CHANGE ORDER NO. 1
DATE: February 19, 1996
PROJECT: CONSTRUCTION OF WELD COUNTY BRIDGE WEL 050.0-067.0A
TO (CONTRACTOR): Les Matson Construction Inc.
JUSTIFICATION: Additional quantities were needed for construction changes in the field.
You are directed to make the following changes in the work. All other terms and conditions of the contract not
expressly modified hereby shall remain in full force and effect.
ITEM NO. DESCRIPTION EST. OTY. UNIT UNIT COST AMOUNT
203 Embankment Material 2344 C.Y. $3.40 $7,969.60
206 Structure Excavation 1071 C.Y. $5.75 $6,158.25
304 Aggr. Base Course 153 Ton $10.50 $1,606.50
403 HBP (asphalt) 334 Ton $30.50 $10,187.00
502 Steel Piling 1909.15 L.F. $28.00 $53,456.20
603 30" Concrete Pipe 88 L.F. $48.00 $4,224.00
603 End Sections 2 Ea. $775.00 $1,550.00
The original contract sum was $ 1,136,136.63
Net change by previous change orders $ 0.00
The contract sum prior to this Change Order was $ 1,136,136.63
The contract sum will be Hummed) (decreased)
or(unchanged) by this Change Order $ 85,151 55
The contract sum including this Change Order
will be $ 1,221,288.18
The new contract time will be(inereand) (decreased) or(unchanged) by thirty-three (33) days.
The date of completion as of the date of this Change Order is therefore February 23, 1996
960379 EGG5
aIa X%3
ACCEPTED BY: BOARD OF COUNTY COMMISSIQQNERS
WELD COUNTY,COLORADO%"
By Matson Construction. Inc. /� 1
^,{ BY, J4 Jza (it_'/ T J77-1G//L_
NAME /25 MA is a.V Barbara J. Kir eyer, C n 0/x/74
(Please Type)
ADDRESS R O i? x / 8 6 o
/
4u•
(Seal) 1861 O) V2--
moils ' WA
ATTEST .+ �O 1rs`� e► D?
�J �+
CONTRACTOR: ��
C//1� —. ty Clerk to the Board
BY oi tss /A 7S a BY F ��,L k 11,,
(Please Type) Deputy( Jerk to the Board
TITLE 19/2 .S/nal /Lir
LES MATSON CuilSTRUCTION INC.
MATSON P.G. Box 1830 • Greeley, CO 80632
Phone )303) 356-3201
January 31, 1996
Weld County Engineering
933 North 11th Avenue
Greeley, Colorado 80631
Attention: Wayne Howard
Re: Weld County Bridge Project Wel 50.0-067.0
We request that additional time be added to the contract time allowed for the completion
of this project. The number of days requested and the reasons these extra days are being
requested are as follows:
(1) There was an increase of 51% in the amount of H-piling driven from the stated
contract amount.
Days added to completion date 15 days
(2) The water table was higher than normal during key phases of pier construction
causing delays.
Days added to completion date 14 days
(3) Additional items added to the project:
321 tons of asphalt
Base preparation for asphalt
Surveying necessary for base preparation
Days added to completion date 4 days
TOTAL DAYS REQUESTED 33 days
Thank You,
Les Matson
��� mEmoRA(1DU !�
I E nr frcou Mt.
122 PM 1-1• ' 0
February 22, 1996
Clerk to the Board to CLERK
W �. To , L THE
COLORADO From Drew Scheltinga, County Engineer
Subject: Consent Agenda Item
Please place the following item on the Board's next agenda:
Consent signature of the Chair for change order approval on Bridge 50/67A
contract with Les Matson Construction.
The appropriate documentation is attached.