HomeMy WebLinkAbout871543.tiff RESOLUTION
RE : APPROVE CHANGE ORDER FOR RBD, INC.
WHEREAS , the Board of County Commissioners of Weld County,
Colorado, pursuant to Colorado statute and the Weld County Home
Rule Charter, is vested with the authority of administering the
affairs of Weld County, Colorado, and
WHEREAS, Weld County entered into a contract for certain
engineering services with RBD, Inc. concerning Bridge No. 58/47B,
and
WHEREAS, additional engineering services are necessary at
said Bridge and the Board has been presented with a Change Order
for said services, with the revised total contract amount not to
exceed $41 ,020 .00 , and
WHEREAS, after review, the Board deems it advisable to
approve said Change Order for RBD, Inc. , a copy of which is
attached hereto and incorporated herein by reference.
NOW, THEREFORE, BE IT RESOLVED by the Board of County
Commissioners of Weld County, Colorado, that the Change Order,
with the revised total contract amount not to exceed $41 ,020 .00 ,
for RBD, Inc. be, and hereby is, approved.
The above and foregoing Resolution was, on motion duly made
and seconded, adopted by the following vote on the 14th day of
December, A.D. , 1987 .
BOARD OF COUNTY COMMISSIONERS
ATTEST: 4Ark p� �� WELD COU Y LORADO
Weld County erk and Recorder
and Clerk to the Board G airman
BY: NOhat lL/ Clerk U C.W irby, Pro- em
Deputy County
APPROVED AS TO FORM: ene R. Brant er \-,
eCe-;7 ac uel ��e Joh o�!
County Attorney
Frank amaguchi
E"•,•� -nI) 871543
WELD COUNTY BRIDGE 58/478
JOB NO. 114-004
ADDITIONAL ENGINEERING SERVICES
RELATED TO SECOND STRUCTURE AT
IRRIGATION DITCH
1. Additional Surveying - (8 hrs x $65.00) = $ 520.00
(Topo. for Crossing Area)
2. CADD Plot - (4 hrs x $50.00) = $ 200.00
3. Coordination with Ditch Co.-(8 hrs x $50.000 = $ 400.00
Re: Requirements for flume redesign
4. Coordination with landowner -(4 hrs x $50.00)= $ 200.00
RE: Irrigation Laterals and
Suspended Crossing
5. Coordination w/Utility Co.-(4 hrs x $50.00) = $ 200.00
RE: Pole and Guy Wire Relocations
6. Conceptual Design and - (8 hrs x $55.00) = $ 440.00
Hydraulics
7. Final Structural and - (16 hrs x $55.00) = $ 880.00
8. Final Design Drafting - (24 hrs x $30.00) _ $ 720.00
9. Clerical - (4 hrs x $15.00) = $ 60.00
10. Expenses = $ 100.00
ESTIMATED TOTAL = $ 3,720.00
Hourly, Not-to-Exceed = $ 4,000.00
Revised Total Contract Amount
(Not-to-Exceed) = $41,020.00
•
8'71543
MEMORAnDUM
1111€. To ___ Clerk to the Board __ Date_ December 9, 1987
COLORADO Front Drew L. Scheltinga, County Engineer 1V-W1/
subject Change Order to RBD for Bridge 58/47B_
Please place on the Commissioners' agenda "Consider Change Order to
RBD Inc. , Consulting Engineers, for design contract for Bridge
58/47B".
The Commissioners have approved a Review/Work Session Request. The
attached Exhibit B should be all that is necessary for the
Commissioners packet.
DLS/bf
Enc.