HomeMy WebLinkAbout991464.tiff '50107-H:t MEMORANDUM
TO: Board of County Commissioners DATE: MAY 26, 1999
FROM: Frank B. Hempen, Jr., P.E., Director of Public Works/County
CEngineer
SUBJECT: Roadway Capital Investment Plan
COLORADO
Attached is the summary of the Department's recommendation for Roadway Capital Investments for the next three
years which are typically financed from the operating budget. We are calling it the Three-Year Firm Plan. It
represents the first element of our recommendation to develop a longer range planning document for roadway
improvements and maintenance.
I am recommending the Board approve a process in which the Department describes the Firm Plan to county-wide
stakeholders (town councils, school boards, etc.). Input from the stakeholders would be solicited for at least an
additional Five Year"Soft" Plan. In concept,the soft plan projects would be prioritized and become the last year
in the firm plan with each of its annual iterations. As always,it is understood that projects not previously identified
may require adjustments to the plan.
Capital projects resulting from implementation of the Impact Fee Study are not included. When this program
commences, they will be programmed accordingly.
Our plan approach is to"hold harmless"System Preservation(SP)projects and designate them as the Department's
number one priorities.Included in SP are the various seals,crack filling,and maintenance overlay projects necessary
for routine maintenance of the roadway system. Also included in SP are roadway rehabilitations, and as a subset,
structural overlays. Rehabilitations and structural overlays are treated differently because they are 20-year
investments and consideration should be given to vertical and horizontal upgrades as a part of their construction.
The second priority should be given to "Spot" Safety Projects. Localized improvements such as intersection
improvements, short sections of shouldering in high volume and accident areas, and limited roadway alignment
corrections are examples of projects in this category.
The balance of the investment program is dedicated to New Construction. Examples of this type of work include
Two Rivers Parkway, a future "South Platte Parkway" (WCR 32 relocation at Platteville), development
improvement projects, etc.
Rehabilitations, structural overlay projects, Spot Safety Projects, and New Construction projects all require
consideration of vertical and horizontal alignment issues. Stated simply, they will typically require new or more
right of way than the existing right of way. Additional project development time is required to design,acquire right
of way,relocate irrigation facilities,coordinate utility relocations,etc.to ensure these issues do not create continual
crisis scenarios.
The plan being presented anticipates longer project development times while continuing to address the work needed
to maintain our roadway infrastructure needs. The transition to advance planning will take place over the next three-
year period. The attached displays delineate the detail of the transition, and I will attempt to explain them in detail
in the presentation.
991464
O r.,- -
) brewtvi=... dxsi
A
4
e 14 No-
le v
ri Ll 11 if Ns
H le ./',
It C)
I t�r
,
COLORADO
D 4
al ' liran
�O IC nail
dap Ma Iran
MIES'OM
INDEX
PAGE l�0tPiC
1 FUTURE EMPHASIS
2 SYSTEM PRESERVATION
3 PAVING AND REHABILITATION
4 SUMMARY LIST OF PAVING PROJECTS
5 SUMMARY LIST OF REHAB PROJECTS
6 SUMMARY LIST OF STRUCTURAL OVERLAYS
7 SPOT SAFETY PROJECTS
8 SPOT SAFETY PROJECT LIST
9 SUMMARY LIST OF SAFETY PROJECTS
10 NEW CONSTRUCTION
11 SUMMARY LIST IF NEW CONSTRUCTION
PROJECTS
12 SPECIAL PROJECTS
13 SUPPORT PROJECTS
14 RESOURCE ALLOCATION TRENDS
15 FIVE-YEAR COST PROJECTION
FUTURE
EMPHASIS
1
SYSTEM PR.ESERI \ TtO
CHIP SEAL
CRACK SEAL
K"--- SLURRY SEAL
MAINTENANCE OVERLAYS
SAND SEAL
r 4 PAVEMENT MANAGEMENT SYSTEM
SN SIEN/I PRESERVATION
HABILITATION
SPOT SAFETY
SHOULDER WORK
ALIGNMENT
DRAINAGE
zz
NENA CONSTRUCTION
SPECIAL PROJECTS
NEW ROADWAYS
1
SYSTEM PRESERVATION/ MAJOR IMPROVEMENTS
COMPARISON
YEAR 99 YEAR 2000 YEAR 2001 YEAR 2002 YEAR 2003 YEAR 2004
SYSTEM PRESERVATION $4,667,457.00 $4,704,482.00 $4,639,111.00 $4,899,098.67 -$5,031,580.01 $4,915,336.42
MAJOR IMPROVEMENT $3,897,128.00 $3,884,222.00 $3,885,165.00 $3,797,964.67 $3,938,790.81 x$3,846,616.64
TOTAL EXPENDATURE $8,564,585.00 $8,588,704.00 $8,524,276.00 $8,687,063.34 $6,970,370.82 $8,761,953.06
TOTAL REVENUE $4,830,501.00 $5,475,416.03 $5,120,331.06 $5,273,940.99 $5,432,159.22 $5,595,124.00
NEW CONST $195,470.00 $225,400.00 $268,650.00 $439,874.00 1510,433.00 $409,613.00
SAFETY CONTRACT $12,000.00 $23,000.00 $12,000.00 $14800.00 $0.00 $0.00
PROFESSIONAL SERVICES $50,000.00 $200,000.00 $75,000.00 $75,000.00 $75,000.00 $75,000.00
NEW CONST.ROW $350,000.00 $100,000.00 $100,000.00 $100,000.00 $100,000.00 $100,000.00
EQUIPMENT RENTAL $90,000.00 $90,000.00 $90,00000 $90,000.00 $80,000.00 $90,000.00
SPECIAL $232880.00 $250000.00 $250,000.00 $25000000 $250,000.00 $250,000.00
SAFETY $179,799.00 $305,860.00 $334,296.00 $510,300.00 $447,477.00 $526,350.00
CHIP SEAL $500,000.00 $800,000.00 $612,000.00 $624,240.00 $836,724.80 .$649.459.30
SAND SEAL $50,000.00 $50,000.00 $50,000.00 $50,000.00 $51,000.00 $52,020.00
SLURRY SEAL $485,000.00 $400,000.00 $408,000.00 $416,180.00 $424,483.20 $432,972.86
TESTING $35,000.00 $30,000.00 $30,900.00 $3182700 $32,781.81 $33;785.28
OVERLAY $554,575.00 $628,083.00 $270,965.00 $287,01900 $418,027.00 "$303.388.00
STRUCTURAL OVERLAY $0.00 $29,000.00 $277,913.00 $55,583.00 $111,165.00 $117,341.00
MILLING $45,000.00 $50000.00 $51,500.00 $53,04500 $54,638.35 $56,275.44
CONTRACT TRUCKING $1,136,600.00 $1,301,850.00 $1,318,350.00 $1,160,000.00 $1,160,000.00 $1,170,000.00
REHAB $461,953.00 $104,989.00 $166,748.00 $402,578.00 �:` $333,486.00 -:$305,704.00
TREE REMOVAL $80,000.00 $100,000.00 $100,000.00 $100,000.00 $100,000.00 ,$100,000.00
MISC.CONST.SUPPLIES $210,000.00 $216,300.00 $222,789.00 $229,472 67 ! $236,366.85 '.:$243.447.`56
CRACKFILL $65,000.00 $100,000.00 $102000.00 $104,040.00 $106,120.80 $108,243.22
STABILIZATION $24,000.00 $24,000.00 $24,000.00 $24,000.00 $24,000.00 $24,000.00
BRIDGE MAINT. $250,000.00 $250,000.00 $250,000.00 $250,000.00 .: $260,000.00 $250,000.00
i}ffi�'�I15P,.'ISF'�l'W'..Y`II'1`yP , ,ff"Y!IG.i�4wir .‘grrM r , -��1
4#?143,:+yrslikwxYi0-4r,,,IT:fi rc+ ;1it47-:n*`rrr:'gt;11`t� ""`Atft''.. 13 MAJOR IMPROVEMENT
W"¢N n ,f`"C u£;'a • �r i y. ;fisu;,b, i; ®SYSTEM PRESERVATION
o P F, T TM.1 J+9, � F Otti^-L"1 ri't-45 f 7 ' ;
+. grs- M.^: ,i" J vrzi,, f jrwa +a,-,..1,•';',..",•±4-1,;i,
2
PAS'' I NJ 0 A.NJ 0
REHABILITATION
PRC?J ECTS
Paving projects are primarily derived from the annual pavement testing program. The results
from the testing together with the PQI(Pavement Quality Index) ratings from the pavement
management system help establish scheduling for routine overlays.
Criteria used for analysis are as follows:
1. Deflection analysis
2. Sub-grade type
3. Sub-grade moisture content
4. Existing base thickness
5. Current traffic volumes
Rehabilitation projects can be a total reconstruction, isolated areas of sub-grade repair, structural
overlays, or a combination of all three. The same criteria is used in determining the
rehabilitation areas as is used in the paving projects.
For Rehab projects, safety improvements will be added where needed.
MILES PER YEAR
25
Design
20
5 Of I Design
o
s - J
�� is -AM
1999 2000 2001 2002 2003 2004
PAVING
I. REHABILITATION
3
05/26/99
SUMMARY LIST OF PAVING
PROJECTS
�
2000 Maintenance Overlay
ROAD LOCATION MILES MILES ASPHALT ASPHALT ASPHALT TOTAL
DESIGN PAVE THICKNESS TONS COST LABIEQUIP.
COST
73 AND 77 2 2 3,088 $55,583 $67,934
44 47AND49 1 3 2,316 $41,687 $50,951
44 1-25 AND 13 2 2 3,088 $55,583 $67,934
ELMORE ROAD S. HWY 66 0.6 2 926 $16,675 $20,380
„.39,5 _,F_ U .-;; 64 TO N. END 0.6 2.5 1,158 $20,843 $25,475
x;;11 , 42 AND 44 1 1.5 1,158 $20,843 $25,475
31 74 AND HWY 14 4 3 9,264 $166,748 $203,803
16 23 AVE AND 35TH AVE 1 3 2,316 $41,687 $50,951
42 11 AND 13 1 1.5 1,158 $20,843 $25,475
77,, , ; HWY 52 AND 16 2 3 4,632 $83,374 $101,901
51 74 AND 80 3 1.5 3,474 $62,530 $76,426
5 34 AND 36.5 1 3 2,316 $41,687 $50,951
TOTAL 18.2 34.893 8628.083 $767.657
2001 Maintenance Overlay
31 74 AND HWY 14 4 3 9,264 $166,746 $203,803
-66 HWY85 AND 37 1 1.5 1,158 $20,843 $25,475
41 AND 45 2 3 4,632 $83,374 $101,901
TOTAL Z 15.054 8270.965 $331,179
I
2002 Maintenance Overlay
39 74 AND 78 2 3 4,632 $88,006 $101,901
43 • HWY 392 AND HWY 14 3 3 6,948 $132,009 $152,852
392 HWY 37 AND 68 2.5 1.5 2,895 $55,004 $63,688
47 HWY66ANDRD34 0 2.5 0 $0 $0
57 44AND46 1 1.5 1,158 $22,001 $25,475
TOTAL 0,5 15.633 8297.019 $343.917
4
0512660
SUMMARY LIST OF REHAB PROJECTS
1999 REHAB SUMMARY
ROAD LOCATION CONSTRUCT ASPHALT ASPHALT COST DESIGN
MILES THICKNESS TONS MILES
:-51s HWY392 AND 74 3 4 9,264 $157,484 0
45 ': 4 AND 6/8 AND 10 2 4 6,178 $104,989 0
59`:: I-NVY 34 AND 46 3.8 4 11,734
5481,953 0199,480 0
TOTAL 8.8 9264
I 2000 REHAB SUMMARY
ROAD LOCATION CONSTRUCT ASPHALT ASPHALT COST DESIGN
MILES THICKNESS TONS MILES
165; RD 59 TO RD 63 2 4 6,178 $104,989 0
13 ! RD 32 TO RD 38 0 4 0 $9,000 3
394.`. HWY85 TO 31 0 4 0 $12,000 4
` 13 RD 38 TO RD 44 0 4 0 $9,000 3
TOTAL 2 6176 $134,989 10
2001 REHAB SUMMARY
ROAD LOCATION CONSTRUCT ASPHALT ASPHALT COST DESIGN
MILES THICKNESS TONS MILES
laill RD 32 TO RD 38 3 4 9,264 $166,748 0
fl RD 38 TO RD 44 0 4 0 $9,000 3
cl HWY 392 TO RD 74 0 4 0 $9,000 3
TOTAL 3 9264 $184,748 6
1 2002 REHAB SUMMARY
ROAD LOCATION CONSTRUCT ASPHALT ASPHALT COST DESIGN
MILES THICKNESS TOT PNS 4 $186,748 MILES
13.+.. RD 38 TO RD 44 I 3
--: 0
35'1 S:RD 394 TO HWY85 0 4 0 56,000 2
(-:35'.:. RD 74 TO AULT 0 4 0 $7,500 3.5
TOTAL 3 9284 $180,248 5.5
. .2003 REHAB SUMMARY
ROAD LOCATION CONSTRUCT ASPHALT ASPHALT COST DESIGN
MILES THICKNESS T
TONS
$166,748 MILES
W 35:. HY392TORD74 3
17 0
RD RD 54 TO RD 62 0 J 4 0 I $12,000 4
TOTAL 3 9264 $178,748 4
5
0526199
STRUCTURAL OVERLAY
SUMMARY
2000
ROAD LOCATION MILES MILES ASPHALT TA TOTAL TOTAL
DESIGN '.
PAVE HIC NESA TONS COST LT LAB/EQUIP.CONTRACT
COST COST
21 74 AND HWY 392 3 0 4 0 $0 $0 $9,000
17 HWY 34 AND 54 2 0 4 0 $0 $0 6,000
25TH AVE F ST. AND O ST. 1 0 4 0 $0 $0 $3,000
TOTAL Q 4 SD $0 $18,000
2001
21 74 AND HWY 392 3 4 9,264 $166,748 $203,803 $0
ti7 ,v HWY 34 AND 54 2 4 6,176 $111,165 $135,868 $0
,....TS; 7 ;':Y.* HWY 66 AND 32 1 0 4 0 $0 $0 $3,000
35 _.;4; ' 44 to 46 1 0 4 0 $0 $0 $3,000
TOTAL 5 15.440 $277.913 $339,671 $0
I 2002
25TH AVE F ST.AND O ST. 1 4 13,088 $55,583 $67,934 $0
7-
x t`,i` RD 34 RD 38 2 0 4 3.088 $55.583 $67,934 $6,000
TOTAL 1
ZOOS '
35 44 to 46 1 4 3,088 $55,583 $67,934 $0
`43,, ',' i> `, HWY 66 AND 32 1 4 3,088 $55,583 $67,934 $0
6.176 $111,166 $135,868 $0
2004
17 -> RD 34 AND RD 38 2 4 .. 1 6,176 $117,341 $135,868 $01
6
SPOT
S. . .' ET'`r'-
P F2O,J CTS
There are three main criteria that are considered in creating a safety project.
• ACCIDENT HISTORY
• TRAFFIC VOLUMES
• FUTURE TRAFFIC PROJECTION OR NEEDS
Each year new accident information and traffic volumes are accumulated for analysis. This
information is then computed to determine the road sections in most need of consideration. The
table created on the following page shows current results based on the ranking system that
associates information and traffic accident information.
MILES PER YEAR
// DESIGN
--/. :cgs::'..
rc..i
i.....
i't
10 J _
0
MILES
1099 MN 2000 Ns 2001
- 2002 MI 2003 M 2004
COST PER YEAR
DESIGN
DESIGN -
$5,000,000
_/ Ill Ill
$4,000,000 III NI NI
$3,000,000 ■ ■ Ill
$2,000,000 ■ ■ . II
$1,000,000 _!_n —!_ 1�
- �
50 I i
1999 2000 2001 2002 2003 2004
MI TOTAL JOB COST MI CONTRACT SERVICES
ASPHALT PURCHASE
7
SPOT SAFETY PROJECT LIST
SECTIONS ARE RANKED BY TRAFFIC AND
NUMBER OF ACCIDENTS IN ONE YEAR
ADT 50% 0 TO 500 = .1 501 TO 2500 =.2 2501 AND OVER =.3
ACCIDENT 50% 0TO3 = .1 4TO5 =.2 6 AND OVER =.3
ROAD LOCATION ADT ACCIDENT COMBINED
1997 RANK #
54 TWO RIVERS AND HWY 257 5406 5 0.5
49 ROAD 48 AND RD 36 2286 6 0.5
64 GREELEY TO WINDSOR 1200 11 0.5
27 RD 2 TO FT LUPTON 1781 11 0.5
49 1-76 AND RD 26 2885 2 0.4
74 RD 19 TO HWY 257 4825 1 0.4
74 RD 13 TO HWY 257 8532 2 0.4
49 RD 36 AND RD 26 2753 3 0.4
FERN AVE E. 16 STREET 2051 5 0.4
32 PLATTEVILLE TO RD 39 3638 3 0.4
59 TH AVE W. 20TH ST TO HWY 34 5000 2 0.4
49 HWY 34 AND ROAD 48 2036 5 0.4
74 AT RD 15 8532 1 0.4
17 AT RD 34 982 4 0.4
54 RD 13 AND 17 1500 2 0.3
74 RD 27 AND RD 29 1600 3 0.3
19 RD 74 AND HWY 392 2343 2 0.3
54 RD 17 AND HWY 257 1500 2 0.3
74 AT RD 19 2028 1 0.3
39 RD 28 TO RD 44 677 2 0.3
41 RD 28 AND HWY 52 1617 0 0.2
66 HWY 85 to RD 41 472 0 0.2
INT 78 & 29 INTERSECTION IMP. 398 0 0.2
37 HWY 85 AND HWY 14 367 2 0.2
8
oaasw
SUMMARY LIST OF SAFETY PR0JECTS1
2000 SAFETY PROJECTS
ROAD LOCATION DESIGN TOTAL CORRECTIVE COST TONS ASPHALT CONTRACT .
MILES MILES ACTION ASPHALT COST COST
-1'4 Al RD 15 0.25 WIDEN SHOULDERS AND INSTALL TURN LANES 575.E 0 72 $i3,1SO-
':
:FERN AVE E 18 STREET 0 SIGNING
HWY 5300,000 7720 3131,237 •
14 WIDEN SHOULDERS 181,500 $20,000
. '•,, ROAD 48 AND 40 24 WIDEN SI•i'OULCERs
•
BM
:. s'j RD 13J6�[SEVANS 5 0 WIDEN-SRDOL "— — -B2b000 0 50—
} AT RD 34 0.25 0 IMPROVE INTERSECTION 5100,000 1,000 $18,009
TOOL
Oil }USING 18992 $323,883 $$22,000 •
2001 SAFETY PROJECTS
ROAD LOCATION DESIGN TOTAL CORRECTIVE COST TONS ASPHALT CONTRACT
MILES MILES ACTION ASPHALT COST COST
•
74 AT RD I5 •
A0.25 ' WIDEN SHOULDERS AND INSTALL TURN LANES $75,000 772 113.896
•.74. : RD 13 TO HWY 257 0 2 WIDEN TO 4 LANES 51.00 4.800 582,
800
0,000 0
30 510,00,(
AT RD 34 i0�000 1,000 318,000
7R� - IBS --"5$33,000 12.200 5219,800 510.000'
,•:.4y.•,;;;:., RD 40 AND RD 28 8
L A 1 .-
• RD 13 AND EVANS 5 0 WIDENgROOMMT $20,000 0 $0 $2.000
TOTAL LA WOLIN 18572 5334.296 522,000
2002 SAFETY PROJECTS I
ROAD LOCATION DESIGN TOTAL CORRECTIVE COST TONS ASPHALT CONTRACT
MILES MILES ACTION ASPHALT COST COST
._ ...,;q4_':-•.TWORP.ERS AND HWY 257 3 5-_` WIDEN SHOULDERS $1.000,003
.00012,200 5129,500 513,00
7,000
5129,500
::4Y•r,o`:,. 17B AND RD 28 8 $863,000 000 800 $11,100
•.v;�;'A.'.:: RD 2 TOE T LLIPT C)N a 4.5
: —en S144,00d. SD
/,',.7:
. `
' .�K" A 0,000
8Tµ .' W.20 TH ST TO HWY 34 1 IMPROVE ALIGNMENT $250.065 30
•
D 1 2 1 AVM-SHOULDERS 5500,000 0 $0
FERN AVE. E 18 STREET 0.25 C` 1,K NMENTr 575.000 0 s0
aim SO
ION. a SUMO 27800 $510,300 $12,000
ROAD LOCATION DESIGN TOTAL CORRECTIVE COST TONS ASPHALT ASPHALT CONTRACTST
WM ACTION
SO
_', RD 28 TOW 0 18 WIDEN GRAVEL SHOULDERS 31,000,000 4,600 $85,100"
T4.. RD 19 TO I4W 257 0 2 WIDEN SHOULDERS 5300,,000 4,000 374,000 52,000
•-. p7••<.,:•. HD 17 YAND68 TO 2573 21.000,000 1,000 S•i6,500
- '•17: ::. HWY68TO3I 0 2 CORRECT ALIG C
. ^-: INiEHSt(;TR7N IMP. 1 HWY 85 NEW ACCESS 5700,006 4,000 574,000 �
s.:y_
�{ '
23 75 RD TO RD 27 2 CORRECT ALIGNMENT/PAVE SHOULDERS 52,000000 8.000 5148,000 $0
8p TM•A W.20 TH ST TO Nw1'34 1 IMPROVE ALIGNMENT 5250.000 3,088 $57.127 CD
1
i, ,:
`"'�3 T RD1 0.25 0 TINTEHSECTION 550,000 0 SD
INTERSECTION IMP. 0.5 CORRECT ALIGNMENT $50,b00 0 S-
'We:11 RD 28 AND HWY 52 7.5 0 WIDEN GRAVEL SHOULDERS 5150,000 0 50
< 9 ' RD 74 ANL)HWY 392 3 0 PAVE SHOULDERS =Ma 0 SO
jOTAL it ILIDLI00 24688 $456,727 52,000
9
NEW
CONSTRUCTION
The New Construction selection process is based on a ranking system. Each year hundreds of
miles of roads have new traffic counts taken. Roads that exceed two hundred cars per day for
three consecutive days are then inventoried for estimated construction costs and then ranked and
cataloged.
The criteria are as follows:
• Average daily traffic(ADT)
• Possible safety improvements
• Cost for construction
MILES PER YEAR
12 Design
Design —
10
a
6
4
2
O
1999 2000 2001 2002 2003 2004
- Miles
10
05/26/99
SUMMARY LIST OF NEW CONSTRUCTION PROJECTS
2000 NEW CONSTRUCTION
LOCATION FROM TO MILES MILES CONTRACT COST
DESIGN CONSTRUCT COST OF ASPHALT
WY 34 RD54 2 $157,159
1IAIQWVERS RARKWAYSPNASE in HCARR EAST 1.3 $68,240
HWY14 RD 84 0.6 $
RpT4C a. RU ML SO
RDt5, ,ANQU}Ins)
-II
. A944 W t P 5 t RD31 HWY&5 1.85 _
,,.RD28 RD1 RU 3.5 1.5
:RD3° 10.5 I-WY52 1.5 0
pa$. HWV 66 RD28 1 0
IS
OTAL Y&' 7/5 4.9 $20,000 $225,402
2001 NEW CONSTRUCTION
LOCATION FROM TO MILES MILES CONTRACT COST
DESIGN CONSTRUCT COST OF ASPHALT
RD HWY 85 0 1.85 U7,121
1 $30,371
Rd 15 CONSTRUCTION) RD 72 RD 74 — $/9,205
1 .r ,� : h v t 119
R 28 0 stabilize
Zi * C▪' 1 ROa P a HRD I SY2,952
+ } '�. C RQ45 �1 1.5
',�_:*r _ .r,,.,,1WJ,R 'i . °:r. RU 10.5 HWY 52 2 $1 11,165
,*.. 7., 0,.b n et., HEHL OTAL 5.9 10.75 $379,814
2002 NEW CONSTRUCTION
LOCATION FROM TO MILES MILES CONTRACT COST
DESIGN CONSTRUCT COST OF ASPHALT
ROA26 CARR WEST 0 2.2 $125,878
'"- - HEHFORD HU128 0 5.5 S314,1%i
i rG'. n`u rf,4iD5-s^n - 21 bS t' HWY 56 I D474 .:::.
7 $0
j1 a -,n 8072 $0
. i"1 k fD 14 ki t yt EHWY56 RD 42 IRE CL RD 3 0.3
1 _ ST
OTAL 3.3 7.7 $439,814
204 NEW CONSTRUCTION
LOCATION FROM TO MILES MILES CONTRT
COSACT COF ASPHALT
OS
,,RD',7 HWYSS RU42 1 $44.003
EIRE CL RD 3 0.3 $13,201
4, RD:-1b GROV RD 128 0 3.5 $154,010
+�''r t S9 ER 1 HWY58 RD425 ,..i 1 $44,003
,� 7 . . :7 7 . .:.. 7 so
TOTAL 0 5.8 '-----$269,217
11
06/26/99
SPECIAL PROJECTS
SPECIAL PROJECTS ARE DERIVED FORM VARIOUS SOURCES.
ANY COST SHARING PROJECTS UNDERTAKEN AS A JOINT
VENTURE BETWEEN PRIVATE ENTERPRISE AND OTHER
AGENCIES WILL BE PLANNED IN THE SPECIAL PROJECTS
PROGRAM.
1999 SPECIAL PROJECTS
ROAD LOCATION TOTAL ASPHALT ASPHALT ASPHALT CONTRACT REVENUES SUBJECT
MILES THICKNESS TONS COST COST
PUBLIC WORKS FACILITY 2.5 3 5,284 $89,480 330.000 DRAINAGE PROJECT
DQ "RR
GREEL ELD A 4 5,388 391,598 $100,725 MISC
PA IINERLAY
NG
.i.NSTREET - 11TH AVE 0.38 1.5 861 $14,842 STRU
MARTIA 908+ 1' RD6 AND RD 10 I 3 2,345 $36,342 310,000 $83,058 NEW SUBDIVISION
TOTAL 3.86 13,867 $232,660 $40,000 3183,783
2000 SPECIAL PROJECTS
ROAD LOCATION DESIGN TOTAL ASPHALT ASPHALT ASPHALT CONTRACT REVENUES SUBJECT
MILES MILES THICKNESS TONS COST COST
/1IRPART ROADS 1 0 0 _ $150,000 $150,000 INTERIOR ROADS
ERIE'AREA-MAINTENANCE 1 0 0 3100,000 $100,000 ROUTINE MAINTENANCE
K OBE1 • RD 20.SQ WREN 1 4 2.807 347,722 GRAVEL PIT
TOTAL 3 2,007 -457,722 30 $250,000
2001 SPECIAL PROJECTS
ROAD LOCATION DESIGN TOTAL ASPHALT ASPHALT ASPHALT CONTRACT REVENUES SUBJECT
MILES MILES THICKNESS TONS COST COST
RADEMACHER PUD RD 9.55125 0.5 4.5 2,010 334,185
4-ANCR10 .^ b RD 35 AND RD 37 1 3 2.680 $45,553 334,133
s'WDE26 E.RO 3 1 3 2,105 335,792
6,766 $116,6 0 30 $34,133
TOTAL 2.5
ESTIMATES BASED ON PROJECTED FUTURE DEVELOPMENT AND PAST SPECIAL
PROJECT EXPENDITURES WOULD INDICATE THE POSSIBLE NEED TO SET ASIDE AT
LEAST$100,000 PER YEAR FOR CAPITAL OUTLAY.
12
o5/2er99
SUPPORT PROJECTS
BRIDGE MAINTENANCE
PROJECTED ANNUAL REPAIRS NEEDED TO MAINTAIN AND UPGRADE MINOR
STRUCTURES.
COST PER YEAR$250,000
'CONTRACT TRUCKING
ADDITIONAL TRUCKS AND DRIVERS HIRED FROM THE PRIVATE SECTOR TO
HAUL CONSTRUCTION MATERIALS.
COST PER YEAR$1,300,000
(EQUIPMENT RENTAL
VARIOUS EQUIPMENT NEEDED FOR SHORT DURATIONS
TO HANDLE CONSTRUCTION NEEDS.
COST PER YEAR$90,000
(MILLING
NEEDED FOR AREAS WHERE ASPHALT IS TO BE
REMOVED OR GRADED.
COST PER YEAR 545,000
(TREE REMOVAL
REMOVAL OF TREES FOR CONSTRUCTION AND SAFETY.
COST PER YEAR$100,000
'CONSTRUCTION SUPPLIE
VARIOUS SUPPLIES NEEDED TO SUPPLEMENT CONSTRUCTION PROCESSES
SUCH AS PAVING AND BASE WORK.
COST PER YEAR$230,000
'TESTING
STRUCTURAL EVALUATION OF EXISTING PAVED
SECTIONS FOR PLANNING AND DESIGN.
COST PER YEAR$31,000
'PROFESSIONAL SERVICE
SERVICES SUCH AS CONTRACT SURVEYING,GEOLOGICAL SURVEYS,OR
ENVIRONMENTAL SERVICES.
COST PER YEAR$90,000
13
RESOURCE
AILOUT1ON TRENDS
MILFAGF COMPARISON MII FS COMM PIED 1998 MILES PROPOSED 1999 YEAR 2009 YEAR 2061 YEAR 2092 YEAR 2003 YEAR 2004
NFW CONSTRUCTION ISPEC,IN.PR(l1FGTS 11.21 UR 134 89 127 77 5.8
255 245
SURFACE PRESERVATION155 215
-SEAL COAT WORN 201 256 212 15 8.5 16 15
SAFETYP OJECTSYATgN-ovERLAVSr REHABILITATION O025 496 675 95 16 17 21.75
SAFETY PROJECTS
TOTAL 2:14.42 196.89 249.85 287.25 25].2 293.8 289.15
IN NEW CONSTRUCTION/SPECIAL PROJECTS
•SURFACE PRESERVATION- SEAL COAT WORK
•SURFACE PRESERVATION-OVERLAYS I REHABILITATION
■SAFETY PROJECTS
YEAR 2004
•
YEAR 2003
YEAR 2002
YEAR 2001
YEAR 2000
MILES PROPOSED 1999
MILES COMPLETED 1998
0% 20% 40% 60% 80% 100%
14
FIVE-YEAR COST PROJECTIO\
YEAR 99 YEAR 2000 YEAR 2001 YEAR 2002 YEAR 2003 YEAR 2004
CONSTRUCTION SUPPLIES $1,833,857.00 $1,759,632.00 $1,791,361.00 $1,962,496.67 -$2152,206.85 $2,155,843.56
CONTRACT SERVICES $3,172,600.00 $3,656,390.00 $3,223,750.00 $3,263845.50 53,289,595.80 53,330,033.40
TOTAL EXPENDITURE $5,006,457.00 $5,416,022.00 $5,015,111.00 $5,226,342 17 55,441,802.65 $5,485,876.96
TOTAL REVENUE $4,830,501.00 $5,475,416.03 $5,120,331.06 $5,273,94099 55,432159.22 $5,595,124.00
NEW CONST $195,470.00 $225,400.00 $268,650.00 $439,874.00 $510,433.00 $409,813.00
OVERLAY $554,575.00 $628,083.00 $270,965.00 $29701900 $418,027.00 $303,388.00
STRUCTURAL OVERLAY $0.00 $29,000.00 $277,913.00 $55,583.00 .$111,185.00 $117,341.00
REHAB $461,953.00 $104,989.00 $166,748.00 $180,248.00 $178,748.00 $305,704.00
SPECIAL $232,060.00 $250,000.00 $250,000.00 $250,000.00 $250,000.00 $250,000.00
SAFETY $179,799.00 $305,860.00 $334,296.00 $510,300.00 $447,477.00 $526,350.00
MISC.CONST.SUPPLIES $210,000.00 $216,300.00 $222,789.00 $229,472.67 5238,358.85. $243,447.56
CHIP SEAL $500,000.00 $600,000.00 $612,000.00 $624,240.00 $836,724.80 $849,459.30
SAND SEAL $50,000.00 $50,000.00 $50,000.00 $50,000 00 $51,000.00 $52,020.00
SLURRY SEAL $485,000.00 $400,000.00 $408,000.00 $416,160.00 $424,483.20 $432,972.86
TESTING $35,000.00 $30,000.00 $30,900.00 $31,827.00 $32,761.81 -$33,765.26
MILLING $45,000.00 $50,000.00 $51,500.00 $53,045.00 $54,638.35 $56,275.44
CONTRACT TRUCKING $1,136,600.00 $1,301,850.00 $1,318,350.00 $1,331,533.50 ._ $1344,848.84 $1,33 50 1 22 9977.32
EQUIPMENT RENTAL $90,000.00 $90,000.00 $90,000.00 $90,000.00 '$90, .
TREE REMOVAL $80,000.00 $100,000.00 $100,000.00 $100,000.00 5100,00000;' "`$100;000.00
PROFESSIONAL SERVICES $50,000.00 ..$200,000.00 $75,000.00 $75,000.00 . $75,000.00 ' $75;000.00
CRACKFILL $65,000.00 $100,000.00 $102,000.00 $104,04000 - $108,120.80 $108,243.22
STABILIZATION $24,000.00 $24,000.00 $24,000.00 $24,000.00 $24,000.00 $24,000.00
SAFETY $12,000.00 $23,000.00 $12,000.00 $14,000.00 $0,00 $0.00
BRIDGE GRANT MATCH $0.00 $337,540.00 $0.00 $0 00 $0:� $250,000.00..•
BRIDGE MAINT. $250,000.00 $250,000.00 $250,000.00 $250,000.00 • $250,000.
NEW CONST.ROW $350,000.00 $100,000.00 $100,000.00 $100,000.00 $100,000.00 $100,000.00
$6,000,000.00 - -
$5,000,000.00
54,000,000.00 -CONSTRUCTION SUPPLIES
(CONTRACT SERVICES
$3,000,000.00 TOTAL EXPENDITURE
-*' TOTAL REVENUE
$2,000,000.00 - -
$1,000,000.00
$0.00
YEAR YEAR YEAR YEAR YEAR YEAR
99 2000 2001 2002 2003 2004
15
Hello