HomeMy WebLinkAbout881017.tiff RESOLUTION
RE: APPROVE CHANGE ORDER TO BASSETT & ASSOCIATES, INC. ,
CONCERNING HUMAN RESOURCES OFFICE BUILDING AND AUTHORIZE
CHAIRMAN TO SIGN
WHEREAS, the Board of County Commissioners of Weld County,
Colorado, pursuant to Colorado statute and the Weld County Home
Rule Charter, is vested with the authority of administering the
affairs of Weld County, Colorado, and
WHEREAS, Weld County entered into construction contracts on
July 11 , 1988 , with Bassett & Associates, Inc. , concerning the
Human Resources Office Building, and
WHEREAS , the Board has been advised that a Change Order
totaling $37 ,579 . 00 is necessary.
NOW, THEREFORE , BE IT RESOLVED by the Board of County
Commissioners of Weld County, Colorado, that a Change Order
totaling $37 , 579 .00 concerning the contract dated July 11 , 1988 ,
with Bassett & Associates, Inc. , be, and hereby is, approved.
BE IT FURTHER RESOLVED by the Board that the Chairman be, and
hereby is, authorized to sign said Change Order.
The above and foregoing Resolution was, on motion duly made
and seconded, adopted by the following vote on the 26th day of
October, A.D. , 1988 .
ATTEST: �/ O� l
tJn BOARD OF COUNTY COMMISSIONERS
WEL OUN/T�Y, COLORADO
Weld County lerk and Recorder /(�
and Clerk to the Board ene R. Brantner, Chairman
BY: L7z�nc �_ z C.W. Kir y, Pr -Tem
Deputy County O4erk
APPROVED AS TO FORM: J.cqu ine o nson
EXCUSED
Gordon E Lacy
County Attorney
Frank Yamaguchi
V .
881017
CHANGE OWNERARCHITECT Li
ORDER CONTRACTOR o RECEIVED OCT 1 7 1988
FIELD
AM DOCUMENT G701 OTHER
• PROJECT: WELD COUNTY, COLORADO CHANGE ORDER NUMBER: ONE
(name, address) HUMAN RESOURCES OFFICE BUILDING
WELD COUNTY BUSINESS PARK
TO (Contractor) GREELEY, COLORADO
Bassett & Associates, Inc. —1 ARCHITECT'S PROJECT NO: 8801
7388 5. Revere Parkway CONTRACT FOR: HUMAN RESOURCES
Suite 806 OFFICE BUILDING
Englewood, Colorado 80112 Greeley, Colorado
L J CONTRACT DATE:Jul y 11 , 1938
You are directed to make the following changes in this Contract:
1 . Owner requested changes (building department) , items 1-5, Architect' s
iecter dated July 25, 1988 and Contractor' s letter da_ed August 1 , , 1338•
ADD: $ 1 ,485.00
2. Addition of an air-conditioning system to electrical room 10 per
Contractor' s letter dated September 29, 1988.
ADD: 4, 103.00
3 . Addition of 2 sections of 12-inch diameter concrete pipe at east
end of pond 112 per Contractor' s letter. ADD: 577.00
4. Extend structural columns as instructed by structural engineer
and per Contractor' s letter dated October 11 , 1988. ADD: 210.00
5. Additional landscaping and sprinkler system, Base Bid over $20,000
allowance, per Contractor' s letter dated October 12 , 1988. ADD: 42,522.00
6. Substitution of Bali Blinds in lieu of Levalors specified. DEDUCT: 185.00
7. Carpet allowance minus carpet bid. ($26,500-$18,386) DEDUCT: 8, 114.00
8. Hardware allowance minus hardware bid. ($15,000-$11 ,981) DEDUCT: 3,019.00
The original Contract Sum was $ 7772.OOO.OU
•
Net change by previous Change Orders $ 0.00
•
The Contract Sum prior to this Change Order was $ 772,000.00
•
The Contract Sum will be (increased) (Efseretlsetf) (anehangedl by this Change Order . . . $ 37,579.00
•
The new Contract Sum including this Change Order will be $ 809,579.00
•
The Contract Time will be (inefeast:1) (degrease) (unchanged) by ( -0- ) Days.
The Date of Completion as of the date of this Change Order therefore is January 7, 1989 •
LARRY E. STEEL ASSOCIATES BASSETCTT�& ASSOCIATES, INC. WELD COUNTY, COLORADO
re ueley National Plaza, Suite 6�t8NT,ffi . Revere Pkwy. Suite0 ER P.O. Box 758
Address Address
Address
Greeley, Colorado C 080631 A r �EEnng�l`ewood, Colorado 80112 }/jf�Gree`ley, Colorado 80632
BY dal E.. 2 tet t , A. I .A YtY -1I14,3 L r By Janet ilt.-Gs�.--
DATE IC /14198 DATE to -12) -SE) DATE /6 _. ‘X6 - j by
AR DOCUMENT C701 • CHANGE ORDER • APRIL 1070 EDITION • AIA® • C 1970 • THE ONE PACE
AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE., NW, WASHINGTON, D.C. 20006 1017