made
and seconded, adopted by the following vote on the 13th day of
March, A. D. , 1974.
BOARD OF COUNTY COMMISSIONERS
WELD COUNTY, COLORADO
I
)1<f < <) able;
ATTEST:`., / � ,� _�
Weld County Clerk and Recorder
and Clerk to the Board
11y � p . ` rut-a-�l
Deputy CountR-
c-------
Clerk
APPROVED AS TO F/ RORM:
`j /7 County Attorney
740592
Rt;, cot
CNC/N H PQ, INC. ARCHITECTS • ENGINEERS • PLANNERS
March 6, 1974
Mr. Barton Buss
Chief Accounting Officer
Weld County Board of Commissioners
Weld County Courthouse
Greeley, Colorado 80631
Dear Mr. Buss:
SUBJECT: WELD COUNTY RECREATION BUILDING, PROJECT NO. 73 1 CCA 0117
Enclosed are four copies of Change Order No. 5 which meets you agreement
with Centric Corporation on the above reference project.
Please sign all copies, retain one copy for your files, and return the
remaining copies to this office.
Change Order No. 5 covers furnishing electrical service to the three
overhead doors in Room 114, exhibit area, which was not shown on the
plans and specifications. This change order also grants a thirty
da? extension cf =cntract construction time due to the delay caused
by late delivery and erection of the double tee prestressed panels
for the office section of the building. Prestressed panels were to
be delivered and erected starting October 8, 1973, and completed on
October 19, 1973. Delivery didn't start until November 5, 1973, and
was not completed until November 16, 1973.
If there are any questions concerning this matter, please feel free to
contact this office.
Respectfully,
CNC/NHPQ, INC. ARCHITECTS ENGINEERS PLANNERS
Crt'bAdtiO2C
Donald K. Fetig, Seniorjd Representative
Construction Contract Administration
DKF/bjr
Enclosure: Change Order J+
TWENTY TWENTY-ONE CLUBHOUSE DRIVE, GREELEY, COLORADO 80631 (303) 353-3434 356-4444
CHANGE OWNER O
ARCHITECT Ej
ORDER CONTRACTOR Q
FIELD al
AIR DOCUMENT G701 OTHER x CCA
PROJECT: Weld County Recreation Bldg. CHANGE ORDER NUMBER: Five (5)
(name, address) Island Grove Park -
Greeley, Colorado 80631
TO (Contractor)
F 7 ARCHITECT'S PROJECT NO: 73 1 CCA 0117
Centric Corporation CONTRACT FOR: Complete Construction Work
51490 West 13th Avenue
P. 0. Box 14026
L Denver, Colorado 80214 j CONTRACT DATE: July 13, 1973
You are directed to make the following changes in this Contract:
1. Provide all labor, materials, and equipment necessary to furnish electrical
service to the three overhead doors in the exhibit area, Room 114.
ADD $1,667.00
2. Due to the late delivery and erection of double tee prestressed panels
for the office section of the building, a thirty (30) day extension of
contact construction time is granted.
NO CHANGE IN CONTRACT COST
The original Contract Sum was $ 691,596.00 .
Net change by previous Change Orders $ 7,031.50
I The Contract Sum prior to this Change Order was $ 698,627.50 .
The Contract Sum will be (increased) kSzcasec*rdmxc*by this Change Order $ 1,667.00 .
The new Contract Sum including this Change Order will be $ 700,294.50 .
The Contract Time will be (increased) ktexceasedkkmximargockt by ( 30 ) Days.
The Date of Completion as of the date of this Change Order therefore is April 30, 1974 .
CNC/NHPQ, INC. CENTRIC CORPORATION WELD COUNTY COMMISSIONERS
ARCHITECT CONTRACTOR OWNER
2021 Clubhouse Drive 9490 West 13th Avenue Weld County Courthouse
Address Address Address
Greele^ Colorado 8063 Denver, Colorado 80214 Greeley, Colorado 80631
�/�! //
BY BY: �1.Q e BY ��C:ILi J L�: G ird
DATE 3.. 4#.. 77 DATE .ifi b 2t jq;y DATE i -Z.�� �.C_0__C c_�
AIA DOCUMENT G701 • CHANGE ORDER • APRIL 1970 EDITION • AIAOO • O 1970 • THE /// ONE PAGE
AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE., NW,WASHINGTON, D.C. 20006