HomeMy WebLinkAbout20251849.tiffResolution
Approve Regulating, Warning, and Guiding Traffic During Temporary Closure of
County Road 72 Between County Roads 33 and 35 for Approximately Six (6) Weeks,
for Storm Water Improvements, Roadway Construction, and Paving
Whereas, the Board of County Commissioners of Weld County, Colorado, pursuant to
Colorado statute and the Weld County Home Rule Charter, is vested with the authority of
administering the affairs of Weld County, Colorado, and
Whereas, pursuant to C.R.S. §42-4-106(6)(a), "...local authorities, with their respective
jurisdiction may, for the purpose of road construction and maintenance, temporarily close
to through traffic or to all vehicular traffic any highway or portion thereof for a period not
to exceed a specified number of work days for project completion and shall, in conjunction
with any such road closure establish appropriate detours or provide for an alternative
routing of the traffic affected...", and
Whereas, pursuant to said Statute and upon the basis of traffic and personnel
investigations, the Board has determined that conditions exist which make it necessary
to temporarily close County Road 72, between County Roads 33 and 35, to through traffic
and to regulate, warn and guide vehicular traffic by posting signs thereon, with said
closure being effective July 14, 2025, for approximately six (6) weeks for storm water
improvements, roadway construction, and paving.
Now, therefore, be it resolved that the Board of County Commissioners of Weld County,
Colorado, deems it necessary to regulate, warn, and guide vehicular traffic on County
Roads and any intersections thereof, and it hereby authorizes and orders the posting of
such traffic control devices as shall be reasonably necessary to regulate, warn, and/or
guide traffic thereon for the safety of the general public and that said traffic control devices
shall conform to the Federal Manual on Uniform Traffic Control Devices.
Be it further resolved that the Board of County Commissioners of Weld County,
Colorado, does declare and establish that County Road 72, between County Roads 33
and 35, be temporarily closed, with said closure being effective July 14, 2025, for
approximately six (6) weeks for storm water improvements, roadway construction, and
paving, and further, that standard official traffic control devices shall be erected at said
closure giving notice of the restrictions.
G c: S O (Rs), D. SP0.t c1N , C SP
O1 /oii/25
2025-1849
EG0024
Temporary Closure — County Road 72
Page 2
The Board of County Commissioners of Weld County, Colorado, approved the above
and foregoing Resolution, on motion duly made and seconded, by the following vote on
the 30th day of June, A.D., 2025:
Perry L. Buck, Chair: Aye
Scott K. James, Pro-Tem: Aye
Jason S. Maxey: Aye
Lynette Peppier: Aye
Kevin D. Ross: Excused
Approved as to Form:
Bruce Barker, County Attorney
Attest:
Esther E. Gesick, Clerk to the Board
2025-1849
EG0024
MEMORANDUM
TO: Clerk to the Board DATE: June 26, 2025
FROM: Amy Mutchie, Public Works Department
SUBJECT: BOCC Agenda Item
Connell Resources, on behalf of Weld County Public Works, is requesting to close CR 72 between CR
33 and CR 35 beginning 7/14/2025 through 8/22/2025 for storm water improvements, road construction
and paving.
See attached closure diagram.
2025-1849
toi3D EC--1o0Z4
www.invarion.com
DETOUR
OV3Hb'
1Ri OM
avoa
ROAD
WORK
AREA
Allow Access to Residents on
either the East or West End
•
Zoe La‘Ain Car
Add flagger symbols and
and flagger if we need
to stop traffic
V3Ht1
SiaoM
odoa
DETOUR
1d'
ROAD
WORK
AHE +
Legend
Comments:
Plan not drawn to scale
Plan will conform to the latest edition of the MUTCD and all
devices used will be in compliance of the NCHRP 350
Sign distancing will be a minimum of 350 feet for speeds 40
and over and 100 feet for speeds under 40
Taper will be a minimum of L for Lane Closures
Taper will be a minimum of 1/2 L for Lane Shifts
Taper will be a minimum of 1/3 L for Shoulder Closures