CHANGE ORDER
CHANGE ORDER N0. 1
DATE: November 28 , 1990
PROJECT: 78/I3A and 80.5/I7A
TO (CONTRACTOR): Paramount Construction Company
JUSTIFICATION: Foundation Modifications and Handling Excess Flow
You are directed to make the following changes in the work. All ot: eer
terms and conditions of the contract not: expressly modified hereby shall
remain in full force and effect.
ITEM N0. DESCRIPTION EST. QTY. UNIT UNIT COST AMC_NT
See Attachments "A" and "B"
The original contract sum was $ 263,000.00
Net change by previous change orders $ - 0 -
The contract sure prior to this Change Order was $ 263,000.00
The contract sum will be (increased) 6decne eed0
or (vmahacngeal by this Change Order $ 45,392.40
The contract sum including this Change Order
will be 3 308,:392.46
The new contract time will be (increased) (=d ac r ) or (-t1-wthtlr A9 by
T:rent•!-Three ( 23 ) days.
The date of completion as of the date of this Change Order is there=cre
January 30 1991 .
ACCy?'_'ED 3Y: ORDERED BY:
'aramount Construct__:: Co. 1__t. ^ ARI) OF WELD CC7N'.Y COMMISEICNE
Contractor or Andress: ?. O. :Sox 73S
?.c:_.ass ,r\
j.lairman _ -
oarL
, • ttetylivz. 3 I q
x A 961
ST
ATTE :
_ Jrt� /
WELD COUNTY CLERK TJ i riE BOARD
•�� DEPUTY CLERK TO THE R,?AiZD
t
' ') 9014.3
.� .
CHANGE ORDER N0. 1
ATTACHMENT "A"
NARRATIVE
This Change Order is made in accordance with sections 18, 19, and 47 of
Article III, General Conditions, of the Contract Documents for the
construction of Weld County Bridges 78/13A, and 80.5/17A. The purpose is
to address foundation modifications and handling excess flaw in the
irrigation ditch for both structures. This Change Order authorizes an
increase in the contract amount, not to exceed $45,392.46. Payment will
be made based on the actual units installed, or hours worked, but in no
case, shall the work for foundation modifications, or handling excess
flow, exceed $45,392.46.
Payment shall be made on unit prices previously bid, or as shown on
Attachment "B", Unit Price Summary, of this Change Order.
The contractor shall submit bills, separately identifying the items and
units that address the foundation modifications or handling excess flow.
All items and units must be field verified and documented by material
tickets, or field work order forms initialed by Weld County's inspectors.
Payment for overtime work at the rate of 1-1/2 times the unit cost shown
on Attachment "B", is authorized for Saturday, Sunday, or holidays for
work on the foundation modifications and handling excess flow. No
overtime payment for work outside the scope of this Change Order is
authorized. Overtime payment shall be reviewed and approved by the
inspector prior to the work.
The twenty-three (23) day time extension is for work completed through
November 28, 1990.
:mwcol
•
CHANGE ORDER N0. 1
ATTACHMENT "B"
UNIT PRICE SUMMARY
Item Description Unit Unit Cost
502 HP 10 X 42 Pile L.F. $ 30.42
502 Piling Tips Each $ 60.42
624 48" Culvert Pipe L.F. $ 22.34
206 Structural Backfill Ton $ 16.00
(1-1/2" Aggregate Complete In Place)
703 Filter Material Ton $ 8.03
(1-1/2" Aggregate)
626 Drott 3.5 Track Hoe Hr. $ 88.00
626 John Deere 644-B Loader Hr. $ 82.50
626 Tandem Dump Truck Hr. $ 42.00
109 Foreman Hr. $ 25.05
109 Laborer Hr. $ 18.37
109 Carpenter Hr. $ 22.55
:mwattb
•
CHANGE ORDER NO. 1
ATTACHMENT "B"
UNIT PRICE SUMMARY
Item Description Unit Unit Cost
502 HP 10 X 42 Pile L.F. $ 30.42
502 Piling Tips Each $ 60.42
624 48" Culvert Pipe L.F. $ 22.34
206 Structural Backfill Ton $ 16.00
(1-1/2" Aggregate Complete In Place)
703 Filter Material Ton $ 8.03
(1-1/2" Aggregate)
626 Drott 35 Track Hoe Hr. $ 88.00
626 John Deere 644-B Loader Hr. $ 82.50
626 Tandem Dump Truck Hr. $ 42.00
109 Foreman Hr. $ 25.05
109 Laborer Hr. $ 18.37
109 Carpenter Hr. $ 22.55
:mwattb