HomeMy WebLinkAbout20242532.tiffRESOLUTION
RE: APPROVE AGREEMENT FOR LOCAL GOVERNMENT LAND USE APPLICATION
FOR TIMELINE EXTENSION FOR USE BY SPECIAL REVIEW PERMIT, USR24-0014,
FOR 1041 MAJOR FACILITIES OF PUBLIC UTILITY OUTSIDE OF SUBDIVISIONS
AND HISTORIC TOWNSITES IN THE A (AGRICULTURAL) ZONE DISTRICT, AND
AUTHORIZE CHAIR TO SIGN - TAELOR SOLAR 1, LLC
WHEREAS, the Board of County Commissioners of Weld County, Colorado, pursuant to
Colorado statute and the Weld County Home Rule Charter, is vested with the authority of
administering the affairs of Weld County, Colorado, and
WHEREAS, the Board has been presented with an Agreement for Local Government
Land Use Application for Timeline Extension for Use by Special Review Permit, USR24-0014, for
1041 Major Facilities of Public Utility outside of subdivisions and historic townsites in the
A (Agricultural) Zone District between the County of Weld, State of Colorado, by and through the
Board of County Commissioners of Weld County, on behalf of the Department of Planning
Services, and Taelor Solar 1, LLC, commencing upon full execution of signatures with further
terms and conditions being as stated in said agreement, and
WHEREAS, after review, the Board deems it advisable to approve said agreement, a copy
of which is attached hereto and incorporated herein by reference.
NOW, THEREFORE, BE IT RESOLVED by the Board of County Commissioners of
Weld County, Colorado, that the Agreement for Local Government Land Use Application for
Timeline Extension for Use by Special Review Permit, USR24-0014, for 1041 Major Facilities of
Public Utility outside of subdivisions and historic townsites in the A (Agricultural) Zone District
between the County of Weld, State of Colorado, by and through the Board of County
Commissioners of Weld County, on behalf of the Department of Planning Services, and Taelor
Solar 1, LLC, be, and hereby is, approved.
BE IT FURTHER RESOLVED by the Board that the Chair be, and hereby is, authorized
to sign said agreement.
cc:PLCERMWDAic4),net (133/ ),CT8(E6/Hain)
09/26424
2024-2532
PL2910
AGREEMENT FOR LOCAL GOVERNMENT LAND USE APPLICATION FOR TIMELINE
EXTENSION FOR USE BY SPECIAL REVIEW PERMIT, USR24-0014, FOR 1041 MAJOR
FACILITIES OF PUBLIC UTILITY OUTSIDE OF SUBDIVISIONS AND HISTORIC TOWNSITES
IN THE A (AGRICULTURAL) ZONE DISTRICT - TAELOR SOLAR 1, LLC
PAGE 2
The above and foregoing Resolution was, on motion duly made and seconded, adopted
by the following vote on the 23rd day of September, A.D., 2024.
BOARD OF COUNTY COMMISSIONERS
WELD COUNTY, COLORADO
ATTEST: theitio jes&o:e.i
Weld County Clerk to the Board
BY:
cAtIcti-rvt . tOcln. w, cJc
Deputy Clerk to the Board
AP"•IEDA RM:
County A :rney Date of signature: aizttl 7
Kevin D. Ross, Chair
Ajl-Lej
Perry L. j ck, Pro-Tem
ike Freeman
. James
aine
2024-2532
PL2910
Docusign Envelope ID: 2119BA22-D4FC-4143-B3FC-2EFE706E2A99
LOCAL GOVERNMENT LAND USE APPLICATIONS
TIMELINE EXTENSION AGREEMENT BETWEEN
THE COUNTY OF WELD, COLORADO
AND
MAJOR FACILITIES OF A PUBLIC UTILITY 1041 PERMIT
September 3, 2024
INTRODUCTION
The County of Weld, Colorado (the "County") and Taelor Solar 1, LLC, a Delaware
limited liability company ("Taelor") (each individually a "Party," or collectively the "Parties")
hereby enter into this Timeline Extension Agreement (the "Agreement") effective as of
sep4embev 25 , 2024, to define the applicable deadlines for review and final
action by the County on MPP's Major Facilities of a Public Utility 1041 Permit application
(the "Application").
ARTICLE L
BACKGROUND
Section 1.01 Taelor intends to develop A Site Specific Development Plan and Use by
Special Review Permit for the construction of a 1041 Major Facility of a Public Utility, including
a Solar Energy Facility (SEF) (solar arrays) with a generating capacity up to 650 megawatt AC;
a Battery Energy Storage Facility planned for 650 MWh with a possible increase to up to 1,300
MWh; a substation (constructed and owned by the applicant) to interconnect the project to the
high voltage transmission system; an operations area, including an operations and maintenance
building, possible water storage, materials storage and parking; anon -site communication system
(communication lines); Meteorological Stations (approximately 15 high, on posts); up to seven
(7) construction trailers and ten (10) conex containers during construction and up to four (4) conex
containers, post -construction, for parts storage, outside of subdivisions and historic townsites in
the A (Agricultural) Zone District (the "Project") within the County's jurisdiction in
unincorporated Weld County.
Section 1.02 The Project is subject to approval by the County pursuant to the: Weld
County, Colorado, County Code (the "WC Code"), specifically Code Chapter 21, Article III,
Division 3, Permit Program for Site Selection and Construction of Major facility of a Public
Utility (the "1041 Regulations").
Section 1.03 The Application and the County's review of the same are subject to various
state statutes, including C.R.S. § 24-65.1-501(2)(a).
Section 1.04 C.R.S. § 24-65.1-501(2) requires local government to publish a hearing
notice for a 1041 application within 30 days after receipt of an application. The initial public
hearing, in turn, must take place between 30 and 60 days after publication of notice.
2024-2532
Docusign Envelope ID: 2119BA22-D4FC-4143-B3FC-2EFE706E2A99
Section 1.05 WC Code Section 21-2-260 also includes deadlines associated with 1041
applications. Specifically, upon the Department of Planning Services' determination that the
application is complete, it must (1) set a Planning Commission public hearing date that cannot
be more than thirty (30) days after the complete application is submitted; (2) provide certain
notices and post signs about the application and the public hearing at least ten (10) days prior
to the public hearing; (3) refer the application to referral agencies for comment with a
deadline to respond of twenty-eight (28) days; and (4) prepare staff comments for the
Planning Commission. After the Planning Commission public hearing and recommendation
on the 1041 application, the Board of County Commissioners must hold a public hearing on
the application within 45 days. That public hearing also requires certain notices at least 10
days prior. WC Code Section 21-2-310.
Section 1.06 As required by the WC Code, Taelor held a pre -application meeting with
the County on February 16, 2022, with a second meeting on January 9, 2024.
Section 1.07 Taelor submitted the Application for the Project on March 6, 2024
Section 1.08 Pursuant to WC Code Section 21-3-320, Taelor was required to submit the
Application and the County would have had to review within ten (10) days after the pre -
application meeting.
Section 1.09 Each of the County and Taelor desires to waive certain of the deadlines set
forth above to allow Taelor to comply a complete Application and allow the County a full and
fair opportunity to review and consider the Application.
Section 1.10 Accordingly, the Parties have come to an agreement to waive the deadlines
with respect to the Application.
Section 1.11 The County and Taelor mutually acknowledge that this Agreement is
supported by appropriate and adequate consideration.
ARTICLE II.
TERMS OF AGREEMENT
The Parties stipulate and agree to an alternative review and local government action
timeline as described below.
Section 2.01 Taelor hereby waives the deadlines set forth in C.R.S. § 24-65.1-501(2)(a)
and WC Code Section 21-2-260 requiring that the County to notify the public the Application
within thirty (30) days and requiring that the County schedule a hearing on the Application in
front of the Planning Commission within thirty (30) days after the Application is deemed
complete.
Section 2.02 The County hereby waives the deadline set forth in WC Code Section
21-3-320 requiring that Taelor submit the Application and the County would have had to
review within ten (10) days after the pre -application meeting.
2
Docusign Envelope ID: 2119BA22-D4FC-4143-B3FC-2EFE706E2A99
IN WITNESS WHEREOF, the Parties have caused this Agreement to be
executed and delivered as of the date set forth below.
Taelor Solar 1, LLC
a Delaware limited liability
,OtrlParl�osa by:
3444 NOV
AAA
eY
Date: 9/16/2024
Date: SEP 2 3 2024
Attest: dodetifeti v'
Weld County clerk of the Board
By:
Deputy Clerk of the Board
APPROYFD AS TO FP
By:
Name: ri n�dcDnugal__
Title: Deputy County Attorney
4
Title: VP of Business Development
COUNTY OF WELD, COLORADO
vin D. Ross
ir, Board of Weld County Commissioners
SEP 2 3 2024
SEP 2 3 2024
Date:
202 -753 Z.
Docusign Envelope ID: 21198A22-D4FC-4143-83FC-2EFE706E2A99
Section 2.03 Notwithstanding anything to the contrary in the WC Code, the Parties
propose the alternative schedule of deadlines for review of and final action on the application as
set forth in Attachment A attached hereto and incorporated herein.
Section 2.04 The Parties agree that this Agreement and the alternative review
and final action timeline set forth in Attachment A are reasonable.
ARTICLE III.
MISCELLANEOUS
Section 3.01 Other than the waiver of the Deadlines, by entering into this Agreement
neither party waives any rights or obligations contained within the WC Code applicable to
the Project.
Section 3.02 This Agreement shall not be binding on any future applications for
projects, by Taelor or a parent company or affiliate thereof or otherwise, within the County.
Section 3.03 The undersigned is authorized to enter into this Agreement on behalf of
Taelor and Taelor has full corporate power and authority to carry out its obligations
hereunder and consummate the transactions contemplated hereby. This Agreement has been
duly executed and delivered by Taelor, and constitutes a legal, valid, and binding obligation
of Taelor enforceable against Taelor in accordance with its terms.
/Signatures on the following page.]
3
ATTACHMENT A
Alternative Review and Final Local Government Action Timeline
Task
Deadline
Original application submitted.
March 6, 2024
Revised Applications submitted
April 24 and May 8., 2024
Referral agency comments due.
June 26, 2024
Staff Report and determination of completeness due
regarding the Revised Applications.
October 2, 2024
County to provide notice of the public hearing with the
Planning Commission on the 1041 Application and the
USR Application.
October 4, 2024
Public hearing with the Planning Commission on the
USR Application and 1041 Application.
October 15, 2024
Decision from Planning Commission on USR
Application (Final Action) and recommendation on the
1041 Permit Application.
Within ten (10) days of the public
hearing with the Planning Commission.
Provide notice of the public hearing with the Board of
County Commissions on the 1041 Application.
Not less than ten (10) days before public
hearing with the Board of County
Commissioners.
Public hearing with the Board of County
Commissioners on the 1041 Application
Within 45 Days of Planning Commission
Recommendation.
Decision from Board of County Commissioners on the
1041 Application (Final Action).
Within twenty one (21) days of the
Public Hearing with the Board of
County Commissioners.