HomeMy WebLinkAbout930725.tiff RESOLUTION
RE: APPROVE CERTIFICATION OF INTENT TO PROCEED TO COLORADO HIGHWAY COMMISSION
AND AUTHORIZE CHAIRMAN TO SIGN SPECIAL BRIDGE FUND PROJECT ESTIMATE -
BRIDGE #32.5/218
WHEREAS, the Board of County Commissioners of Weld County, Colorado,
pursuant to Colorado statute and the Weld County Home Rule Charter, is vested
with the authority of administering the affairs of Weld County, Colorado, and
WHEREAS, the Board has been presented with a Certification of Intent to
Proceed to certify the County of Weld's intent to proceed with Bridge Project,
Structure Number WEL 032.5-021.0B, to the Colorado Highway Commission and a
Special Bridge Fund Project Estimate for said bridge, with the terms and
conditions being as stated in said documents, and
WHEREAS, after review, the Board deems it advisable to approve said
documents, copies of which are attached hereto and incorporated herein by
reference.
NOW, THEREFORE, BE IT RESOLVED by the Board of County Commissioners of Weld
County, Colorado, that the Certification of Intent to Proceed to certify the
County of Weld's intent to proceed with Bridge Project, Structure Number WEL
032.5-021.OB, to the Colorado Highway Commission be, and hereby is, approved.
BE IT FURTHER RESOLVED by the Board that the Chairman be, and hereby is,
authorized to sign said Special Bridge Fund Project Estimate for Bridge
#32.5/21B.
The above and foregoing Resolution was, on motion duly made and seconded,
adopted by the following vote on the 4th day of August, A.D. , 1993.
J1111 // A BOARD OF COUNTY COMMISSIONERS
ATTEST: G� WEL COUNTY, COLORADO
Weld County Clerk to the Board
Const nce L. Harbert, ha��ir9yman
BY: k/ t
Deputy Clerk the Board W. H. bs''EEer, Pro-(( Tem 66666
APPROVED AS TO FORM: „;,0;:4:
/ry
e . Baxter
t
/ e?”County A a1 K. Hall
Attorney
arbara J. Kirkmey
930725
SPECIAL BRIDGE FUND
BRIDGE PROJECT ESTIMATE
Structure Number WEL 032.5-021.OB County WELD
Engineering:
Preliminary Engineering $ 25,000.00
Design Engineering 35.000.00
Construction Engineering 70.000.00
and staking
Project Engineering 75.000.00
Final Inspection 2,000.00
TOTAL ENGINEERING COSTS: $ 207,000.00
Labor - Materials - Equipment:
Mobilization $ 65,000.00
Site Preparation 75.000.00
Excavation 70.000.00
Abutments/Piers/Piling 100,000.00
Structure/Deck/Guard Rail 386,940.00
Approaches 200,000.00
Pavement 75,000.00
TOTAL LABOR - MATERIALS - EQUIPMENT COSTS: $ 971.940.00
Contingencies: $ 100,000.00
TOTAL PROJECT COST $1.278,940.00
Date of Bid Proposal: May 1, 1994
Project Start Date: September 15. 1994
Project Completion Date: January 15, 1995
Estimate Prepared By: 1"/ /� Civil Engineer I
(signature and title)
Approved Chairman, 2,2 22.Board of County Commissioners: 1y
(signature) 081O/93
330'725
CERTIFICATION OF INTENT TO PROCEED
The County of WELD hereby certifies to the Colorado
Highway Commission that it intends to proceed with the Bridge Project,
Structure Number WEL 032.5-021.OB , for which it received Special
Bridge Fund Account monies; and certifies that it has, or will have
September 1, 1993 (date) , the required twenty percent local
matching funds. Attached is a design engineer's preliminary cost estimate and
a specific construction schedule, including a project start date and a
projected project completion date, pursuant to the State Department of Highways
Procedural Directive Number 43.1, paragraph 5*.
By: FLEX tri.
(county official
DREW SCHELTINGA
(official's name printed)
COUNTY ENGINEER
(title)
Date: JULY 29, 1993
* This attachment is a requirement unless good cause is shown for a delayed
transmittal.
intent.cer
930725
fet* mEMORAnDU
WilkTo Clerk to the Board oem July 29, 1993
COLORADO From Denny M. Graham, Civil Engineer II I fS/ovJ/'
subjectAgenda Item
Please add the following to the Board's agenda for Wednesday, August 4, 1993:
1. Certification of Intent to Proceed -
WEL-032.5-021.0B
2. Certification of Intent to Proceed -
WEL-023.0-074.0A
Appropriate documentation is attached.
DG/pds:ctb2O
Attachment
cc: Commissioner Baxter
File
930725 .