Loading...
HomeMy WebLinkAbout851174.tiff SSINS NO. : 6835 IN 85-72 UNITED STATES WELD cp ,i,y NUCLEAR REGULATORY COMMISSION wf OFFICE OF INSPECTION AND ENFORCEM ' , •,_ WASHINGTON, D.C. 20555o August 22, 1985 Adlp0 91985 ir GREEIEY, Cp La IE INFORMATION NOTICE NO. 85-72: UNCONTROLLED LEAKAGE OF REACTOR COOLANT OUTSIDE CONTAINMENT Addressees: All boiling water reactors holding an operating license (OL) or a construction permit (CP). Purpose: This information notice is provided to alert recipients of a significant event involving an uncontrolled primary coolant leak outside containment. It is expected that recipients will review the information for applicability to their facilities and consider actions, if appropriate, to preclude similar events from occurring at their facilities. However, suggestions contained in this information notice do not constitute requirements; therefore, no specific action or written response is required. Description of Circumstances: On June 12, 1985, a reactor scram occurred from 99% power at Oyster Creek Nuclear Generating Station. The scram occurred following failure of the elec- tric pressure regulator that subsequently caused a turbine bypass valve to open. This resulted in a reactor pressure decrease to the low pressure trip set point, causing the main steam isolation valves (MSIVs) to shut and the reactor to scram. As part of the scram sequence, the scram discharge volume (SDV) vent and drain valves are required to shut to contain the water released during a scram. However, in this event, the two drain valves did not fully close, allowing hot, reactor coolant to drain to the reactor building equipment drain tank. The hot fluid flashed in the drain system creating steam that flowed up through various drains in the 51-ft and 23-ft building levels. The steam combined with the fumes from the blistering paint on the SDV drain piping and caused a por- tion of the reactor building deluge fire protection system to actuate and spray down the 51-ft level . Approximately 500 gal of reactor coolant flowed to the drain tank before the scram system could be reset, which took approximately 38 minutes. The fire protection deluge system actuated approximately 20 minutes after the scram and was shut off in approximately 5 minutes. No safety equip- ment inside the reactor building was adversely affected by actuation of the deluge system. 8508200630 851174 IN 85-72 August 22, 1985 Page 2 of 3 Discussion: The failure of the SDV drain valves to properly close caused the following: 1. Uncontrolled reactor coolant leakage outside containment. 2. Temperatures of the control rod drive (CRD) seals exceeding the alarm setting. 3. Actuation of the reactor building fire protection deluge system. 4. Radioactive contamination of the 23-ft level of the reactor building. Each SDV drain valve that failed had a different failure mechanism. The upstream valve stem/disc travel stopped approximately 1/8 inch before fully seating onto the valve seat. This was caused by the valve actuator not having the stroking length properly adjusted. The downstream valve had an improperly sized spring in the valve actuator. It is believed that the valve initially closed, but was then forced open when the system pressure exerted a force below the valve seat that exceeded the spring closing force of the actuator. The high CRD seal temperature alarms were received intermittently after the scram. The alarms are an indication of abnormal flow of reactor coolant within or out of the CRD system. Degradation, or possibly failure, of the seals could occur following prolonged exposure at elevated temperatures. As a result, abnormal leakage could occur that might adversely affect proper rod motion or rod scramming ability. The reactor building fire protection system actuated on the 51-ft level of the reactor building. Although no equipment was adversely affected by the deluge system spray the potential existed for damaging electrical equipment and pos- sibly aggravating an already serious problem. Although the SDV vent and drain valves are stroke tested monthly in accordance with the inservice testing (IST) program, there were no criteria or requirements, for leak testing these valves. Following the initial installation of the down- stream valve as part of a system backfit in 1984, no postinstallation leak rate test of either valve against operating pressure was conducted. Both valve problems could have been detected by such a test. IE Information Notice 84-35, "BWR Post-Scram Drywell Pressurization" described an event of August 1982 at the Hatch Nuclear Plant Unit 2 where there was a similar leakage from the SDV. That event was also the subject of an AEOD case study and was included in the 3rd quarter, 1983, "Report to Congress on Abnormal Occurrences." IN 85-72 August 22, 1985 Page 3 of 3 No specific action or written response is required by this information notice. If you have any questions regarding this matter, please contact the Regional Administrator of the appropriate NRC regional office or this office. 1 764/11144-- d Lrdan, Director Divisi of Emergency Preparedness . and ngineeringg Response Office of Inspection and Enforcement Technical Contact: David Powell , IE (301) 492-8373 Attachment: List of Recently Issued Information Notices Attachment 1 IN 85-72 August 22, 1985 LIST OF RECENTLY ISSUED IE INFORMATION NOTICES information Date of Notice No. Subject Issue Issued to 85-71 Containment Integrated Leak 8/22/85 All power reactor Rate Tests facilities holding an OL or CP 85-70 Teletherapy Unit Full 8/15/85 All material Calibration And Qualified licensees Expert Requirements (10 CFR 35.23 And 10 CFR 35.24) 85-69 Recent Felony Conviction For 8/15/85 All power reactor Cheating On Reactor Operator facilities holding Requalification Tests an OL or CP 85-68 Diesel Generator Failure At 8/14/85 All power reactor Calvert Cliffs Nuclear facilities holding Station Unit 1 an OL or CP 85-42 Loose Phosphor In Panasonic 8/12/85 Materials and fuel Rev. 1 800 Series Badge Thermo- cycle licensees luminescent Dosimeter (TLD) Elements 85-67 Valve-Shaft-To-Actuator Key 8/8/85 All power reactor May Fall Out Of Place When facilities holding Mounted Below Horizontal Axis an OL or CP 85-66 Discrepancies Between 8/7/85 All power reactor As-Built Construction facilities holding Drawings And Equipment an OL or CP Installations 85-65 Crack Growth In Steam 7/31/85 All PWR facilities Generator Girth Welds holding an OL or CP 85-64 BBC Brown Boveri Low-Voltage 7/26/85 All power reactor K-Line Circuit Breakers, With facilities holding Deficient Overcurrent Trip an OL or CP Devices Models OD-4 and 5 OL = Operating License CP = Construction Permit SSNSINS No. : 6835 WELD tuuN8IP5 C7 1 UNITED STATES D F1 NUCLEAR REGULATORY COMMISSION I EI VE OFFICE OF IOD.C. 0555 AND 20555 AUG 3 9 1985 WASHINGTON, August 22, 1985 GREELEY, COLO. IE INFORMATION NOTICE NO. 85-71: CONTAINMENT INTEGRATED LEAK RATE TESTS Addressees: All nuclear power reactor facilities holding an operating license (OL) or a construction permit (CP): Purpose: This information notice is provided as a notification of a potentially signifi- cant problem pertaining to containment integrated leak rate tests (CILRTs). It is expected that recipients will review the information for applicability to their facilities and consider actions, if appropriate, to preclude a similar problem occurring at their facilities. However, the suggestion contained in this information notice (namely, that licensees review their programs with respect to the guidelines provided), does not constitute an NRC requirement. Therefore, no specific action or written response is required. Description of Circumstances: Recent staff reviews of the CILRTs performed at San Onofre, Kewaunee, and Monticello nuclear power plants have indicated that many utilities are misin- terpreting the relationship between local leak rate testing and CILRTs. 10 CFR 50, Appendix J, discusses containment leakage testing in terms of Type A, B, and C tests. The Type A test is a measurement of the overall integrated leakage rate of the primary containment; whereas Type B and C tests are local leak rate tests designed to detect and measure local leakage across each pressure-containing or leakage-limiting boundary for primary containment. As a result of Type B and C tests, some utilities are performing repairs and adjustments before conducting Type A tests without properly adjusting the Type A test results for the Type B anti C leakage rates. Without this adjustment, the "as found" condition of the primary containment cannot be properly determined. In some cases, when this adjustment is made properly, a Type A test may fail to meet the acceptance criteria of Apprndix J with regards to the "as found" condition. When two successive Type A test failures occur, Appendix J requires more frequent CILRTs. However, if Type B and C leakage rates constitute an identified contributor to this failure of the "as found" condition for the CILRT, the general purpose of maintaining a high degree of containment integrity might be better served through an improved maintenance and testing program for 8508200623 ! I_. I_� IN 85-71 August 22, 1985 Page 2 of 4 containment penetration boundaries and isolation valves. In this situation, the licensee may submit a Corrective Action Plan with an alternative leakage test program proposal as an exemption request for NRC staff review. If this submittal is approved by the NRC staff, the licensee may implement the corrective action and alternative leakage test program in lieu of the required increase in Type A test frequency incurred after the failure of two successive Type A tests. Discussion: Sections III.D.1.a, 2.a and 3.a of Appendix J require that a set of three periodic Type A tests be performed at approximately equal intervals during each 10-year service period, and that Type B and C tests be performed during reactor shutdown for refueling but in no case at intervals greater than 2 years. Under these test requirements, there are many occasions when Type A, B, and C tests must be performed during the same reactor shutdown period. Questions are frequently raised concerning the correct sequence of conducting the Type A, B, and C tests and the potential impact of the results of the Type B and C tests on the success or failure of a periodic Type A test. The NRC staff has previously provided partial guidance to utilities on these questions on an individual case basis with respect to inspection and enforce- ment activities (see Attachment 1). The staff position on these questions, as previously employed in inspection and enforcement, may be summarized as follows: 1. Section III.A.3 of Appendix J requires that all CILRTs be conducted in accordance with the provisions of ANSI N45.4-1972. Paragraph 4.2 of ANSI N45.4-1972 states that for periodic CILRTs no repairs or adjustments are to be made to the containment structure prior to conducting the test in order to disclose the normal state of repair of the containment structure. 2. Type B and C tests may be performed either before the start of or after completion of the periodic Type A test provided that the pretest require- ments of Paragraph 4.2 of ANSI N45.4-1972 and Section III.A.1.a of Appen- dix J are met; i.e. , no repairs or adjustments to the primary containment boundary are made so that the containment can be tested in as close to the "as is" condition as practical . As such, the leakage information obtained from the "as is" (sometimes called "as found") Type A test results can be used to assess the containment condition and its integrity following a period of plant operation. 3. If repairs or adjustments performed as a result of the Type B and C testing programs or for any other reasons are made to the primary contain- ment boundary before the Type A test sequence, local leak tests must be performed on the affected portion of the containment boundary to determine the minimum pathway leakage rates before and after the repairs or adjust- ments are made. The minimum pathway leakage would be the smaller leakage rate of in-series valves tested individually, one-half the leakage rate IN 85-71 August 22, 1985 Page 3 of 4 for in-series valves tested simultaneously by pressurizing between the valves, and the combined leakage rate for valves tested in parallel . The "as found" Type A test results can then be obtained by adding the differ- ences between the affected minimum path leakage before and after repairs or adjustments to the overall measured Type A test result. A periodic Type A test would be called a "failure" if the "as found" Type A test result (with appropriate correction from local leak tests) exceeds the acceptance crtieria of Appendix J. 4. The question has been raised by various utilities as to how far in advance of the Type A test the Type B and C tests may be conducted without having to add the leakage differences to the Type A test results. The staff position on this question has been that after Type B and C tests, the penetrations and valves should experience some period of normal service conditions before the Type A test. If the Type B and C tests are con- ducted before the Type A test during the same refueling outage, the service condition criterion would not be met. If, however, some operating service time is achieved, the Type A test can be conducted essentially independent of the time duration of exposure to the normal service condi- tions. Thereafter, a Type A test could be conducted without having to consider the local leak rate results in determining the "as found" condition. The continuance of containment leak-tight integrity is the primary importance in performing Type A, B, and C tests. Therefore, it may be beneficial for li- censees to implement improved maintenance and testing programs for containment penetrations to ensure that known or likely leaking penetrations will not result in the overall loss of containment leak-tight integrity and in the ensuing penalties for Type A test failure. It should also be noted that containment leak-tight integrity is monitored between CILRTs through the Type B and C test programs. Failure to meet the acceptance criteria of Appendix J for those tests generally constitutes a loss of containment integrity as defined in the Technical Specifications and may be reportable by the licensee under the provisions of 10 CFR 50.73. , Sections (a)(2)(ii) and (a)(2)(v)(C). It is suggested that licensees review their CILRT program with respect to the above guidelines. IN 85-71 August 22, 1985 Page 4 of 4 No specific action or written response is required by this information notice; however, if you have any questions regarding this notice, please contact the Regional Administrator of the appropriate NRC regional office or the technical contacts listed below. 'Edward 1. rdan�tor Division o Emergency Preparedness and En. neering Response Office of Inspection and Enforcement Technical Contacts: Y. S. Huang, NRR (301) 492-9493 D. C. Kirkpatrick, IE (301) 492-4510 S. A. McNeil , IE (301) 492-9602 Attachments: 1. Documentation from NRC to Utilities, Related to Repairs and Adjustments Done Prior to Type A Tests 2. List of Recently Issued IE Information Notices Attachment 1 IN 85-71 August 22, 1985 Page 1 of 2 Documentation from NRC to Utilities, Related to Repairs and Adjustments Done Prior to Type A Tests 1. Letter to Consumers Power Company from R. L. Spessard, "Big Rock Point CILRT Schedule," February 3, 1983 This letter informed the licensee of the necessity to increase the CILRT frequency because of the failure of two consecutive Type A tests conducted in 1977 and 1982. During the 1982 refueling outage, Type B and C tests were conducted and several valves were found to leak excessively and were repaired. Subsequently the Type A test was conducted and the licensee reported a successful test, but it did not include the initial Types B and C leakage in the Type A test results. The NRC staff reviewed the tests and determined that the Type B and C leakage should be added to the Type , A test results, because the plant had not been in service between the time of the Type B and C tests and the Type A test. With the addition of the Type B and C leakage to the Type A test result, the leakage was excessive and the containment was deemed to have failed the "as found" test condition. 2. Letter to Commonwealth Edison Company from R. L. Spessard, "Quad Cities Unit 1 Containment Integrated Leak Rate Test Frequency," October 7, 1983. This letter also informed the licensee of the necessity to increase the CILRT frequency because of the failure of two consecutive Type A tests. These tests were conducted in 1979 and 1982. Type B and C tests conduct- ed during the 1982 refueling outage, prior to the Type A test, showed that the combined leakage from several valves exceeded the allowable Technical Specification. In addition, the seal between the drywell head and the drywell vessel flange was found to be leaking to such an extent that the leakage could not be measured. The licensee repaired these leaks and then conducted a Type A test that showed the leakage to be within the allowable limits. The NRC staff, however, determined that the containment had failed the CILRT with respect to the "as found" condition. This determi- nation was based on the position that the Type B and C test results could be excluded from the "as found condition" only if some period of normal station service existed between Type B and C tests and the Type A test. 3. Inspection Report No. 50-305/84-19 (DRS), Kewaunee, November 27, 1984 and Notice of Violation to Wisconsin Public Service Corporation - Docket No. 50-305, November 28, 1984. Attachment 1 IN 85-71 August 22, 1985 Page 2 of 2 The inspection report discusses an exemption to Appendix J issued to Wisconsin Public Service Corporation by the NRC. The exemption permitted Type B and C tests and repair work on penetrations to be performed at Kewaunee before Type A tests were conducted. The exemption required that leakage reduction caused by the repairs be added to the Type A test result for the purpose of evaluating the "as found" condition. The licensee then wrote to the NRC stating that it did not believe that an exemption was required to perform Types B and C tests before performing a Type A test. The licensee based this on the belief that Type A testing and Type B and C testing were two separate events performed on two separate schedules. In 1984, the licensee performed Type B and C tests before performing the Type A test and failed to add the pre- and post-repair differential leakage to the "as found" Type A test results in its CILRT report. As stated in the inspection report, the NRC staff did not agree with the licensee' s position because Type B and C testing (with repair) would invalidate part of the purpose of the Type A test (that is, to establish the "as found" condition). As a result, the notice of violation covering this failure was issued on November 28, 1984. 4. Inspection Report No. 50-206/85-12 San Onofre Unit 1, April 5, 1985. Paragraph 6 of this report discusses the results of the CILRT performed at San 0nofre during1985. Type C testing and repair work was performed on six sets of valves just before the Type A test was conducted. However, differential leakage resulting from the repair was not added to the Type A test results reported. As a result a notice of violation covering this failure is under consideration. Attachment 2 IN 85-71 August 22, 1985 LIST OF RECENTLY ISSUED IE INFORMATION NOTICES Information Date of Notice No. Subject Issue Issued to 85-70 Teletherapy Unit Full 8/15/85 All material Calibration And Qualified licensees Expert Requirements (10 CFR 35.23 And 10 CFR 35.24). 85-69 Recent Felony Conviction For 8/15/85 All power reactor Cheating On Reactor Operator facilities holding Requalification Tests an OL or CP 85-68 Diesel Generator Failure At 8/14/85 All power reactor Calvert Cliffs Nuclear facilities holding Station Unit 1 an OL or CP 85-42 Loose Phosphor In Panasonic 8/12/85 Materials and fuel Rev. 1 800 Series Badge Thermo- cycle licensees luminescent Dosimeter (TLD) Elements 85-67 Valve-Shaft-To-Actuator Key 8/8/85 All power reactor May Fall Out Of Place When facilities holding Mounted Below Horizontal Axis an OL or CP 85-66 Discrepancies Between 8/7/85 All power reactor As-Built Construction facilities holding Drawings And Equipment an OL or CP Installations 85-65 Crack Growth In Steam 7/31/85 All PWR facilities Generator Girth Welds holding an OL or CP 85-64 BBC Brown Boveri Low-Voltage 7/26/85 All power reactor K-Line Circuit Breakers, With facilities holding Deficient Overcurrerit Trip an OL or CP Devices Models OD-4 and 5 85-63 Potential for Common-Mode 7/25/85 All power reactor Failure of Standby Gas Treat- facilities holding ment System on Loss of Off- an OL or CP Site Power OL = Operating License CP = Construction Permit - o°EPa aec1/4gJ UNITED STATES ° . NUCLEAR REGULATORY COMMISSION I ) '' I ; m ; REGION IV 1' 611 RYAN PLAZA DRIVE, SUITE 1000 do -, ° ARLINGTON,TEXAS 76011 h'(!P p;,,.,,,,. AUG 2 7 1985 ( (' Docket: 50-267 I( `r , AUG 2 g 1985 GREELEY. Public Service Company of Colorado coLo. ATTN: 0. R. Lee, Vice President Electric Production P. 0. Box 840 Denver, Colorado 80201-0840 Gentlemen: We have reviewed your December 30, 1983, application "Proposed Changes to the Inservice Inspection and Testing Requirements" and find that additional information is needed. The findings of our review were discussed with members of your staff during meetings held during the week of July 22, 1985, on the Technical Specifications Upgrade Program. We have coordinated our review with corresponding portions of the Fort St. Vrain Technical Specification Upgrade Program now in progress. This has been done by associating as well as possible the corresponding "Draft Items" from the upgrade program with each of the surveillances reviewed. In doing this we have found many Draft Upgrade Items which are unsatisfactory, although in a few cases we find them superior to the proposed surveillances. Identification and discussion of these items now appears in the enclosure (identified by following the assigned number with a "U" for upgrade). Major items of importance are: The December 30, 1983, submittal does not complete the surveillance program PSC committed to implement. We observe that, together with the material addressed by Fort St. Vrain License Amendment 33, the current review deals with the higher priority items but some Category II systems remain as well as the majority of the Category III and IV systems. Whether these surveillances should be addressed in the context of the present technical specifications or as part of the upgrade program should be based on the anticipated rate of progress of the upgrade program. ° Many of the systems we addressed were reviewed in the context of the July 1, 1983, edition of the ASME Code which includes "Rules for Inspection and Testing of Components of Gas-Cooled Plants ," (Section XI, Division 2). This reference expedited our review, provided suitable comparability with light water reactors, and otherwise strengthened the quality of the Fort St. Vrain surveillance program. It is our recommendation that this Code be used wherever practicable. While there may be some necessary exceptions both parties will have to take, our review has illustrated the benefits of consistency, completeness and efficiency in spite of some potential difficulties. This practice would be similar to that used for older LWRs. 9. I S/Hlz, Public Service Company -2- of Colorado 0 Fort St. Vrain License Amendment 33 and document prepared by ASIA Inc. , which formed part of the basis were also reviewed. One of the ASTA recommendations was that PSC investigate the application of visual examination techniques to certain portions of the thermal barriers in the lower plenum. While it was concluded in the SER supporting Amendment 33 that no practical access was available for such examinations, we believe that this issue should not remain closed. It is our opinion that PSC should commit to a continuing awareness of advancements in inspection techniques, particularly those involving miniaturization of instrumentation, and be prepared to implement such inspections should the technology become available. A copy of our evaluation is enclosed for your review and comment. It is our understanding, based on discussions at the above mentioned meeting, that PSC will provide a resubmittal of these requirements within 90 days of your receipt of this evaluation. Since this reporting requirement relates solely to the Fort St. Vrain Station, OMB clearance is not required under P.L. 96-511. Sincerely, Dorwin R. Hunter, Chief Reactor Safety Branch Enclosure: Evolution of ISI/TSI cc: Mr. D. W. Warembourg, Manager Nuclear Engineering Division Public Service Company of Colorado P. 0. Box 840 Denver, Colorado 80201 Mr. David Alberstein, 14/159A GA Technologies, Inc. P. 0. Box 85608 San Diego, California 92138 Kelley, Stansfield & O'Donnell Public Service Company Building 550 15th Street, Room 900 Denver, Colorado 80202 Public Service Company -3- of Colorado /Chairman, Board of County Comm. of Weld County, Colorado Greeley, Colorado 80631 Regional Representative Radiation Programs Environmental Protection Agency 1860 Lincoln Street Denver, Colorado 80203 Mr. H. L. Brey, Manager Nuclear Licensing/Fuels Div. Public Service Company of Colorado P. 0. Box 840 Denver, Colorado 80201 J. W. Gahm, Manager, Nuclear Production Division Fort St. Vrain Nuclear Station 16805 WCR 19} Platteville, Colorado 80651 L. Singleton, Manager, Quality Assurance Division (same address) Colorado Radiation Control Program Director Hello