Loading...
HomeMy WebLinkAbout972516.tiffTO: Board of County Commissioners 64; FROM: Lee D. Morri , ssistant Weld County Attorney DATE: July 21, 1997 Wcttine RE: Hirsch Dairy Conditions of Approval COLORADO The Board of County Commissioners approved the Hirsch Dairy USR # 1091 subject to conditions of approval. Conditions of Approval #'s2.A., 2.B., 2. C. and 2.D. are required to be reviewed and approved by the Board. The environmental health staff is of the opinion that the required plans have not been yet been completely formulated and neither the State or County Staff have been presented with final plans to review. The applicant is submitting a timeline which will provide for completion of the plans and review of those plans by the County Health Department by mid -September. Much of the construction consistent with those plans will have been completed by that date as well. The final decision is that of the Board of County Commissioners's and the staff is requesting authorization to schedule a hearing so that the Board can make the decision. The recommended action is that the staff be authorized to schedule a hearing for the Board of County Commissioners after September 15, 1997 at which time the Board will review the plans required to be submitted under the listed Conditions of Approval. George Baxter Dale Hall Connie Harbert Barb Kirkmeyer Bill Webster Agree Disagree Schedule Work Session xc:Planning, John Pickle, Environmental Health, Clerk to the Board (PL 1059) 972516 g EXHIBIT 1452 /aqi Atrit TO: Board of County Commissioners DATE: Sep,' ber 29,1997 FROM: Trevor Jiricek, Health Department • COLORADO SUBJECT: Hirsch Dairy, Recommendation for Condition of Approval #'s 2.A., 2.B, 2.C., and 2.D. of U.S.R. # 1091 MEMORANDUM dTB On Monday, September 29, 1997, our Department received an updated version of the Hirsch Dairy, Manure and Wastewater Management Plan (the Plan). The Plan is dated September 26, 1997. This version of the Plan was updated, from a "draft" plan submitted to the Department on Thursday, September 18, 1997, following a meeting with our Department, the Planning Department and representatives of the Hirsch Dairy. Condition of Approval #'s 2.A., 2.B, 2.C., and 2.D. of U.S.R. # 1091, required that a manure and wastewater management plan, dust abatement plan, fly control plan, and an odor abatement plan, be submitted to the Health Department for review and approval. The Plan includes all four of these elements. A recommendation for each specific plan follows: MANURE AND WASTEWATER MANAGEMENT PLAN: The Department recommends for approval of this plan with the following conditions: 1) Due to the minimal separation between groundwater and the retention pond liner observed near MW -1, the Department recommends that the Hirsch Dairy obtain a minimum of eight consecutive quarters of "groundwater elevation" readings in each of the three monitoring wells surrounding the retention structure. Following each four quarters of data accumulation, the Hirsch Dairy shall submit a report to the Health Department demonstrating the date of measurement, well number, top of casing elevation, depth to water, groundwater elevation, pond bottom elevation, and separation difference. In the event that these readings demonstrate that the groundwater elevation exceeds that of the base of the pond liner, the facility shall develop a mitigation plan to protect groundwater quality. The mitigation plan shall be developed and implemented (pending review and approval) within 30 days of determining that the groundwater elevation exceeds that of the base of the pond liner. The plan shall be submitted to both the Weld County Health Department and the Colorado Department of Public Health and Environment (CDPHE) for review and approval. Board of County Commissioners September 29, 1997 Page 2 DUST ABATEMENT PLAN: The Department recommends fo r approval as submitted. FLY ABATEMENT PLAN: The Department recommends for ODOR ABATEMENT PLAN: The Department recommends for tj\833 approval as submitted. approval as submitted. 97251.+6 Forrest Leaf, P.E. 13946 CR 56 Hillrose, CO 80733 (970) 590-1787 LEAF ENGINEERING November 10, 1997 Mr. Tom Hellerich, Esq. Doyle, Otis, Frey and Hellerich West Greeley Law Center 1812 56th Avenue Greeley, CO 80631 Re: Hirsch Dairy, USR 1091 (Amended Report) Dear Tom: This letter report amends my November 5, 1997 and will present my technical review of Paragon's Manure and Wastewater Management Plan for the Hirsch Dairy, submitted to the Weld County Commissioners on September 26, 1997. My review will follow the section numbers contained in the above referenced report. 1. Introduction Paragon alleges that since the USR 1091 application is pending, the Hirsch Dairy is in compliance with County regulations even though there are more then 960 animals on site, and have more than 960 animals on site since September 1995. 1.3 Site Geology and Hydrology Paragon states the Hirsch Daily does not overlay a designated aquifer. However, the purpose and intent of the Classification and Standards for Groundwater is to protect all groundwater of the state. All groundwater of the state is protected pursuant to the Statewide Standards. Specifically, 5 CCR 1002 Section 41.5(C)(6) addresses aquifers not classified as being protected by interim narrative standards or Table values 1-4 in the Classification and Standards regulation. The limited shallow aquifer in the Eaton area is not excepted. There are numerous domestic, stock and irrigation wells in the area that are receiving surface and subsurface water from the area of the Hirsch Dairy land, lagoon and irrigation system. Baseline groundwater quality samples collected in 1996 show that the concentration of nitrate -nitrogen in the alluvial aquifer underlaying Lind Farms, Inc, the Habrock Property and Town of Severance is 2.24 mg/1. LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality E:\LEAFLIND\Paragon Review Letter Report.wpd 97ti`.v, Paragon Report Review Page 2 2. Storm Water and Process Wastewater Management Paragon states that "Land application of liquid and solid wastes and off -site storage and use of solid manure is an important aspect of the waste -disposal process." However, the proposed plan does not explain how much and when this solid manure will be applied and how agronomic rates will be determined and tracked. In addition, the off -site storage of solid manure is not discussed. While CAFO may not require this explanation, there are requirements under the Weld County Zoning Ordinance Sections 45 and 47. 2.1 Storm Water Conveyance The applicant proposes, and has initiated construction of a retention pond east of the Smith Lateral and south of the employee housing. Paragon sized the retention pond to capture storm runoff from 17.6 acres above the Smith Lateral and hold 4.7 acre-feet. However, the drainage basin above the Smith Lateral is 31 acres with a total of 8 acre-feet of generated runoff at a peak discharge of 19 cfs for a 25 year, 24 -hour storm event. Paragon references a plan in Appendix A of their report. This plan is, at best, a concept plan for the retention pond. There are no detailed specifications pertaining to the sizing of the pond, in -situ compaction testing, erosion control structures, appurtenances, grading plan and or ditch sizing and alignment. In addition, Paragon does not state how this water will be handled. If this retention pond is to be evaporative, Section 4.8.3(C)(5)(b) requires that all "evaporative systems shall be designed to withstand a 10 -year period of maximum recorded rainfall". Table 1 shows a 2 year water budget on the 4.7 acre-foot capacity retention pond. As is evident from Table 1, the proposed size of the retention pond is not adequate to detain and evaporate precipitation and generated runoff over a two year period, let alone a ten year period. A March 17, 1997 letter to Victor Sainz from Terracon stated that a field technician would be on site during construction to conduct in -situ testing. My visit to the site and drive along the Smith Lateral on October 9, 1997 revealed that the retention pond was under construction but no in -situ testing was being conducted. In addition, soil conditions were dry, thus, compaction at 95 percent standard proctor would be highly unlikely. Section 2.4.4 of Paragon's report states that in -place density compaction testing will be performed during construction of the pond and ditch. Paragon does not address storm water runoff from the 147 acres irrigated with process water from the existing lagoon and proposed retention pond above the Smith Lateral. Review of the map prepared in Appendix A shows drainage flow paths from the 147 acres and a tail water pond located adjacent to Weld County Road (WCR) 23 approximately 1200 feet north of the intersection of WCR 78 and 23. My understanding of the CAFO regulations is that all facilities which come in contact with process wastewater must be designed to contain a 25 year, 24 -hour storm event and have a maximum permeability of 1 x 10'6 cm/sec. Paragon states that this facility LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality E:ILEAFLIND\Paragon Review Letter Report.wpd Paragon Report Review Page 3 is a "pass -through" facility. CAFO regulations do not define such a structure. In my opinion, this facility must meet the criteria set forth in CAFO Section 4.8.4. The size of the tail water pond is not discussed, nor is its specific design. Under CAFO, this pond, if it is to receive and hold process wastewater must be sized to hold generated runoff from a 25 year, 24 hour storm totaling 38 acre-feet. Enclosed is a letter of September 30, 1997, from Derald Lang from the Water Quality Control Division of the Colorado Department of Public Health responding to an inquiry by Mr. Jiricek (letter of September 24, 1997) regarding tail water ponds and their applicability to CAFO. Mr. Lang states section 4.8.5(A)(2) of the regulation is "intended to cover impacts to surface water quality from runoff due to flood irrigation practices." Furthermore, Mr. Lang's opinion is the applicant's proposed tail water pond does not pose a significant threat to groundwater quality based on the resident time of the process wastewater in the pond. Mr. Lang was not advised of the shallow depth -to -water, nor the proposed pass -through operation. I do not agree with Mr. Lang that there is "no significant threat" to groundwater or surface water quality from the retention of process wastewater or the overflow potential of process wastewater due to storm water runoff. The depth -to -water in this location is 5 - 6 feet, measured by Well #2 (see Figure 2), at current ground surface elevation. Excavation of this tail water pond will eliminate the separation distance between the bottom of the pond and the groundwater surface. Typical tail water reuse ponds are significantly deeper then 3 - 4 feet deep, which would be the depth of this pond if a minimum separation distance of 1 - 2 feet is to be maintained. Using Terracon's 30 inch per minute percolation rate (measured above the Smith Lateral in similar soil characteristics for employee housing septic/leach fields), process wastewater standing in the tail water pond for 12 hours will percolate 24 inches, thus reaching the groundwater. Given the separation distance from the bottom of the proposed tail water pond and existing groundwater, this pond should be lined in addition to being properly sized and constructed for containment of storm water runoff. However, the Weld County Zoning Ordinance also applies. Section 45.1.6 of the Weld County Zoning Ordinance requires that all drainage facilities or improvements shall be constructed to protect any adjacent river, streams or other bodies of water from pollution. Section 47.1.5 have the same requirement. As the proposed tail water pond is a drainage facility that will store process wastewater and must be designed to contain this process wastewater and contaminated storm water runoff under the above referenced sections of the Zoning Ordinance. 2.4 Retention Basins The existing lagoon has a capacity of 39.9 acre-feet with a free -board capacity of 29.9 acre-feet. I have observed the lagoon at, or near full (29.9 acre-feet and above) over the past 18 months. Paragon (formerly Terracon) conducted in -situ compaction tests and laboratory permeability tests at several locations in October 1996. Several of these tests failed, thus requiring further field compaction. Apparently 50 lineal feet of lagoon dam on the south side was re -compacted to meet LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality E:V.EAFILINDWaragon Review Letter Report.wpd 97251E Paragon Report Review Page 4 CAFO permeability criteria. However, these in -situ samples collected in October 1996 were around the perimeter of the lagoon since the lagoon was full of process wastewater. Paragon did not collect samples from the center of the lagoon since the lagoon was full of process wastewater. An April 30, 1997 letter to Victor Sainz from Terracon indicated that the northwest corner of the lagoon would be filled to increase the distance of the lagoon from existing homes. A March 17, 1997 letter to Mr. Sainz, Terracon indicated that a coffer dam would be installed to facilitate the draining, drying, in -situ testing and re -compaction of the west end of the pond. Neither of these activities was conducted. Based on my observations of the construction of the lagoon under saturated conditions, my water balance and Paragon's retesting, the lagoon still leaks and Paragon has not demonstrated that CAFO permeability criteria has been met or exceeded consistently throughout the lagoon. Subsequently, the lagoon is contaminating area groundwater. Process water from the lagoon will be used on 147 acres shown on Figure 3 of Paragon's September 26, 1997 report. Paragon estimated the daily and annual water collected by the existing lagoon from the dairy parlor, in addition to the Storm water runoff into the lagoon and proposed retention pond. Table 2 is my estimate of water utilization based on Paragon's water utilization study, and includes actual measured precipitation from the Eaton area (NCWCD weather station) and irrigation use from the lagoon reported by observant landowners, the Smith Lateral Ditch Rider and a June 12, 1997 letter from Mr. Jiricek, to myself, in which he stated that Mr. Rau informed him that no application from the lagoon process wastewater would occur until installation of the tail water pond. The tail water pond is not yet constructed. I calculated seepage from the lagoon based on inflow and outflow volumes discussed above. I estimate that 37 acre-feet of process wastewater has percolated into the underlying aquifer of the lagoon from September 1995 through September 1997. This volume compares with the allowable CAFO seepage rate of 1/32 inch per day, or 1.9 feet over the two years. This 1.9 feet allowable seep over a 4.1 acre lagoon surface is 7.7 acre-feet. Thus, I estimate that the lagoon has seeped over 400 percent of the allowable seepage volume pursuant to CAFO. Allowable seepage for this lagoon is in excess of the CAFO permissible seepage rate of 1/32 inch per day. Over the past two years, the allowable seepage total 1.9 feet. Assuming a 30 percent soil voids ratio, this total 1.9 feet of allowable seepage would fill the pore space in 6.33 feet of soil. Paragon's Table 4 shows the separation distance in MW -1 was 1.09 feet in September 1997. Thus, there is direct communication between lagoon seepage and the groundwater. Figure lA shows an illustration of allowable seepage and measured groundwater levels. Figure 1B shows the seepage and separation distance for the measured permeability of 9.6x10-° cm/sec reported by Terracon in November 1996 at location #5. Sections 45 and 47 of the Weld County Zoning Ordinance require that all drainage facilities or improvements shall be constructed to protect any adjacent river, streams or other bodies of water from pollution. The existing lagoon is a drainage facility that will store process wastewater and LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality EALEARLIND\Paragon Review Letter Report.wpd 97251.6 Paragon Report Review Page 5 storm water runoff and must be designed to contain this process wastewater and contaminated storm waterrunoff under the above referenced sections of the Zoning Ordinance. 2.4.5 Existing Retention Basin - Groundwater Monitoring Wells In February 1997, Paragon constructed three monitoring wells around the lagoon. Table 4 of Paragon's report summarizes depth -to -water samples from these wells from February 1997 to present. As can be seen from Table 4, depth -to -water measurements decrease over the summer and fall season. MW -1 on Table 4 shows the depth -to -water decreasing from 13.71 feet in the winter to 9.63 feet in the fall. The separation distance from the bottom of the lagoon to the top of the groundwater surface range from 5.16 feet to 1.08 feet in the fall. Clearly the water table increases due to irrigation return flows over the growing season. Regionally, the highest water table occurs in the late fall and early winter of each year. Paragon's report does not contain data during this time period. MW -3 is reported to be dry. However, a monitoring well drilled in October 1997, adjacent to WCR 78 located due south of the lagoon (Figure 2) was 20.8 feet to bedrock with a depth -to - water of 9.95 feet (10.85 feet of saturated alluvium). The applicants MW -3 is approximately 6 feet higher in elevation, at ground surface, then the Monitoring Well #1. If MW -3 is truly dry, then the well was not properly constructed. This well, in addition to two others, should be re - drilled. At a minimum, additional properly constructed wells should be located between MW -1 and MW -2 and at the southeast corner of the lagoon. A March 17, 1997 letter to Victor Sainz from Terracon indicated that water quality in addition to depth -to -water measurements would be collected. In a October 27, 1997 telephone discussion with Mr. Jiricek, he indicated there were no water quality sample results in the file. Given the nature of this operation and the request by the applicant to apply large amount of nutrients water, a comprehensive groundwater quality monitoring program should be required. The negative impact this operation is having on groundwater quality should be documented and tracked. Paragon did not install monitoring wells in the location of the proposed east retention pond or tail water pond adjacent to WCR 23. Nor did Paragon make any statements as to the depth -to -water at these locations. Monitoring Well #2, Figure 2, was installed near the location of the proposed tail water pond in mid -October and sampled. The depth -to -water was 5.25 feet below the ground surface. At a minimum, monitoring wells should be constructed in the area of the proposed east retention pond and tail water pond and depth -to -water measurements and water quality samples collected by the applicant on a bi-monthly frequency. LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality E:ILEARLIND\Paragon Review Letter Report.wpd 97251. Paragon Report Review Page 6 2.5 Process Water Use/Land Application Enclosed is a letter from Agronomist Randy Ray in which he concludes at proposed expanded animal numbers (2,000 milking cows) Mr. Hirsch needs 7 additional acres to apply lagoon effluent to avoid the over application of nutrients. In addition, the application of dry manure during the week of October 20, 1997 will result in over application of 15,722 pounds of nitrogen if the lagoon effluent is applied next season,. The constant over application of thy manure and lagoon effluent and leachate on the 147 acres the past several years results in a gross over loading of nitrates to the aquifer system underlying the Hirsch Dairy, Lind Farms, Inc., Mr. Habrock's property and the Town of Severance. This over application will result in the continued mineralization of nitrates for years, thus perpetuating loading of nitrates to the aquifer. The aquifer volume underlying Mr. Hirsch and Lind Farms, Inc. totals 446 acre-feet based on depth -to -water measurements from Monitoring Wells #2 and #3. A drain tile sample collected in November 1996 had a concentration of 7.59 mg/I nitrate -nitrogen. In October 1997, the drain tile had a concentration of 12.2 mg/1. A groundwater sample collected from Lind Farms, Inc. stock well, located approximately 200-300 feet west of the proposed tail water pond (Figure 2), had a concentration of 2.24 mg/1 nitrate -nitrogen in November 1996. For that same well in October 1997, the concentration was 4.86 mg/1. Table 3 demonstrates how nitrate concentrations increased from 2.24 mg/I to 4.86 mg/I in the aquifer under Lind Farms, Inc. The annual incremental nitrate increase is estimated by the loading to the aquifer from the over application of nutrients and the volume of water in the aquifer. The incremental increase correlates well with the observed increase in the Lind Farms, Inc. stock well. Mr. Hirsch, for the past several years has applied in excess of 25,700 pounds of nitrogen annually. This over application resulted in aquifer loading and an increase in aquifer concentrations from 7.59 mg/I in 1996 to 12.2 mg/I in 1997, This violates 5 CCR 1002-41.5(C)(6). The volume of water underlying Hirsch's 147 acres is 221 acre-feet at a saturated thickness of 5 feet (see Figure 2). The loading of 25,700 pounds annually of nitrogen to this 221 acre-feet results in a concentration of 7.59 mg/1. This 7.59 mg/I in 221 acre-feet of groundwater volume equates to 4,746 pounds of nitrate -nitrogen (essentially, 221 acre-feet of water having 4,746 pounds of nitrate will have a concentration of 7.59 mg/I nitrate - nitrogen). Thus, there appears to be a 5 to 1 nitrogen leaching to aquifer response ratio (25,700/4,746). Table 3 below demonstrates how this continued over loading of nitrogen to the aquifer will increase nitrate concentrations in the aquifer underlying Lind Farms, Inc., Habrock's Property and the Town of Severance. This increase in nitrate concentrations has been observed by a noted increase in the aquifer concentration (as measured in the Lind Farms, Inc. stock well). In November 1996, the concentration of the aquifer was 2.24 mg/1. In November 1997, the concentration increased to 4.86 mg/1. Table 3 includes a 48,226 pound increase of nitrate contained in the 37 acre-feet of lagoon leachate which occurred during September 1996 to September 1997 (Table 2). LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality E:\LEAFILIND\Paragon Review Letter Report.wpd 9'7251.F Paragon Report Review Page 7 Table 4 contains a summary of groundwater quality samples collected over the past several years which show increases in groundwater nitrate concentrations. Drain tile samples represent subsurface water underlaying the Hirsch property. This water is collected via a perforated drain tile located under the Hirsch property. The proposed Hirsch Dairy (1) is a much to intensive use on the number of acres owned by the applicant, and (2) has polluted, and continues to pollute shallow groundwater underlaying surrounding land owners from the existing lagoon, the over application of process wastewater and solid manure and improper containment of storm water runoff contaminated with manure. In addition, the current activity is in violation of the interim narrative standards for groundwater contained in 5 CCR 1002-41 Section 41.5. Continued overloading of the aquifer will result in degradation of aquifer water quality and will result in conditions that will render the aquifer useless for domestic, livestock and irrigation purposes. Past activities and approved future activities will have a dramatic negative impact on the environment, health and welfare of the community. Sincerely, Forrest Leaf, P.E. Enclosures cc: Ken Lind LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality E:\LEAF\LIND\Paragon Review Letter Report.wpd 97251.6 lagoon water balance2.123 u 02) C 0 61 col aE un t. 00 %./D 00 ‘D ch V D\ er D\ .-r \D v) t. \D M of et eun O et Ch D\ D\ et N O O O O het h et eel- min et M M M M M 0 et O N vi vi vt h v1 h n n Mr 00 vi l-: O O O C O O C M vi of ri [V N N M M M M M M M M M 7 el- v) vl et C\ n N M .vr N00 O O et D\ eh N M VD .fir �Nr CO O O er M 0 0 0 0 0 0 _ N N 0 0 0 0 0 0 N N O O O O C O C C O O O O C O O C C C C O O C O O C M '. h D\ h O 01 M N eF4n.. M v1 D\ v7 O D\ M N et et O N 0 0 0 O N N N M M N O O O O N N N M M N k _ O O O O O O O C O C O 0 0 0 0 0 0 0 0 0 0 0 0 0 0 R Pr 1/40 N N 'r 00 M wn h D1 N N O M N N l- M M et v1 et en eV t? 0 0 0 0 0 v1 O N O N N O O O O O O O CO CO M O 00 O In v) C O O O O N O vzt v1 M O C O O C O N 7 OG C O N VD 00 n 00 et 00 D\ N O v1 en n D\ n O M 00 O �D O O ..� et N M 'r M .ter �-r V) 00 N N O er M M O h m et M 00 (� N vl 00 In N O O C O O ^-� O N N M �--� .r 0 0 0000.-4 t r Sri O M C a a a a a a a a a a a a a a M a a a a a r - a a Oz°Q w C sdv10ZAtiw e'er ° o ,f) �C�titi�v� 0 L F S o4 2 m '$ 3 iv a a 10 M 4i O r 0) 0 O 97251 C v L 00 t� O O O O O O O O O O m o w w ., O C ,n b ,n O I Q w O O O O O O O O O O O w O 0 O• _ Q 0_ ... r O1 0 m P N 0666666666406 666 m In O w N In N O O, O m 0 0 0 0 0 0 0 0 0 0 0 0 0 D, P P P P D` T a P 4• 4• N N 10 T O 4 Q .� N 6 P U P 0 P 6 U P T U T 'n ^ N N N N N N N N N N N N N N N N N M y NQ ON 66 000 000 in in 0 '1.'1- 00 M MO O 80 n 00 N CC O Q N ^' M m N O O O h N b N N N O N 1O N 0 O� Q w 0 ON 'O O -� O O N N b M 10 M N O N O N N N N M 1O 060666600666666066 M o N 0 w_ N w Q w 01 N O vn O1 M 1O O m w O 0 N 0 --� m M 0 v1 w N N Q m M O m m n V1 w M N N O O O O O- O N M '+ 0 0 0 0 0 0 0 o (r� O Nj p M NQ ^ 0 N M NN00gWm00 M N N b O N M Nm 00 M M NN 0 0 0 0 0 0 0^ O-+ •0 •0 0 0 0 0 0 -• O• --t ^• -s O• u v d L i Q0^ m m 0 0 O m N 0 m M .r 0 0 0 O M N Q ”0 N -� O O O O N N N M M N ^ O O O O N N N M M N Oy 6666666666666666666606666 W 04 O v 3 zPe ^ N O Q Q O M O to 0 10 O b Q N 0 D` ym h r` N N N N •-. N N v1 h h b M Q Q N M M Q Q Q m m Na r m o 0 Q O� W 0 0W M 0 b b- � O$� N N VQi m r N O M a m P w 00 w N v1 w M OQ M M M Q M M M 0 0 0 C Q Q Q Q 'V Q C Q Q Q Q Q Q 10 Q M M 1O m N C 0^ y1 w v1 O O O O CO 0 00 N w N N w m `O C C 'n m O N M m of C O O O O M M Q P a\ N N m 0 0 0 C C C C b w w w w w w w w w N N N N N N N N N a Q Q w a P P T o O1 b b V b 1O 1D o N n h n g q T Q Q 01 g 1 Q Q 01 Q O\ P Cl- OzA7.O1dL 3 eS0 `{i m u a am 3 p C' d 5 W �'dti�''>^�drA' a N m N O N rn 0 9'7251 lagoon water balance2.123 Table 3 Hirsch Dairy USR 1091 ial Aquifer Loading Nitrogen Land Application Incremental Cummluative Nitrate Nitrate Nitrate Nitrate Year Loading Recieved * Increase Increase (lbs) (lbs) (mg/i) 0118/1) 1996 2.24 1997 15700 3140 2.59 4.83 1998 73926 14785 12.19 17.02 1999 73926 14785 12.19 29.22 2000 73926 14785 12.19 41.41 2001 73926 14785 12.19 53.61 2002 73926 14785 12.19 65.80 2003 73926 14785 12.19 78.00 * Based on 5 to 1 reduction from root zone leaching to aquifer 11/07/97,07:44:34 AM Aquifer Leach Table.123 97251.8 Table 4 Summary of Groundwater Quality Sample Nitrate Depth Location Date (mg/1) (feet) MW#1 10/30/97 8.47 9.95 MW#2 10/30/97 9.36 5.25 MW#3 10/30/97 9.88 3.00 Drain Tile 10/06/96 7.59 Drain Tile 10/30/97 12.20 Stock Well 10/06/96 2.24 Stock Well 10/30/97 4.86 11/06/97,02:17:49 PM water quality summary table.123 97251P W w H '"A0 si 0 O1 la woo x� I L C a) E 0 73 N as is L m t (Oh — F 97251.g a� co mai '-' ad is A O Di 14 94 O x� I I a� as s Cn 9'7?'� 15 22 :99/ J�14969 _• 4`25 940 !New Windsor Oil Hold 4936 494/ 14 Well I mkt 18 P - STUDY .t fj� 986 �r�-� • �� 5002 _ It It Nik4narnMalt4 to jKsu, s 4956 - 5025 4936 4949 US (O3.1 t_tra 1.LGI,SASgi G _ Rou(a rd f X4904 5 =_ 4900; 3b ti9Pl.. I I Ce 7 G a „. �8• 4904 a CD 0 gn 'o YSeverance l• (I) Baldridge Lake 851 Schneider Lake Angel 4893 • 4,0 c 0 4900 972516 WELD COUNTY HEALTH DEPT 19703564966 P.01 i OCT-27-1997 1.5:19 Posl-ir Fax Note re 4c' Lfq Co 7671 Phojte I#ot pages From 'PPM �i�l(/k! Co. Date 'Phone # Fax 330— LIM Fax # September 24, 1997 )EPARTMENT OF HEALTH 1517 16TH AVENUE COURT GREELEY, CO 80631 ADMINISTRATION (970) 353-0586 HEALTH PROTECTION (970) 353-0635 COMMUNITY HEALTH (970) 353-0639 FAX (970) 356-4966 Derald Lang Water Quality Control Division Colorado Department of Public Health and Enviro 4300 Cherry Creek Drive South Denver, Colorado 80222-1530 Dear Derald: As you are aware, our County Commissioners have Hirsch Dairy, manure and waste water management with the Confined Animal Feeding Operation Conti However, due to a "gray area" in the CAFO Regula complete our review. Specifically, it is not apparel would capture and temporarily store process waste methods, are required to be lined. Due to this "gray area" we are requesting that your taff provide an interpretation in regard to this requirement. As you know, Section .8.4 of the CAFO Regulations requires that retention structures constructed after ugust 30, 1992, have evidence that a liner has been constructed and meets a specified p eability. However, it does not indicate if tailwater ponds must be lined. ent requested that our staff review the plan (the Hirsch Plan) for compliance Si Regulations (5 CCR 1002-81). ions we are finding it difficult to whether tailwater ponds which water, applied through flood irrigation The Hirsch Plan is proposing an unlined tailwater ond. This pond will capture and temporarily hold process waste water which has ben land applied through flood irrigation practices. According to the Hirsch Plan, y captured process waste water will be imnjediately pumped back into the facility's prirpary retention structure. I am in receipt of a letter dated December 20, 1996, to Victor Sainz from Dave Rau and Brick Smith of Terracon Environmental, Inc, which is a summary of a meeting in which you attended. This letter indicates that tailwater ponds are not required to meet lining requirements. The letter indicates that you have received a copy of this letter. However, subsequent conversations with you lead me to believe that evidence of a liner is required by the CAFO Regulations. 9'72`-,'! ! OCT-27-1997 15:19 WELD COUNTY HEALTH DEPT 19703564966 P.02 1i t Derald Lang! Water Quality Control Division September 24, 1997 Page 2 It is apparent that there is not a consensus on the inte CAFO Regulations and that additional review of this scheduled to present our review to our County Co 1997. Therefore, we would request that your written Tuesday,) September 30, 1997. We trulyappreciate your assistance in this matter. I not hesitate to call me at (970) 353-0635, extension: Sincerely, Trevor Jiricek Supervisor Environmental Protection Services tj1830 cc: John Pickle, Weld County Health Department Dave Holm, Water Quality Control Division Lee orrison, Weld County Attorneys Office Dav Rau, Paragon Consulting Group Viet r Sainz, Water Quality Control Division gpretation of this portion of the hem is warranted. We are iissioners on Wednesday, October 1, interpretation be faxed to us by you have any questions, please do 232. 972:71 F OCT-27-1997 15:20 WELD COUNTY HEALTH DEPT 19703564966 P.03 STAT OF COLORADO Roy Romer, Governor Pas) Shwayder, Executive Director Dedicated to protecting and improving the health and environment of the people of 430 OS+e yt"te'1A. S. tabonion and Radiation seMes Div.. n I Denver, Cddoaraaddoo 802 6-1530 8100 Lowry Blvd. i Phone (303) 692-2000 Denver CO 80220.6928 Located M Glendale, Colorado (3031692.3090 I hap://www.cdphestafr.caus PP a September 30, 1997 Weld County Health Department 1517 16th Avenue Court Greeley,i CO 80631 Attn: Trevor Jiricek Re: CAFO Regulations Question on Tai -' Dear Trevor: This letter is in response to your wherein lyou requested an interprets concerning the need to seal tatiwat statingthat this is a somewhat "gr CAFO regulations. Understanding;the d will hopefully aid in applying the r The section of the regulation (; tailwater ponds installation is in surface I water quality from rUn-of practices. Thus, the need to seal when the regulation was developed for common practice with flood irritati land application disposal plan incorp of a cited loop system; then the pot quality 'would need to considered. From the description in the Hirsch P potential for groundwater quality i that the resident time of any proces is minimal. Under this situation I this tailwater pond because the poi other t ilwater ponds in use with fld surrounding area. foredo ColoradoPubricitem of and Environment ,57757575-71 144( � water Ponds. etter of September 24, 1997 on of the CAFO regulations ponds. You are right in y area" in interrupting the velopment of the regulations lation to the Hirsch Plan. 1.5(A)(2)) which addresses fended to cover impacts to due to flood irrigation ese ponds was not an issue he use of tailwater ponds is However, should a feedlot rate a tailwater pond as part ntial impacts to groundwater an it would appear that the pacts will be very small in water in the tailwater pond ould not see a need to seal antial impact is not unlike d irrigation practiced in the 9r7a r1 gq OCT-27-1997 15:20 WELD COUNTY HERLTH DEPT 19703564966 P.04 question Should you have any further ,3561. .Sincerely, all'tinge PE please call me at 303/692 - cc: Johh Pickle, Weld County H alth apartment Dave Rau, Paragon Consulting Gro,p Dave Holm, WQCD Victor Sainz, WQCD 972516, Hirsch Dairy Nitrogen Balance Prepared by Randy W. Ray, Agronomist Forrest Leaf, P.E. Leaf Engineering Route 1, Box 75 Merino, CO 80741 Forrest: October 28, 1997 I have reviewed the nutrient management plan for the Hirsch Dairy near Severance, CO. Based on my knowledge and expertise in nutrient management plans and overall water quality monitoring, I have made some conclusions regarding the report preformed by Paragon Consulting Group. Below is a table (Table 1) containing information for the effluent application at the Hirsch Dairy. Table 1. Hirsch Dairy Effluent Balance Current Facility (766 Milking Cows) Total Nitrogen Net Crop Acres Req. Additional Water Content Nitrogen Nitrogen Agronomic Acres for Volume Effluent Load Demand Rate Application (gal) (Ibs) (lbs) (lbs/acl (ac) (ac) 4,598,674 18,395 11,957 154 77.64 68.56 Hirsch Dairy Effluent Balance Proposed Facility (1,380 Milking Cows) Total Nitrogen Net Crop Acres Req. Additional Water Content Nitrogen Nitrogen Agronomic Acres for Volume Effluent Load Demand Rate Application (gall (Ibs) (Ibs) (Ibs/ac) (ac) (ac) 9,096,193 36,385 23,650 154 153.57 7.37 972516 Page 2 Table 1 indicates that only 78 acres are required for application of effluent and runoff nutrients from the current dairy. This will allow the Hirsch Dairy to apply dry manure to the additional 68 acres. This additional application of dry manure must be closely monitored to prevent over application of nitrogen. Considering the proposed expansion of the dairy, Hirsch Dairy is going to need additional acres to apply this effluent. From calculations, an additional 7 acres is needed to keep the nitrogen application at or under agronomic rates. There will be an annual variation in precipitation runoff volumes, but not a dramatic change in net nitrogen load since the majority of the water in the lagoon consists of dairy process water. The nutrient value for the calculations were taken from the BMP's for Agriculture, published by Colorado State University. A value of 4 Ibs/1000 gallons of nitrogen was used in this table. I was advised that on the week of October 20, Hirsch Dairy applied feedlot manure to the 146 acres. I am assuming a typical application rate of 20 ton per acre, and using the BMP Guide for nutrient content. Table 2 shows the effects on the nutrient balance with consideration of the effluent applied as irrigation water. Table 2. Manure Application and the Effect on Effluent Application Hirsch Dairy Current Facility Effluent Application Nitrogen Nitrogen Nitrogen Net Excess Rate Content Content Allowable Nitrogen Nitrogen (T/acl (Ibs/Tl fibs) _ I (Ibs) (Ibs) 20 9 26,280 22,515 11,957 15,722 972516 Page 3 Manure Application and the Effect on Effluent Application Hirsch Dairy Proposed Facility Effluent Application Nitrogen Nitrogen Nitrogen Net Excess Rate Content Content Allowable Nitrogen Nitrogen Mara QUM (Ibs1 (Ibs)(Ibs) fibs) 20 9 26,280 22,515 23,650 27,415 The concern is evident in Table 2. The Hirsch lagoon is currently nearly full of effluent, and the dry manure applied this fall already exceeds crop nutrient demand, without including possible soil nitrogen contents, and additional irrigation water (Smith Lateral) nutrient content. From my calculations, Hirsch Dairy will exceed agronomic nitrogen application rates for the 1998 growing season (15,722 Ibs), under current conditions (766 milking cows). The proposed facility will have a huge effect on the nitrogen balance if dry manure is applied to all 146 acres. The over application of nitrogen will be 27,415 Ibs, nearly doubling the effect on the current facility. Another concern is the constant application of organic nitrogen, which will continue to mineralize in the soil over a period of several years. As an example, only 30% of the first year applied organic nitrogen will be mineralized. This leads to a building effect where the mineralized nitrogen builds to a point where little or no effluent or dry manure can be applied and maintain agronomic application rates. Phosphorus and other minerals may be of concern at this site where a large concentration of animals are located. 9'725'.6 ti t LO —o � LC3 '5 2 k ca ok! $/®§J / c To >< {� up 0 OD CO LO CN I/]) 22 #f 22 i$/ ai )/\5 Cr a]/ Z eft — 2;2 }§§* 7] § co gu/\ I- J in x c w To Rig to C ( /� CO ) /§ S E o 7 '- > ) ( Q2E Z 0ru > co( 0 a) e -o C 0. \k ca tv) OS 1.0 \ { CO 0 J/ i§ Z/�k \� �� rt) -®,� LO fl ! !7]) \CD co a 2 OR Z "2 ID niiT /el k �3/e o. A 03 /co w 11 ]7 { 03 r {§ e$( in z 03 lx > @ ( co § co § ) z k 0_2 > Dry Feedlot Manure Applied @20 T/acre 10/21-10/23 97231.5 Forrest Leaf, P.E. 13946 CR 56 Hillrose, CO 80733 (970) 590-1787 LEAF ENGINEERING November 10, 1997 Mr. Tom Hellerich, Esq. Doyle, Otis, Frey and Hellerich West Greeley Law Center 1812 56th Avenue Greeley, CO 80631 Re: Hirsch Dairy, USR 1091 Dear Tom: Enclosed is a supplement to my analysis of the Hirsch Dairy Use By Special Review (USR) 1091 currently pending before Weld County. Please note that I revised this letter report to reflect an error I made in my estimate of 4,823 pounds of nitrogen lagoon leachate which should have been 48,226 pounds of nitrogen lagoon leachate. This letter report is my review of the applicant's Manure and Wastewater Management Plan prepared by the applicant's consultant Paragon on September 26, 1997. In my review I noted numerous inconsistences with the applicant's plan and non-compliance with the Confined Animal Feeding Operations Control Regulation (CAFO) 5 CCR 1002-19 and Weld County Zoning Ordinance Sections 45 and 47. In particular, I found that the current dairy operation is polluting area shallow groundwater. Table 1, enclosed, shows my prediction of how shallow alluvial groundwater is being loaded with nitrate -nitrogen, which I correlated directly to current over application of manure process wastewater and dry manure and lagoon leachate on 147 acres owed by the Hirsch Dairy and is subject to the pending USR 1091. The predicted increase in nitrate -nitrogen was developed from nitrate samples collected from a drain tile underlaying and draining subsurface water under the 147 acres. In November 1996, nitrate concentrations from the drain tile were 7.59 mg/1 nitrate - nitrogen. This 7.59 mg/1 nitrate is representative of the nitrate concentration of 221 acre-feet of groundwater underlaying the 147 acres. I estimated that in 1996 the applicant over applied 15,700 pounds of nitrogen from the land application of process wastewater and dry manure. This over application resulted in an observed aquifer response of 7.59 mg/1 nitrate -nitrogen. Over the 1997 growing season I estimated that there was an over application of 25,700 pounds of nitrogen from the land application of process wastewater and dry manure. In addition, the lagoon had LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality E:\LEAFLIND\Nitrate Loading Lettetwpd Hirsch Dairy Pollution Page 2 seepage of 37 acre-feet resulting in 48,000 pounds of nitrogen leached directly into the aquifer (4 pounds nitrogen per 1000 process wastewater). Drain tile samples collected in October 1997 contained 12.2 mg/I nitrate -nitrogen. Continued loading of nitrogen into the aquifer underlaying the 147 acres will result in dramatic increases nitrate concentrations, as shown in Table 1. This shallow aquifer primarily exists from the deep percolation from the 147 acres. Annually, the percolation is drained completely from the aquifer underlaying the Hirsch 147, resulting in a virtually dry aquifer over part of the year. Thus, measured nitrate concentrations via the drain tile underlaying the Hirsch 147 provides a direct measurement of the aquifer response to this nitrogen over loading. The groundwater underlaying the Hirsch property drains into an aquifer that stores groundwater year around. This aquifer has been defined from the installation of irrigation, stock and domestic wells located in a line as shown on Figure 2 of my letter report. This aquifer receives all of the groundwater underflow from the Hirsch property. A stock well, as shown on Figure 2 of my letter report, sampled in November of 1996 had a nitrate concentration of 2.24 mg/I. Samples collected in October 1997 show a concentration of 4.86 mg/I nitrate -nitrogen, as shown in Table 2. The location of this stock well is such that it receives all of the groundwater underfiow from the Hirsch Dairy, thus the noted increase in nitrate concentrations. As shown in Table 1, estimated nitrate concentrations will continue to increase over the next 5 years resulting in concentrations well above Table Values contained in 5 CCR 1002-41. While this aquifer is not specifically classified, it is protected pursuant to 5 CCR 1002-41.6.C.b., Interim Narrative Standards and is subject to protection at the 2.24 mg/I interim standard. Finally, this activity is in violation of Weld County Zoning Ordinance Sections 45 and 47 because (1) the east retention pond has not been adequately designed and constructed to contain process wastewater and storm water runoff required, (2) the existing lagoon exceeds the CAFO allowable seepage rate and is polluting area groundwater, (3) the proposed tail water pond has not been designed to meet CAFO criteria for storm water runoff detention and seepage requirements, (4) land application of nutrients are being grossly over applied and will continue to be grossly over applied (based on the applicants disregard of his consultants recommendations and County and State requirements) and is polluting area groundwater and (5) the December 16, 1997 Resolutions and Conditions of Approval, page 3, ¶ 2. (A) 1. and 2. LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality EALEARLDIDNitraia Loading Ltttar.wpd 372515 Hirsch Dairy Pollution Page 3 The ongoing activities are violations of CAFO in that this is not a "no -discharge" facility, thus the appropriate groundwater discharge permits must be applied for the lagoon seepage and resulting seep for the east retention pond. Sincerely, Enclosures cc: Ken Lind Forrest Leaf, P.E. LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality E:\LEAFILINDwitrate Loading Letter.wpd 372: 1 Table 1 Hirsch Dairy USR 1091 ial Aquifer Loading Nitrogen Land Application Incremental Cummluative Nitrate Nitrate Nitrate Nitrate Year Loading Recieved * Increase Increase (Ibs) (lbs) (mg/I) (mgn) 1996 2.24 1997 15700 3140 2.59 4.83 1998 73926 14785 12.19 17.02 1999 73926 14785 12.19 29.22 2000 73926 14785 12.19 41.41 2001 73926 14785 12.19 53.61 2002 73926 14785 12.19 65.80 2003 73926 14785 . 12.19 78.00 * Based on 5 to 1 reduction from root zone leaching to aquifer 11/07/97,07:54:55 AM Aquifer Leach Table.123 972516 Table 2 Summary of Groundwater Quality Sample Nitrate Depth Location Date (mg/1) (feet) MW#1 10/30/97 8.47 9.95 MW/42 10/30/97 9.36 5.25 MW#3 10/30/97 9.88 3.00 Drain Tile 10/06/96 7.59 Drain Tile 10/30/97 12.20 Stock Well 10/06/96 2.24 Stock Well 10/30/97 4.86 11/07/97,07:55:17 AM water quality summary table.123 9721.6 QUESTIONS FOR TODD AND STAFF 1. In comparing the 1996 Plan as submitted by the applicant, which formed the foundation for the approval by the Board of County Commissioners at the hearing in December of 1996, as compared to the Plan now submitted, and in particular, the manure and wastewater management plan prepared by Paragon, are there significant differences, to require a new hearing and notice to all agencies? In particular, major changes in the plans include; 1) the removal and offsite storage of the manure piles, 2) the increased traffic created by the trucking of the manure, 3) the new lagoon which was not in the original plan submitted, and the fact that it is now on the property line, and is within 300 feet of the Cabala's residence, and is even closer to the Town of Severance, 4) and the application of the effluent now is by surface application as opposed to the sprinkler application. Has the staff, considering all of these major changes, conducted an investigation of the impact on the compatibility with the Town and the neighbors and with existing users, pursuant to 24.4.3 of the Zoning Ordinance, is it compatible with the future development, pursuant to 24.4.2.4 considering the Town of Severance now lies across Road 78 from the Dairy, and has the staff re-evaluated the affect on the health, safety and welfare of the residence, pursuant to 24.4.2.7? 372:51 QUESTIONS FOR TREVOR AND THE HEALTH DEPARTMENT: Has the Weld County Health Department approved a manure handling and disposal plan, pursuant to 45.1.2? Has the Weld County Health Department approved a method for scraping, grading and cleaning for the site pursuant to 45.1.5 and 47.1.4? Has the Weld County Health Department approved the drainage facilities and plans to protect adjacent bodies of water from pollution, pursuant to 45.1.6 and pursuant to the Resolution adopted by the Board of County Commissioners? Has the Weld County Health Department provided for the protection of adjacent bodies of water from pollution, pursuant to 47.1.5 and consistent with the Resolution adopted by the Board of County Commissioners? Has the Weld County Health Department approved the manure storage sites to determine they have a water -tight surface to prohibit seepage or percolation of manure pollutants into the ground, pursuant to 47.1.1 and the prior Resolution adopted by the Board of County Commissioners? 6. Has the Weld County Health Department approved the feedbunks, water tanks, feeding tanks, feeding devices and aprons, pursuant to 47.1.3 and the prior Resolution of the Board of County Commissioners? 7. Considering there is no detail submitted by the applicant, what is the sizing of the tailwater pond, including the depth, and the depth to groundwater for the tailwater pond as projected to be installed? What is the depth to groundwater of the new lagoon submitted in the new proposal? What protections have been made to assure that the groundwater is not being and will not be contaminated? What sizing of the tailwater pond is necessary to hold runoff when irrigation effluent is being applied? 10. Has the tailwater pond been adequately sized to provide for containing runoff water, and in particular, has the tailwater pond been sized to retain the runoff water should a rain storm happen during the time the effluent is being applied? 11. There is no provisions in the manure and wastewater management plan which provides for manure storage in summer and winter months. Where is this going to be stored? Who will be storing it? Will this be on impermeable pads? Has this been approved by the Weld County 972r1 Health Department pursuant to 47.1.1 and the prior Resolution of the Board of County Commissioners. 12. Section 31.2 provides that in the uses allowed by right in the A District, uses within the A District shall be subject to the additional requirements contained in Section 40, Supplemental District Regulations and Section 50 Overlay Districts. 13. The plan states that ditches have been constructed along the north and west sides of the property of the applicant, to capture and deliver the tailwaters to the tailwater pond. In actuality no such ditches have been constructed, nor do they exist. Has the County approved such a plan, and if so, what is the deadline for installation of the ditches? 14. The Dairy has been in violation of the number of animal units since September of 1996, and discharge has occurred from the facility. What protections have been established pursuant to Sections 45 and 47 to avoid pollution of the water and to preserve the water quality? 15. The plan, as submitted, stated that testing of the new lagoon area, and the ditches and storage areas would occur. No information has been provided, however, as to any such testing, or whether such testing, in fact, occurred. For the existing lagoon, the original proposed lagoon, monitoring wells have been spaced too far apart. Additional monitoring wells should be required, and water samples to test the quality of the water should be required, pursuant to 47.1.7. ;3'1^. .4. Forrest Leaf, P.E. 13946 CR 56 Hillrose, CO 80733 (970) 590-1787 LEAF ENGINEERING Mr. John Pickle, Director Environmental Protection Services Weld County Health Department 1517 15 Avenue Court Greeley, CO 80631 RE: Hirsch Dairy, USR 1091 Dear John: November 10, 1997 As you are probably aware, I represent landowners adjacent to the Hirsch Dairy. On November 5, 1997 in a hearing before the County Commissioners, your staff recommended approval of the above referenced USR. Furthermore, your staff indicated that the applicant's plan was technically sound and thus met all applicable CAFO regulations and Weld County Zoning Ordinance Sections 45 and 47. You are also not doubt aware, that I have taken strong issue with your staffs evaluation and recommendation. Of particular concern is the proposed east lagoon or retention pond, which is actually constructed in a location other then indicated in the applicant's September 26, 1997 report. I personally observed construction of this pond and it is my opinion that it is a violation of CAFO and Weld County Zoning Ordinance Sections 45 and 47. The applicant's consultant indicted in the September 26, 1997 Manure and Wastewater Management Report, that in -situ sampling would be conducted with respect to compaction and permeability testing. On November 5, 1997 neither the applicant nor your staff indicated that this had been accomplished. Appendix D of the September 26, 1997 report contains boring logs from various locations above the Smith Lateral. It is important to note that all of these logs were at depths less then 5 feet, with exception of log #7 were groundwater was noted at 11.5 feet. Also, boring log #2 did was at a depth of 5 feet with no accompanying falling head permeability tests (Appendix E). Thus, this lagoon was placed in a location were soil characteristics were unknown by Paragon, the State, your staff and Mr. Hirsch. This lagoon has already been constructed and was excavated to a depth which may have exposed groundwater, as shown in copies of photographs taken by Mr. Cabala on November 6, 1997, LEAF ENGINEERQ G Hydrology ° Hydraulics ° Water Resources ° Water Quality E:ILEARLIND1Pi°kl° lagoon lata.wpd 9'7251.6 Pickle Letter Page 2 from Mr. Cabala's land. Your staff informed the County Commissioners that this did not pose any contamination potential to local shallow groundwater. I personally observed the construction of this lagoon and noted that there were no personnel present to ensure that the optimum soil moisture and compaction was occurring, and depth -to -groundwater measurements were taken, which was indicated by the applicant's consultants would be monitored and documented. Please provide me with all technical documentation and on -site visit information that your staff relied on to ensure the integrity of the east lagoon to assure construction in accordance with submitted plans and to recommend its approval. I have not seen any data which indicates the lagoon has been constructed to meet the 1x10'5 cm/sec CAFO permeability standard. In addition, since this lagoon may have intercepted groundwater, it should be constructed with a synthetic liner since a compacted clay liner will fail under negative hydrostatic pressure from an elevated groundwater table. If allowed to fill with process wastewater, it will pollute the shallow groundwater aquifer underlaying the lagoon and adjacent landowners. Mr. Rauh, located immediately to the south and east of this facility, owns a domestic well that will be contaminated. There are other irrigation, domestic and livestock wells in the immediate vicinity of this lagoon. Enclosed you will find a letter from Mr. Chilson, Mr. Hirsch's attorney, in which he indicates that this lagoon will be located directly over Mr. Rauh's irrigation supply line from the Smith Lateral. This location was not approved by Mr. Rauh, and during the construction of this facility, the 14 inch vitrified clay tile was intentionally destroyed. This location was not the location identified in the Paragon report and approved by your staff. The current location of this lagoon is less then 400 feet from Mr. Cabala's residence. Was your staff informed of the existing Rauh pipeline and the change in location of the lagoon? I appreciate your prompt response regarding this matter. Sincerely, Forrest Leal; P.E. Enclosure cc: Torn Hellerich Ken Lind LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality E:\LEAFLIND\Pickle Lagoon Ldter.wpd ,.,.,o, ,:pax -7 372:x1 g JOHN H. CHILSON Attorney At Law 6610 Chokecherry Drive Loveland, Colorado 80537 303-667-3214 October 9, 1997 Dan and Wendy Rauh 11570 Weld Co. Road 78 Eaton, CO 80615 Dear Mr. and Mrs. Rauh; My client, Hirsch Dairy, is in the process of con- structing a holding pond as part of its drainage control plan. The location of this pond is partially on an ease- ment serving your property with a pipeline. In order to protect your pipeline and not interfere with the working purpose of your easement, Hirsch Dairy has hired engineers to design a bypass around the hold- ing pond which will maintain the same gradient and flow capacity. A copy of this design drawing is enclosed with this letter. Should you have any specific questions about the engineering design or the functional operation of your line after bypass installation, please contact Mr. Dave Rau at the engineering firm shown on the enclosed design drawing. Hirsch Dairy fully recognizes your easement and has no intention of interfering with it. If any problems arise in the future with the operation of this bypass, Hirsch Dairy will correct the same. Truly yours, John H. Chilson cc: Hirsch Dairy 9'7251 97?r.;1g Oct. 1,1997 Dear Weld County Commissioners• In 1974 we purchased our farm because we felt it would be a healthy environment in which to raise our children. We both worked other jobs in order to finance our dream and like many of our neighbors raised a small herd of cattle and crops. At that time, we were bordered on the west, south and east by farms and the north by a 5,000 head sheep feedlot. This feedlot was expanded to 20,000 head in 1987. This expansion had a detrimental effect on our lives due to a tremendous increase in dust, odor and flies. In 1993, Mr. Hirsch purchased the farm contiguous to us on the west, northwest. He approached us with his dairy plan, hoping to gain our approval. He stated the dairy entrance would be from county road 23, a paved road which would eliminate most of the dust problem and road damage caused by large trucks. If he had actually followed his plan, then we would not have heavy traffic, dust and a washboard for a road. If the entrance were on county road 23, our tax dollars would not be paying for widening the road and repairing the culvert. Mr. Hirsch assured us the fly population would be controlled as well as the dust pollution from his 850 head of cattle. If that were the case, why do we fill a fly trap once a week? On a dry windy day there is so much dust that you can't even see the dairy. He spoke with us about employee housing. There were supposed to be three trailers (not four) located out of our view. Instead, they are right next to our fence about 500 feet from our house, where his employees have been known to hang their laundry and throw beer bottles into our pasture. As far as we can tell, the plan he presented to us is not anything like he said it would be. It appears he has total disregard for his neighbors. Otherwise, why would he construct a lagoon 600 feet from Mr. Lind"s home when he told us it would be centrally located on his property so it wouldn't be offensive to his neighbors? Now we understand Mr. Hirsch has proposed a second lagoon 600 feet from our home! 46c1; Presently, the dust,odor and flies are oftentimes unbearable. What will it be like with three times the cattle, three times the traffic, three times the amount of dust and three times the odor? What will it be like with a lagoon practically in our backyard with the prevailing winds out of the west? This is not our idea of lakefront property. Please take into account the well-being of our community, not just a corporation. We are no longer just a farming community like we were when we moved here twenty- three years ago. We are a rapidly growing area that is no longer sparsely Populated. If you allow this expansion, not only will our and our neighbor's property values plummet, we will be living in a very unhealthy environment. Not only will we have a 20,000 head sheeplot bordering us on the north, we will have a 2,000 head dairy bordering us on the west! It is obvious that majority of people in this area are against expansion judging from the signed petition and the large number of people who attended the last meeting to oppose it. If the overwhelming majority of people in the area are against this (with the exception of the dairy employees), how can you allow this travesty to continue? Yakxr t r ly, , am and Jack Cabala Cabala 11529 WCR #78 Eaton, CO 80615 • STATE OF COLORADO Roy Romer, Governor Patti Shwayder, ExecutNe Director Dedicated w protecting and Improving the health and environment of the people o(Colorado 4300 Cherry Creek Dr. 5. Laboratory and Radiation Services Division Denier, Colorado 80246-1530 8100 Lowry Blvd. Phone 0031 692-2000 Denver CO 80220-6928 Located in Glendale, Colorado 0 031 692-3 090 hap://wtiw.cdphe.rtate.co.u, October 28, 1997 Jacob Hirsch. Owner/Operator 11283 Weld County Road 78 Eaton, Colorado 80615 Colorado Department of and i Public tot�t REF: Mich Dairy, Confined Animal Feeding Operations Control Regulations, Manure and Wastewater Mostaganem Plan, Weld County. Dear Mr Hirsch: This letter is to inform you that the Technical Services Unit, Water Quality Control Division (the Division), has reviewed your Manure and Wastewater Management Plan (the Plan), submitted September 26, 1997. The Plan, as submitted, conforms with the Confined Animal Feeding Operoflons Control Regulations 4.8.0 (5 CCR 100219) as amended. However, we have the following comments: 1. The Division will require 45 days notice time before manure is stockpiled on site, to review soil compaction information and drainage patterns. 2. For future compliance inspections, we recommend you maintain in your files the private agreements with landowners where manure will be applied. 3. The Division would like to review the agronomic analysts, mentioned in the Plan, before any process wastewater is land applied on your property. If you have any questions or comments, please call me at (303)692-3564, or Derald Lang at (303) 692-3561 Sincerely, FOR DIRECTOR, WATER QUALITY CONTROL DIVISION ictor nz P. Distric Engineer Technical Services Unit sc. Paragon Consulting Group. Inc. - Ann: Dave M. Rau tat Engineering - Ann. Porten Leaf Weld County Health Depanntm - Ann: Trevor 3iricck Permit, and Enforcement - Ann: Phil Hegeman Technical Swvissa Unit - Ann: Derald Lang Environmental Redaction Agency. Region VIII M3-3 Film EXHIBIT I er 372.171 tf` 'b S m c+ p3 to /+ I-} O c+ IV c7 cr :f <: F'• N• H c+ r+ I! C] c+ 1'• :>7 10 r:l r1 Q, J O 'o ;y c+ c+ 9 :Y q IV P 1: (D 1.'• to C+ <1 y' . m (n ]' a ,n b I-' .. ry o '1 CD 0 to S CD ra :1 O r O c' N 't1 p. ,T• •; I r ,. I . rJ II' ;7 m (D I -b H 'i Di- 90 ,), O, m m :' rn b I 1 tt• ' r H H N• O 03 H 0 Sn C" yi 0 F7 1'. H .0 (0 ':) '1 I-' rr, O 0 m :,I !.) m c1 O O P CD (; to :; ;J• ' Ii m N IH N tT c) ci c i 1t 1; 1:1 'T lb 't O 1-•':1 O\ P :. m U H 11 1-'• (D /'• CY o O, 1 o t0 m ... <+ 1-'- 1-r• Cl, Id (1\ N• c+ r-] is m fn P c+ ti 11 m i( « 'T 1:11 e' ' b fD c+ (n "<' 'T rn I 1' .- O, Ii. :pa F 7 P m m. ti I :i 's r) •+ m ;t, 0 rr c) t^ m (D cD c+ r) r1 P+ n {ND + n. o p. I o-i n, (D O o Co 1 i ,i rn o m o • c ) tr. I ' to Q•, <+ (D It c+ O 0 :Y 1'• :1 Cnt!: b Ii '4 h7 ';1 ''b n, fn q C hJ 11.9 01 1.' .T 3. N C], n, :P.S ) cY :m1 0, I1 iv rD t' O {.: N I-9. m ;), G+ c+ c' .t :5. 1�. N 1r 't IT p, co Ire,, 0' F. C.. C; :'+ ,. '� m I -t ?) I-' 0. .0 c.n 'T O t.' O CO :y .. rF I H U n . a) Ii r 1-, r 1 r,; <+ !? ':) I J. 1-"ct M l.: :if rD 1 ct (o In I c+ i'! r,^ 1'. O '), I-, q'• ti` '' (7' O C1 ICS I b IN -1. I.. c+ p, .1 cr) :: r I a �+ to 'J' P r rD (0 co • to 1 o m (.1 a' `s )t ar 1 '1) .f O H. d T c+ m e< i %L 9 '-J (0 ED r) 'T r0 rn fP c• I'• I- m co C) rb r♦ Q O N• CD v 'n O 1J..L r n, O I,1 Iq Fl. r,) '1 C) N• 1 1-'• :L o O n, m- I ra _ i t., H O U 'Ci H Ib )-y t1 (D '1 Ip 1. ' b CL H. <Yl p, m 1 I S:I ch IJ Ft r: 'J Ci ft) ''b P c1 T o V. F- .. .. �, J CO R+ n <+ H. t r G] ti 0` ft, I J F'• ) O r\) 11 :D 1D 'J ( I O C; O (D 1 to c1 'b CL )b C; O ( S• o C).'T O I-' N•O H .„ t' {). c+S'' P 1' l'iO N m n i0 0 r 1J ,i I I+) l: CJ N I-4 (Y I' ,i P O ,f I'• •. Ii a) co e4 P c+ 'd O, m c' ail .. m O (D I) 'y, %' c1 P • + '' <r IS '31 O. o H c1 'd 1-' co i1 •b 0 m C) Ii ti ':f o (D 1-. 'd b 0 c-; (D N.. 3 o m< r r ' b m CL o �': o 'U C].)c1 ., w. 'n '1 7• µ O O ID 1. U '1 {+� J Pan, H • 0 e t:! c- H ' a h C O cY I'- '1 r1 H Y O. I <D I-1 n .. r5 <+ H (L m .r IJ•<Lr 1,. q m rD O f,l C] 'J y S F P CI. I '4 n C 1 'S c+ t^ m ::a .❑'c1 i o (y {- U m c NI ' d 4 ii m O ,t ty O O ,L 1 .3 -• m <} (J O 0. CL it. V+ �i. t. In 0 (•h P. O tD �1 t ' m (D f C,, c+ �1l O ' �. c1 .. O m •'! ' c+ m 7 rD O O CJ Iy 11 <+ r1 rD P n i 'i ❑. )1 �; � m T o O I -b El fD ;s c+ c m 'T t1 r) rn m b-' H c r �Y 0' C <, •,• o p (D Id 10 O N• I b i% to c+ c+ 9 m I'• ]. o 10 t0 ;S '4 (+... O iy O 9, r;Y Ix is c+ c+ !L tf o r0 '11 r) J r1 tb J < .. (NJI c+ i (D t1 0 1i IJ. a' !. N'• (0 :1 1O 1-'., iy i p, CD O •• r+ t3 '- m 1-" 'J i] m m o ra -I 9 rn 1'• O (0 Of F'• I b O '-b 1_.• cr ID (l. '�+ ti c+'d c+ P .Y m !1 O C; m '-1 :1' ) - i ''b U m 'd !0 '4 -' I-'• rt ' b + I+ P N• rP r'• O O, r.0 n 1-'• C, ,, m D , a, co H 'a O U. I' 4 a m m' O c o ;J, m ti' b i (D �I C' 1 n r] c+ N• J '- o M m n, <+ O L1 '! .} 1b o 1 :Y o r c1 O P (b ! t i m p�� �% rC o I -q rd m m O c+ P' -. c' ' b (J Li I N ii O d ',Pi '.1x O .L D <+ F� i hJ IT O a1 m c+ (DI r) to t] :], -' (D ' t1 O c+ H 0 Ct ' Y 1-'• I -' ' 1 +I IV r.'• )T q, m o H m N 1! H ] r i H •i e m r CD cr N• t� o H LI H tS rn !-'1 �IJ O P cC i ? l- -I O I's 9 ( -I 0. 1_I c' cF L1 'i1 t(` �, m 1 7 P '1 O {= + tD `'i r) '1 i-'•'rJ ti o m 'b m c1 T n, 4• 'a � µ rr00 is tS m c -r P I'• c+ ti o :1 ' ' (D : ''' r.. H 10 A f m c o Ds m LA m ,L <+ rD '(�' '.1 r+' o c♦ H 'L U\` 'S r q. C+ c+ SD `S ec, (n r+ k+ U' I,. is C' N• -J + O m CA C: H. U1 (n Cr P Ci <.Y r I ... 1,. m tY I.) o c+ y ;is FD u7 0 )1 o C] m i o 0. ,0 '-b (1.7): m m 'T :7 1 c 0 -r 19 Co ']' n F• P J' e1 y (O '1 I -r. (D ED m O 1.,. (L E.) 'I ,`1 N CL O IJ :1 O (D a .q G m O U Ii P o C1 r: '�? (,, ' la ,,7, ''b )-' rY K 'c) I) '(1 14 \)1 to to I-' 91 'CS O M CD f0] I'. • q 'd :Y ,-b [: (D 1-' (C Cr' Lt m H C) rb ]: IJ 1,..4 f r+ tb i ,0 o ▪ H I1 P N O 9 rn o U t+ o o r c+.• o O r+ o 4 0, a I'- O ('; 1-' ;y .; 1-1.'d 0 (b t(1 1-b i0 r IT I' m c''' 11 'U V • C' n' y a, O O id P N• ED It '1 ,.t E m '1 m !y �; . 1.,. I, IJ• O rn P. H <+ N Y W m G; U) P N• IT i1 ,y Cl. C1 FF t) n �' U at [D O ',7' m ID C/ ro tb 1,- " .; H 1.I. O ' b , C], c ri C r a, •t,• + • 117 In I b •• :1 ;:; iI, c I I.'t (L I+ ' b c+ .J r1 c :J r i]1 :1' c r�- cc; r m (4 ,. o '.L :,. m m t: (:L ('• Cy o 1+ R'I • D'1 0 i I '1. O rn U m n (D l)1 .' Iy In CL I -I I I ' b •.71 O f C' 1 c+ :Y r1 : r� I1 O ,1 v : `4 H. (n :S I:) ._) cD O N F' 0.i I c r �y (D c. '1 •.e ' 4 7! c1 f+ 4 rY (. P. r V. :). I,1 .i .r R G '! o -), 'T O m m H o C 4. {n to Y m ID rn .)' 'i -, '� Is m ,J CD 1-'• cr :1 If c+ J-+ (r 't en N• +''S 1.r. nj Cl Fri t0 Y (D rn o r,+ I'• 4.1 P, • I'• ' .3 b c) n. C7 m ro (A r. '� `;' 1 c1 H m IJ FD .S r+ U ti P :J t 'D ii, 0E) it : :J Ct PI V• .Y .161) ] O 111 1 :y' .J Ii • rO- c+ a t4 m o r, , '! Li r.1 t) m ' b O P' n. rn I %n `4 a. ' )' _ i a ,1 '+ U '1 CD m "C o 'i O 1' (n m CD c+ rara - 1.,• c+ 6 O 4 . r H. H •F H. 'J a 'T P : o ID O� :,1 I'. O. $, ;n to co Ri •� rr IJ is i d G I'• a ' t.Y I. :1 '1 I,. ra 1'- r.. Ir tf 1.`• ED Cl O IJ. 0 o. i -' c0. ti CL P 1).co- `t1 + rf Cc: X W O tT itlasliill!IMfaltsirrant' 1 'mMgnn11orafVI BourneM1aiintunesanrtnmetteR1M+1ornigNIFillint.Tnrn, w uveltiNusztttrag herein bo•and hereby is adjudged'nenior to ell ren:ar.voirn whose!i.It1et1•:cji.tohes arelooftod,abovo the:hondente of the )(aernt and ldottol Mlii race, hotweern• tlio let day of December and. the fi.ret day of March following and. at ru.oh Other times an water: -in not needed for di.root, i.rri— getion amid. mount o:r. fiew;to continua up. to•the sto— rage capacity of nieirace.ntta• rrnnervoir, whether maid floc; of sixty cubic feet per mound flail flow con4itnntiy during nald perloe'through raid Macon and Mattel Hill .raon, or not. • That: certain rreservoir known an the Wood rouer.— voiar belonging to reservoir. ointment. Ho. 20, The Weed reservoir and Ditch Company, having been found in manner a. orcneld to be a reservoir located on neon. 5 end 6 and sec. 32 in twp. 7, north range 66 went in Weld County, (;Olorado, tined for tho irrigation of lends onct taking i.tn supply of rater. front the Cache la. return river by means of the Lorimer end Weld. canal and from seepage and fiend waters that Dome clown the dzaw lit tre reservoir is nituate, which said draw oxtenln beyond. the Lorimer end Weld canal, le entitled to two appropriations of rater for the purpose of filling usid reservoir and to priority Ho. 41 by oonstructlon thereof once to the amount of water herninefter mentioned for the benefit of the party or parties lawfully entitled thereto; ft in hereby adjudged and decreed that said reservoir be allowed to have stored in it; from mid daehe In Poudre river by memo of the Lorimer and Weld oanal and the feeder ocnetruiteri therefrom; else' Prom the »Otte•••::0:... ..Our...:....:a:'..r+.!5•,.e,n..q,: rr..n 1itt ?'•1'�:..a -... :?i�}Cr,�'.' .-. ......- 972 1 It and from the seepage and flood wagers that oome down the draw in W.hidh' thl, reflOtoir'lio situate, and for the be;:eflt of the party or parties aforesaid under and in virtue of nnid apprepr.intien tby' dontrr.t.otirn pri.orlty No+. g1, . so' nl.oh water ae . in?. neeeeanry to -fill said re- sorvoir•t,o a depth nf.2,0 feet'.from the'bbno Of the, out - lot tube and a onpaoi.ty' of; 1!0, 000; 000 ouliio feet, whic], app rop;'ie.t i.on of aster for paid storage. Purposes took effect on and nni.d prio.r,ity thereof da.tnn from tho 22nd day of. December, 1893. . And further maid Wood redervnir in e.,titlod by approprintlon to priority No.'7/. by i.noreanod nto-- rarc and henefi.ni.ni app]i.ontion of Rater and thereby to the quantity of rater hereinafter montlonen for the vno and benefit; of thei party or parties lohfuliy entitled thereto; It le hereby'adjudged and. decreed that said reservoir be allowed to have stored in it, from said acumen of supply abovr, mentioned by reanon of said first enlargement and for the benefit of the party or Part. ire: aforonai_,t under and in virtue of said opnropr. i-. ation by nnlargomont'No. 7/, no much water an in neoe-• nrrnry: to fill naid renervoi.r to an additional depth of 5 .feet, or a total depth` of. 75 feet from the' bane of the outlet,. tube and n capacity of 110,000,000-oubia feet which appropriation of water for aaid additional eterade took effect on andsaid ptieritiv. therenf'dgte*k.froM the 15th day of October, : 1903: t Provided however;. that: no water Ahail be taken or•divertod from-naidt_caohe'ifir:'Poudre river into the canal and feeder 'for nt.orare in said renerroi.r Other than a'ld, except i.h virtue of the ownernhip by• said vlai.mant, hin hoirn and. a:3ni.gnn, of oapit,al nt nok in t hn La.rimer and. Wr.1d Trri grit i.nn Company. e4 97kr?.F o CD 4 4 IL O m Ii ('] C) O P • F R° U (T Rick f CA tc- IV y, J 01 m• t/1 CD CD 13 cn 0 m t, fl P• Io1 I_• O O P. t1 O 0 4 m 0 in m 1� O It I. o. UO N•ci cr o a f1 :-I m O m • m O 'I 0 O Co. CD(D CD m I O :I 114.14 y i nJ-r m; i i, l .0, o c] 9 P D 'l1 Vj •,1 0 --1 ID P. • CD r c+ I -I IJ) (T .4 J w ` Jl •if D. 71.• {1. O C] It•-rI 1 •• 1•, I �n I I ;, Ca P. co • ti p (f DI '1 I•. (r •'10 .1 m 'I O 0 iL O. '- C.. Co C III J cm 1 11. 0 m (J C1 CD 1'• cc; O (, Cj r 1-' in o N c 11 `;p O (I O 1,.:1 m m 0 J co- IEl ;U U 0 o C (n i (r (a I.1• :D :] p' :(LtY O t,• 0 r'. I" CD I'•:.•• O VI ,. 11 {: I0.•C .11 O O C, N• '1 41 (r 1y O (1 I'Dv •. o •o ,iO. :., cc '44 (T n n I-1 cn I� to 0 1a Cl (O m ( CA ct h IU Y i. F 4 (Ti (I m • 000'00C`0tt (V (A CA coo Ioo 6061 `9Z 'z°0 (A • O 3691 `ZZ '°aQ 1 cf to CD N O cI N CD De r) 0 c 11 m et • I 8 rro f l: •' I (ACV O1 CA CA 01 col Cs N (0 NON 1 0 a'0 IA CA w (D 1a la (O (D IO cis to C7 Zco' J0 4 Ocpa D O cr F••(... f° ID m (ono oS. N I.•. I J FD p O ,O r'F+•p 19if-a zrF'~ po w ((DD P• W .P u C � co r,. co C pr„' D,O 73 5--,w O1 t.1 tD r ul m O 0 O nPc `P' ii t a P. • c -I co • 4 t U O. o d �Y] co (D CD G U .7 ✓11 N I- laid Wx CO D O o Om I F.. Fa •'.1 0Fr' m v C OI ( w V. • COmm O _-- I-1 (D 0 ii 1 WOOD RESERVOIR FINDINGS 1. The allegations of fact in the claim herein filed for said reservoir are supported by the evidence. 2. The name of the claimant is The Eaton Investment Company, and its post office address Is Eaton, Colorado. 3. The name of the reservoir for which this water right is claimed is WOOD RESERVOIR. 4. The location, sources of supply, date of commencement of work and enlargement, area, capacity and purpose of said reservoir, is as set forth in statements of claim heretofore filed therefor and in the findings relating thereto, and in the decree heretofore entered hereicase Numbered 1591 in thin Court whereby it was determined that said reservoir was entitled to a decree for storage to a depth of 20 feet above the base of its outlet tube, and 120,000,000 cubic feet of water, with priority No 30, as of date December 22, 1892, and for additional storage to a depth of 25 feet above the base of its outlet tube and 140,000,000 cubic feet of water (including priority No. 30) with priority No. 54 as of date October 15, 1903. That annually ever since the date of said later appropriation, when- ever water was available, said reservoir was filled with water to said capacity in accordance with said decree and priorities, and said water was beneficially applied within reasonable time for irrigation of approximately 1500 acres of land of the stockholders of said claimant. That on and after said date there was unappropriated water in said sources of supply of said reservoir, and in subsequent years whenever such water has been available said reservoir has been filled and water withdrawn therefrom within a reasonable time for beneficial use in the irrigation of said lands during the same season. During the same season from such 2b'. InIpti ;frirg• tr. On, VJYk. 1 Y..0• T.nii•w 4.101.110.9.0.6.9.1%••.• s.. ..u-.. 97 rr wi4 1,400N.«f,k.+hra1!awr rJq1 444 u\ i yf. '.n . tl 1 ifN..^r w. ',�nt.�af1♦ J. .y. inlets,to thb 1tr11 amount of the unappropriated waters available and capable of diversion into said reservoir. The highest amount of such water so stored under said refilling right equalled the full capacity of said reservoir above its 12 foot contour, to wit: 62,000,000 cubic feet, or 1377.42 acre feel, of water. CONCLUSIONS OF LAW Said reservoir is entitled by law and in equity to a decree awarding it a further appropriation of water by refilling, annually, after it has been filled once in'accordence with its decreed priorities numbered 30 and 54, by farther storage under right to refill from un- appropriated waters and beneficial anrlicatien and use of water, to wit, 1377.42 acre feet of water, for the benefit or the parties entitled thereto, for irrigation, as of date December 31., 1916, and Reservoir Refill Priority No. _/3G f� in former decrees. hut inferior and junior to awards DECREE WHEREFORE, IT IS ORDERED, AOJNP0!;D AND DECREED, that, ;'.COD Rr3ERV0TR, located in sections 5 and 6, T. 6 N., and 32, T. 7 N., Range 66 W. of the Gth P. M., he and It is hereby awarded an annual refilling priority for irrigation purposes, for use of the party or parties entitled thereto from its present sources, for the storage therein of the amount or 1377.42 acre feet of water, with Reservoir Refill Priority No. /730‘ , as or date December 31, 191.6, tut junior and inferior t.o the latest reservoir priority, as of date June 1S, 1925, awarded in the last prior water adjudication decree in Water Cis- trict No. 3. e.a 972;1., • Cl7• • lliM ',ilk... f,” mawdi+�`�i. r{i+iiw" . t ; ,.:, +,•t RIkWi '!Cttlink4mb• ,, 't' . •r • 4, , ! 41,- iiliera ti FINDINGS 1. The allegations of fact in the claim herein filed for said reservoir are supported by the evidence. 2. The name of the claimant Is The Eaton Investment Company, and its posts office address Is Eaton, Colorado. 3. The name of the reservoir for which this water right is claimed in ANGEL �IJIKE,I��1 ii. A general description of said reservoir, as set forth in the claim therefor, is as follows: Angel Lake is a reservoir in a natural depression with a dam about 16 feet in height and 700 feet in length, running along the south line of the Southeast Quarter (SE)) of Section Thirty-one (31), in Township Seven (7) North, Range Sixty-six (66) West of the Sixth Principal Meridian, in Weld County, Colorado. It is situated in said southeast quarter of Section 31. and covers an area of approximately 150 acres of land. Its source of supply is Roullard Draw, the natural run-off, seepage and percolating waters from all intersecting draws and depressions and the drainage area to the north and west, including the waters of that certain seepage or drain ditch known as Daisy Drain Ditch. It is also filled in part from the "Eaton Ditch" of The Larimer and Weld Irrigation Company through an Inlet ditch 1n the South part of said Section 31 fran the canal of Roullard Lateral Company. The run-off, seepage and percolating under- ground waters collecting and flowing into Raid reservoir are not naturally tributary to any natural stream. .it Said inlet ditch originates in a concrete structure in the South- east Quarter (SE ) of said Section 31 in said Roullard Lateral, which is 22 feet long, 6# feet wide, 3i feet deep with a two foot tile running there- from 99 feet to a settling basin, thence by means of an open ditch Oi feet -1- 266 r-..,....• •- .. 972! -;lc u,, ♦• .1 r: e.'. u, .. ., :..p • roves rn.w I. :w w.....yr�..ib.•Li.i....�-ra...�rL- extending approximately a quarter of a mile to the vest edge of said reservoir. its outlet is a ditch extending from its southerly boundary in said SE4 of said Section 3L. It has a capacity of 18,500,000 cubic feet at a gate height of 20.17 feet, and has been filled annually to its capacity. Raid reservoir covers an area of 80 acres at high water line. 5. Said reservoir is located on land owned by claimant allirrigated from ditches taking water from the Cache la Poudre River, supplemented by water from its reservoirs, and said land Is located within Water District No. 3, Water Division 1 of the State of Colorado. 6. The appropriation for Bald reservoir wan initiated by construction and use of said reservoir and its inlet and outlet ditch in the year 1899, since when it has been continuously used for the irrigation of 1490 acres of land belonging to The Eaton Investment Company, and members of the Eaton family, its predecessors in title. The amount of water claimed for said reservoir by original appro- priation and beneficial use is 18,500,000 cubic feet of water and a storage depth of 20.17 feet on its gauge rod an presently located, or 424.7 acre feet. All of said water so appropriated has been and will be used bene- ficially for the irrigation of approximately 1490 acres of land in Sections numbered Five (5), Eight (8) and Nine (9), in Township Six (6) North, Range Sixty-six (66) West of the Sixth Principal Meridian, in Weld County, Colorado, owned by said claimant. i Claimant, since March 31, 1900, from the sources above described, as often as such waters were available has refilled said reservoir, appro- priated and beneficially used said waters for the irrigation of said lands of its stockholders lying under and irrigated from said lake. Claimant in addition to a first annual filling claims under said appropriation and water right/sufficient water to fill as a second filling said reservoir to a depth of 20.17 feet on its gauge 2'6'7 '^'n,... 'MFG--usasnae:ar....... . ��. I... ale .tth ". 'M 1-.Okmpi'In .w..u•...ro w.U4'm HAh1.04A0 .i t t • u.. L ..1 a with n priority ante of March 31, 1900. CONCLUSIONS OF LAW Claimant to entitled by appropriation and use by lax and in equity to n decree permitting it to capture, collect, store, divert and use by and through snid reservoir, run-off, waste, seepage and underground percolat- ing water and water from said "Eaton Pitch", for the irrigation of 11(90 noes of land, the amount of water required to fill said reservoir to a depth of 20.17 feet, or h2h7 acre feet of water, with Reservoir Priority No./2a/ an of date December 31, 1099, and to ansecond filling in like amount with Reservoir Refilling Priority No. /34,6 as of date March 31. 1900. DECREE THEREFORE,. IT IS ORDERED, ADJUDGED AND DECREED, that the party or parties entitled to ANGEL LAKE, which covers So acres of land in the South- east quarter (SEe) of Section Thirty-one (31), in Township Seven (7) North, Range Sixty-six (66) Went of the Sixth Principal Meridian, in Weld County, Colorado, be and they are hereby permitted to capture, collect, store, divert and use the river, run-off, seepage, drainage and underground and other waters described in Raid claim and findings herein, through and by means of the said reservoir and equipment, annually, the amount of water necessary to fill said reservoir to a depth of 20.17 feet, to wit 424.7 acre feet of water, with a priority date of December 31, 1899, and Reservoir Priority No. /36 /Q/ IT IS FURTHER ORDERED, ADJUDGED AND DECREED, that said party or parties shall be permitted to refill said reservoir annually, when water is available from said sources, after same has once been filled, to the same amount and capacity with priority date of March 31, 1900, and Reservoir Refill Priority No. /0‘,(9. Roth of said priorities, however, are junior and inferior to the latest reservoir priority, an of date June In, 1925, awarded in the last prior water adjudication in Water District No. 3. -3- r z58 TT- T19 -fl xwp4� IN)r`a l.I S. *.Jd..'_... .t �. .o... .y � . .,..�"n-.wrr. .,. ,rrr-mu. • • .. .. . ._ . .. . .... .. 1..'.w.vio r?s• ,t--,- .� u!... l.n'ui • COLORADO June 14, 1984 Alvin Steinmark Attorney at Law 1424 Eighth Avenue P. 0. Box 1955 Greeley, CO 80632 Dear Mr. Steinmark: OFFICE OF COUNTY ATTORN PHONE (303) 350-000. EXT - PO. BOx GREELEY. COLORADO 3C. This letter is in response to your letter of May 29, 1984, to Dr. Wooley, and is to advise you that your assumption that the Weld County Health Department is no longer interested in the matter regarding the Woods Lake inlet ditch is quite incorrect. The Weld County Health Department cannot and will not abdicate its statutory responsibilities regarding the health and welfare of the citizens of Weld County in general and water quality in particular. Therefore, you should not consider this matter to be closed. I would remind you that the Health Department in addition to its duties, has also attempted to act as a mediator between the parties in this matter. It is unfortunate that the lack of the engineering information and Mr. Dickson's family business forced cancellation of prior meetings. The long delayed report from Mr. Gutterson's engineer should be available this week. The Department would still like to work toward an agreement between the parties rather than proceed by means of an enforcement action for nuisance, water pollution, or illegal dumping of solid wastes. A copy of this letter is being sent to Mr. Dickson along with a request 'y this copy that he contact me following receipt of the report, to set up another meeting. It is still hopeful that an agreement can be made to resolve the interests of the Department and the Guttersons and Mr. Rotharmel. cc: 'Chuck Dickson George Vargulich Dr. Ralph Wooley Sineflely, Lee D. Morrison Assistant County Attorney Forrest Leaf, P.E. 13946 CR 56 Hilirose, CO 80733 (970) 590-1787 LEAF ENGINEERING November 5, 1997 Mr. Tom Hellerich, Esq. Doyle, Otis, Frey and Hellerich West Greeley Law Center 1812 56th Avenue Greeley, CO 80631 Re: Hirsch Dairy, USR 1091 Dear Tom: This letter report will present my technical review of Paragon's Manure and Wastewater Management Plan for the Hirsch Dairy, submitted to the Weld County Commissioners on September 26, 1997. My review will follow the section numbers contained in the above referenced report. 1. Introduction Paragon alleges that since the USR 1091 application is pending, the Hirsch Dairy is in compliance with County regulations even though there are more then 960 animals on site, and have more than 960 animals on site since September 1995. 1.3 Site Geology and Hydrology Paragon states the Hirsch Dairy does not overlay a designated aquifer. However, the purpose and intent of the Classification and Standards for Groundwater is to protect all groundwater of the state. All groundwater of the state is protected pursuant to the Statewide Standards. Specifically, 5 CCR 1002 Section 41.5(C)(6) addresses aquifers not classified as being protected by interim narrative standards or Table values 1-4 in the Classification and Standards regulation. The limited shallow aquifer in the Eaton area is not excepted. There are numerous domestic, stock and irrigation wells in the area that are receiving surface and subsurface water from the area of the Hirsch Dairy land, lagoon and irrigation system. Baseline groundwater quality samples collected in 1996 show that the concentration of nitrate -nitrogen in the alluvial aquifer underlaying Lind Farms, Inc, the Habrock Property and Town of Severance is 2.24 mg/1. LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality E:\L.EAF\LIND\Paragon Review Letter Reportwpd 972r' Paragon Report Review Page 2 2. Storm Water and Process Wastewater Management Paragon states that "Land application of liquid and solid wastes and off -site storage and use of solid manure is an important aspect of the waste -disposal process." However, the proposed plan does not explain how much and when this solid manure will be applied and how agronomic rates will be determined and tracked. In addition, the off -site storage of solid manure is not discussed. While CAFO may not require this explanation, there are requirements under the Weld County Zoning Ordinance Sections 45 and 47. 2.1 Storm Water Conveyance The applicant proposes, and has initiated construction of a retention pond east of the Smith Lateral and south of the employee housing. Paragon sized the retention pond to capture storm runoff from 17.6 acres above the Smith Lateral and hold 4.7 acre-feet. However, the drainage basin above the Smith Lateral is 31 acres with a total of 8 acre-feet of generated runoff at a peak discharge of 19 cfs for a 25 year, 24 -hour storm event. Paragon references a plan in Appendix A of their report. This plan is, at best, a concept plan for the retention pond. There are no detailed specifications pertaining to the sizing of the pond, in -situ compaction testing, erosion control structures, appurtenances, grading plan and or ditch sizing and alignment. In addition, Paragon does not state how this water will be handled. If this retention pond is to be evaporative, Section 4.8.3(C)(5)(b) requires that all "evaporative systems shall be designed to withstand a 10 -year period of maximum recorded rainfall". Table 1 shows a 2 year water budget on the 4.7 acre-foot capacity retention pond. As is evident from Table 1, the proposed size of the retention pond is not adequate to detain and evaporate precipitation and generated runoff over a two year period, let alone a ten year period. A March 17, 1997 letter to Victor Sainz from Terracon stated that a field technician would be on site during construction to conduct in -situ testing. My visit to the site and drive along the Smith Lateral on October 9, 1997 revealed that the retention pond was under construction but no in -situ testing was being conducted. In addition, soil conditions were dry, thus, compaction at 95 percent standard proctor would be highly unlikely. Section 2.4.4 of Paragon's report states that in -place density compaction testing will be performed during construction of the pond and ditch. Paragon does not address storm water runoff from the 147 acres irrigated with process water from the existing lagoon and proposed retention pond above the Smith Lateral. Review of the map prepared in Appendix A shows drainage flow paths from the 147 acres and a tail water pond located adjacent to Weld County Road (WCR) 23 approximately 1200 feet north of the intersection of WCR 78 and 23. My understanding of the CAFO regulations is that all facilities which come in contact with process wastewater must be designed to contain a 25 year, 24 -hour storm event and have a maximum permeability of 1 x 10-6 cm/sec. Paragon states that this facility LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality EALEAF\LINIARaragon Review Letter Report.wpd Paragon Report Review Page 3 is a "pass -through" facility. CAFO regulations do not define such a structure. In my opinion, this facility must meet the criteria set forth in CAFO Section 4.8.4. The size of the tail water pond is not discussed, nor is its specific design. Under CAFO, this pond, if it is to receive and hold process wastewater must be sized to hold generated runoff from a 25 year, 24 hour storm totaling 38 acre-feet. Enclosed is a letter of September 30, 1997, from Derald Lang from the Water Quality Control Division of the Colorado Department of Public Health responding to an inquiry by Mr. Jiricek (letter of September 24, 1997) regarding tail water ponds and their applicability to CAFO. Mr. Lang states section 4.8.5(A)(2) of the regulation is "intended to cover impacts to surface water quality from runoff due to flood irrigation practices." Furthermore, Mr. Lang's opinion is the applicant's proposed tail water pond does not pose a significant threat to groundwater quality based on the resident time of the process wastewater in the pond. Mr. Lang was not advised of the shallow depth -to -water, nor the proposed pass -through operation. I do not agree with Mr. Lang that there is "no significant threat" to groundwater or surface water quality from the retention of process wastewater or the overflow potential of process wastewater due to storm water runoff. The depth -to -water in this location is 5 - 6 feet, measured by Well #2 (see Figure 2), at current ground surface elevation. Excavation of this tail water pond will eliminate the separation distance between the bottom of the pond and the groundwater surface. Typical tail water reuse ponds are significantly deeper then 3 - 4 feet deep, which would be the depth of this pond if a minimum separation distance of 1 - 2 feet is to be maintained. Using Terracon's 30 inch per minute percolation rate (measured above the Smith Lateral in similar soil characteristics for employee housing septic/leach fields), process wastewater standing in the tail water pond for 12 hours will percolate 24 inches, thus reaching the groundwater. Given the separation distance from the bottom of the proposed tail water pond and existing groundwater, this pond should be lined in addition to being properly sized and constructed for containment of storm water runoff. However, the Weld County Zoning Ordinance also applies. Section 45.1.6 of the Weld County Zoning Ordinance requires that all drainage facilities or improvements shall be constructed to protect any adjacent river, streams or other bodies of water from pollution. Section 47.1.5 have the same requirement. As the proposed tail water pond is a drainage facility that will store process wastewater and must be designed to contain this process wastewater and contaminated storm water runoff under the above referenced sections of the Zoning Ordinance. 2.4 Retention Basins The existing lagoon has a capacity of 39.9 acre-feet with a free -board capacity of 29.9 acre-feet. I have observed the lagoon at, or near full (29.9 acre-feet and above) over the past 18 months. Paragon (formerly Terracon) conducted in -situ compaction tests and laboratory permeability tests at several locations in October 1996. Several of these tests failed, thus requiring further field compaction. Apparently 50 lineal feet of lagoon dam on the south side was re -compacted to meet LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality E:ILEAFILIND\Paragon Review Letter Report.wpd Paragon Report Review Page 4 CAFO permeability criteria. However, these in -situ samples collected in October 1996 were around the perimeter of the lagoon since the lagoon was full of process wastewater. Paragon did not collect samples from the center of the lagoon since the lagoon was full of process wastewater. An April 30, 1997 letter to Victor Sainz from Terracon indicated that the northwest corner of the lagoon would be filled to increase the distance of the lagoon from existing homes. A March 17, 1997 letter to Mr. Sainz, Terracon indicated that a coffer dam would be installed to facilitate the draining, drying, in -situ testing and re -compaction of the west end of the pond. Neither of these activities was conducted. Based on my observations of the construction of the lagoon under saturated conditions, my water balance and Paragon's retesting, the lagoon still leaks and Paragon has not demonstrated that CAFO permeability criteria has been met or exceeded consistently throughout the lagoon. Subsequently, the lagoon is contaminating area groundwater. Process water from the lagoon will be used on 147 acres shown on Figure 3 of Paragon's September 26, 1997 report. Paragon estimated the daily and annual water collected by the existing lagoon from the dairy parlor, in addition to the Storm water runoff into the lagoon and proposed retention pond. Table 2 is my estimate of water utilization based on Paragon's water utilization study, and includes actual measured precipitation from the Eaton area (NCWCD weather station) and irrigation use from the lagoon reported by observant landowners, the Smith Lateral Ditch Rider and a June 12, 1997 letter from Mr. Jiricek, to myself, in which he stated that Mr. Rau informed him that no application from the lagoon process wastewater would occur until installation of the tail water pond. The tail water pond is not yet constructed. I calculated seepage from the lagoon based on inflow and outflow volumes discussed above. I estimate that 37 acre-feet of process wastewater has percolated into the underlying aquifer of the lagoon from September 1995 through September 1997. This volume compares with the allowable CAFO seepage rate of 1/32 inch per day, or 1.9 feet over the two years. This 1.9 feet allowable seep over a 4.1 acre lagoon surface is 7.7 acre-feet. Thus, I estimate that the lagoon has seeped over 400 percent of the allowable seepage volume pursuant to CAFO. Allowable seepage for this lagoon is in excess of the CAFO permissible seepage rate of 1/32 inch per day. Over the past two years, the allowable seepage total 1.9 feet. Assuming a 30 percent soil voids ratio, this total 1.9 feet of allowable seepage would fill the pore space in 6.33 feet of soil. Paragon's Table 4 shows the separation distance in MW -1 was 1.09 feet in September 1997. Thus, there is direct communication between lagoon seepage and the groundwater. Figure lA shows an illustration of allowable seepage and measured groundwater levels. Figure 1B shows the seepage and separation distance for the measured permeability of 9.6x104 cm/sec reported by Terracon in November 1996 at location #5. Sections 45 and 47 of the Weld County Zoning Ordinance require that all drainage facilities or improvements shall be constructed to protect any adjacent river, streams or other bodies of water from pollution. The existing lagoon is a drainage facility that will store process wastewater and LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality E:U.EAFLIND\Paragon Review Letter Reportwpd 972x1 g Paragon Report Review Page 5 storm water runoff and must be designed to contain this process wastewater and contaminated storm waterrunoff under the above referenced sections of the Zoning Ordinance. 2.4.5 Existing Retention Basin - Groundwater Monitoring Wells In February 1997, Paragon constructed three monitoring wells around the lagoon. Table 4 of Paragon's report summarizes depth -to -water samples from these wells from February 1997 to present. As can be seen from Table 4, depth -to -water measurements decrease over the summer and fall season. MW -1 on Table 4 shows the depth -to -water decreasing from 13.71 feet in the winter to 9.63 feet in the fall. The separation distance from the bottom of the lagoon to the top of the groundwater surface range from 5.16 feet to 1.08 feet in the fall. Clearly the water table increases due to irrigation return flows over the growing season. Regionally, the highest water table occurs in the late fall and early winter of each year. Paragon's report does not contain data during this time period. MW -3 is reported to be dry. However, a monitoring well drilled in October 1997, adjacent to WCR 78 located due south of the lagoon (Figure 2) was 20.8 feet to bedrock with a depth -to - water of 9.95 feet (10.85 feet of saturated alluvium). The applicants MW -3 is approximately 6 feet higher in elevation, at ground surface, then the Monitoring Well#1. If MW -3 is truly dry, then the well was not properly constructed. This well, in addition to two others, should be re - drilled. At a minimum, additional properly constructed wells should be located between MW -1 and MW -2 and at the southeast corner of the lagoon. A March 17, 1997 letter to Victor Sainz from Terracon indicated that water quality in addition to depth -to -water measurements would be collected. In a October 27, 1997 telephone discussion with Mr. Jiricek, he indicated there were no water quality sample results in the file. Given the nature of this operation and the request by the applicant to apply large amount of nutrients water, a comprehensive groundwater quality monitoring program should be required. The negative impact this operation is having on groundwater quality should be documented and tracked. Paragon did not install monitoring wells in the location of the proposed east retention pond or tail water pond adjacent to WCR 23. Nor did Paragon make any statements as to the depth -to -water at these locations. Monitoring Well #2, Figure 2, was installed near the location of the proposed tail water pond in mid -October and sampled. The depth -to -water was 5.25 feet below the ground surface. At a minimum, monitoring wells should be constructed in the area of the proposed east retention pond and tail water pond and depth -to -water measurements and water quality samples collected by the applicant on a bi-monthly frequency. LEAF ENGINEERING Hydrology ° Hydraulics 0 Water Resources ° Water Quality E:\LEAF\LIND\Paragon Review Letter Report.wpd Paragon Report Review Page 6 2.5 Process Water Use/Land Application Enclosed is a letter from Agronomist Randy Ray in which he concludes at proposed expanded animal numbers (2,000 milking cows) Mr. Hirsch needs 7 additional acres to apply lagoon effluent to avoid the over application of nutrients. In addition, the application of dry manure during the week of October 20, 1997 will result in over application of 15,722 pounds of nitrogen if the lagoon effluent is applied next season,. The constant over application of dry manure and lagoon effluent and leachate on the 147 acres the past several years results in a gross over loading of nitrates to the aquifer system underlying the Hirsch Dairy, Lind Farms, Inc., Mr. Habrock's property and the Town of Severance. This over application will result in the continued mineralization of nitrates for years, thus perpetuating loading of nitrates to the aquifer. The aquifer volume underlying Mr. Hirsch and Lind Farms, Inc. totals 446 acre-feet based on depth -to -water measurements from Monitoring Wells #2 and #3. A drain tile sample collected in November 1996 had a concentration of 7.59 mg/1 nitrate -nitrogen. In October 1997, the drain tile had a concentration of 12.2 mg/1. A groundwater sample collected from Lind Farms, Inc. stock well, located approximately 200-300 feet west of the proposed tail water pond (Figure 2), had a concentration of 2.24 mg/I nitrate -nitrogen in November 1996. For that same well in October 1997, the concentration was 4.86 mg/I. Table 3 demonstrates how nitrate concentrations increased from 2.24 mg/I to 4.86 mg/1 in the aquifer under Lind Farms, Inc. The annual incremental nitrate increase is estimated by the loading to the aquifer from the over application of nutrients and the volume of water in the aquifer. The incremental increase correlates well with the observed increase in the Lind Farms, Inc. stock well. Mr. Hirsch, for the past several years has applied in excess of 25,700 pounds of nitrogen annually. This over application resulted in aquifer loading and an increase in aquifer concentrations from 7.59 mg/1 in 1996 to 12.2 mg/I in 1997. This violates 5 CCR 1002-41.5(C)(6). The volume of water underlying Hirsch's 147 acres is 221 acre-feet at a saturated thickness of 5 feet (see Figure 2). The loading of 25,700 pounds annually of nitrogen to this 221 acre-feet results in a concentration of 7.59 mg/I. This 7.59 mg/I in 221 acre-feet of groundwater volume equates to 4,746 pounds of nitrate -nitrogen (essentially, 221 acre-feet of water having 4,746 pounds of nitrate will have a concentration of 7.59 mg/I nitrate - nitrogen). Thus, there appears to be a 5 to 1 nitrogen leaching to aquifer response ratio (25,700/4,746). Table 3 below demonstrates how this continued over loading of nitrogen to the aquifer will increase nitrate concentrations in the aquifer underlying Lind Farms, Inc., Habrock's Property and the Town of Severance. This increase in nitrate concentrations has been observed by a noted increase in the aquifer concentration (as measured in the Lind Farms, Inc. stock well). In November 1996, the concentration of the aquifer was 2.24 mg/1. In November 1997, the concentration increased to 4.86 mg/I. Table 3 includes a 4,823 pound increase of nitrate contained in the 37 acre-feet of lagoon leachate which occurred during September 1996 to September 1997 (Table 2). LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality E:\LEA\LlNDWaragon Review Letter Report.wpd 972r1 Paragon Report Review Page 7 Table 4 contains a summary of groundwater quality samples collected over the past several years which show increases in groundwater nitrate concentrations. Drain tile samples represent subsurface water underlaying the Hirsch property. This water is collected via a perforated drain tile located under the Hirsch property. The proposed Hirsch Dairy (1) is a much to intensive use on the number of acres owned by the applicant, and (2) has polluted, and continues to pollute shallow groundwater underlaying surrounding land owners from the existing lagoon, the over application of process wastewater and solid manure and improper containment of storm water runoff contaminated with manure. In addition, the current activity is in violation of the interim narrative standards for groundwater contained in 5 CCR 1002-41 Section 41.5. Continued overloading of the aquifer will result in degradation of aquifer water quality and will result in conditions that will render the aquifer useless for domestic, livestock and irrigation purposes. Past activities and approved future activities will have a dramatic negative impact on the environment, health and welfare of the community. Sincerely, LE EKING Forrest Leaf, P.E. Enclosures cc: Ken Lind LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality E:\LEANILIND\Paragon Review Letter Report wpd ? 9 2/+ . /wae lagoon water balance2.123 Q0 CS > R W " ^-� en 00 n 00 o 00 hD c O\ et D\ en un n v, en et vl O et O\ O\ o V' N O O O O un 7 h 7 7 M et et un M M M M O 7 Ch O\ vl O N In h vl h v1 h n N: 06 00 Vt r-:6 C do C C C M b h [V r1/4410 ^ N N M M M M M M M M M et et on h et n N^ M oD .�. CA 00 O O et ON [� N M \O un el CO O O eh M O O O O O O O N N O O O O O O ^ N N ee O O O O O O O O o O O O O O C O O O C O O O C O O U N ad C 7^ .. M^ h Ol ken O O\ M N a en^ M h ON h0 ON M N et 7O x N ^O O O O N N N M M N ^ O O O O N N N M M N e 0 0 0 0 0 0 0 666 0 0 0 0 0 0 0 666 0 0 0 0 0 s. ita 0i W `O ee N N CO M VD M un un O\ N N O M N N t- M M et un <n O O O O O on O N O N N O O O O O O O 00 O M co 00 O Val N vi O O O 0 0 N O 1/445 vi ri nj M O O 666 0 N 7 0C O n O M O N^ 00 .. h 00 et CO O\ N O v1 on n O\ b t. O M 00 O VO n 7 N M CD M^^ h 00 N N O 7 M M O V'1 M 7 Moo (� t` vl 00 en ^ N O O C O C O N N eV ^^ C O C C O OM O eV C in in v+ v %o v vo D o% O1 0% ON O1 O\ O1 O1 a a a P a oN a a a\ a q L 00 off' _C= >c UawiCu eCC tO)C4 �,r�,gd titidv:OZAti� °� W le C d CS a 00 Cm a es it C C• 3 C C L DL 4 CI; a • e a m U a C e • m 00 v 12.1 R .c aA O O O O O O O O O O f1MC O O O0. = O b n b g O M q n vcNo .v froMo e P N O 00 N N N O P e O M 0 0 0 0 0 Q P O g Q Q Q o r N • r e M Q N r M 0 P N P en P P P P OO�� Q. N U C v1 �O r 66644-666666666666666 ^+ N N N N N N N N N N N N N N N N N O MMa et ON 0 r 000 coo 8 88 s xE ON N p O .42 Q e e b O N v t= 00 a0 Pic M e O N N^ N e e N 0 0 0 N N b N N N O N b N N P e 00 0 b O -+ O 0 1� N b M b M N O N O r N M N 00000 N 0 M O O O 0 0 O M Q 00 0 00 O VD in M O N 00 _^ r oo 4 N N O C M M r P b n O M 00 O �p r O a N 0 C 0 0 0 -+ O N M O N M e M 00 r r M ^O C OOOC ^ MoMO NMN^ O N M N 00 00 tM+� N ONrn M P �O Q .-. o N rn N e 00 v� N O C G O C C O G -+ O -+ N M O 00 M M P ^� O O O G O O C p^^^ O CO Q M 0 N P N O t+1 N e .� M Vl pp.. Vt O M N Q "0 N O O O O N N N M M N -+ O O O O N N N M M N a 6666666666666666666006600 a= vgig 0 .. a 9 N O Q Q O M O M O O b P e P P e r N P N N N e. N N N N N N N N N b N e Q Q e N M M e e M M bM vrf a O Ob}0 e 000 a0 0000 b h W M b b b^ r O Vi O. N N vqf M P U O O vMi P P W O N O W r01� 00 00 p0 Q M M M Q Q M M M e e N N N Q Q V Q Q v, Y Q Q Q e y Q e M M b M l� b N en M W '0 0 0 0 0 N n N MN 0 N N n C 00 00® m 00® 00 Q a Q a O. T a O. Q �p b b b b b b N N r N 1� r T* g q q q q a q q q q q a," q q a w e a lagoon water balance2.123 i a N N vi N O 9'%M;«? n Table 3 Hirsch Dairy USR 1091 ial Aquifer Loading Nitrogen Land Application Year 1995 1996 1997 1998 1999 2000 2001 2002 Nitrate Loading (lbs) 15700 25748 25748 25748 25748 25748 25748 Nitrate Recieved (lbs) 3140 5150 5150 5150 5150 5150 5150 Incremental Nitrate Increase On8/0 2.59 4.25 4.25 4.25 4.25 4.25 4.25 * Based on 5 to 1 reduction from root zone leaching to aquifer 11/04/97,04:28:11 PM Cummluative Nitrate Increase (mg/1) 2.24 4.83 9.08 13.32 17.57 21.82 26.07 30.31 Aquifer Leach Table.123 97251. Table 4 Summary of Groundwater Quality Sample Nitrate Depth Location Date (mg/1) (feet) MW#1 10/30/97 8.47 9.95 MW#2 10/30/97 9.36 5.25 MW#3 10/30/97 9.88 3.00 Drain Tile 10/06/96 7.59 Drain Tile 10/30/97 12.20 Stock Well 10/06/96 2.24 Stock Well 10/30/97 4.86 11/04/97,04:26:44 PM water quality summary table.123 Gradient Flow cc a 4) m x min et *ri as 0 m A 0 0 wrl • O 1 of Cu 97 tent' 4993 Well 5025 • ,,I \(LJ sJ t I „x (zzs A:F i • Sroc111iRSu+) ° `I1 �� way, ��` ICal .dPJ °III Loop Lake II I II II II 1i 4925 494/ h 9 • 14 4958 J. 4940 !New Windsor OII Fall 6 ty) 496/ arm. 5002 • • ; 5/03 II I cP 11 I • �\1 5� _ t‘. `aKoUAiingfv -rt-12- AQ.u,ntZi fl'. DY 1DR•SA 3` 49,1 1"• oMP7bQ19J (v 4986 5025 4956 -' 4904 _ 49361 rn 4944 • I-4 R.sci,14-71),a I zy U& RI cost Roala IN •114904 /n e1 i ; Ji: Severance • rc. Ba(dridge Lake BM• • 4574 Schneider Lake Aug,' Lady 4893 6900 0 OCT-27-1997 15:19 WELD COUNTY HEALTH DEPT 19703564966 P.01 i Pospir Fax Note To i Co 7671 Le Dab From Co. Nom* Moe* M Faxja 7P— 1J7a it C LOR DO September 24, 1997 Fax* Derald Lang Water Quality Control Division Colorado Department of Public Health and Enviro 4300 Cherry Creek Drive South Denver,' Colorado 80222-1530 Dear Derald: IEPARTMENT OF HEALTH 1517 16TH AVENUE COURT GREELEY, CO 80631 ADMINISTRATION (970) 353-0586 HEALTH PROTECTION (970) 353-0635 MMUNITY HEALTH (970) 353-0639 FAX (970) 356-4966 ent As you are aware, our County Commissioners have requested that our staff review the Hirsch Dairy, manure and waste water managemen plan (the Hirsch Plan) for compliance with the Confined Animal Feeding Operation Con 1 Regulations (5 CCR 1002-81). However, due to a "gray area" in the CAFO Regula 'tins we are finding it difficult to complete our review. Specifically, it is not appar whether tailwater ponds which would capture and temporarily store process waste water, applied through flood irrigation methods, are required to be lined. Due to this "gray area" we are requesting that your ff provide an interpretation in regard to this requirement. As you know, Section .8.4 of the CAFO Regulations requires that retention structures constructed after ugust 30, 1992, have evidence that a liner has been constructed and meets a specified p eability. However, it does not indicate if tailwater ponds must be lined. The Hirsch Plan is proposing an unlined tailwater pond. This pond will capture and temporarily hold process waste water which has be an land applied through flood irrigation practices. According to the Hirsch Plan, any captured process waste water will be imnjediately pumped back into the facility's prirpary retention structure. I am in receipt of a letter dated December 20, 1996, to Victor Sainz from Dave Rau and Brick Smith of Tetragon Environmental, Inc, whit 1 is a summary of a meeting in which you attended. This letter indicates that tailwater ponds are not required to meet lining requirements. The letter indicates that you have received a copy of this letter. However, subsequent conversations with you lead me to bell ve that evidence of a liner is required by the CAFO Regulations. 972r,1! ,5.. OCT-27-1997 15:19 WELD COUNTY HEALTH DEPT 19703564966 P.02 Derald Lang:.. Water Quality Control Division September 24, 1997 Page 2 It is apparent that there is not a consensus oa the i CAFO Regulations and that additional review of thi scheduled to present our review to our County Co. 1997. Therefore, we would request that your mitt Tuesday) September 30, 1997. We truly;appreciate your assistance in this matter. not hesitate to call me at (970) 353-0635, extension Sincerely, Trevor Jiiicek Supervisor Environmental Protection Services tj1830 cc: John Pickle Weld County Health Department Dave) Holm, Water Quality Control Division Lee Morrison, Weld County Attorneys Office Dave Rau, Paragon Consulting Group Victor Sainz, Water Quality Control Division retation of this portion of the item is warranted We are ssioners on Wednesday, October 1, interpretation be faxed to us by you have any questions, please do 232. 972'5" OCT-27-1997 15:20 WELD COUNTY HEALTH DEPT 19703564966 P.03 S ZA OF COLORADO Roy Romer, Governor Pee! Shwayder, Executive Direemr Derkaetd to end improving the health and environment of the people of 5. 100l aad Radatibn SeMc6 Da+var Le ade 61530 Bf 001a,ry Blvd. Phalle (303) 692- Denver OD 802204928 Located In Glendale, ado 003) 692.3090 http://www.cdpheaste.co.us 0 September 30, 1997 Weld County Health Department 1517 16th Avenue Court Greeley,! CO 80631 Attn: Trevor Jiricek Re: CAFO Regulations Question on Tai flDeaf Trewo=: This letter is in response to your whereinlyou requested an interpreta. concerning the need to seal ta3.lwat stating ;that this is a somewhat "gr CAFO regulations. Understandingthe d will hopefully aid in applying the r The section of the regulation (' tailwater ponds installation is in surface water quality from riun-of practices. Thus, the need to Seal when the regulation was developed for common practice with flood irrigati land application disposal plan incorp of a closed loop system; then the pot qualitylwould need to considered. From the description in the Hirsch P potential for groundwater quality i that the resident time of any proces is minimal. Under this situation I this tailwater pond because tYe po other t ilwater ponds in use with fld surrounding area. do Cd 1pentroDeper�m andFnvboommt ri-0577P5-71! 1991 1 water Ponds. etter of September 24, 1997 on of the CAFO regulations ponds. You are right in y area" in interrupting the evelopment of the regulations lation to the Hirsch Plan. 1.5(A)(2)) which addresses :ended to cover impacts to due to flood irrigation ese ponds was not an issue he use of tailwater ponds is However, should a feedlot rate a tailwater pond as part ntial impacts to groundwater an it would appear that the acts will be very small in water in the tailwater pond ould not see a need to seal ntial impact is not unlike irrigation practiced in the 972516 OCT-27-1997 15:20 WELD COUNTY HEALTH DEPT 19703564966 P.04 se 'Should you have any further guesltions} please call me at 303/692- 3561. .Sincerely, tticl Liing, PE cc: Johh Pickle, Weld County Health epartment Dave Rau, Paragon Consulting Gro.p Dave Holm, WQCD Vjck.0r Saint, WQCD 3725Z.S Hirsch Dairy Nitrogen Balance Prepared by Randy W. Ray, Agronomist Forrest Leaf, P.E. Leaf Engineering Route 1, Box 75 Merino, CO 80741 Forrest: October 28, 1997 I have reviewed the nutrient management plan for the Hirsch Dairy near Severance, CO. Based on my knowledge and expertise in nutrient management plans and overall water quality monitoring, I have made some conclusions regarding the report preformed by Paragon Consulting Group. Below is a table (Table 1) containing information for the effluent application at the Hirsch Dairy. Table 1. Hirsch Dairy Effluent Balance Current Facility (766 Milking Cows) Total Nitrogen Net Crop Acres Req. Additional Water Content Nitrogen Nitrogen Agronomic Acres for Volume Effluent Load Demand Rate Application (gal) (Ibs) (Ibsl llbs/ac) Jac1 (ac) 4,598,674 18,395 11,957 154 77.64 68.56 Hirsch Dairy Effluent Balance Proposed Facility (1,380 Milking Cows) Total Nitrogen Net Crop Acres Req. Additional Water Content Nitrogen Nitrogen Agronomic Acres for Volume Effluent Load Demand Rate Application (gal (Ibs) (Ibsl (lbs/ac) (acl (ac) 9,096,193 36,385 23,650 154 153.57 7.37 97251.E Page 2 Table 1 indicates that only 78 acres are required for application of effluent and runoff nutrients from the current dairy. This will allow the Hirsch Dairy to apply dry manure to the additional 68 acres. This additional application of dry manure must be closely monitored to prevent over application of nitrogen. Considering the proposed expansion of the dairy, Hirsch Dairy is going to need additional acres to apply this effluent. From calculations, an additional 7 acres is needed to keep the nitrogen application at or under agronomic rates. There will be an annual variation in precipitation runoff volumes, but not a dramatic change in net nitrogen load since the majority of the water in the lagoon consists of dairy process water. The nutrient value for the calculations were taken from the BMP's for Agriculture, published by Colorado State University. A value of 4 Ibs/1000 gallons of nitrogen was used in this table. I was advised that on the week of October 20, Hirsch Dairy applied feedlot manure to the 146 acres. I am assuming a typical application rate of 20 ton per acre, and using the BMP Guide for nutrient content. Table 2 shows the effects on the nutrient balance with consideration of the effluent applied as irrigation water. Table 2. Manure Application and the Effect on Effluent Application Hirsch Dairy Current Facility Effluent Application Nitrogen Nitrogen Nitrogen Net Excess Rate Content Content Allowable Nitrogen Nitrogen (T/ac) (Ibs/Tl (Ibs1 (Ibs) (lbs) fibs) 20 9 26,280 22,515 11,957 15,722 972516 Page 3 Manure Application and the Effect on Effluent Application Hirsch Dairy Proposed Facility Effluent Application Nitrogen Nitrogen Nitrogen Net Excess Rate Content Content Allowable Nitrogen Nitrogen IT/acl Ilbs/T) flbs1 (Ibs) (Ibs) IIbs1 20 9 26,280 22,515 23,650 27,415 The concern is evident in Table 2. The Hirsch lagoon is currently nearly full of effluent, and the dry manure applied this fall already exceeds crop nutrient demand, without including possible soil nitrogen contents, and additional irrigation water (Smith Lateral) nutrient content. From my calculations, Hirsch Dairy will exceed agronomic nitrogen application rates for the 1998 growing season (15,722 Ibs), under current conditions (766 milking cows). The proposed facility will have a huge effect on the nitrogen balance if dry manure is applied to all 146 acres. The over application of nitrogen will be 27,415 Ibs, nearly doubling the effect on the current facility. Another concern is the constant application of organic nitrogen, which will continue to mineralize in the soil over a period of several years. As an example, only 30% of the. first year applied organic nitrogen will be mineralized. This leads to a building effect where the mineralized nitrogen builds to a point where little or no effluent or dry manure can be applied and maintain agronomic application rates. Phosphorus and other minerals may be of concern at this site where a large concentration of animals are located. 97251 c ) mocid J/2\J k[ E.92oS 2CO mr oa ow ®§ C I/]§ q z = $§]y 703 mm Z •5 - mE • Tit 15m= (73o - 9.4- f} m� 0-c '2 |t2 I0C §0 2• 2k! ) -It .? 0 E a . >< ow OZawc oRw cc 7772 � k\ 0«| w>> CM CO Cc) W• M 05 CO Too Dry Feedlot Manure Applied X20 T/acre 10/21-10/23 D • e _ O 07E2 Li $a2] • c• m m E aE2 3 J i-alu z /wo 2;;= N- A co 2 N 0 Co �\ \ k K DOYLE, OTIS, FREY & HELLERICH, LLC ATTORNEYS AT LAW 1CHARD N. DOYLE HENRY C. FREY THOMAS E. HELLERICH FRED L. OTIS G. BRENT LOAN ELLEN S. MINNIG West Greeley Law Center 1812 56th AVENUE GREELEY, COLORADO 80634 The Board of County Commissioners Weld County 915 Tenth Street Greeley, CO 80631 Dear County Commissioners: (970) 330-6700 November 11, 1997 RE: Hirsch Dairy USR 1091 DENVER METRO (303)659-7576 FAX (970) 330-2969 Pursuant to your request, I am submitting in writing the questions I posed to staff, to the Health Department, and to the Board of County Commissioners at the most recent hearing. These questions are submitted in writing pursuant to the request of the Board. In addition, I am enclosing herewith a copy of the correspondence and the supplemental report I have received from Leaf Engineering, Mr. Forrest Leaf, concerning his analysis and review of the manure and wastewater management plan submitted by Hirsch Dairy on September 26, 1997. As you will note in the report and in Mr. Leafs correspondence to me, Mr. Leaf acknowledge an error in the calculation of the pounds of nitrogen lagoon leachate. The correct poundage was 48,226 pounds of nitrogen lagoon leachate which resulted in even greater nitrate concentration. As Mr. Leaf notes in his report and his correspondence to me dated November 10, 1997, the Dairy is currently polluting the area groundwater, and there has been an over -application of the processed wastewater and dry manure. In addition, there has been a seepage from the existing lagoon, resulting in an additional 48,000 pounds of nitrogen leached into the aquifer, based upon actual water samplings. I am also enclosing a copy of Mr. Leafs letter to Mr. John Pickle, Director of Environmental Protection Services of the Weld County Health Department, expressing the concerns relating to the east lagoon which is constructed in a location different than proposed by the applicant, and not as submitted in the report of Paragon to the County. 0,e. t -It_ i)( , 0 0 972516 Please accept the questions I have submitted, Mr. Leafs letter of November 10, 1997, and Mr. Leafs amended report dated November 10, 1997, and Mr. Leaf's letter to John Pickle as part of the record in the above USR application. TEH:cjm Enc. pc: Weld County Health Department Todd Hodges Very yours, -a f k THOMAS E. HELLERICH Attorney at Law 97251r Forrest Leaf, P.E. 13946 CR 56 Hillrose, CO 80733 (970) 590-1787 LEAF ENGINEERING November 10, 1997 Mr. Tom Hellerich, Esq. Doyle, Otis, Frey and Hellerich West Greeley Law Center 1812 56th Avenue Greeley, CO 80631 Re: Hirsch Dairy, USR 1091 Dear Tom: Enclosed is a supplement to my analysis of the Hirsch Dairy Use By Special Review (USR) 1091 currently pending before Weld County. Please note that 1 revised this letter report to reflect an error I made in my estimate of 4,823 pounds of nitrogen lagoon leachate which should have been 48,226 pounds of nitrogen lagoon leachate. This letter report is my review of the applicant's Manure and Wastewater Management Plan prepared by the applicant's consultant Paragon on September 26, 1997. In my review I noted numerous inconsistences with the applicant's plan and non-compliance with the Confined Animal Feeding Operations Control Regulation (CAFO) 5 CCR 1002-19 and Weld County Zoning Ordinance Sections 45 and 47. In particular, I found that the current dairy operation is polluting area shallow groundwater. Table 1, enclosed, shows my prediction of how shallow alluvial groundwater is being loaded with nitrate -nitrogen, which I correlated directly to current over application of manure process wastewater and dry manure and lagoon leachate on 147 acres owed by the Hirsch Dairy and is subject to the pending USR 1091. The predicted increase in nitrate -nitrogen was developed from nitrate samples collected from a drain tile underlaying and draining subsurface water under the 147 acres. In November 1996, nitrate concentrations from the drain tile were 7.59 mg/I nitrate - nitrogen. This 7.59 mg/1 nitrate is representative of the nitrate concentration of 221 acre-feet of groundwater underlaying the 147 acres. I estimated that in 1996 the applicant over applied 15,700 pounds of nitrogen from the land application of process wastewater and dry manure. This over application resulted in an observed aquifer response of 7.59 mg/1 nitrate -nitrogen. Over the 1997 growing season I estimated that there was an over application of 25,700 pounds of nitrogen from the land application of process wastewater and dry manure. In addition, the lagoon had LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality E:'LEAFLIND\Nitrate Loading l etter.wpd 972516 Hirsch Dairy Pollution Page 2 seepage of 37 acre-feet resulting in 48,000 pounds of nitrogen leached directly into the aquifer (4 pounds nitrogen per 1000 process wastewater). Drain tile samples collected in October 1997 contained 12.2 mg/1 nitrate -nitrogen. Continued loading of nitrogen into the aquifer underlaying the 147 acres will result in dramatic increases nitrate concentrations, as shown in Table 1. This shallow aquifer primarily exists from the deep percolation from the 147 acres. Annually, the percolation is drained completely from the aquifer underlaying the flinch 147, resulting in a virtually dry aquifer over part of the year. Thus, measured nitrate concentrations via the drain tile underlaying the Hirsch 147 provides a direct measurement of the aquifer response to this nitrogen over loading. The groundwater underlaying the Hirsch property drains into an aquifer that stores groundwater year around. This aquifer has been defined from the installation of irrigation, stock and domestic wells located in a line as shown on Figure 2 of my letter report. This aquifer receives all of the groundwater underflow from the Hirsch property. A stock well, as shown on Figure 2 of my letter report, sampled in November of 1996 had a nitrate concentration of 2.24 mg/l. Samples collected in October 1997 show a concentration of 4.86 mg/1 nitrate -nitrogen, as shown in Table 2. The location of :his stock well is such that it receives all of the groundwater underflow from the Hirsch Dairy, thus the noted increase in nitrate concentrations. As shown in Table 1, estimated nitrate concentrations will continue to increase over the next 5 years resulting in concentrations well above Table Values contained in 5 CCR 1002-41. While this aquifer is not specifically classified, it is protected pursuant to 5 CCR 1002-41.6.C.b., Interim Narrative Standards and is subject to protection at the 2.24 mg/I interim standard. Finally, this activity is in violation of Weld County Zoning Ordinance Sections 45 and 47 because (1) the east retention pond has not been adequately designed and constructed to contain process wastewater and storm water runoff required, (2) the existing lagoon exceeds the CAFO allowable seepage rate and is polluting area groundwater, (3) the proposed tail water pond has not been designed to meet CAFO criteria for storm water runoff detention and seepage requirements, (4) land application of nutrients are being grossly over applied and will continue to be grossly over applied (based on the applicants disregard of his consultants recommendations and County and State requirements) and is polluting area groundwater and (5) the December 16, 1997 Resolutions and Conditions of Approval, page 3, ¶ 2. (A) 1. and 2. LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality E.`.LEAFIL ND\Nitrau Loamg Lauar.wpd 972516 Hirsch Dairy Pollution Page 3 The ongoing activities are violations of CAFO in that this is not a "no -discharge" facility, thus the appropriate groundwater discharge permits must be applied for the lagoon seepage and resulting seep for the east retention pond. Sincerely, Enclosures cc: Ken Lind Forrest Leaf, P.E. LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality E:\L,EAFLIND\Nitrate Loading Letter. wpd 972516 Table 1 Hirsch Dairy USR 1091 ial Aquifer Loading Nitrogen Land Application Year 1996 1997 1998 1999 2000 2001 2002 2003 Nitrate Loading (lbs) 15700 73926 73926 73926 73 926 73926 73926 Nitrate Recieved * (lbs) 3140 14785 14785 14785 14785 14785 14785 - Incremental Nitrate Increase (mg/I) 2.59 12.19 12.19 12.19 12.19 12.19 12.19 * Based on 5 to 1 reduction from root zone leaching to aquifer 11/07/97,07:54:55 AM Cummluative Nitrate Increase (mg/1) 2.24 4.83 17.02 29.22 41.41 53.61 65.80 78.00 Aquifer Leach Table.123 972516 Table 2 Summary of Groundwater Quality Sample Nitrate Depth Location Date (mg/1) (feet) MW# 1 10/30/97 8.47 9.95 MW#2 I0/30/97 9.36 5.25 MW#3 10/30/97 9.88 3.00 Drain Tile 10/06/96 7.59 Drain Tile 10/30/97 12.20 Stock Well 10/06/96 2.24 Stock Well 10/30/97 4.86 11/07/97,07:55:17 AM water quality summary table.123 972516 QUESTIONS FOR TODD AND STAFF 1. In comparing the 1996 Plan as submitted by the applicant, which formed the foundation for the approval by the Board of County Commissioners at the hearing in December of 1996, as compared to the Plan now submitted, and in particular, the manure and wastewater management plan prepared by Paragon, are there significant differences, to require a new hearing and notice to all agencies? In particular, major changes in the plans include; 1) the removal and offsite storage of the manure piles, 2) the increased traffic created by the trucking of the manure, 3) the new lagoon which was not in the original plan submitted, and the fact that it is now on the property line, and is within 300 feet of the Cabala's residence, and is even closer to the Town of Severance, 4) and the application of the effluent now is by surface application as opposed to the sprinlder application. 2. Has the stag, considering all of these major changes, conducted an investigation of the impact on the compatibility with the Town and the neighbors and with existing users, pursuant to 24.4.3 of the Zoning Ordinance, is it compatible with the future development, pursuant to 24.4.2.4 considering the Town of Severance now lies across Road 78 from the Dairy, and has the staff re-evaluated the affect on the health, safety and welfare of the residence, pursuant to 24.4.2.7? 972516 QUESTIONS FOR TREVOR AND THE HEALTH DEPARTMENT: 1. Has the Weld County Health Department approved a manure handling and disposal plan, pursuant to 45.1.2? 2. Has the Weld County Health Department approved a method for scraping, grading and cleaning for the site pursuant to 45.1.5 and 47.1.4? 3. Has the Weld County Health Department approved the drainage facilities and plans to protect adjacent bodies of water from pollution, pursuant to 45.1.6 and pursuant to the Resolution adopted by the Board of County Commissioners? 4. Has the Weld County Health Department provided for the protection of adjacent bodies of water from pollution, pursuant to 47.1.5 and consistent with the Resolution adopted by the Board of County Commissioners? 5. Has the Weld County Health Department approved the manure storage sites to determine they have a water -tight surface to prohibit seepage or percolation of manure pollutants into the ground, pursuant to 47.1.1 and the prior Resolution adopted by the Board of County Commissioners? 6. Has the Weld County Health Department approved the feedbunks, water tanks, feeding tanks, feeding devices and aprons, pursuant to 47.1.3 and the prior Resolution of the Board of County Commissioners? 7. Considering there is no detail submitted by the applicant, what is the sizing of the tailwater pond, including the depth, and the depth to groundwater for the tailwater pond as projected to be installed? 8. What is the depth to groundwater of the new lagoon submitted in the new proposal? What protections have been made to assure that the groundwater is not being and will not be contaminated? 9. What sizing of the tailwater pond is necessary to hold runoff when irrigation effluent is being applied? 10. Has the tailwater pond been adequately sized to provide for containing runoff water, and in particular, has the tailwater pond been sized to retain the runoff water should a rain storm happen during the time the effluent is being applied? 11. There is no provisions in the manure and wastewater management plan which provides for manure storage in summer and winter months. Where is this going to be stored? Who will be storing it? Will this be on impermeable pads? Has this been approved by the Weld County 972516 Health Department pursuant to 47.1.1 and the prior Resolution of the Board of County Commissioners. 12. Section 31.2 provides that in the uses allowed by right in the A District, uses within the A District shall be subject to the additional requirements contained in Section 40, Supplemental District Regulations and Section 50 Overlay Districts. 13. The plan states that ditches have been constructed along the north and west sides of the property of the applicant, to capture and deliver the tailwaters to the tailwater pond. In actuality no such ditches have been constructed, nor do they exist. Has the County approved such a plan, and if so, what is the deadline for installation of the ditches? 14. The Dairy has been in violation of the number of animal units since September of 1996, and discharge has occurred from the facility. What protections have been established pursuant to Sections 45 and 47 to avoid pollution of the water and to preserve the water quality? 15. The plan, as submitted, stated that testing of the new lagoon area and the ditches and storage areas would occur. No information has been provided, however, as to any such testing, or whether such testing, in fact, occurred. For the existing lagoon, the original proposed lagoon, monitoring wells have been spaced too far apart. Additional monitoring wells should be required, and water samples to test the quality of the water should be required, pursuant to 47.1.7. 972516 Forrest Leaf, P.E. 13946 CR 56 Hillrose, CO 80733 (970) 590-1787 LEAF ENGINEERING Mr. John Pickle, Director Environmental Protection Services Weld County Health Department 1517 15 Avenue Court Greeley, CO 80631 RE: Hirsch Dairy, USR 1091 Dear John: November 10, 1997 As you are probably aware, I represent landowners adjacent to the Hirsch Dairy. On November 5, 1997 in a hearing before the County Commissioners, your staff recommended approval of the above referenced USR. Furthermore, your staff indicated that the applicant's plan was technically sound and thus met all applicable CAFO regulations and Weld County Zoning Ordinance Sections 45 and 47. You are also not doubt aware, that I have taken strong issue with your staff's evaluation and recommendation. Of particular concern is the proposed east lagoon or retention pond, which is actually constructed in a location other then indicated in the applicant's September 26, 1997 report. I personally observed construction of this pond and it is my opinion that it is a violation of CAFO and Weld County Zoning Ordinance Sections 45 and 47. The applicant's consultant indicted in the September 26, 1997 Manure and Wastewater Management Report, that in -situ sampling would be conducted with respect to compaction and permeability testing. On November 5, 1997 neither the applicant nor your staff indicated that this had been accomplished. Appendix D of the September 26, 1997 report contains boring logs from various locations above the Smith Lateral. It is important to note that all of these logs were at depths less then 5 feet, with exception of log #7 were groundwater was noted at 11.5 feet. Also, boring log #2 did was at a depth of 5 feet with no accompanying falling head permeability tests (Appendix E). Thus, this lagoon was placed in a location were soil characteristics were unknown by Paragon, the State, your staff and Mr. Hirsch. This lagoon has already been constructed and was excavated to a depth which may have exposed groundwater, as shown in copies of photographs taken by Mr. Cabala on November 6, 1997, LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality E:1LEAPLIND&Pi°k!° Lagoon fanc.wpd 97251G Pickle Letter Page 2 from Mr. Cabala's land. Your staff informed the County Commissioners that this did not pose any contamination potential to local shallow groundwater. I personally observed the construction of this lagoon and noted that there were no personnel present to ensure that the optimum soil moisture and compaction was occurring, and depth -to -groundwater measurements were taken, which was indicated by the applicant's consultants would be monitored and documented. Please provide me with all technical documentation and on -site visit information that your staff relied on to ensure the integrity of the east lagoon to assure construction in accordance with submitted plans and to recommend its approval. I have not seen any data which indicates the lagoon has been constructed to meet the 1x10'5 cm/sec CAFO permeability standard. In addition, since this lagoon may have intercepted groundwater, it should be constructed with a synthetic liner since a compacted clay liner will fail under negative hydrostatic pressure from an elevated groundwater table. If allowed to fill with process wastewater, it will pollute the shallow groundwater aquifer underlaying the lagoon and adjacent landowners. Mr. Rauh, located immediately to the south and east of this facility, owns a domestic well that will be contaminated. There are other irrigation, domestic and livestock wells in the immediate vicinity of this lagoon. Enclosed you will find a letter from Mr. Chilson, Mr. Hirsch's attorney, in which he indicates that this lagoon will be located directly over Mr. Rauh's irrigation supply line from the Smith Lateral. This location was not approved by Mr. Rauh, and during the construction of this facility, the 14 inch vitrified clay tile was intentionally destroyed. This location was not the location identified in the Paragon report and approved by your staff. The current location of this lagoon is less then 400 feet from Mr. Cabala's residence. Was your staff informed of the existing Rauh pipeline and the change in location of the lagoon? I appreciate your prompt response regarding this matter. Sincerely, LE RING Forrest Leaf, P.E. Enclosure cc: Tom Hellerich Ken Lind LW ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality E:\LEARLIND\Pickle Lagoon Lett°r.wpd 972516 972516 JOHN H_ CH1t.SON Attorney At Law 6610 Chakecnerry urive Loveland, Colorado 80537 303-667-3214 October 9, 1997 Dan and Wendy Rauh 11570 Weld Co. Road 78 Eaton, CO 80615 Dear Mr. and Mrs. Rauh; My client, Hirsch Dairy, is in the process of con- structing a holding pond as part of its drainage control plan. The location of this pond is partially on an ease- ment serving your property with a pipeline. In order to protect your pipeline and not interfere with the working purpose of your easement, Hirsch Dairy has hired engineers to design a bypass around the hold- ing pond which will maintain the same gradient and flow capacity. A copy of this design drawing is enclosed with this letter. Should you have any specific questions about the engineering design or the functional operation of your line after bypass installation, please contact Mr. Dave Rau at the engineering firm shown on the enclosed design drawing. Hirsch Dairy fully recognizes your easement and has no intention of interfering with it. If any problers arise in the future with the operation of this bypass, Hirsch Dairy will correct the same. Truly yours, John H. Chilson cc: Hirsch Dairy 972516 972516 PARAGON Forrest Leaf, P.E. 13946 CR 56 Hillrose, CO 80733 (970) 590-1787 LEAF ENGINEERING November 10, 1997 Mr. Tom Hellerich, Esq. Doyle, Otis, Frey and Hellerich West Greeley Law Center 1812 56th Avenue Greeley, CO 80631 Re: Hirsch Dairy, USR 1091 (Amended Report) Dear Tom: This letter report amends my November 5, 1997 and will present my technical review of Paragon's Manure and Wastewater Management Plan for the Hirsch Dairy, submitted to the Weld County Commissioners on September 26, 1997. My review will follow the section numbers contained in the above referenced report. 1. introduction Paragon alleges that since the USR 1091 application is pending, the Hirsch Dairy is in compliance with County regulations even though there are more then 960 animals on site, and have more than 960 animals on site since September 1995. 1.3 Site Geology and Hydrology Paragon states the Hirsch Dairy does not overlay a designated aquifer. However, the purpose and intent of the Classification and Standards for Groundwater is to protect all groundwater of the state. All groundwater of the state is protected pursuant to the Statewide Standards. Specifically, 5 CCR 1002 Section 41.5(C)(6) addresses aquifers not classified as being protected by interim narrative standards or Table values 1-4 in the Classification and Standards regulation. The limited shallow aquifer in the Eaton area is not excepted. There are numerous domestic, stock and irrigation wells in the area that are receiving surface and subsurface water from the area of the Hirsch Dairy land, lagoon and irrigation system. Baseline groundwater quality samples collected in 1996 show that the concentration of nitrate -nitrogen in the alluvial aquifer underlaying Lind Farms, Inc, the Habrock Property and Town of Severance is 2.24 mg/I. LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality £:\L£AF\LIND.Paragon Review Letter Report.wpd 972516 Paragon Report Review Page 2 2. Storm Water and Process Wastewater Management Paragon states that "Land application of liquid and solid wastes and off -site storage and use of solid manure is an important aspect of the waste -disposal process." However, the proposed plan does not explain how much and when this solid manure will be applied and how agronomic rates will be determined and tracked. In addition, the off -site storage of solid manure is not discussed. While CAFO may not require this explanation, there are requirements under the Weld County Zoning Ordinance Sections 45 and 47. 2.1 Storm Water Conveyance The applicant proposes, and has initiated construction of a retention pond east of the Smith Lateral and south of the employee housing. Paragon sized the retention pond to capture storm runoff from 17.6 acres above the Smith Lateral and hold 4.7 acre-feet. However, the drainage basin above the Smith Lateral is 31 acres with a total of 8 acre-feet of generated runoff at a peak discharge of 19 cfs for a 25 year, 24 -hour storm event. Paragon references a plan in Appendix A of their report. This plan is, at best, a concept plan for the retention pond. There are no detailed specifications pertaining to the sizing of the pond, in -situ compaction testing, erosion control structures, appurtenances, grading plan and or ditch sizing and alignment. In addition, Paragon does not state how this water will be handled. If this retention pond is to be evaporative, Section 4.8.3(C)(5)(b) requires that all "evaporative systems shall be designed to withstand a 10 -year period of maximum recorded rainfall". Table 1 shows a 2 year water budget on the 4.7 acre-foot capacity retention pond. As is evident from Table 1, the proposed size of the retention pond is not adequate to detain and evaporate precipitation and generated runoff over a two year period, let alone a ten year period. A March 17, 1997 letter to Victor Sainz from Terracon stated that a field technician would be on site during construction to conduct in -situ testing. My visit to the site and drive along the Smith Lateral on October 9, 1997 revealed that the retention pond was under construction but no in -situ testing was being conducted. In addition, soil conditions were dry, thus, compaction at 95 percent standard proctor would be highly unlikely. Section 2.4.4 of Paragon's report states that in -place density compaction testing will be performed during construction of the pond and ditch. Paragon does not address storm water runoff from the 147 acres irrigated with process water from the existing lagoon and proposed retention pond above the Smith Lateral. Review of the map prepared in Appendix A shows drainage flow paths from the 147 acres and a tail water pond located adjacent to Weld County Road (WCR) 23 approximately 1200 feet north of the intersection of WCR 78 and 23. My understanding of the CAFO regulations is that all facilities which come in contact with process wastewater must be designed to contain a 25 year, 24 -hour storm event and have a maximum permeability of 1 x lean/sec. Paragon states that this facility LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality E:1LEARLIND\Paragon Review Letter Report.wpd 972516 Paragon Report Review Page 3 is a "pass -through" facility. CAFO regulations do not define such a structure. In my opinion, this facility must meet the criteria set forth in CAFO Section 4.8.4. The size of the tail water pond is not discussed, nor is its specific design. Under CAFO, this pond, if it is to receive and hold process wastewater must be sized to hold generated runoff from a 25 year, 24 hour storm totaling 38 acre-feet. Enclosed is a letter of September 30, 1997, from Derald Lang from the Water Quality Control Division of the Colorado Department of Public Health responding to an inquiry by Mr. Jiricek (letter of September 24, 1997) regarding tail water ponds and their applicability to CAFO. Mr. Lang states section 4.8.5(A)(2) of the regulation is "intended to cover impacts to surface water quality from runoff due to flood irrigation practices." Furthermore, Mr. Lang's opinion is the applicant's proposed tail water pond does not pose a significant threat to groundwater quality based on the resident time of the process wastewater in the pond. Mr. Lang was not advised of the shallow depth -to -water, nor the proposed pass -through operation. I do not agree with Mr. Lang that there is "no significant threat" to groundwater or surface water quality from the retention of process wastewater or the overflow potential of process wastewater due to storm water runoff. The depth -to -water in this location is 5 - 6 feet, measured by Well #2 (see Figure 2), at current ground surface elevation. Excavation of this tail water pond will eliminate the separation distance between the bottom of the pond and the groundwater surface. Typical tail water reuse ponds are significantly deeper then 3 - 4 feet deep, which would be the depth of this pond if a minimum separation distance of 1 - 2 feet is to be maintained. Using Terracon's 30 inch per minute percolation rate (measured above the Smith Lateral in similar soil characteristics for employee housing septic/leach fields), process wastewater standing in the tail water pond for 12 hours will percolate 24 inches, thus reaching the groundwater. Given the separation distance from the bottom of the proposed tail water pond and existing groundwater, this pond should be lined in addition to being properly sized and constructed for containment of storm water runoff. However, the Weld County Zoning Ordinance also applies. Section 45.1.6 of the Weld County Zoning Ordinance requires that all drainage facilities or improvements shall be constructed to protect any adjacent river, streams or other bodies of water from pollution. Section 47.1.5 have the same requirement. As the proposed tail water pond is a drainage facility that will store process wastewater and must be designed to contain this process wastewater and contaminated storm water runoff under the above referenced sections of the Zoning Ordinance. 2.4 Retention Basins The existing lagoon has a capacity of 39.9 acre-feet with a free -board capacity of 29.9 acre-feet. I have observed the lagoon at, or near full (29.9 acre-feet and above) over the past 18 months. Paragon (formerly Terracon) conducted in -situ compaction tests and laboratory permeability tests at several locations in October 1996. Several of these tests failed, thus requiring further field compaction. Apparently 50 lineal feet of lagoon dam on the south side was re -compacted to meet LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality E: 'LEAFILIND\Paragon Review Letter Report.wpd 972516 Paragon Report Review Page 4 CAFO permeability criteria. However, these in -situ samples collected in October 1996 were around the perimeter of the lagoon since the lagoon was full of process wastewater. Paragon did • not collect samples from the center of the lagoon since the lagoon was full of process wastewater. An April 30, 1997 letter to Victor Sainz from Terracon indicated that the northwest corner of the lagoon would be filled to increase the distance of the lagoon from existing homes. A March 17, 1997 letter to Mr. Sainz, Terracon indicated that a coffer dam would be installed to facilitate the draining, drying, in -situ testing and re -compaction of the west end of the pond. Neither of these activities was conducted. Based on my observations of the construction of the lagoon under saturated conditions, my water balance and Paragon's retesting, the lagoon still leaks and Paragon has not demonstrated that CAFO permeability criteria has been met or exceeded consistently throughout the lagoon. Subsequently, the lagoon is contaminating area groundwater. Process water from the lagoon will be used on 147 acres shown on Figure 3 of Paragon's September 26, 1997 report. Paragon estimated the daily and annual water collected by the existing lagoon from the dairy parlor, in addition to the Storm water runoff into the lagoon and proposed retention pond. Table 2 is my estimate of water utilization based on Paragon's water utilization study, and includes actual measured precipitation from the Eaton area (NCWCD weather station) and irrigation use from the lagoon reported by observant landowners, the Smith Lateral Ditch Rider and a June 12, 1997 letter from Mr. Jiricek, to myself, in which he stated that Mr. Rau informed him that no application from the lagoon process wastewater would occur until installation of the tail water pond. The tail water pond is not yet constructed. I calculated seepage from the lagoon based on inflow and outflow volumes discussed above. I estimate that 37 acre-feet of process wastewater has percolated into the underlying aquifer of the lagoon from September 1995 through September 1997. This volume compares with the allowable CAFO seepage rate of 1/32 inch per day, or 1.9 feet over the two years. This 1.9 feet allowable seep over a 4.1 acre lagoon surface is 7.7 acre-feet. Thus, I estimate that the lagoon has seeped over 400 percent of the allowable seepage volume pursuant to CAFO. Allowable seepage for this lagoon is in excess of the CAFO permissible seepage rate of 1/32 inch per day. Over the past two years, the allowable seepage total 1.9 feet. Assuming a 30 percent soil voids ratio, this total 1.9 feet of allowable seepage would fill the pore space in 6.33 feet of soil. Paragon's Table 4 shows the separation distance in MW -1 was 1.09 feet in September 1997. Thus, there is direct communication between lagoon seepage and the groundwater. Figure 1 A shows an illustration of allowable seepage and measured groundwater levels. Figure I B shows the seepage and separation distance for the measured permeability of 9.6x1O cm/sec reported by Terracon in November 1996 at location #5. Sections 45 and 47 of the Weld County Zoning Ordinance require that all drainage facilities or improvements shall be constructed to protect any adjacent river, streams or other bodies of water from pollution. The existing lagoon is a drainage facility that will store process wastewater and LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality E:\LEAF'LIND\Paragon Review Letter Report.v.pd 972516 Paragon Report Review Page 5 storm water runoff and must be designed to contain this process wastewater and contaminated storm waterrunoff under the above referenced sections of the Zoning Ordinance. 2.4.5 Existing Retention Basin - Groundwater Monitoring Wells In February 1997, Paragon constructed three monitoring wells around the lagoon. Table 4 of Paragon's report summarizes depth -to -water samples from these wells from February 1997 to present. As can be seen from Table 4, depth -to -water measurements decrease over the summer and fall season. MW -1 on Table 4 shows the depth -to -water decreasing from 13.71 feet in the winter to 9.63 feet in the fall. The separation distance from the bottom of the lagoon to the top of the groundwater surface range from 5.16 feet to 1.08 feet in the fall. Clearly the water table increases due to irrigation return flows over the growing season. Regionally, the highest water table occurs in the late fall and early winter of each year. Paragon's report does not contain data during this time period. MW -3 is reported to be dry. However, a monitoring well drilled in October 1997, adjacent to WCR 78 located due south of the lagoon (Figure 2) was 20.8 feet to bedrock with a depth -to - water of 9.95 feet (10.85 feet of saturated alluvium). The applicants MW -3 is approximately 6 feet higher in elevation, at ground surface, then the Monitoring Well #1. If MW -3 is truly dry, then the well was not properly constructed. This well, in addition to two others, should be re - drilled. At a minimum, additional properly constructed wells should be located between MW -1 and MW -2 and at the southeast corner of the lagoon. A March 17, 1997 letter to Victor Sainz from Terracon indicated that water quality in addition to depth -to -water measurements would be collected. In a October 27, 1997 telephone discussion with Mr. Jiricek, he indicated there were no water quality sample results in the file. Given the nature of this operation and the request by the applicant to apply large amount of nutrients water, a comprehensive groundwater quality monitoring program should be required. The negative impact this operation is having on groundwater quality should be documented and tracked. Paragon did not install monitoring wells in the location of the proposed east retention pond or tail water pond adjacent to WCR 23. Nor did Paragon make any statements as to the depth -to -water at these locations. Monitoring Well #2, Figure 2, was installed near the location of the proposed tail water pond in mid -October and sampled. The depth -to -water was 5.25 feet below the ground surface. At a minimum, monitoring wells should be constructed in the area of the proposed east retention pond and tail water pond and depth -to -water measurements and water quality samples collected by the applicant on a bi-monthly frequency. LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality E:'LEAFILIND\Paragon Review Letter Report.wpd 972516 Paragon Report Review Page 6 23 Process Water Use/Land Application Enclosed is a letter from Agronomist Randy Ray in which he concludes at proposed expanded animal numbers (2,000 milking cows) Mr. Hirsch needs 7 additional acres to apply lagoon effluent to avoid the over application of nutrients. In addition, the application of dry manure during the week of October 20, 1997 will result in over application of 15,722 pounds of nitrogen if the lagoon effluent is applied next season,. The constant over application of dry manure and lagoon effluent and leachate on the 147 acres the past several years results in a gross over loading of nitrates to the aquifer system underlying the Hirsch Dairy, Lind Farms, Inc., Mr. Habrock's property and the Town of Severance. This over application will result in the continued mineralization of nitrates for years, thus perpetuating loading of nitrates to the aquifer. The aquifer volume underlying Mr. Hirsch and Lind Farms, Inc. totals 446 acre-feet based on depth -to -water measurements from Monitoring Wells #2 and #3. A drain tile sample collected in November 1996 had a concentration of 7.59 mg/I nitrate -nitrogen. In October 1997, the drain tile had a concentration of 12.2 mg/I. A groundwater sample collected from Lind Farms, Inc. stock well, located approximately 200-300 feet west of the proposed tail water pond (Figure 2), had a concentration of 2.24 mg/1 nitrate -nitrogen in November 1996. For that same well in October 1997, the concentration was 4.86 mg/I. Table 3 demonstrates how nitrate concentrations increased from 2.24 mg/I to 4.86 mg/1 in the aquifer under Lind Farms, Inc. The annual incremental nitrate increase is estimated by the loading to the aquifer from the over application of nutrients and the volume of water in the aquifer. The incremental increase correlates well with the observed increase in the Lind Farms, Inc. stock well. Mr. Hirsch, for the past several years has applied in excess of 25,700 pounds of nitrogen annually. This over application resulted in aquifer loading and an increase in aquifer concentrations from 7.59 mg/1 in 1996 to 12.2 mg/1 in 1997. This violates 5 CCR 1002-41.5(C)(6). The volume of water underlying Hirsch's 147 acres is 221 acre-feet at a saturated thickness of 5 feet (see Figure 2). The loading of 25,700 pounds annually of nitrogen to this 221 acre-feet results in a concentration of 7.59 mg/l. This 7.59 mg/I in 221 acre-feet of groundwater volume equates to 4,746 pounds of nitrate -nitrogen (essentially, 221 acre-feet of water having 4,746 pounds of nitrate will have a concentration of 7.59 mg/I nitrate - nitrogen). Thus, there appears to be a 5 to 1 nitrogen leaching to aquifer response ratio (25,700/4,746). Table 3 below demonstrates how this continued over loading of nitrogen to the aquifer will increase nitrate concentrations in the aquifer underlying Lind Farms, Inc., Habrock's Property and the Town of Severance. This increase in nitrate concentrations has been observed by a noted increase in the aquifer concentration (as measured in the Lind Farms, Inc. stock well). In November 1996, the concentration of the aquifer was 2.24 mg/I. In November 1997, the concentration increased to 4.86 mg/1. Table 3 includes a 48,226 pound increase of nitrate contained in the 37 acre-feet of lagoon leachate which occurred during September 1996 to September 1997 (Table 2). LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality E:',LEAR IND1Paragon Review Letter Report.wpd 972516 Paragon Report Review Page 7 Table 4 contains a summary of groundwater quality samples collected over the past several years which show increases in groundwater nitrate concentrations. Drain tile samples represent subsurface water underlaying the Hirsch property. This water is collected via a perforated drain tile located under the Hirsch property. The proposed Hirsch Dairy (1) is a much to intensive use on the number of acres owned by the applicant, and (2) has polluted, and continues to pollute shallow groundwater underlaying surrounding land owners from the existing lagoon, the over application of process wastewater and solid manure and improper containment of storm water runoff contaminated with manure. In addition, the current activity is in violation of the interim narrative standards for groundwater contained in 5 CCR 1002-41 Section 41.5. Continued overloading of the aquifer will result in degradation of aquifer water quality and will result in conditions that will render the aquifer useless for domestic, livestock and irrigation purposes. Past activities and approved future activities will have a dramatic negative impact on the environment, health and welfare of the community. Sincerely, Forrest Leaf, P.E. Enclosures cc: Ken Lind LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ° Water Quality E:ILEAFILIND\Paragon Review Letter Report.wpd 972516 lagoon water balance2.123 Cr O > i :z W MIN 'v -- el 00 N oo NO 00 \D Ch et CN et ON ... un N ND on et +n O et cs a C1 N O O O O on et 41et et wn el'et rn on on en m C Cs --• O, h.- C N v1 u-; v:n ' N N r+1 00 v N C O O O O C O r^, V^ v- et N rV •,• N N rn on rn rn rn rn r; rn en et et h un et Oh N N .+ rn %.p 41 N 00 O O Tr O\ N N .--r M ND vn 00 O O et en O 0 0 0 0 0 0 ee rr e. N N .--r O O O O G O -- N N ee O O O O O O O O C O C O O O C C C O O O O 6 0 0 N om- r C v) ON h O CN rn N et rn -- h v1 O OK M N et et O G O O N N r1 rn N -� O O O CD N N N rn en O O O C C G 666 666 O 0 0 0 0 G 6 0 0 0 0 0 0 N N oo rn r; u; v; CN N N C rn N N N r1 rn et in Tr ,n N r1 0 0 0 CD O r, C N C N N C. O C C O .Y O 0C O rn CD 0C C V, O p O C O N C rs O O O C C O N 0G O N O M O N ND 00 .-+ N 00 et 00 C\ N CO v1 on N O� N C M 00 O N C et N rn rn -1 on 00 N N O et rn fn c) len rn et r1 00 0C M 6 O O C J --• O N N rl -. ••: 0 0 0 0 0 0 •- r'i O r1 a a Os CviNo O V No No V 1C N N n N N n N N N @N a Ch cs erN Ch C1 C1 O\ Q� Ch r 1 r 1 r 1 I r r r C C L .. i. = DD Oftw Y ' L'adets '� V h i1 L' Op - w 4tXti"a4 n0Zto a L C fmIgQZn'5Qvi R B 6- F4 ,• o ti 8 N t; 0 2 0 R P4 ci* * * 11/04197, 04:31:01 PM 972516 00 0 0 0 0 0 0 0 O M O 00 00 -+ 0 b H b Ui O h Q 00 0 O 0 0 0 00 0 0 0 0 0 0 E- Q b- Ni P O M a n O O O O O O O O O Q O N O ' Ni Q P O M 0 a M O CC N, N O P 7 O M 0 0 0 O O O O O O O O O O Q M y r. M Q OC n M n a N a- P P 0 P a P a a P a a a P NN N c� O Q c — n a o0 0 CC O P CC a 0' C' ci ai 0 a '^ N 00 — ^ N N N N N N N N N N N N N N N N N C N N N ON M Q f C 66” Q v V a G 0 0 0 0 00 R n 000 ON 0 0 0 0 0 O x C N O m L v =Q Q x CO Q o O Q Q on t a �0 O M M O b ✓t v1 N— vC M Q N O O O Un N V N N N O N CO N Un P Q 00 0 `D O^ 0 ^ O N N CO M V M N O N O N [� N N M vC 6 0 0 0 6 N O CO vi n N m 0 0 0 6 O 0 M, Q o0 O 00 O ON Q O N W" n O0 00 N O h U, N a .c N O M CO O G , M N N o Qm vl M Q M W n N W M tsNM 6 O 6 0- 0 N N M-^ 0 0 0 0 0 0-- M O M O 1 .v c n Ni vl ^ Q" n N Q M N N Mi U, - Q- N N Q W wt N N a ^ O N M 0 o0 " M M V' -< O N M O CO - M M 0 0 0 0 0 0 0- O_ -- 0 0 0 0 0 0 0- O- -� -- 0 < v1 '-' M- O O M N ^^ M- v1 a v1 O M N Q y O N- - 0 0 0 0 N N N M M N N ^ 0 0 0 0 N N N M M N G 0 6 0 0 0 0 6 0 0 0 6 0 0 0 6 0 0 6 6 0 6 6 6 66 4 ^ N O Q O M O M O O CO a 0 a P n N P T 't n Q - y 0 'N N N N- N N vi v-, vC •p w1 Q Q Q Q N N M M Q M Q M m Si" ' � M M M Q W a n 00 N vl N O 00 O 00 00 M N 00 Q M b CO- eO OC n Q Q Q .a O 00 N O W W N e N N vl 00 0 Vl M M Q 00 CO U, 00 M. b M M� VN O U M M a P OCC N N 0 MO 00 P cc OO n co CD 0 CO ‘.0 Q I- O Q P N N N OO N O P 0 P 0 O N 00 N 00 00 0 Q Q o0 b N N Q P Q MMMQQMMMQQQCQQ Q Q Q Q oN 00 - O Q M M U' M n V 0- U 00 vi 0 0 0 0 •C '0 00 N 00 N N OO N Y. C VV' CCO CO O Cp CO 00 00 000 00OVO 00 00 000 000 Ni N N N N N N N N �z� VtbNN T OTC a .TN q OCC A G, T C� 0 CO CO CO ON 0,T Oni P Q On1 T n P ON T L '� m W m Op > > b Y O i C a 4 O' Ri C ?L C Za-�L- <Z OZ2 LAG Qa-O� < OL 2R R O L lagoon water balance2.123 11104/97, 04:29:22 PM 972516 Table 3 Hirsch Dairy USR 1091 ial Aquifer Loading Nitrogen Land Application Incremental Cummluative Nitrate Nitrate Nitrate Nitrate Year Loading Recieved * Increase Increase (lbs) (lbs) (mg/i) (mg/1) 1996 2.24 1997 15700 3140 2.59 4.83 1998 73926 14785 12,19 17.02 1999 73926 14785 12.19 29.22 2000 73926 14785 12.19 41.41 2001 73926 14785 12.19 53.61 2002 73 926 14785 12.19 65.80 2003 73 926 14785 12.19 78.00 * Based on 5 to 1 reduction from root zone leaching to aquifer 11/07/97,07:44:34 AM Aquifer Leach Table.123 972516 Table 4 Summary of Groundwater Quality Sample Nitrate Depth Location Date (mg/i) (feet) MW# 1 10/30/97 8.47 9.95 MW#2 10/30/97 9.36 5.25 MW#3 10/30/97 9.88 3.00 Drain Tile 10/06/96 7.59 Drain Tile 10/30/97 12.20 Stock Well 10/06/96 2.24 Stock Well 10/30/97 4.86 11/06/97,02:17:49 PM water quality summary table.123 972516 04 U) 4rj) 0 (i) A° 0 4ro tn x� 1.0 co - i Gradient Flow cp a C ,W '- arti 972516 04 k� w N m U) N A O 0 •rio xr� 972516 9) Field 5,03 p _\ II \II o II • 11 <952.��� _ JI. 4969 I<94p 5025 1F1Rt tr (C7 D • Lt.. LS • Ssotic 111R.Su+) ,.) wsa.• .1 (zzi,�)°°�� • — �;v1 ' Loop Lake ••� � �� —� u Ill "—` " 5002 • • • y *1 N‘h 4,10NarT02414 fo WCU,S 3325 'd�<9 Hew Windsor 4936 494/ '—e m 503/ i1 7Z.oc..uN p>in>Z A2uw -it, STu Dr .t t& 986 5025 • 4949 VSR toil L�r�F EkJ, G1 >zi G • _ !: Severance • 4574 BaldriddeLake P01119 B1 __.. Sr ?Bpi La its • A )hgcl Lake 4900 9/2516.. OCT-27-1057 :5:15 WELD COUNTY HERLTH DEPT Post -h' Fax Note 7671 Phone # Date # o1 pages 11 From fit.Pbr L jiiCIV'(: Co. Phone* Fax Wib�.. COLOR DO September 24, 1997 Fax # C 1970 564966 P.01 IEPARTMENT OF HEALTH 1517 16TH AVENUE COURT GREELEY, CO 80631 ADMINISTRATION (970) 353-0586 HEALTH PROTECTION (970) 353-0635 )MMUNITY HEALTH (970) 353-0639 FAX (970) 356-4966 Derald Lang Water Quality Control Division Colorado Department of Public Health and Environment 4300 Cherry Creek Drive South Denver„Colorado 80222-1530 Dear Derald: As you are aware, our County Commissioners have requested that our staff review the Hirsch Dairy, manure and waste water manegemen plan (the Hirsch Plan) for compliance with the Confined Animal Feeding Operation Control Regulations (5 CCR 1002-81). However, due to a "gray area" in the CAFO Regula 'ons we are finding it difficult to complete our review. Specifically, it is not apparea_ whether tailwater ponds which would capture and temporarily store process waste ter, applied through flood irrigation methods, are required to be lined. Due to this "gray area" we are requesting that your staff provide an interpretation in regard to this requirement. As you know, Section 4.8.4 of the CAFO Regulations requires that retention structures constructed after August 30, 1992, have evidence that a liner has been constructed and meets a specified pecaieability. However, it does not indicate if tailwater ponds must be lined. The Hirsch Plan is proposing an unlined tailwater ond. This pond will capture and temporarily hold process waste water which has be n land applied through flood irrigation practices. According to the Hirsch Plan. y captured process waste water will be immediately pumped back into the facility's primary retention structure. I am in receipt of a letter dated December 20, 199 to Victor Sainz from Dave Rau and Brick Smith of Terracon Environmental, Inc, whit is a summary of a meeting in which you attended. This letter indicates that tailwater ponds are not required to meet lining requirements. The letter indicates that you have received a copy of this letter. However, subsequent conversations with you lead me to believe that evidence of a liner is required by the CAFO Regulations. I 1 972516 -7 re.+J�=750 F. ;2.G Derald Lang: Water Quality Control Division September 24, 1997 Page 2 It is apparent that there is not a consensus on the inte CAFO Regulations and that additional review of this scheduled to present our review to our County Co,t� 1997. Therefore, we would request that your written Tuesday,' September 30, 1997. We truly; appreciate your assistance in this matter. I not hesitate to call me at (970) 353-0635. extension Sincerely, Trevor Ji icek Supervisor Environmental Protection Services tj1830 cc: IohnPickle, Weld County Health Department Dave Holm, Water Quality Control Division Lee Morrison, Weld County Attorneys Office Dave Rau, Paragon Consulting Group Victor Sainz, Water Quality Control Division retation of this portion of the item is warranted. We are ssioners on Wednesday, October 1, interpretation be faxed to us by you have any questions, please do 232. 972516 RoyRomer. Governor' Pali Shwayder, Executive Director Dedicated to protecting and improving the health and environment of the people of treat 4300 °.a, Creek Di.9. taborxory and Radiation Seniees Divion I Denver, Colorado 30t46-1530 8700 Lon, Blvd. 1 Phone (303) 692-2000 Denver 00 80220.6928 (303) 692.3090 STAT OF COLORADO Located in Glendale, Colorado http:/Mww.cdphesra fe,:.vs d September 30, 1997 Weld County Health Department 1517 16th Avenue Court Greeley,, CO 80631 Attn: Trevor Jiricek Re: CAFO Regulations Question on Tai 'ibear Trevor: This letter is in response to your wherein jyou requested an interpreta concerning the need to seal taiiwat stating Hthat this is a somewhat "gr, CAFO regulations. Understanding the d will hopefully aid in applying the r The section of the regulation ( tailwater ponds installation is in surface; water quality from run -of practices. Thus, the need to seal when the' regulation was developed for common practice with flood irrieatia land application disposal plan incorp. of a closed loop system; then thie pot qualityiwould need to considered. From the description in the Hirsch P potential for groundwater quality i that the resident time of any proces is minimal. Under this situation I this tdiwater pond because the po other tailwater ponds in use with fl surrounding area. • Colorado imt af Polak and m water Ponds. etter of September 24, 1997 on of the CAFO regulations ponds. You are right in y area" in interrupting the velopment of the regulations lation to the Hirsch Plan. 1.5(A)(2)) which addresses ended to cover impacts to due to flood irrigation ese ponds was not an issue he use of tailwater ponds is However, should a feedlot rate a tailwater pond as part ntial impacts to groundwater an it would appear that the pacts will be very small in water in the tailwater pond ould not see a need to seal ntial impact is not unlike d irrigation practiced in the 972516 aL )• )'— -t . . JG Should you have ;3561. Sincerely, bald Itng, PE cc: Johh Pickle, Weld County H alth apartment Dave Rau, Paragon Consulting Gro p Dave Holm, WQCD Victor Saint, WQCD any further questions k please call me at 303/692- 972516 1 Hirsch Dairy Nitrogen Balance Prepared by Randy W. Ray, Agronomist Forrest Leaf, P.E. Leaf Engineering Route 1, Box 75 Merino, CO 80741 Forrest: October 28, 1997 I have reviewed the nutrient management plan for the Hirsch Dairy near Severance, CO. Based on my knowledge and expertise in nutrient management plans and overall water quality monitoring, I have made some conclusions regarding the report preformed by Paragon Consulting Group. Below is a table (Table 1) containing information for the effluent application at the Hirsch Dairy. Table 1. Hirsch Dairy Effluent Balance Current Facility (766 Milking Cows) Total Nitrogen Net Crop Acres Req. Additional Water Content Nitrogen Nitrogen Agronomic Acres for Volume Effluent Load Demand Rate Application (sue (Ibsl (Ibsl (lbs/ac) 1ac.1 (ac) 4,598,674 18,395 11,957 154 77.64 68.56 Hirsch Dairy Effluent Balance Proposed Facility (1,380 Milking Cows) Total Nitrogen Net Crop Acres Req. Additional Water Content Nitrogen Nitrogen Agronomic Acres for Volume Effluent Load Demand Rate Application Lac jlbsl (Ibsl (Ibs/ac.) (ac) _WI 9,096,193 36,385 23,650 154 153.57 7.37 972516 Page 2 Table 1 indicates that only 78 acres are required for application of effluent and runoff nutrients from the current dairy. This will allow the Hirsch Dairy to apply dry manure to the additional 68 acres. This additional application of dry manure must be closely monitored to prevent over application of nitrogen. Considering the proposed expansion of the dairy, Hirsch Dairy is going to need additional acres to apply this effluent. From calculations, an additional 7 acres is needed to keep the nitrogen application at or under agronomic rates. There will be an annual variation in precipitation runoff volumes, but not a dramatic change in net nitrogen load since the majority of the water in the lagoon consists of dairy process water. The nutrient value for the calculations were taken from the BMP's for Agriculture, published by Colorado State University. A value of 4 Ibs/1000 gallons of nitrogen was used in this table. I was advised that on the week of October 20, Hirsch Dairy applied feedlot manure to the 146 acres. I am assuming a typical application rate of 20 ton per acre, and using the BMP Guide for nutrient content. Table 2 shows the effects on the nutrient balance with consideration of the effluent applied as irrigation water. Table 2. Manure Application and the Effect on Effluent Application Hirsch Dairy Current Facility Effluent Application Nitrogen Nitrogen Nitrogen Net Excess Rate Content Content Allowable Nitrogen Nitrogen T/ac abs/T,) (Ibs) (Ibsa Ibs ibs 20 9 26,280 22,515 11,957 15,722 972516 Page 3 Manure Application and the Effect on Effluent Application Hirsch Dairy Proposed Facility Effluent Application Nitrogen Nitrogen Nitrogen Net Excess Rate Content Content Allowable Nitrogen Nitrogen (T/ac) (Ibsrr) (lbs) (Ibs) (lbs) (lbs) 20 9 26,280 22,515 23,650 27,415 The concern is evident in Table 2. The Hirsch lagoon is currently nearly full of effluent, and the dry manure applied this fall already exceeds crop nutrient demand, without including possible soil nitrogen contents, and additional irrigation water (Smith Lateral) nutrient content. From my calculations, Hirsch Dairy will exceed agronomic nitrogen application rates for the 1998 growing season (15,722 lbs), under current conditions (766 milking cows). The proposed facility will have a huge effect on the nitrogen balance if dry manure is applied to all 146 acres. The over application of nitrogen will be 27,415 lbs, nearly doubling the effect on the current facility. Another concern is the constant application of organic nitrogen, which will continue to mineralize in the soil over a period of several years. As an example, only 30% of the first year applied organic nitrogen will be mineralized. This leads to a building effect where the mineralized nitrogen builds to a point where little or no effluent or dry manure can be applied and maintain agronomic application rates. Phosphorus and other minerals may be of concern at this site where a large concentration of animals are located. 972516 co a) C 5 O • w z o 0 < OZ U_ cn0 E .- • O O C (0 < NW 2X U a)� E.��. o 0 T5 a> Q M 2 x Q C 0 (1 0 C O CO CO L O E U + 2 C N C O a M III() Z20(13 rna) Y_ m C et 11) 13 C tD CD Cr) N w M.alg 22°M M o z ClZ�' C C R (A w 7 U. O W7 J Z N X C (aia 0 0 o H +- z c o 0 C 7 M (O _ > z U W M a, (D 0 • (0 ti N. O O — U, N 0 0 N Na) L O 41 O) 7.v CO v � • M OD M 0)0 U) O .O nr _ 0 C' M 0 E . 6 }--?M O 0) Ch > ~- 0 w a) 0 O a; E u) C M 3 m (p rx > > v. N '7 0 a r v a E y N U co 7 M N d > > II1N co o z c z W C 0 • O 0 j z C . z C 0 0 .M 0 O M C • 00 co • 0 2z > To `w E o co 0 q N N 0 O 0 .0l0 U MN M LO N- 0 (O N N (n . M M M O OQ a u) o w? E in C (-0 7 (o O) > rn(0 N 0 a)D E U ((pp M M (n d �> 2-45 -'(CO Dry Feedlot Manure Applied @20 T/acre 10/21-10/23 a .E C)0(U O • C 4 ~ O f▪ 5 E o , M I-- U Z te -1 17) w 0 C U C C a m a .0 0) oo°oA I- U UZJ �'a 0 O w M a - n E 00 O �J �. (iJ J a(13 C a) W 'O CO 0 C d U O ti M OD N. N C 0 (C O p) 7 7 M O 2W C l3l O ►- >�� (o z N `) 0 N M y X O O O ai O N O O O O N 97216 WELD CQc f LE, OTIS, FREY & HELLERICH, LLC RICHARD N. DOYLE HENRY C. FREY THOMAS E. HELLERICH FRED L. OTIS G. BRENT LOAN ELLEN S. MINNIG ATTORNEYS AT LAW 1997 KW 17 CM 2: 22 West Greeley Law Center 1812 56th AVENUE CLERK GREELEY, COLORADO 80634 TO THE P','` ;` (970)330.6700 November 17, 1997 Board of County Commissioners Weld County 915 Tenth Street Greeley, CO 80631 RE: Hirsch Dairy USR 1091 Dear County Commissioners: DENVER METRO (303)659-7576 FAX (970) 330-2969 HAND DELIVER I am enclosing herewith a copy of a letter from Forrest Leaf, dated November 17, 1997, with regard to the above -captioned matter. Please include this as a part of the record in USR 1091. Very truly yours, THOMAS E. HELLERICH Attorney at Law TEH:cjm Enc. pc: Via Fax: Todd Hodges do , Pt, C A 972516 14 EXHIBIT jr. Forrest Leaf, P.E. 13946 CR 56 Hilirose, CO 80733 (970) 590-1787 LEAF ENGINEERING November 17, 1997 Mr. John Pickle, Director Environmental Protection Services Weld County Health Department 1517 15 Avenue Court Greeley, CO 80631 RE: Hirsch Dairy, USR 1091 Dear John: This letter is to follow up on my letter of November 10, 1997 and to summarize my concerns with regards to the applicant's proposed Mature Management Plan, your staff's review of this plan and the issues that I have identified with this plan and your staffs approval of this plan. The applicant was directed to meet the requirements of the County Commissioners December 16, 1996 Resolutions and Development Standards. Subsequently, the applicant's consultant, Paragon, prepared a September 26, 1997 report entitled "Manure and Wastewater Management Plan for the Hirsch Dairy". This plan is the basis of my review, in addition to observations I have made at the USR location. It is important to note, that I observed construction activities and land application activities on the subject USR site directly related to the USR requirements prior to submission of this proposed plan on September 26, 1997. It is obvious that even though this plan has not been approved by the County, the applicant and County staff have willfully allowed this expansion to proceed. It was the express intent of the County Commissioners, that public input would be part of the review process prior to the approval of this plan, either officially by the Commissioners or indirectly by your staff and the County Planning staff. Your staffs actions approving such activities prior to the approval of this USR is viewed as a willful and wanton act which contradicts the December 16, 1997 Board Resolutions and Development Standards. Of greater concern is the fact that the applicant has and continues to provide false and inaccurate information to your staff but your staff never does an independent review of the applicant's or its consultant's proposed plan. Below are a few brief ieueat examples from the September 26, 1997 "Manure and Wastewater Management Plan". 'LEAF ENGINEERING Hydrology ° Hydraulics ° Water Resources ' Water Quality EAIEAFLMMAIe Pon I.efrwpd ;372516 Pickle Letter Page 2 1. In a letter dated March 17, 1996 from Terracon to Victor Sainz (copy to WC13D), the applicant was to take water quality samples. In the Septeber 26, 1997 plan, no mention of this testing is made. Considering the demonstrated shallow aquifer and ongoing pollution of this resource by the applicant's existing lagoon and land application practices (as shown in my amended letter of November 10, 1997) it is inconceivable that your staff could forget to require this quality monitoring, let alone state to the Commissioners, at the November 5, 1997 hearing, that they informed the Commissioners the applicant's plan met all December 16, 1997 Resolutions and Development Standards. 2. Section 2.2 of the plan, page 5 states that "unconsumed process tail water will be captured by drainage/diversion ditches which have been installed along the north and west boundaries of the property and will be directed to the proposed tail water pond sump system." In fact no such ditches have been installed In addition, pursuant to the December 16, 1997 Resolution 2.A.(2), there is no design criteria to show how these ditches will meet the 1 x 10' cm/sec for all waste water retention structures. 3. Page 11 of the September 26, 1997 plan, states that in -place compaction tests in the location of the proposed east retention pond will be conducted to ensure 1 x 10' cm/sec CAFO permeability standard is met. Please refer to the December 16, 1996 Resolution 2.(A) which requires (in addition to CAFO requriements) that all wastewater retention facilities and wastewater collection and conveyance structures be designed for a 25 year, 24 hour storm event with permeability of 1 x 10' cm/sec. The applicant has not demonstrated that this criteria has been met for the retention pond and conveyance ditches. Your staff informed the Commissioners that the plan was adequate on November 5, 1997, even though no required in -place samples were presented to your staff or the Commissioners. In addition in my opinion, this facility has not been designed to capture and detain generated storm water runoff for the 31 acre basin, it is not in the location as indicated in the September 26, 1997 plan, and was purposely located over an easement without Mr. Rauh's permission, thus destroying the pipeline. Finally, this structure does not meet the criteria for evaporative systems required by CAFO 4.8.3(C)(5)(B). Of particular concern is the gross deception presented by the applicant concerning the east retention pond. The applicant submitted to your staff Figure 4 and Figure 3 showing details of this facility. This was submitted on September 26, 1997. However, prior to October 9, 1997 the applicant, his attorney and engineers already knew that the lagoon would not be constructed as presented to your staff, the state and the Commissioners. Enclosed is a copy of an October 9, 1997 letter and lagoon plan Why didn't the applicant disclose to your staff and the state the "new plan" in early October'? Why didn't the applicant disclose the "as constructed" pond at the November 5, 1997 hearing? If your staff had conducted a site inspection they would have known the east pond was • LEAF ENGMEERI NG Hydrology • Hydraulics • Water Resources ° Water Quality F.: \ LEAFUNISPickle Plan 1n4 972516 Pickle Letter Page 3 constructed without a permit and not as proposed. Your staff apparently had knowledge of the construction of this pond because of the applicant's application on October 10, 1997 for a building permit. Why didn't your staff disclose the new location, configuration and the fact this facility existed to the Commissioners on November 5, 19977 4. Section 2.5 and 2.6 discuss that site specific agronomic analyses will be performed before applying solid manure. In fact, no agronomic analyses, or information of any kind, has been performed and provided to your staff However, the applicant has applied an estimated 30 tons per acre of dry manure during the week of October 20, 1997 and again on November 7, 1997. Obviously, the over application of manure continues to get worse and is being willfully allowed by your staff. 5. The applicant's proposed tail water pond, also part of the October 10, 1997 building permit application, does not meet the requirements of the December 16, 1997 Resolution at 2.(A.)(2) in that it will not be designed to detain a 25 year, 24 hour storm event and meet the permeability standard of 1 x 104 cm/sec. While the state may not require that this facility met the standards set forth in 4.8.3 of CAFO, (see enclosed letter from Derald Lang) it is apparent that this is required of the applicant by the County pursuant to the Resolution at 2.(A.X2). John, I have raised numerous concerns and questions of the applicant's and your staffs preparation review and presentation of this USR plan. This letter identifies only some of the inadequacies of the applicant's September 26, 1997 plan. Until these issues, and others, are properly reviewed a recommendation of' approval is grossly negligent. Sincerely, LE cc: Tom Hellerich Ken Lind Enclosures Forrest Leaf, P.E. LEAF ENGINEERING Hydrology • Hydraulics • Water Resources • Water Quality muntuxquorisk PI® rime vpd 972516 P L 1059 NOVEMBER 19, 1997, HEARING DATE EXHIBITS M, O, Q, U, V, AND W PLEASE SEE ORIGINAL FILE 972516 Hello