PROJECT: Island Grove Regional Treatment CHANGE ORDER NUMBER: 3
(name, address) 1140 14 Street •
Greeley, CO 80631 DATE: December 22, 1994
TO CONTRACTOR:Thissen Construction Corp. ARCHITECT'S PROJECT NO:6B006
(name, address) 2900 F Street CONTRACT DATE: April 11, 1994
Greeley, CO 80631
CONTRACT FOR: General construction
The.Contract is changed as follows:
A. Add items 1 through 8 as desribed on proposal dated December 15, 1994
Add: $3,642.00
•
•
- Not valid until signed by the Owner, Architect and Contractor.
•
The original(Contract Sum)(Guts tusitwor)was S 1,068,297.00
Net change by previously authorized Change Orders $ — 42,038.00
The(Contract Sum)(6 "' ' • ^ ' )prior to this Change Order was $ 1,026,259.00
The(Contract Sum)rwainsissesskiiinismagokan will be(increased)(depeasad)
praalassad)by this Change Order in the amount of $ 3,642.00
The new(Contract Sum)(414entiteuelttednournt4100 including this Change Order will be $ 1,029,901.00
The Contract Time will be(L ls(deaased)(unchanged)by ( )days.
The date of Substantial Completion as of the date of this Change Order}therefore is Decettiber 1, 1994
NOTE: This summary does not refect changes in the Contract Sum,Contract Time or Guaranteed Maximum Price which have been authorized by
Construction Change Directive.
Rnherf.a Architarfa Thissnn Ponctrttritinn r'orp r'nnnty of Weld ARCHITECT CONTRACTOR OWNER
809 9TH Street 2900 F Street 915 10Th Street
Address Address
Address
Greg/]�Jy, rt ..
BY BY
DATE DATE 12/2'2/ DATE
AIACAUTION: You should sign an original AIA document which has this caution printed in red.
An original assures that changes will not be dbretired as may occur when documents are reproduced.
AN DOCUMENT a 761 • CHANGE ORDER • 1987 EDmON • AIA. • Q I%7 • THE
AMERICAN.INETITUTE OF ARCHITECTS, 1735 NEW YORK AVE., N.W., WASHINGTON, D.C. 21)15x6 941 348
)t?X)/8 WARNING:Unlicensed photocopying violates US.copyright laws and is subject to legal prosecution.
rm
THISSEN
CONSTRUCTION
COIWOR.1"l'H )N
Roberts Architects December 15, 1994
809 9TH Street
Greeley, CO 80631
RE: Island Grove Regional Treatment Center
Dear Wayne,
In order to finalize this project I have compiled a list of all the outstanding change
orders I have not so far priced. The following is what I believe to be a complete list of all
remaining change orders for this project.
1) Add garbage disposal hookup and switch at kitchen sink
ADD: $ 209.00
2)Add for changing regular mount closers to parallel arm closers to accommodate exit
signs at exterior doors
ADD: $ 158.00
3)Add for outlet in equipment room for water heater controls and for fire sprinkler
system compressor.
ADD: $ 143.00
4)Add horn and strobe units per fire department request
z� ADD: $ 881.00
5)Add backflow preventer for water service per City of Greeley requirements.
ADD: $ 785.00
6)Add insulation on attic over water pipes to prevent freezing:
ADD: $1,152.00
7)Add to key cabinets alike
ADD: $ 123.00
8)Add to change lockset at door#30 to exit only
ADD: $ 191.00
Total Add $3,642.00