Approve Regulating, Warning, and Guiding Traffic During Extension of Temporary
Closure of County Road 29 Between County Road 74 and State Highway 14 for
Approximately an Additional Three (3) Weeks, for Unanticipated Delays Due to
Inclimate Weather
Whereas, the Board of County Commissioners of Weld County, Colorado, pursuant to
Colorado statute and the Weld County Home Rule Charter, is vested with the authority of
administering the affairs of Weld County, Colorado, and
Whereas, pursuant to C.R.S. §42-4-106(6)(a), "...local authorities, with their respective
jurisdiction may, for the purpose of road construction and maintenance, temporarily close
to through traffic or to all vehicular traffic any highway or portion thereof for a period not
to exceed a specified number of work days for project completion and shall, in conjunction
with any such road closure establish appropriate detours or provide for an alternative
routing of the traffic affected...", and
Whereas, on the 10th day of February, 2025, pursuant to said Statute and upon the basis
of traffic and personnel investigations, the Board determined that conditions existed which
made it necessary to temporarily close County Road 29, between County Road 74 and
State Highway 14, to through traffic and to regulate, warn and guide vehicular traffic by
posting signs thereon, with said closure being effective February 24, 2025, for
approximately four (4) months, through July 2, 2025, for a culvert replacement and
roadway construction, and
Whereas, on the 16th day of June, 2025, pursuant to said Statute and upon the basis of
traffic and personnel investigations, the Board has determined that conditions exist which
make it necessary to extend said temporary closure of County Road 29, between County
Road 74 and State Highway 14, with said extended closure being effective July 2, 2025,
for approximately an additional three (3) weeks through July 25, 2025, for unanticipated
delays due to inclimate weather, and further, that standard official traffic control devices
shall be erected at said closure giving notice of the restrictions.
Now, therefore, be it resolved that the Board of County Commissioners of Weld County,
Colorado, deems it necessary to regulate, warn, and guide vehicular traffic on County
Roads and any intersections thereof, and it hereby authorizes and orders the posting of
such traffic control devices as shall be reasonably necessary to regulate, warn, and/or
guide traffic thereon for the safety of the general public and that said traffic control devices
shall conform to the Federal Manual on Uniform Traffic Control Devices.
cc:so(as),U.sp. tek, CSP
06/iq /2S
2025-1656
EG0024
Extension to Temporary Closure — County Road 29
Page 2
Be it further resolved that the Board of County Commissioners of Weld County,
Colorado, does declare and establish that County Road 29, between County Road 74
and State Highway 14, be, and hereby is, extended, with said extended closure being
from July 2, 2025, for approximately an additional three (3) weeks through July 25, 2025,
for unanticipated delays due to inclimate weather, and further, that standard official traffic
control devices shall be erected at said closure giving notice of the restrictions.
The Board of County Commissioners of Weld County, Colorado, approved the above
and foregoing Resolution, on motion duly made and seconded, by the following vote on
the 16th day of June, A.D., 2025:
Perry L. Buck, Chair: Aye
Scott K. James, Pro-Tem: Aye
Jason S. Maxey: Aye
Lynette Peppier: Aye
Kevin D. Ross: Aye
Approved as to Form:
Bruce Barker, County Attorney
Attest:
Esther E. Gesick, Clerk to the Board
2025-1656
EG0024
MEMORANDUM
TO: Clerk to the Board DATE: June 11, 2025
FROM: Amy Mutchie, Public Works Department
SUBJECT: BOCC Agenda Item
Weld County Public Works is requesting permission to extend the closure on WCR 29 between WCR 74
and SH 14 from the original end date of 7/2/2025 to 7/25/25 due to weather conditions. This road was
closed on 3/10/2025 for a culvert replacement and road construction.
See attached closure diagram.
2025-1656
EC1OUZ4I-
www.invanon.com
,. ,014:
T`N U/ 1
uk 3.0143
71
M4I-10
w
4
0
et
i S 4 -
anoi3a
anoi3a
i
1!(1O130
M4-103
r
DETOUR
M4-103
PROJECT # HRP-100
ROAD CLOSURE DESCRIPTION
i
WCR 29 between WCR 74 and SH 14
Closed 3/10/2025 thru 7/25/2025
for Culvert Replacement and Road Construction
NOTICE TO PUBLIC
Road signs and barricaded
Message boards to be used
DETOUR ROUTE
WCR 74 between
WCR 31 between
SH 14 between
WCR 29 and WCR 31 1 mile paved
WCR 74 and SH 14 4 miles paved
WCR 31 and WCR 29 1 mile paved
NOTES
ADT of WCR is: 1115/2023
Culvert Replacement and Road Construction
Prepared by: Ryan Reynolds
2/5/2025
Hello