HomeMy WebLinkAbout931755.tiff --VESSELS OIL & GAS COMPANY
SUITE 2000,PRUDENTIAL PLAZA 1050 SEVENTEENTH STREET•DENVER,COLORADO 80265
303 825-3500
THOMAS 0 VESSELS,Chairman of the Board I}}y++��}
THOMAS J.VESSELS,President a i' I
12 November 1993 NOV 16 1993
c
Mr . Keith Schuett Wok' *Pi
Weld County Department of Planning
1400 North 17th Avenue
Greeley, CO 80631
Subject : Permits submitted under USR 589
Mr . Schuett
Thank you for taking the time this morning to review with me the
permits Vessels Oil & Gas (VOG) has applied for under USR 589 in
conjunction with the expansion of VOG' s Ft . Lupton processing
facility. I also appreciate the opportunity to address in writing
the concerns that have been expressed about the permit applications
in question and the how the work alluded to in these applications
conforms to the approved plan.
A. TB26138 - Inlet gas dehydration equipment
In the case of this equipment VOG sees essentially no devia-
tion from the approved plan. The approved plot plan clearly
shows dehydration equipment ( "Dehydrators" ) located at the
area VOG intends to install this equipment as shown on the
permit application. The only difference between the represen-
tation shown on the approved plot and that submitted with the
permit application is in the detail of the representations .
The plot plan shows an idealized representation of a dehydra-
tion unit installation, i . e . , an area devoted to dehydration
equipment containing at least one major vessel with an
associated contacter. The drawing submitted with the permit
application identifies this equipment by name and shows exact
details as to its configuration. This does not constitute a
major difference any more than an actual representation a
compression unit on a permit application showing an engine and
compressor with its associated scrubbers and heat exchangers
would constitute a major difference from the block representa-
tion shown on the approved plan.
7 ) 755
pLOO 5
12 November, 1993
2
B . TB26140 - Inlet gas filter/separators
The same argument as that given above can be applied to the
permit application for the installation of the inlet gas
filter/separator equipment . These filter/separators are inlet
gas treating equipment, used to separate entrained liquid and
particulate matter from field grade natural gas prior to its
entering the process unit . Combined they comprise a "Gas
Treating System" , an area for which is clearly shown on the
approved plot plan with this being the same area VOG has
indicated these to be located on the permit application.
Again the difference lies in the detail of the respective
representations, which VOG would not construe to constitute a
major deviation from the plan.
C . TB26139 - Natural gas processing unit
In the case of this permit application the difference between
what has been approved per the plan and what has been proposed
for permitting is mainly in the addition of the product pump
and product pump surge tank module . The original approval was
for two 20 MMscfd processing units to be located proximal to
each other directly north of the existing processing unit and
directly west of the main N-S utility rack. VOG is attempting
to permit a single 40 MMscfd process unit located in the same
area, The major equipment for this is contained on two process
skids located proximal to each other with a third area devoted
to process liquids pumps and a surge vessel . The surge vessel
is needed to provide suction head for these pumps and has been
sized based on the safety consideration that, should there be
an upset or shutdown downstream of the processing unit
sufficient liquid holding capacity be available to contain the
high vapor pressure liquids produced at the process unit
during the time it takes to properly take the process unit off
line. The size of the surge vessel makes it impractical to
mount it on one of the process skids .
VOG does not feel that the combination of two 20 MMscfd
process units into one 40 MMscfd unit of essentially the same
total size constitutes a major change from the approved plan.
VOG does not consider the addition of the surge vessel/pump
module to be significant or unwarranted as the approved plan
gives VOG permission to install associated pumps and piping
and should give VOG implied permission to install reasonable
auxiliary equipment based on process safety considerations .
12 November, 1993
3
As to the moving of the process skids approximately 50 feet
north of their positions as shown on the approved plot and the
extension of the E-W utility rack to connect with the main N-S
rack this was done as the result of maintenance access
considerations . VOG does not feel that this constitutes a
major deviation from the plan especially in light of Weld
County Planning' s recent approval of the permit application
for the installation of refrigeration and recompression units .
These units have been approved for a location approximately 75
feet south and 30 feet east of their locations as shown on the
approved plot plan and this change also alters the configura-
tion of their auxiliary utility rack from that shown on the
approved plot plan.
D. TB26278 - Natural gas liquids treating equipment
The approved plant expansion plan lists installation of gas
liquids processing equipment, including a contaminated liquid
handling system and a butane splitting system, as being
covered under the plan. While the approved plot shows
locations allocated to the butane splitting equipment it
unfortunately fails to identify any areas allotted to the
processing of contaminated liquids, in this case liquids
containing higher than acceptable concentrations of carbon
dioxide that result from the cryogenic recovery and subsequent
processing of these liquids . Recongizing this VOG submitted
a permit request to install the contaminated liquid processing
equipment in the area allocated to the butane splitting
equipment on the approved plot plan. Areas unidentified but
obviously set aside for liquids processing are shown on the
approved plot to the east of the existing fractionator heaters
and other liquid processing modules are shown to the south of
the existing fractionation plant . The equipment involved is
essentially generic for separation processes involving natural
gas liquids - staged separation vessels, heaters , heat
exchangers, and pumps . VOG has applied merely to substitute
one specific process for another, neither involving the use of
different equipment, use of equipment on a greater lesser
scale, or being inherently more hazardous than the other, and
to make minor relocations of some equipment . VOG does not see
how this contradicts the plan, which permits the installation
of equipment to perform either process, and under which some
relocation of equipment has been permitted. The utility rack
shown on the application is not shown on the approved plot but
VOG feels that the installation of piping, etc . auxiliary to
the processes approved is covered under the plan.
12 November, 1993
4
E . TB26330 -- Installation of pipeline pumps and surge tank
The plan as approved allows VOG to install liquid handling
facilities at the north central area of the facility and to
the south of the main storage batteries . VOG feels that
relocating this equipment on a smaller scale than is shown on
the approved plot plan to the area shown on the permit
application does not constitute a major deviation from the
approved plan. It should be noted here that the vessel in
question is not a storage vessel but is process equipment
designed to provide constant suction head to the pipeline
pumps . This vessel has been sized to provide a margin of
safety for proper shutdown of liquids processing equipment in
the event pipeline problems prevent the continuous flow of
high vapor pressure liquids from the plant . While the
relocation of approved equipment in this case involves a
fairly large distance with respect to the approved plot plan
VOG will point out that in January 1991 Weld County Planning
approved the installation of a recompression unit at the Ft .
Lupton facility at a similar distance from the approved
location as shown on the plot plan.
I have tried to show above that the deviations from the plan, most
of them involving discrepancies with the approved plot plan,
discussed during our conversation of this morning should not be
considered significant deviations from the approved plan for
purposes of permit approval . I feel that the arguments related to
ideal representation with respect to the approved plot plan and
those related to modifications based on engineering and safety
considerations are sound. I have cited precedent as to the
approval of past permits where I could because these precedents
have guided VOG in the making of decisions regarding the selection
and placement of equipment at the Ft . Lupton plant .
Again I thank you for giving me this opportunity to present the
position of VOG in this matter and should you have any questions
please do not hesitate to contact me .
Sincerely
Steven D. Smith
Engineer
�• ;�
i DEPARTMENT OF PLANNING SERVICES
N, PHONE(303)353-3845, EXT. 3540
r .
-y` �- . , WELD COUNTY ADMINISTRATIVE OFFICES
Rt.
. 1400 N. 17TH AVENUE
GREELEY, COLORADO 80631
.•
COLORADO
November 8, 1993
Steven D. Smith
Vessels Oil and Gas Company
Suite 2000 Prudential Plaza
1050 Seventeenth Street
Denver, CO 80265
Subject: Special Use Permit 589 , located on property described as part of the
SE4 of Section 28, T1N, R67W of the 6th P.M. , Weld County, Colorado.
Dear Mr. Smith:
Thank you for your August 24 Letter. I have reviewed the Amended Special Review
permit file and determined that the conditions of approval have been met for the
proposed expansion. Building permits must be applied for and released prior to
the start of construction for the proposed approved expansion.
Building permits for the installation of equipment requested in the attached
unissued building permits and a special review permit (Conquest Oil) for an
injection well, have been applied for through our office. The Department of
Planning Services' staff has reviewed these applications and determined that this
equipment and the new special review permit were not approved as part of the
existing special review permit and is considered to be a material deviation from
the plans or standards. An amended special review permit will need to be
approved and conditions of approval met prior to the release of building permits.
Please, call or write me if you have any questions.
Respectfully,
tO �
/ 'tgYch et
Current Planner
KAS/sfr
pc: Amended Special Review Permit 589-8
95 /755
pL ooh
ESSELS OIL & GAS COMPANY
SUITE 2000,PRUDENTIAL PLAZA•1050 SEVENTEENTH STREET•DENVER,COLORADO 90255
303 825.3500
THOMAS G VESSELS,Chairman of the Board
THOMASJ VESSE LS,President
24 August 1993
Mr. Kieth Schuett
Weld County Planning
1400 North 17th Avenue
Greeley, CO 80631
Reference: USR 589 (Amended)
Mr. Schuett
Pursuant to our telephone conversation of 08/18/93 regarding the amended USR 589,
approved 06/15/88, I am requesting that you review your file on USR 589 and grant
VOG permission to draw building permits under USR 589. VOG is preparing to begin
construction on expansion work at the natural gas processing facility for which
the USR was obtained.
My review of the VOG files indicates that conditions of USR 589 and the appended
Development Standards have been complied with. Notices of compliance with
individual conditions or standards should have been communicated to Weld County
Planning as these conditions and standards were met. Should this not have
occurred VOG is prepared to demonstrate compliance with individual conditions or
standards at this time.
A good deal of the work VOG undertook to meet the Development Standards under USR
589 involved the independent fire safety review conducted by the Brighton Fire
Protection District. We have been in communication with the BFPD on this issue
and as regards the construction that is to take place. Fire Protection Officer
Robert L. Parker of the BFPD, (303) 659-4101, should be able to answer any
questions you might have pertaining to this part of our compliance with the
Development Standards or the compatibility of our expansion plans with the
conditions of the independent fire safety review.
Vessels Oil and Gas is anxious to begin work on this project. Should you need
information or wish to inspect the facility please contact me and I will arrange
to meet your requirements immediately.
Sincerely
Steven D. Smith
Engineer
g3 /755
pLaoa
Hello