HomeMy WebLinkAbout20242439.tiffRESOLUTION
RE: REGULATING, WARNING, AND GUIDING TRAFFIC DURING EXTENSION OF
TEMPORARY CLOSURE OF 83RD AVENUE BETWEEN WEST 4TH STREET AND
O STREET FOR APPROXIMATELY ONE (1) ADDITIONAL MONTH, FOR
UNANTICIPATED DELAYS DUE TO CONFLICT WITH EXISTING UTILITY LINE
WHEREAS, the Board of County Commissioners of Weld County, Colorado, pursuant to
Colorado statute and the Weld County Home Rule Charter, is vested with the authority of
administering the affairs of Weld County, Colorado, and
WHEREAS, pursuant to C.R.S. §42-4-106(6)(a):
"...local authorities, with their respective jurisdiction may, for the
purpose of road construction and maintenance, temporarily close to
through traffic or to all vehicular traffic any highway or portion
thereof for a period not to exceed a specified number of work days
for project completion and shall, in conjunction with any such road
closure establish appropriate detours or provide for an alternative
routing of the traffic affected...", and
WHEREAS, on the 19th day of June, 2024, pursuant to said statute and upon the basis
of traffic and personnel investigations, the Board determined that conditions exist which made it
necessary to temporarily close 83rd Avenue, between West 4th Street and 0 Street, to through
traffic and to regulate, warn and guide vehicular traffic by posting signs thereon, with said closure
being effective June 27, 2024, for approximately three (3) months, through September 20, 2024,
for the installation of an 18 -inch sewer main and a 16 -inch non -potable water line, and
WHEREAS, on the 16th day of September, 2024, pursuant to said statute and upon the
basis of traffic and personnel investigations, the Board has determined that conditions exist which
make it necessary to extend said temporary closure of 83rd Avenue, between West 4th Street
and 0 Street, with said extended closure being effective September 20, 2024, for approximately
one (1) additional month through October 18, 2024, for unanticipated delays due to a conflict with
an existing utility line, and further, that standard official traffic control devices shall be erected at
said closure giving notice of the restrictions.
NOW, THEREFORE, BE IT RESOLVED that the Board of County Commissioners of Weld
County, Colorado, deems it necessary to regulate, warn and guide vehicular traffic on County
roads and any intersections thereof, and it hereby authorizes and orders the posting of such traffic
control devices as shall be reasonably necessary to regulate, warn and/or guide traffic thereon
for the safety of the general public and that said traffic control devices shall conform to the Federal
Manual on Uniform Traffic Control Devices.
cc So(RAD 3rcx -ct,, CSP
oct /2o/2 -I
2024-2439
EG0024
EXTEND TEMPORARY CLOSURE - 83RD AVENUE
PAGE 2
BE IT FURTHER RESOLVED that the Board of County Commissioners of Weld County,
Colorado, does declare and establish that the closure of 83rd Avenue, between West 4th Street
and O Street, be, and hereby is, extended, with said extended closure being effective
September 20, 2024, for approximately one (1) additional month through October 18, 2024, for
unanticipated delays due to a conflict with an existing utility line, and further, that standard official
traffic control devices shall be erected at said closure giving notice of the restrictions.
The above and foregoing Resolution was, on motion duly made and seconded, adopted
by the following vote on the 16th day of September, A.D., 2024.
BOARD OF COUNTY COMMISSIONERS
WELD COUNTY, COLORADO
ATTEST:
Weld County Clerk to the
Board
Deputy Clerk to the Board
County orneyI
,
Date of signature: �I Z� Z`"'
EXCUSED
Kevin D. Ross, Chair
2024-2439
EG0024
MEMORANDUM
TO: Clerk to the Board DATE: September 10, 2024
FROM: Amy Mutchie, Public Works Department
SUBJECT: BOCC Agenda Item
Crow Creek Construction, on behalf of the City of Greeley, is requesting to extend the closure of 83`d Ave
between W. 4. St. and O St through 10/18/24 for installation of an 18" sanitary sewer main and a 16"
non -potable water line along 83`d Ave.
Conflict with an existing utility line has delayed construction.
Original closure approved from 06/27/2024 through 09/20/2024.
See attached closure diagram.
2024-2439
Cdcl/ 1 co
et.9OOa i
www.invanon.com
Hello